JPH11117323A - Construction method of foundation structure - Google Patents
Construction method of foundation structureInfo
- Publication number
- JPH11117323A JPH11117323A JP28572597A JP28572597A JPH11117323A JP H11117323 A JPH11117323 A JP H11117323A JP 28572597 A JP28572597 A JP 28572597A JP 28572597 A JP28572597 A JP 28572597A JP H11117323 A JPH11117323 A JP H11117323A
- Authority
- JP
- Japan
- Prior art keywords
- footing
- underground
- underground beam
- beams
- footings
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 28
- 238000009415 formwork Methods 0.000 claims description 10
- 238000000034 method Methods 0.000 claims description 6
- 230000003014 reinforcing effect Effects 0.000 claims description 4
- 238000009412 basement excavation Methods 0.000 description 26
- 239000004576 sand Substances 0.000 description 12
- 239000013049 sediment Substances 0.000 description 11
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 4
- 238000009434 installation Methods 0.000 description 3
- 230000002787 reinforcement Effects 0.000 description 3
- 238000005266 casting Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Foundations (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】この発明は、建築物の土台と
なる基礎構造の施工方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a foundation structure serving as a foundation of a building.
【0002】[0002]
【従来の技術】従来、建築物の基礎構造は図7ないし図
9に示すように地表1をほぼ逆台錐形に掘削してフーチ
ング用掘削部2を形成し、この掘削部2の底面の地盤3
に直接又はラップルコンクリート4を介してフーチング
5を設けている。このフーチング5はベース部6と柱部
7とからなり、このフーチング5を図9に示すように
縦,横に複数個整列して並べ、このように整列されたフ
ーチング間を地中梁8によって橋絡して一体化し、フー
チング用掘削部2及び地中梁8を形成するために地表1
に設けた断面逆台形状の地中梁用掘削部11を埋め戻す
ことにより、基礎構造として形成している。2. Description of the Related Art Conventionally, as shown in FIGS. 7 to 9, a foundation structure of a building is formed by excavating a ground surface 1 into a substantially inverted truncated cone shape to form a footing excavation portion 2. Ground 3
Is provided with a footing 5 directly or via a lap concrete 4. The footing 5 is composed of a base portion 6 and a column portion 7, and a plurality of the footings 5 are arranged vertically and horizontally as shown in FIG. In order to form a footing excavation part 2 and an underground beam 8 by bridging and integrating,
Is formed as a basic structure by backfilling the underground beam excavation portion 11 having an inverted trapezoidal cross-section provided in.
【0003】上記フーチング5及び地中梁8は何れも、
その内部に鉄筋が一体化されており、フーチング5の内
部の鉄筋と地中梁8の内部の鉄筋とは溶接によって一体
化されている。このフーチング5と地中梁8の成形に際
しては、その内部の鉄筋を配筋した後、型枠の内部にコ
ンクリートを打設することにより、フーチング5及び地
中梁8が一体なものとして完成する。上記地中梁8及び
フーチング5の上には通常スラブが設けられ、そしてフ
ーチング5の柱部7の上に建築物の柱が建てられること
になる。[0003] Both the footing 5 and the underground beam 8 are
A reinforcing steel is integrated therein, and the reinforcing steel inside the footing 5 and the reinforcing steel inside the underground beam 8 are integrated by welding. In forming the footing 5 and the underground beam 8, after arranging reinforcing steel therein, concrete is poured into the inside of the formwork to complete the footing 5 and the underground beam 8. . A slab is usually provided on the underground beam 8 and the footing 5, and a column of a building is to be built on the column 7 of the footing 5.
