JPH10140586A - Precast foundation for deep foundation - Google Patents

Precast foundation for deep foundation

Info

Publication number
JPH10140586A
JPH10140586A JP29647696A JP29647696A JPH10140586A JP H10140586 A JPH10140586 A JP H10140586A JP 29647696 A JP29647696 A JP 29647696A JP 29647696 A JP29647696 A JP 29647696A JP H10140586 A JPH10140586 A JP H10140586A
Authority
JP
Japan
Prior art keywords
foundation
concrete
concrete block
precast
deep
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP29647696A
Other languages
Japanese (ja)
Inventor
Hiroyuki Hoshino
弘之 星野
Mikio Hirai
幹男 平井
Hiromitsu Takagi
博光 高木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Cable Ltd
Original Assignee
Hitachi Cable Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Cable Ltd filed Critical Hitachi Cable Ltd
Priority to JP29647696A priority Critical patent/JPH10140586A/en
Publication of JPH10140586A publication Critical patent/JPH10140586A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

(57)【要約】 【課題】コンクリート打設において、天候に左右され
ず、コンクリート品質の工場と均一化を図れ、孔内作業
員の削減及び作業の簡略化を図れる、深礎基礎用プレキ
ャスト基礎体を提供。 【解決手段】予め決められた形状に作成されたコンクリ
ートブロックを積み上げ組み立て、所定の基礎構造を構
築した。コンクリートブロックは、基礎体を構築した時
にブロック群を一体化する鉄筋を貫通可能とし、また、
コンクリートブロックの組み立てにより円筒状にして基
礎体内部に空隙部を有せしめた。また、コンクリートブ
ロックは、セメントモルタル等の流動体を縦横に流入・
出できる貫通孔を有せしめ、セメントモルタルの注入に
よる基礎体の固結一体化及び基礎体と掘削地盤との密着
を図れる。さらに、コンクリートブロックには、隣接す
るコンクリートブロックに凹凸嵌合する突起または溝を
有せしめた。
(57) [Summary] [Problem] A precast foundation for deep foundation foundation that can achieve a uniform concrete quality factory and reduce the number of workers in boreholes and simplify work, regardless of the weather, in concrete casting. Provide body. SOLUTION: Concrete blocks created in a predetermined shape are stacked and assembled to construct a predetermined foundation structure. The concrete block can penetrate the rebar that integrates the blocks when the foundation is constructed,
The concrete block was made cylindrical by assembling the concrete block, and a gap was provided inside the base body. In addition, the concrete block flows fluid such as cement mortar vertically and horizontally.
By providing a through hole that can be discharged, solidification and integration of the foundation by injecting cement mortar and close contact between the foundation and the excavated ground can be achieved. Further, the concrete block was provided with a projection or a groove that fits unevenly with the adjacent concrete block.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、送電線路等を架設
するための鉄塔の基礎を形成する技術に関し、とりわ
け、深礎基礎に関する。この深礎基礎には、基礎体内部
に空隙部を有する深礎基礎体を包含する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a technology for forming a foundation of a steel tower for erection of a transmission line or the like, and more particularly to a deep foundation. The deep foundation includes a deep foundation having a void inside the foundation.

【0002】[0002]

【従来の技術】[Prior art]

1.送電線路用深礎基礎の形成方法;鉄塔基礎体に加
わる圧縮力及び引上げ力に対抗する基礎径及び深度を確
保する深礎孔を掘削、基礎体コンクリート加わる引上
げ力に対抗する鉄筋を基礎孔に配置、鉄塔材据え付け
位置までコンクリートを打設、鉄塔材を据えつけた
後、さらにコンクリート打設、掘削土の一部を埋め戻
し、掘削土の大部分を搬出する。
1. Method of forming a deep foundation for transmission line; excavating a deep foundation hole to secure the foundation diameter and depth against the compressive and pulling forces applied to the steel tower foundation, and rebars in the foundation hole against the lifting force applied to the concrete of the foundation After placing the concrete to the location of the tower and installing the tower material and installing the tower material, further concrete placement, backfilling of part of the excavated soil, and transporting most of the excavated soil.

