JPH11344591A - Lining storage tank construction method - Google Patents

Lining storage tank construction method

Info

Publication number
JPH11344591A
JPH11344591A JP10152510A JP15251098A JPH11344591A JP H11344591 A JPH11344591 A JP H11344591A JP 10152510 A JP10152510 A JP 10152510A JP 15251098 A JP15251098 A JP 15251098A JP H11344591 A JPH11344591 A JP H11344591A
Authority
JP
Japan
Prior art keywords
lining
storage tank
wall
base material
reinforcements
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10152510A
Other languages
Japanese (ja)
Inventor
Yoshiaki Nakada
義章 仲田
Nobuyoshi Kawamura
信義 川村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Hitachi Industry and Control Solutions Co Ltd
Original Assignee
Hitachi Engineering Co Ltd Ibaraki
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Engineering Co Ltd Ibaraki, Hitachi Ltd filed Critical Hitachi Engineering Co Ltd Ibaraki
Priority to JP10152510A priority Critical patent/JPH11344591A/en
Publication of JPH11344591A publication Critical patent/JPH11344591A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To obviate a backing material installing margin, to eliminate an increase in an excess wall thickness, and to shorten a work period by previously integrating reinforcements, backing materials and a lining material, and integrally hanging in and installing the wall part and the floor part by a crane in execution work of a nuclear power plant lining storage tank. SOLUTION: A lining material 1, a backing material (the surface) 2, a backing material (the embedding part) 3 and reinforcements 4 are integrally assembled in a factory outside of a nuclear power plant to be transported up to a lining storage tank installing building in the power plant after being transferred on the sea by a carrier vessel, and are integrally hung in by a crane to be arranged on a floor reinforcement so that the reinforcements 4 and the floor reinforcement 11 are connected by grip joints 5. Next, a wall reinforcement 12 is connected to the reinforcements 4 by the grip joints 5, and after connecting the backing material (the embedding part) 3 by an adjacent backing material (the embedding part) 3 and a separator 3, concrete is poured into the part of a wall building frame 7.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、原子力発電所ライ
ニング貯蔵槽を施工する際の工事方法において、鉄筋,
下地材,ライニング材をあらかじめ、一体化する。特に
下地材の躯体埋め込み部に鉄筋を貫通させ、一体化しさ
らに下地材にライニング材を溶接取り付けしてから、壁
部,床部をクレーンにて一体吊り込みし、取り付けを行
う施工方法である。
BACKGROUND OF THE INVENTION The present invention relates to a method for constructing a lining storage tank for a nuclear power plant,
The base material and the lining material are integrated in advance. In particular, it is a construction method in which a reinforcing bar is penetrated into a buried portion of a base material, integrated, a lining material is welded and mounted on the base material, and then the wall and floor are suspended by a crane and mounted.

【0002】[0002]

【従来の技術】原子力発電所ライニング貯蔵槽を施工す
る際の工事方法は、鉄筋取り付け,下地材取り付け,ラ
イニング材取り付けを個別に行う施工法であり、鉄筋の
施工部分の上に下地材取り付け代を確保している。
2. Description of the Related Art The construction method for installing a lining storage tank at a nuclear power plant is a method in which a reinforcing bar, a base material, and a lining material are individually installed. Is secured.

【0003】[0003]

【発明が解決しようとする課題】従来の技術であれば、
鉄筋取り付け,下地材取り付け,ライニング材取り付け
を個別に行う為、下地材取り付け代を必要とし、余分に
壁厚さを増加する必要がある。また工事期間が長くな
る。
SUMMARY OF THE INVENTION In the prior art,
Since the rebar, the base material, and the lining material are individually mounted, a base material mounting margin is required, and the wall thickness needs to be increased extra. Also, the construction period becomes longer.