【0004】[0004]
【発明が解決しようとする課題】しかし、従来は図9に
示すように施工に際してはフーチング用掘削部2及び地
中梁用掘削部11を先に掘削して配筋してから型枠をセ
ットしてコンクリートを打設して、フーチング5,地中
梁8を形成するのであるが、これによれば上記掘削部
2,11で囲まれる閉ループLが形成されることにな
り、この閉ループLの内部にコンクリートミキサー車が
搬入することができないので、フーチング5及び地中梁
8のコンクリート打設のためには閉ループLの外側から
行う必要がある。しかし、外側に位置するフーチング及
び地中梁については比較的容易にコンクリートを打設す
ることができるのであるが、その内部側のフーチング5
W,地中梁8Wについてはコンクリートミキサー車から
ホースを延長して、このホースによってコンクリートを
施工現場の内部側に送り込んで手作業で打設しなければ
ならないので、作業者にとって負担となり、また、作業
の工期が長くなってしまうという欠点を有していた。However, in the prior art, as shown in FIG. 9, the excavating section 2 for footing and the excavating section 11 for underground beams are excavated first and arranged in a construction, and then the formwork is set. Then, concrete is cast and the footing 5 and the underground beam 8 are formed. According to this, a closed loop L surrounded by the excavated portions 2 and 11 is formed. Since the concrete mixer truck cannot be carried into the inside, the concrete placing of the footing 5 and the underground beam 8 needs to be performed from outside the closed loop L. However, concrete can be cast relatively easily on the footing and the underground beam located on the outside.
As for the W and the underground beam 8W, the hose must be extended from the concrete mixer truck, and concrete must be sent into the inside of the construction site by this hose and must be cast by hand. There was a disadvantage that the work period was long.
【0005】この発明は上記課題を解決するためになさ
れたもので、コンクリートミキサー車あるいは重機等が
フーチングと地中梁で囲まれるべき領域にまで入ること
ができるようにして上記欠点を除去するものである。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and an object of the present invention is to eliminate the above-mentioned drawbacks by allowing a concrete mixer truck or heavy equipment to enter a region to be surrounded by a footing and an underground beam. It is.
【0006】[0006]
【課題を解決するための手段】この請求項1に係る発明
は、地中梁とフーチングによる閉ループが生じないよう
に、少なくとも一つの地中梁を残して他の地中梁とフー
チングを施工してから、上記残りの地中梁を最後に施工
するようにして、この残りの地中梁が施工される前にお
いて、その内部にコンクリートミキサー車が自由に出入
りできるようにするものである。According to the first aspect of the present invention, at least one underground beam is left and footing is performed so that a closed loop due to the underground beam and footing does not occur. After that, the remaining underground beams are constructed last, so that the concrete mixer truck can freely enter and exit before the remaining underground beams are constructed.
【0007】この請求項2に係る発明は、地中梁として
プレキャストを用いて構成し、土砂の埋め戻しを早期に
行えるようにするものである。[0007] The invention according to claim 2 is to use precast as an underground beam, so that backfill of earth and sand can be performed at an early stage.
【0008】[0008]
実施の形態1.図1ないし図6は本発明による基礎構造
の施工方法の一実施の形態を示す図であり、各図におい
て、図7ないし図9と同じものは同一符号を用いてい
る。本発明では、図1,図2に示すように基礎構造の施
工に際しては、縦,横に整列して並べられるフーチング
の中でコーナー部に位置する一つのフーチング5aを起
点として、このフーチング5aから順次S字状を描くよ
うに隣のフーチング及び地中梁を順次施工して行くもの
である。具体的にはフーチング5a及び、このフーチン
グ5aに接続される地中梁8a,8aが完成すると、次
のフーチング5b及び、このフーチング5bに接続され
る地中梁8b,8bを施工し、次に、つぎのフーチング
5c,地中梁8cを施工していく。Embodiment 1 FIG. FIGS. 1 to 6 are views showing an embodiment of a method for constructing a foundation structure according to the present invention. In each of the drawings, the same reference numerals are used for the same components as those in FIGS. In the present invention, as shown in FIGS. 1 and 2, when the foundation structure is constructed, one footing 5a located at a corner of the footing arranged in a vertical and horizontal arrangement is used as a starting point. The adjacent footing and underground beam are sequentially constructed so as to sequentially draw an S-shape. Specifically, when the footing 5a and the underground beams 8a, 8a connected to the footing 5a are completed, the next footing 5b and the underground beams 8b, 8b connected to the footing 5b are constructed, and then, Next, the footing 5c and the underground beam 8c will be constructed.