【0003】2.基礎体内部に空隙部を有する深礎基礎
の形成方法;(1) 前述工法と同じ設計条件で深礎孔を掘
削、(2) 前述工法と同じ設計条件で鉄筋を深礎孔に配
置、(3) 空隙部の下面までコンクリートを打設、(4) 空
隙部を確保する枠体を据え付け、(5) 深礎基礎孔と枠体
との間にコンクリートを打設、(6) コンクリート硬化
後、枠体を取り外し、(7) コンクリートで周面を囲まれ
た空隙部に掘削土の一部を埋め戻し、(8) 掘削土で埋ま
った空隙部の上側に鉄塔材据え付け位置までコンクリー
トを打設し、空隙部に蓋を設置、(9) 鉄塔材を据え付
け、さらにコンクリートを打設、(10)掘削土の一部を埋
め戻し、(11)掘削土の残りを搬出する。
[0003] 2. A method of forming a deep foundation with a void inside the foundation body; (1) excavating a deep foundation hole under the same design conditions as the previous method, (2) placing rebar in the deep foundation hole under the same design conditions as the previous method, ( 3) Pour concrete up to the bottom of the gap, (4) Install a frame to secure the gap, (5) Pour concrete between the deep foundation hole and the frame, (6) After concrete hardens , Remove the frame, and (7) fill back a part of the excavated soil in the void surrounded by the concrete, and (8) pour concrete up to the installation position of the tower material above the void filled with the excavated soil. A cover is installed in the void, (9) steel tower material is installed, concrete is further poured, (10) part of the excavated soil is backfilled, and (11) the rest of the excavated soil is carried out.

【0004】尚、1,2の工法共に、基礎体は生コンク
リートを打設し所定の形状に仕上げている。これにより
掘削地盤と基礎体が密着し、鉄塔引き上げ荷重に耐える
設計となっている。
[0004] In both the first and second construction methods, the foundation is cast into fresh concrete and finished in a predetermined shape. As a result, the excavated ground and the foundation are brought into close contact with each other, and are designed to withstand the tower lifting load.

【0005】[0005]

【発明が解決しようとする課題】前述した従来技術のう
ち、送電線路用鉄塔基礎形成方法には、次の問題があ
る。屋外作業のため、雨天時にコンクリート打設が行
えない。鉄塔打設箇所までのコンクリート運搬には、
ヘリコプターや索道等の必要となり、この運搬手段によ
り1日のコンクリート打設量が決定される。生コンク
リートプラントから現地打設位置へ運搬するまでに時間
を要し、コンクリート品質が低下する。また、このコン
クリート品質低下を見込み、コンクリート強度を設計し
ている。深礎孔へのコンクリート打設中には、孔内に
作業員が必要となる。コンクリート打設準備、打設後
の洗浄、片付け等に手間を要する。
Among the above-mentioned prior arts, the method for forming a power transmission tower foundation has the following problems. Due to outdoor work, concrete cannot be cast in rainy weather. For transporting concrete to a steel tower placement point,
Helicopters and cableways are required, and the amount of concrete poured per day is determined by this transportation method. It takes time to transport from the ready-mixed concrete plant to the casting site, and the quality of concrete deteriorates. The concrete strength is designed in anticipation of the deterioration of concrete quality. While concrete is being cast into a deep foundation hole, workers are required inside the hole. Preparing for concrete placement, cleaning after placing, clearing, etc. are troublesome.

【0006】また、鉄筋配置において次の問題がある。
深礎孔の深さは、地上より20m程度あり、孔内に鉄
筋を入れ込む際、地上と孔内に作業員を配置する必要が
ある。孔内に入れた鉄筋を籠状に組み立てる作業に手
間を要する。
Further, there is the following problem in the arrangement of reinforcing bars.
The depth of the deep foundation hole is about 20 m above the ground, and it is necessary to arrange a worker on the ground and in the hole when inserting a reinforcing bar into the hole. It takes time and effort to assemble the rebar placed in the hole into a cage.

【0007】さらに、基礎体内部に空隙部を有する深礎
基礎の形成方法には、次の問題がある。(1) 空隙部を確
保する枠体の取り付け、撤去に手間を要する。(2) 空隙
部を確保する枠体の費用が高い。(3) 空隙部を確保する
枠体が周辺のコンクリート打設時に移動する。(4) コン
クリート打設回数が増加する。
Further, the method for forming a deep foundation having a void inside the foundation has the following problem. (1) It takes time to install and remove the frame that secures the gap. (2) The cost of the frame for securing the void is high. (3) The frame that secures the gap moves when the surrounding concrete is poured. (4) The number of concrete castings increases.