【0004】[0004]

【課題を解決するための手段】本発明の特徴は、ライニ
ング貯蔵槽を施工する際の工事方法において、鉄筋,下
地材,ライニング材をあらかじめ、一体化する。特に下
地材の躯体埋め込み部に鉄筋を貫通させ、一体化しさら
に下地材にライニング材を溶接取り付けしてから、壁
部,床部をクレーンにて一体吊り込みし、取り付けを行
う施工法である。即ち、本発明によれば、ライニング材
と下地材の躯体埋め込み部に鉄筋を貫通させ、一体化す
ることにより、下地材取り付け代を不要とし、余分に壁
厚さを増加することを不要とする。また、クレーンにて
一体吊り込みし、取り付けを行うことで工事期間を短縮
することが可能となる。
A feature of the present invention is that in a construction method for constructing a lining storage tank, a reinforcing bar, a base material, and a lining material are integrated in advance. In particular, it is a construction method in which a reinforcing bar is penetrated into a buried portion of a base material, integrated, a lining material is welded to the base material, and then the wall and floor are integrally hung by a crane and mounted. That is, according to the present invention, the reinforcing bar is penetrated into the skeleton embedding portion of the lining material and the base material, and integrated, thereby eliminating the need for mounting the base material and unnecessary increase in the wall thickness. . In addition, it is possible to shorten the construction period by hanging and attaching the unit integrally with a crane.

【0005】[0005]

【発明の実施の形態】(実施例1)本発明における原子
力発電所ライニング貯蔵槽、施工法の一実施例の概略図
を図1に示す。
(Embodiment 1) A schematic view of an embodiment of a lining storage tank and a construction method of a nuclear power plant according to the present invention is shown in FIG.

【0006】ライニング材1,下地材(表面)2,下地
材(埋め込み部)3,鉄筋4,グリップジョイント5,
セパレーター6,壁躯体7,中間架台8,床躯体9,天
井躯体10,床鉄筋11,壁鉄筋12から構成される。
[0006] Lining material 1, base material (surface) 2, base material (embedded portion) 3, rebar 4, grip joint 5,
It is composed of a separator 6, a wall frame 7, an intermediate frame 8, a floor frame 9, a ceiling frame 10, a floor reinforcing bar 11, and a wall reinforcing bar 12.

【0007】まず、ライニング材1,下地材(表面)
2,下地材(埋め込み部)3,鉄筋4を原子力発電所外
部の工場で一体化組み立てし、運搬船による海上移送
後、発電所内のライニング貯蔵槽設置建屋まで運搬し、
クレーンにて一体吊り込みし床鉄筋11の上に設置し、
グリップジョイント5にて鉄筋4と床鉄筋11を接続す
る。
First, lining material 1, base material (surface)
2, Base material (embedded part) 3, Reinforcing bar 4 are assembled integrally in a factory outside the nuclear power plant, transported to the sea by a carrier, and transported to the lining storage tank installation building in the power plant,
It is suspended by a crane and installed on the floor reinforcing bar 11,
The reinforcing bar 4 and the floor reinforcing bar 11 are connected by the grip joint 5.

【0008】次に、壁鉄筋12をグリップジョイント5
にて鉄筋4に接続し、下地材(埋め込み部)3を隣接す
る下地材(埋め込み部)とセパレーター6で接続したの
ち壁躯体7の部分にコンクリートを流し込む。
Next, the wall reinforcement 12 is connected to the grip joint 5.
Then, the base material (embedded portion) 3 is connected to the adjacent base material (embedded portion) by the separator 6 and then concrete is poured into the wall frame 7.

【0009】[0009]

【発明の効果】以上説明したように本発明によれば、下
地材取り付け代を不要とし、余分に壁厚さを増加するこ
とを不要とする。また、クレーンにて一体吊り込みし、
取り付けを行うことで工事期間を短縮することが可能と
なる。
As described above, according to the present invention, it is not necessary to attach a base material, and it is not necessary to increase an extra wall thickness. In addition, it is suspended by a crane,
Installation can shorten the construction period.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施例1による原子力発電所貯蔵槽の
一部を示す概略断面図である。
FIG. 1 is a schematic sectional view showing a part of a storage tank of a nuclear power plant according to Embodiment 1 of the present invention.