【0009】この施工方法によれば、フーチング5dと
フーチング5eとの間及びフーチング5eとフーチング
5fとの間が開放された状態となるので、この開放され
た部分Qを介して外からコンクリートミキサー車を搬入
できるので、フーチング5a,5b,5cを成形するた
めの型枠にコンクリートを容易に打設することができ
る。According to this construction method, the space between the footing 5d and the footing 5e and the space between the footing 5e and the footing 5f are in an open state. Can be carried in, and concrete can be easily poured into a mold for forming the footings 5a, 5b, 5c.
【0010】本実施の形態では、地中梁8a,8b,8
cについては工場などで予め製造しておいたもの、即
ち、プレキャストを用いることとし、このプレキャスト
を工事現場まで運搬した後、地中梁用掘削部11に設置
した後に、すぐに埋め戻すようにするものである。この
プレキャストの設置は重機を用い、上記開放された部分
Qから重機を搬入させて行う。In this embodiment, the underground beams 8a, 8b, 8
About c, what was manufactured beforehand in a factory etc., ie, a precast is used, and after transporting this precast to a construction site, after installing it in the underground beam excavation part 11, immediately backfill it. Is what you do. The installation of the precast is performed by using a heavy machine and carrying the heavy machine from the open portion Q.
【0011】このように一部の部分Qを開放した状態で
基礎構造を施工した後、図2に示すように上記開放され
た部分Qを掘削してプレキャストからなる地中梁8d,
8eを設置して、この地中梁8d,8eの両端のフーチ
ング5d,5e,5fを成形するようにし、このような
成形を繰り返すことにより、即ち、蛇行するような状態
でフーチング及び地中梁を成形することにより基礎構造
として完成する。After the foundation structure is constructed with the part Q open as described above, the open part Q is excavated and the precast underground beam 8d, as shown in FIG.
8e, and the footings 5d, 5e, 5f at both ends of the underground beams 8d, 8e are formed. By repeating such forming, that is, the footing and the underground beams are formed in a meandering state. To complete the basic structure.
【0012】次に、フーチングの成形及びプレキャスト
から成る地中梁両端のフーチングへの一体化について図
3ないし図6を用いて説明する。まず、地表には墨出し
と称するフーチング及び地中梁の位置決め用の目印を付
記する。この場合、上記地中梁8については予め工場等
で生産されたプレキャストを用いるものとする。上記墨
出を行ったフーチングの場所を図3に示すように掘削し
て逆台錐形のフーチング用掘削部2を形成し、次に、ラ
ップルコンクリート4を地盤3に打設した後、フーチン
グを形成するべき部分の外周にリング状の土砂止め板9
を垂直に立てる。この土砂止め板9には内側に倒れない
ように図外の補強材が設けられ、また内部に出入りでき
るように梯子が設置される。次に、土砂止め板9の外側
の空間に掘削時に地表1に堆積しておいた堆積土砂1a
を投入して埋め戻しを行う。Next, the formation of the footing and the integration of both ends of the underground beam into the footing, which are made by precasting, will be described with reference to FIGS. First, a marking for footing called "inking out" and positioning of an underground beam are added to the ground surface. In this case, for the underground beam 8, a precast previously produced in a factory or the like is used. As shown in FIG. 3, the footing site where the above-mentioned summing was performed was excavated as shown in FIG. 3 to form an inverted frustum-shaped excavated portion 2 for footing. A ring-shaped sediment stop plate 9 is provided around the outer periphery of the portion to be formed.
Upright. A reinforcement member (not shown) is provided on the earth and sand stopper 9 so as not to fall inward, and a ladder is installed so as to be able to enter and exit the interior. Next, the sediment 1a deposited on the surface 1 at the time of excavation in the space outside the sediment stop plate 9
And backfill.