【0008】そこで、本発明の主たる課題(目的)は、
コンクリート打設において、天候に左右されず、コンク
リート品質の工場と均一化を図れ、孔内作業員の削減及
び作業の簡略化を図れる、深礎基礎用プレキャスト基礎
体を提供することにある。
Therefore, the main problems (objects) of the present invention are:
It is an object of the present invention to provide a precast foundation for a deep foundation, in which a concrete casting plant can be made uniform and the number of workers in a hole can be reduced and the operation can be simplified irrespective of the weather in concrete casting.

【0009】その他の課題(目的)は、鉄筋の配置にお
いて、配置人員の削減と作業の簡易化を図れる、深礎基
礎用プレキャスト基礎体を提供することにある。或い
は、空隙基礎体の形成において、枠体の省略、枠体周辺
コンクリートの省略を可能とする、深礎基礎用プレキャ
スト基礎体を提供することにある。
Another object (object) of the present invention is to provide a precast foundation for a deep foundation, which can reduce the number of staff and simplify the work in arranging reinforcing bars. Another object of the present invention is to provide a precast foundation for a deep foundation, in which a frame can be omitted and concrete around the frame can be omitted in forming a void foundation.

【0010】[0010]

【課題を解決するための手段】本発明により提供する深
礎基礎用プレキャスト基礎体は、予め決められた形状に
作成されたコンクリートブロックを積み上げ組み立て、
所定の基礎構造を構築してなるものである。
A precast foundation for a deep foundation provided by the present invention is constructed by stacking concrete blocks formed in a predetermined shape by stacking them.
It is constructed by building a predetermined basic structure.

【0011】実施態様として、コンクリートブロック
は、基礎体を構築した時にブロック群を一体化する鉄筋
を貫通可能とし、また、コンクリートブロックの組み立
てにより円筒状にして基礎体内部に空隙部を有せしめて
なる構造を提供する。
[0011] As an embodiment, the concrete block can be made to penetrate a reinforcing bar that integrates the blocks when the foundation is constructed, and the concrete block is made cylindrical by assembling the concrete block so as to have a void inside the foundation. To provide a structure.

【0012】また、コンクリートブロックは、セメント
モルタル等の流動体を縦横に流入・出できる貫通孔を有
せしめ、セメントモルタルの注入による基礎体の固結一
体化及び基礎体と掘削地盤との密着を図れる構造を提供
する。さらに、コンクリートブロックには、隣接するコ
ンクリートブロックに凹凸嵌合する突起または溝を有し
てなる構造を提供することができる。
Further, the concrete block has through holes through which a fluid such as cement mortar can flow in and out in a vertical and horizontal direction, and solidifies and integrates the foundation by injecting the cement mortar and adheres the foundation to the excavated ground. Provide a structure that can be achieved. Further, the concrete block can be provided with a structure having a projection or a groove that fits unevenly into the adjacent concrete block.

【0013】[0013]

【発明の実施の形態】図1〜図2は、本発明に係る深礎
基礎用プレキャスト基礎体の実施例にして、図1は送電
線用としての空隙部を有する深礎基礎用プレキャスト基
礎体を透視概略的に示し、図2はコンクリートブロック
の組み立て状況を透視状態で示している。
1 and 2 show an embodiment of a precast foundation for a deep foundation according to the present invention. FIG. 1 shows a precast foundation for a deep foundation having a gap for a transmission line. FIG. 2 is a perspective view schematically showing the assembling state of the concrete block.

【0014】この実施例の深礎基礎は、円弧状のコンク
リートブロック1を円筒状にして積み上げ組み立て、上
下のコンクリートブロックに鉄筋3を串刺し状態に貫通
して両端を緊張することにより、コンクリートブロック
群を一体化し、以て、空隙部4を有する基礎体2として
なるものである。空隙部4の大きさは、コンクリートブ
ロック1の組み立て数の変更で任意に設定できる。
The deep foundation of this embodiment is constructed by stacking circular arc-shaped concrete blocks 1 in a cylindrical shape, assembling them, piercing upper and lower concrete blocks with reinforcing bars 3 in a skewered state, and tensioning both ends of the concrete blocks. To form the base body 2 having the voids 4. The size of the gap 4 can be arbitrarily set by changing the number of assembling the concrete blocks 1.