【符号の説明】[Explanation of symbols]

1…ライニング材、2…下地材(表面)、3…下地材
(埋め込み部)、4…鉄筋、5…グリップジョイント、
6…セパレーター、7…壁躯体、8…中間架台、9…床
躯体、10…天井躯体、11…床鉄筋、12…壁鉄筋。
DESCRIPTION OF SYMBOLS 1 ... Lining material, 2 ... Base material (surface), 3 ... Base material (embedded part), 4 ... Reinforcing bar, 5 ... Grip joint,
6: Separator, 7: Wall frame, 8: Intermediate frame, 9: Floor frame, 10: Ceiling frame, 11: Floor reinforcement, 12: Wall reinforcement.

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】原子力発電所ライニング貯蔵槽を施工する
際の工事方法において、鉄筋,下地材,ライニング材を
あらかじめ、一体化し、壁部,床部をクレーンにて一体
吊り込みし、取り付けを行うことを特徴とするライニン
グ貯蔵槽施工法。
In a construction method for constructing a lining storage tank for a nuclear power plant, a reinforcing bar, a base material, and a lining material are integrated beforehand, and a wall and a floor are suspended by a crane and attached. A lining storage tank construction method, characterized in that:
【請求項2】請求項1において、コンクリート躯体部分
における下地材の取り付け代を不要とすることを特徴と
するランニング貯蔵槽施工方法。
2. The running storage tank construction method according to claim 1, wherein an allowance for attaching a base material to the concrete skeleton is unnecessary.
【請求項3】請求項1において、鉄筋,下地材,ライニ
ング材をあらかじめ、一体化し、壁部,床部をクレーン
にて一体吊り込みすることにより工事期間を短縮するこ
とを特徴とするランニング貯蔵槽施工方法。
3. The running storage system according to claim 1, wherein the rebar, base material and lining material are integrated in advance, and the wall and floor are suspended by a crane to shorten the construction period. Tank construction method.
JP10152510A 1998-06-02 1998-06-02 Lining storage tank construction method Pending JPH11344591A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10152510A JPH11344591A (en) 1998-06-02 1998-06-02 Lining storage tank construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10152510A JPH11344591A (en) 1998-06-02 1998-06-02 Lining storage tank construction method

Publications (1)

Publication Number Publication Date
JPH11344591A true JPH11344591A (en) 1999-12-14

Family

ID=15542038

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10152510A Pending JPH11344591A (en) 1998-06-02 1998-06-02 Lining storage tank construction method

Country Status (1)

Country Link
JP (1) JPH11344591A (en)

Similar Documents

Publication Publication Date Title
JP6748470B2 (en) A suspending structure for mounting an insert on a deck plate with a reinforcing bar truss and suspending and supporting ceiling equipment on a lower floor under the deck, and a method for mounting ceiling equipment on a lower portion of a deck plate with a reinforcing bar truss using the insert.
JPH01214636A (en) Execution method for water closet of japanese style
CN113250494A (en) Assembled integrated toilet and construction method
CN215563552U (en) Vertical joint construction of prefabricated wallboard based on ultra high performance concrete form
JP3077914U (en) Tunnel reinforcing steel hanging bracket
JPH11344591A (en) Lining storage tank construction method
CN220469309U (en) Installation structure of prefabricated concrete exhaust pipes in high-rise residential buildings that is easy to replace
CN115341573B (en) An underground structure main beam connection structure and installation method for underground connecting walls
JP3849234B2 (en) Reinforced concrete underground outer wall construction method
JP2003003603A (en) Precast concrete beam
JP2002364008A (en) Large section synthetic arch tunnel and its construction method
JPH09256645A (en) Reinforcement method of existing columns in multi-story buildings
CN208184021U (en) A kind of construction wall
CN220768428U (en) Wall body and precast beam mounting structure and building system
JP2544104Y2 (en) Underground outer wall using PCa board
CN111101648A (en) Embedded structure function integrated plate and mounting method thereof
JP2759361B2 (en) Pillar support members for building reinforced concrete buildings
CN214996146U (en) Detachable tool system for installing prefabricated superposed shear wall
CN210658446U (en) Coincide assembled utility tunnel attaches wall formula coincide roof support piece
JPH0227104Y2 (en)
JP2551970B2 (en) Japanese-style toilet construction method
JP3566360B2 (en) Construction method of trench for pipe laying
JPH05499Y2 (en)
JPH11131657A (en) Foundation form
JPH10237886A (en) Method for constructing underground tank