【0013】図4は、このように埋め戻しを行った埋め
戻し土砂1bが土砂止め板9の外側の部分に堆積された
状態を示す。上記土砂止め板9の内側にはフーチング用
の鉄筋5が配筋され、フーチング用の型枠10が設けら
れる。FIG. 4 shows a state in which the backfilled earth and sand 1b thus backfilled is deposited on the outer portion of the earth and sand stopper plate 9. Reinforcing bars 5 for footing are arranged inside the earth and sand stopper plate 9, and a formwork 10 for footing is provided.
【0014】また、フーチングに接続すべき地中梁の設
置場所に対応して地表1を掘削して地中梁用掘削部11
を形成し、ついで、地中梁に対応する上記土砂止め板9
の上部の一部をU字状にカットして、カット部12を設
け、ここに地中梁を設置できるようにする。In addition, the ground surface 1 is excavated corresponding to the installation location of the underground beam to be connected to the footing, and the underground beam excavating portion 11 is formed.
, And then the earth and sand stopper plate 9 corresponding to the underground beam
Is cut into a U-shape to provide a cut portion 12, where an underground beam can be installed.
【0015】次に、図5に示すように地中梁8を上記地
中梁用掘削部11及びカット部12の内部にセットし、
地中梁8の先端から突出する地中梁主筋8Mを、上記鉄
筋5Mに接近する位置に位置決めするものとする。次
に、上記地中梁用掘削部11を地表にあらかじめ堆積し
てある埋め戻し土砂8Kで埋め戻した後、上記地中梁主
筋8Mと型枠10から上方に突出する柱用鉄筋とを溶接
し、取り合い部を配筋した後に、上記型枠10の内部に
コンクリートを打設することによりフーチングを成形す
る。この場合、埋め戻し土砂1bが存在するので、コン
クリートミキサー車を型枠10が設置される空間まで比
較的容易に近づけることができるので、コンクリートの
打設を容易に行うことができる。コンクリートミキサー
車は前述の開放された部分Qを介して工事現場の中に搬
入できる。コンクリート打設後は型枠10を取り払って
土砂止め板9で囲まれる内部に、さらに外部の土砂を投
入して埋め戻すことで一個のフーチング及び、これに接
続される地中梁の施工が完成する。Next, as shown in FIG. 5, the underground beam 8 is set inside the underground beam excavation section 11 and the cut section 12,
The underground beam main reinforcement 8M protruding from the tip of the underground beam 8 is positioned at a position approaching the reinforcing bar 5M. Next, after the underground beam excavation portion 11 is backfilled with backfilled soil 8K previously deposited on the surface of the ground, the underground beam main reinforcement 8M and the column reinforcing bar projecting upward from the formwork 10 are welded. Then, after arranging the connecting portions, concrete footing is formed by casting concrete inside the formwork 10. In this case, since the backfill soil 1b is present, the concrete mixer truck can be relatively easily brought close to the space where the formwork 10 is installed, so that concrete can be easily poured. The concrete mixer truck can be carried into the construction site via the open part Q described above. After the concrete is cast, the formwork 10 is removed and the inside surrounded by the sediment stop plate 9 is further filled with external earth and sand to backfill, thereby completing one footing and the construction of an underground beam connected to this. I do.
【0016】上記図3ないし図6に示す工程を用いて図
1に示すように、まず、土砂止め板9aを設置してフー
チング5a及び地中梁8a,8aを設けることとする。
なお、本実施の形態ではフーチング用掘削部2aを形成
したときには、フーチング5aが接続される地中梁8
a,8aの他端側のフーチング5b,5fを形成するた
めのフーチング用掘削部2b,2fも掘削によって予め
形成して、ここに土砂止め板9b,9fを設け、さら
に、この土砂止め板9b,9fの外側の空間を堆積土砂
1aで埋めるようにし、さらに土砂止め板9b,9fの
上端にU字状のカット部12を設けるようにすれば、地
中梁8a,8aを何らの障害なく、あらかじめ設けてお
いた地中梁用掘削部11a,11aに水平に設置するこ
とができる。次に、フーチング5b及び地中梁8b,8
bの施工に際しては地中梁8b,8bを設置するための
掘削部11b,11bを設けておき、また、この地中梁
8b,8bの他端側のフーチング用掘削部2c,2eも
設けておき、この掘削部2c,2eにおける土砂止め板
9c,9eの上端にU字状のカット部12を設けて、こ
の状態でプレキャストの地中梁8b,8bを外から搬入
して設置し、この地中梁8b,8bを埋め戻した後に、
上述した工程と同様フーチング5bのためのコンクリー
トを打設すればよい。As shown in FIG. 1 by using the steps shown in FIGS. 3 to 6, first, a sediment stop plate 9a is installed to provide a footing 5a and underground beams 8a, 8a.