【0015】コンクリートブロック1は、円を1/4に
分割した円弧状にして、周方向に3本の縦方向貫通孔5
を有する。そして、周方向に4個のコンクリートブロッ
クを組み合わせて円筒にし、上方向には周方向に45°
ずらして積み上げることにより周方向の継目が上下に連
ならないようにし、そして、何れの上下隣接コンクリー
トブロックにおいても、上下に連通する上側右サイドの
孔と下側左サイドの孔に鉄筋3を貫通し、最終的には上
下の両端からナット等で締め付けることにより、コンク
リートブロック群の一体化を図るのである。
The concrete block 1 is formed into an arc shape obtained by dividing a circle into quarters, and has three longitudinal through holes 5 in the circumferential direction.
Having. Then, four concrete blocks are combined in the circumferential direction into a cylinder, and 45 ° in the circumferential direction upward.
By shifting and stacking, the seam in the circumferential direction is not connected vertically, and in any of the upper and lower adjacent concrete blocks, the reinforcing bar 3 penetrates through the upper right side hole and the lower left side hole communicating vertically. Finally, the concrete blocks are integrated by tightening the upper and lower ends with nuts or the like.

【0016】上記のようなコンクリートブロックの積み
上げ組み立ては、鉄筋据え付け架台8上で鉄筋3をガイ
ドとして、掘削孔内に降ろし、積み上げるようにすれば
良い。この場合、コンクリートブロック1を、図4のよ
うに上下の端面に凹凸嵌合の可能な突起9と溝10を設
け、以て、コンクリートブロック1を降下させた時、目
的の位置となるように積み重ねることが容易になる。
The above-mentioned concrete blocks can be stacked and assembled by lowering them in the excavation hole and stacking them on the reinforcing bar mounting base 8 with the reinforcing bars 3 serving as guides. In this case, as shown in FIG. 4, the concrete block 1 is provided with projections 9 and grooves 10 which can be fitted into the upper and lower end faces so that the concrete block 1 can be lowered to a target position when the concrete block 1 is lowered. It becomes easy to stack.

【0017】コンクリートブロック1は、図3のように
セメントモルタルの注入が可能な貫通孔6や端部の溝7
を設け、積み上げ組み立て時にモルタルを注入すること
により、コンクリートブロック群の一体化を強化するこ
ともできる。
As shown in FIG. 3, the concrete block 1 has a through hole 6 and a groove 7 at an end into which cement mortar can be injected.
By injecting mortar at the time of stacking and assembling, the integration of the concrete block group can be enhanced.

【0018】鉄筋3の緊張は、市販の緊張ジャッキと固
定具で緊張状態を保持し、この状態で、コンクリートブ
ロック1と鉄筋3の隙間にセメントモルタルを流入し、
モルタル固結により、コンクリートブロックと鉄筋が一
体化した後、緊張固定具を外す。緊張する張力は、鉄塔
基礎に加わる設計引上げ力程度まで与えると良い。この
張力に応じ鉄筋3の径や、本数を調整するが、鉄筋3は
一般建設で主に採用されているPC鋼線に置き換えるこ
ともできる。
The tension of the reinforcing bar 3 is maintained in a tensioned state by a commercially available tensioning jack and a fixing tool. In this state, cement mortar flows into the gap between the concrete block 1 and the reinforcing bar 3,
After the concrete block and the rebar are integrated by mortar consolidation, the tension fixture is removed. It is recommended that the tension be applied up to the design pulling force applied to the tower foundation. The diameter and the number of the reinforcing bars 3 are adjusted according to the tension, but the reinforcing bars 3 can be replaced with PC steel wires mainly used in general construction.

【0019】コンクリートブロックの孔は、地盤に接触
する面にも貫通、またはブロック形状の変形で積み上げ
時に地盤側に空隙を与えるものとし、セメントモルタル
の注入で基礎体と掘削地盤の空隙を埋め、地盤との密着
を図ることができる。
The holes of the concrete block shall penetrate the surface in contact with the ground, or give a space to the ground side during stacking by deformation of the block shape, and fill the gap between the foundation and the excavated ground by injection of cement mortar. Adhesion with the ground can be achieved.