In the present embodiment, when the footing excavation part 2a is formed, the underground beam 8 to which the footing 5a is connected is formed.
The footing excavations 2b and 2f for forming the footings 5b and 5f on the other end side of the a and 8a are also formed in advance by excavation, and sediment stop plates 9b and 9f are provided here. , 9f is filled with the sediment 1a, and the U-shaped cut portion 12 is provided at the upper end of the sediment stop plates 9b, 9f, so that the underground beams 8a, 8a can be installed without any obstacle. , Can be installed horizontally in the underground beam excavation sections 11a, 11a provided in advance. Next, the footing 5b and the underground beams 8b, 8
In the construction of b, excavation parts 11b, 11b for installing the underground beams 8b, 8b are provided, and footing excavation parts 2c, 2e on the other end side of the underground beams 8b, 8b are also provided. A U-shaped cut portion 12 is provided at the upper end of the sediment stop plates 9c and 9e in the excavated portions 2c and 2e, and in this state, precast underground beams 8b and 8b are carried in from outside and installed. After backfilling the underground beams 8b, 8b,
The concrete for the footing 5b may be cast in the same manner as in the above-described process.
【0017】次に、フーチング5cの成形に際しては、
地中梁8cのための地中梁用掘削部11cを設けるので
あるが、この地中梁8cの他端側のフーチング5dを形
成するための掘削部2dを設けて上述した工程と同様に
地中梁8cをセットし、フーチング掘削部2c内の型枠
内にコンクリートを打設してフーチング5cを形成する
ことができる。Next, when forming the footing 5c,
An underground beam excavation portion 11c for the underground beam 8c is provided. An excavation portion 2d for forming a footing 5d at the other end of the underground beam 8c is provided, and the underground beam is excavated similarly to the above-described process. The footing 5c can be formed by setting the center beam 8c and placing concrete in the formwork in the footing excavation part 2c.
【0018】次に、図2に示すように掘削部2dに対し
て地中梁8dを橋絡し、また、掘削部2iを設けて、そ
の間に地中梁8dを橋絡し、フーチング5dをコンクリ
ートの打設により成形し、次に、フーチング用掘削部2
e,2f間に地中梁8eを橋絡し、さらに、フーチング
用掘削部2e,2h間にも地中梁8eを梁絡してコンク
リートを打設することにより、フーチング5e,5fを
完成する。このように蛇行するような状態で順次フーチ
ングを成形していく。Next, as shown in FIG. 2, the underground beam 8d is bridged to the excavated portion 2d, and the excavated portion 2i is provided, and the underground beam 8d is bridged therebetween, and the footing 5d is connected. It is formed by casting concrete, and then excavated for footing 2
The footing 5e, 5f is completed by bridging the underground beam 8e between e and 2f, and bridging the underground beam 8e between the footing excavations 2e, 2h and placing concrete. . The footing is sequentially formed in such a meandering state.
【0019】本実施の形態によれば、図1に示すように
フーチング5a,5b及び地中梁8a,8bで囲まれる
空間は閉ループとはならず一部が開放された状態とな
り、このためフーチング掘削部2a,地中梁掘削部11
a,11aの掘削作業を施工現場の内部側からも行うこ
とができるので、掘削の作業を迅速に行うことができ
る。また、開放された部分Qを介して施工現場の内部側
にコンクリートミキサー車が入り込めるので、その中央
側に位置する例えばフーチング用掘削部2e,2hにつ
いてもコンクリートを容易に打設することができ、従来
のように施工現場の外側からホースを引き回してコンク
リートを打設するという煩雑な手間を省くことができ作
業者の負担を軽減することができ、また工期を短縮でき
る。また、施工現場の内部に重機が入り込めるので、プ
レキャストの地中梁を内部側から所定の場所に容易に搬
入して設置することができるので、プレキャストの地中
梁を用いたことによる問題は何ら生じない。According to the present embodiment, as shown in FIG. 1, the space surrounded by the footings 5a and 5b and the underground beams 8a and 8b does not form a closed loop but is partially open, so that the footing is formed. Excavation part 2a, underground beam excavation part 11
Since the excavation operations a and 11a can be performed from the inside of the construction site, the excavation operation can be performed quickly. Further, since the concrete mixer truck can enter the inside of the construction site through the opened portion Q, concrete can be easily poured into the excavating portions 2e and 2h for the footing located at the center side thereof, for example. As in the related art, the troublesome work of laying a hose from outside the construction site and placing concrete can be omitted, the burden on the operator can be reduced, and the construction period can be shortened. In addition, since heavy equipment can enter the inside of the construction site, the precast underground beam can be easily carried into the specified place from the inside and installed.There is no problem with using the precast underground beam. Does not occur.
【0020】また、本実施の形態では次の効果を奏す
る。従来、狭い敷地で工事を行う場合には掘削して得た
土砂を仮置きする場所がなく、このため、一般的には施
工現場から離れた別な場所にトラックで運搬して廃棄処
分することになる。そのため、躯体構築後埋め戻しを行
う時には新たに埋め戻し用の土砂を購入することにな
り、処分するコストだけでなく、購入するコストも必要
となるので、工事費用の増大につながるという欠点があ
った。しかし、本実施の形態によれば、フーチングを形
成するための必要な空間を残して土砂止め板の回りをす
ぐに埋め戻し、また、プレキャストの地中梁を使用する
ことにより早期の埋め戻しを可能としている。そのた
め、場外処分に関わる費用(運搬処分コスト及び購入土
砂のコスト)低減に寄与することが可能となる。The present embodiment has the following effects. Conventionally, when performing construction on a narrow site, there is no place to temporarily store the excavated earth and sand.Therefore, in general, transport by truck to another place away from the construction site and dispose of it by truck become. Therefore, when performing backfilling after building the frame, it is necessary to purchase new earthfill for backfilling, which requires not only disposal costs but also purchasing costs, which leads to an increase in construction costs. Was. However, according to the present embodiment, the space required for forming the footing is immediately rebuilt around the sediment retaining plate, leaving a necessary space for forming the footing, and the early backfilling is performed by using a precast underground beam. It is possible. Therefore, it is possible to contribute to a reduction in costs related to off-site disposal (transportation disposal cost and cost of purchased earth and sand).
【0021】また、本実施の形態によれば、S字状に沿
うように順番に工事を進めて行くので、コンクリートミ
キサー車,重機等を工事現場まで搬入できるので、効率
的にコンクリートの打設、掘削土砂の早期埋め戻し、プ
レキャストの地中梁の設置が可能となる。Further, according to the present embodiment, since the construction proceeds in order along the S-shape, the concrete mixer truck, heavy equipment and the like can be carried to the construction site, so that concrete can be efficiently poured. In this way, early backfill of excavated earth and sand and installation of precast underground beams are possible.