【0020】以上の構造の深礎基礎用プレキャスト基礎
体によれば、次のような効果が得られる。1.コンクリ
ート打設;天候にかかわらずコンクリートを運搬可
能、コンクリート品質の向上と均一化(コンクリート
ブロックは事前に工場にて生産)、孔内作業員の削
減、準備、洗浄、片付け作業の省略(現場での生コン
クリート打設回数が減少)。2.鉄筋配置;配置人員の
削減と作業の簡易化。3.空隙基礎体の形成;枠体の
省略、枠体周辺コンクリートの省略。
According to the precast foundation for a deep foundation having the above structure, the following effects can be obtained. 1. Concrete placement; can transport concrete regardless of the weather, improve and equalize concrete quality (concrete blocks are produced in advance at the factory), reduce the number of workers in the hole, omit preparation, cleaning and clearing work (on site) The number of ready-mixed concrete is reduced.) 2. Rebar arrangement; reduction of staffing and simplification of work. 3. Formation of void foundation; elimination of frame, elimination of concrete around frame.

【0021】[0021]

【発明の効果】以上説明したような本発明によれば、コ
ンクリート打設において、天候に左右されず、コンクリ
ート品質の工場と均一化を図れ、孔内作業員の削減及び
作業の簡略化を図れる、深礎基礎用プレキャスト基礎体
を提供するという所期の課題(目的)を達成することが
できる。
According to the present invention as described above, in concrete placing, the quality of concrete can be made uniform with the factory regardless of the weather, the number of workers in the hole can be reduced, and the work can be simplified. Thus, the intended problem (objective) of providing a precast foundation body for a deep foundation can be achieved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施例にして、空隙部を有する深礎基
礎用プレキャスト基礎体を透視状態で示す概略図。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a schematic view showing a precast foundation for a deep foundation having a void portion in a see-through state according to an embodiment of the present invention.

【図2】本発明の実施例にして、コンクリートブロック
により構築された深礎基礎用プレキャスト基礎体の組み
立て状況を透視状態で示す説明図。
FIG. 2 is an explanatory diagram showing a perspective view of an assembling state of a precast foundation for a deep foundation constructed of concrete blocks according to the embodiment of the present invention.

【図3】本発明の実施例にして、コンクリートブロック
の孔、溝の状況を示す斜視図。
FIG. 3 is a perspective view showing the state of holes and grooves in a concrete block according to the embodiment of the present invention.

【図4】本発明の実施例にして、コンクリートブロック
の凹凸の状況を示す斜視図。
FIG. 4 is a perspective view showing a state of irregularities of a concrete block according to the embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 コンクリートブロック 2 基礎体 3 鉄筋 4 空隙部 5 孔 6 モルタル貫通孔 7 溝 8 鉄筋据え付け架台 9 突起 10 溝 DESCRIPTION OF SYMBOLS 1 Concrete block 2 Foundation 3 Reinforcing bar 4 Void portion 5 Hole 6 Mortar through hole 7 Groove 8 Reinforcing bar mounting base 9 Protrusion 10 Groove

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】予め決められた形状に作成されたコンクリ
ートブロックを積み上げ組み立て、所定の基礎構造を構
築してなる、深礎基礎用プレキャスト基礎体。
1. A precast foundation for a deep foundation, wherein concrete blocks formed in a predetermined shape are piled up and assembled to construct a predetermined foundation structure.
【請求項2】コンクリートブロックは、基礎体を構築し
た時にブロック群を一体化する鉄筋を貫通可能である、
請求項1記載の深礎基礎用プレキャスト基礎体。
2. The concrete block is capable of penetrating a reinforcing bar that integrates the blocks when the foundation is constructed.
A precast foundation for a deep foundation as claimed in claim 1.
【請求項3】コンクリートブロックの組み立てにより円
筒状にして基礎体内部に空隙部を有せしめてなる、請求
項1記載の深礎基礎用プレキャスト基礎体。
3. The precast foundation for a deep foundation foundation according to claim 1, wherein the concrete block is formed into a cylindrical shape by assembling the concrete block so that a void portion is provided inside the foundation.
【請求項4】コンクリートブロックは、セメントモルタ
ル等の流動体を縦横に流入・出できる貫通孔を有してな
る、請求項1記載の深礎基礎用プレキャスト基礎体。
4. The precast foundation for a deep foundation according to claim 1, wherein the concrete block has a through hole through which a fluid such as cement mortar can flow in and out in a vertical and horizontal direction.
【請求項5】コンクリートブロックには、隣接するコン
クリートブロックに凹凸嵌合する突起または溝を有して
なる、請求項1記載の深礎基礎用プレキャスト基礎体。
5. The precast foundation for a deep foundation according to claim 1, wherein the concrete block has a projection or a groove which fits unevenly with an adjacent concrete block.
JP29647696A 1996-11-08 1996-11-08 Precast foundation for deep foundation Pending JPH10140586A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29647696A JPH10140586A (en) 1996-11-08 1996-11-08 Precast foundation for deep foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29647696A JPH10140586A (en) 1996-11-08 1996-11-08 Precast foundation for deep foundation