【0022】また、本実施の形態では、プレキャストの
地中梁を用いたことにより、次の効果を奏する。即ち、
狭い敷地で工事を行う場合掘削する場所が隣地に近接し
た作業となる。そのために近接した場所では敷地境界線
に近接して山留めを設けるのが一般的であるが、本実施
の形態のように基礎部分に土砂止め板を設けて早い時期
に埋め戻し、地中梁も掘削したらプレキャストの地中梁
をセットした後、早期に埋め戻すことから近接して山留
めを設ける場合にも軽微な山留めでよくなり、場合によ
っては山留め自体が省略できることにもつながる。In this embodiment, the following effects are obtained by using the precast underground beams. That is,
When performing construction on a narrow site, the excavation site is an operation that is close to the adjacent land. For this purpose, it is common to provide a landscaping near the site boundary line in a place close to the site, but as in the present embodiment, provide a sand stopper on the foundation and backfill it early, After excavation, the precast underground beam is set and then backfilled at an early stage. Therefore, even when a mountain stay is to be provided in the vicinity, a small mountain stay can be used, and in some cases, the mountain stay itself can be omitted.
【0023】[0023]
【発明の効果】本発明によれば、地中梁とフーチングに
よる閉ループが生じないように、少なくとも一つの地中
梁を残して他の地中梁とフーチングを施工してから、上
記残りの地中梁を最後に施工するようにしたので、施工
現場の内部にコンクリートミキサー車等が容易に入るこ
とができるので、施工を作業者に負担を与えることなく
容易に行え、しかも早期に行うことができる。According to the present invention, at least one underground beam is left and footing is applied to another underground beam so that a closed loop due to the underground beam and footing does not occur. Since the center beam is constructed last, a concrete mixer truck etc. can easily enter the inside of the construction site. it can.
【0024】請求項2の発明によれば、地中梁をプレキ
ャストを用いてフーチングに一体化するようにしたの
で、プレキャストを埋めるためのプレキャスト用掘削部
の埋め戻しを迅速に行うことができ、これによっても工
期を短縮できる。According to the second aspect of the present invention, the underground beam is integrated with the footing using the precast, so that the precast excavation portion for filling the precast can be quickly backfilled, This can also shorten the construction period.
【図1】 この発明の基礎構造の施工方法の一実施の形
態を示す平面図である。FIG. 1 is a plan view showing an embodiment of a method for constructing a foundation structure according to the present invention.
【図2】 この発明の一実施の形態を示す平面図であ
る。FIG. 2 is a plan view showing an embodiment of the present invention.
【図3】 この発明の一実施の形態を示す断面図であ
る。FIG. 3 is a sectional view showing one embodiment of the present invention.
【図4】 この発明の一実施の形態を示す断面図であ
る。FIG. 4 is a sectional view showing an embodiment of the present invention.
【図5】 この発明の一実施の形態を示す断面図であ
る。FIG. 5 is a sectional view showing an embodiment of the present invention.
【図6】 この発明の一実施の形態を示す断面図であ
る。FIG. 6 is a sectional view showing an embodiment of the present invention.
【図7】 従来のフーチングの施工例を示す斜視図であ
る。FIG. 7 is a perspective view showing a construction example of a conventional footing.
【図8】 従来のフーチング及び地中梁の施工例を示す
断面図である。FIG. 8 is a cross-sectional view showing a construction example of a conventional footing and underground beam.
【図9】 従来のフーチング及び地中梁の施工例を示す
平面図である。FIG. 9 is a plan view showing an example of construction of a conventional footing and underground beam.
1 地表、1a 堆積土砂、2 フーチング用掘削部、
3 地盤、4 ラップルコンクリート、5M 鉄筋、6
ベース部、7 柱部、8 地中梁、9 土砂止め板、
10 型枠、11 地中梁用掘削部、12 カット部。1 ground, 1a sediment, 2 footing excavation,
3 Ground, 4 Rapple concrete, 5M steel bars, 6
Base part, 7 pillar part, 8 underground beam, 9 earth and sand stopper,
10 Formwork, 11 Underground beam excavation section, 12 Cut section.
Claims (2)
する地中梁よりなる基礎構造の施工方法において、上記
地中梁とフーチングとによる閉ループが生じないよう
に、少なくとも一つの地中梁を残して他の地中梁とフー
チングを施工してから、上記残りの地中梁を最後に施工
するようにしたことを特徴とする基礎構造の施工方法。1. A method for constructing a foundation structure comprising underground beams bridging between vertical and horizontal footings, wherein at least one underground beam is provided so that a closed loop due to the underground beams and the footing does not occur. A footing with another underground beam, leaving the underground beam last, and then finally installing the remaining underground beam.
クリートを打設することにより形成し、地中梁はプレキ
ャストを用いて当該フーチングに一体化したことを特徴
とする請求項1に記載の基礎構造の施工方法。2. The footing according to claim 1, wherein the footing is formed by arranging a reinforcing bar and placing concrete in a formwork, and the underground beam is integrated with the footing by using a precast. Construction method of foundation structure.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP28572597A JPH11117323A (en) | 1997-10-17 | 1997-10-17 | Construction method of foundation structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP28572597A JPH11117323A (en) | 1997-10-17 | 1997-10-17 | Construction method of foundation structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH11117323A true JPH11117323A (en) | 1999-04-27 |
Family
ID=17695236
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP28572597A Pending JPH11117323A (en) | 1997-10-17 | 1997-10-17 | Construction method of foundation structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH11117323A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002146960A (en) * | 2000-11-17 | 2002-05-22 | Shimizu Corp | Building floor structure |
| JP2020070627A (en) * | 2018-10-31 | 2020-05-07 | 戸田建設株式会社 | Joint structure of pile and foundation concrete portion, precast concrete body, and construction method |
| JPWO2023175836A1 (en) * | 2022-03-17 | 2023-09-21 |
-
1997
- 1997-10-17 JP JP28572597A patent/JPH11117323A/en active Pending
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002146960A (en) * | 2000-11-17 | 2002-05-22 | Shimizu Corp | Building floor structure |
| JP2020070627A (en) * | 2018-10-31 | 2020-05-07 | 戸田建設株式会社 | Joint structure of pile and foundation concrete portion, precast concrete body, and construction method |
| JPWO2023175836A1 (en) * | 2022-03-17 | 2023-09-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH09242067A (en) | Building method for cast-in-place concrete pile | |
| JP4881555B2 (en) | Construction method of underground structure | |
| JP2004232328A (en) | Structure of semi-precast arch culvert and its construction method | |
| JP3625892B2 (en) | Construction method of underground structure using precast concrete column | |
| JP2004027609A (en) | Construction method of underground structure and underground structure | |
| JPH11117323A (en) | Construction method of foundation structure | |
| JP3760304B2 (en) | Building foundation construction method | |
| JP4611113B2 (en) | Integrated construction method of pile and column | |
| JP3037912B2 (en) | Power transmission tower foundation construction method and pillar formwork | |
| JPH07243269A (en) | How to build an underground parking lot | |
| JPH08253947A (en) | Installation method of form support for reverse casting | |
| JPH10299003A (en) | Foundation method using precast concrete members | |
| JPH06193084A (en) | Construction method for undeground structure | |
| JP7204228B2 (en) | Underground beam construction method | |
| KR102656370B1 (en) | Underground structure capable of forming a supporting point of a molded beam and its construction method | |
| JPH04293824A (en) | Construction method for large span underground structure | |
| JPH10131300A (en) | Construction method of building by preceding construction of steel frame | |
| JPH08291526A (en) | How to build an underground structure | |
| JPH0874265A (en) | Precast concrete foundation column and its manufacturing method | |
| JPS6319642B2 (en) | ||
| JPH10195886A (en) | Foundation construction method | |
| JP2006322179A (en) | Integrated construction method of pile and column | |
| JPH04347214A (en) | Pc pile anchoring precast concrete base and pile foundation method | |
| JPH02248527A (en) | Constructing foundation structure | |
| JP2000144757A (en) | Preparation of foundation for building |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A131 | Notification of reasons for refusal |
Effective date: 20041026 Free format text: JAPANESE INTERMEDIATE CODE: A131 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20041116 |
|
| A131 | Notification of reasons for refusal |
Effective date: 20050125 Free format text: JAPANESE INTERMEDIATE CODE: A131 |
|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20050524 |