Publications (1)

Publication Number Publication Date
JPH10140586A true JPH10140586A (en) 1998-05-26

Family

ID=17834056

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29647696A Pending JPH10140586A (en) 1996-11-08 1996-11-08 Precast foundation for deep foundation

Country Status (1)

Country Link
JP (1) JPH10140586A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108914718A (en) * 2018-06-07 2018-11-30 中铁二院工程集团有限责任公司 High-speed railway reinforced earth bulkhead roadbed contact net basic preformed hole construction and its construction method
CN112012557A (en) * 2020-08-28 2020-12-01 河南鼎力杆塔股份有限公司 Multifunctional concrete balancing weight and preparation device and method thereof
JP2021188354A (en) * 2020-05-29 2021-12-13 東京製綱株式会社 Precast prestressed concrete foundation structure and its construction method
CN114960719A (en) * 2022-06-28 2022-08-30 中国电建集团西北勘测设计研究院有限公司 An assembled ring foundation and its assembly method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108914718A (en) * 2018-06-07 2018-11-30 中铁二院工程集团有限责任公司 High-speed railway reinforced earth bulkhead roadbed contact net basic preformed hole construction and its construction method
CN108914718B (en) * 2018-06-07 2023-11-17 中铁二院工程集团有限责任公司 Construction method for foundation preformed hole structure of high-speed railway reinforced earth retaining wall subgrade contact net
JP2021188354A (en) * 2020-05-29 2021-12-13 東京製綱株式会社 Precast prestressed concrete foundation structure and its construction method
CN112012557A (en) * 2020-08-28 2020-12-01 河南鼎力杆塔股份有限公司 Multifunctional concrete balancing weight and preparation device and method thereof
CN114960719A (en) * 2022-06-28 2022-08-30 中国电建集团西北勘测设计研究院有限公司 An assembled ring foundation and its assembly method
CN114960719B (en) * 2022-06-28 2024-01-05 中国电建集团西北勘测设计研究院有限公司 Assembled annular foundation and assembling method thereof

Similar Documents

Publication Publication Date Title
KR101302743B1 (en) Phc pile and its using the same soil cement wall construction methode
US11976431B2 (en) Methods for constructing tensionless concrete pier foundations and foundations constructed thereby
JP2002256573A (en) Existing foundation reinforced steel tower foundation and its construction method
CN115059112B (en) Assembled retaining wall structure and construction method for existing roadbed width
JP4819835B2 (en) Offshore structure and construction method of offshore structure
KR100787178B1 (en) Lightweight steel frame base plate and construction method
JP2008208533A (en) Caisson and its construction method
JPH0996197A (en) Support wall structure and construction method
JPH10140586A (en) Precast foundation for deep foundation
KR101181619B1 (en) Building method of high wall block for large scale underground structure using earth anchor represtressing
KR100974513B1 (en) Caisson type pile method
JP4159148B2 (en) Construction method of shaft
KR100573371B1 (en) Construction method of cast-in-place pile applied with perforated steel pipe
JP2001303592A (en) Method for installing and fixing block
JPS6354093B2 (en)
KR20010019079A (en) Precast steel Plate &Concrete Pile Structure of Semi Down Wall Construction System
JPH1077644A (en) Earthquake resisting pile foundation construction method
JP4968676B2 (en) Pile foundation reinforcement method using increased piles
JP3806069B2 (en) Seismic isolation method from the ground of existing buildings
JP2000240075A (en) Penetration type retaining wall
JPH10231527A (en) Deep foundation method for steel towers
CN220079740U (en) Stable tunnel anchor
JP6534026B2 (en) Seismic isolation building and its construction method
JPH02190517A (en) Retaining wall structure
JPH1061266A (en) Mounting method of wall and wall construction