JPS559964A - Method of constructing upper-structure for wall of steel anchor-plate - Google Patents
Method of constructing upper-structure for wall of steel anchor-plateInfo
- Publication number
- JPS559964A JPS559964A JP8317978A JP8317978A JPS559964A JP S559964 A JPS559964 A JP S559964A JP 8317978 A JP8317978 A JP 8317978A JP 8317978 A JP8317978 A JP 8317978A JP S559964 A JPS559964 A JP S559964A
- Authority
- JP
- Japan
- Prior art keywords
- wall
- channel
- plates
- steel anchor
- web
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title abstract 6
- 239000010959 steel Substances 0.000 title abstract 6
- 238000005452 bending Methods 0.000 abstract 1
- 239000002184 metal Substances 0.000 abstract 1
- 238000000926 separation method Methods 0.000 abstract 1
- 238000003466 welding Methods 0.000 abstract 1
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
- Revetment (AREA)
Abstract
PURPOSE: To enable to construct an upper-structure to be fixed to a top of a wall of steel anchor-plates simply and economically by utilizing bolts or the like.
CONSTITUTION: A wall 2 of steel anchor-plates is constructed continuously by utilizing U-shaped steel anchor-plates, for example, and connecting each nail portions thereof, and an upper-structure 1 therefor is attached to the tops of each anchor- plates, the heights of which are aligned at the same level. The upper-structure 1 is made of a steel channel 5 formed by press or bending work for a steel plate and the height (dimension of the web) of which is wider than the width of the wall 2. The channel 5 is put on the wall 2 so that the flange portions thereof are directioned upwardly and is fixed to the top of the wall 2 by welding at the lower surface of the web thereof. A channel 7 of expander metal, the flange portions of which are directioned downwardly, is fixed to the web of the channel 5 in order to prevent concrete 4 from damages or separation, and thereafter, the recessed portion 6 of the channel 5 is filled with the concrete 4 to complete the upper-structure 1.
COPYRIGHT: (C)1980,JPO&Japio
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8317978A JPS559964A (en) | 1978-07-08 | 1978-07-08 | Method of constructing upper-structure for wall of steel anchor-plate |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8317978A JPS559964A (en) | 1978-07-08 | 1978-07-08 | Method of constructing upper-structure for wall of steel anchor-plate |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS559964A true JPS559964A (en) | 1980-01-24 |
| JPS5644208B2 JPS5644208B2 (en) | 1981-10-17 |
Family
ID=13795061
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP8317978A Granted JPS559964A (en) | 1978-07-08 | 1978-07-08 | Method of constructing upper-structure for wall of steel anchor-plate |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS559964A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6023507A (en) * | 1983-07-19 | 1985-02-06 | Shinwa Kousetsu Kk | Construction of dam |
| JPS63130817A (en) * | 1986-11-21 | 1988-06-03 | Ohbayashigumi Ltd | Underwater large-size coffering structure |
-
1978
- 1978-07-08 JP JP8317978A patent/JPS559964A/en active Granted
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6023507A (en) * | 1983-07-19 | 1985-02-06 | Shinwa Kousetsu Kk | Construction of dam |
| JPS63130817A (en) * | 1986-11-21 | 1988-06-03 | Ohbayashigumi Ltd | Underwater large-size coffering structure |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5644208B2 (en) | 1981-10-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPS56131712A (en) | Removing method of defective concrete at upper part of pile when driving pile in site | |
| AU1797697A (en) | Composite-structure building framework | |
| JPS55114717A (en) | Combination method of support and foundation | |
| JPS53138972A (en) | Package device for catalyst block | |
| JPS56157602A (en) | Method of repairing triangular shoe of building machine for use on marshy ground and doubling plate therefor | |
| GB730389A (en) | Improvements relating to shuttering for concrete and the like | |
| FR2418415A1 (en) | T=Shaped beam made from insulating material - joined by corner pieces and capable of being joined in a structure | |
| JPS57123324A (en) | Pile foundation work | |
| JPS57140413A (en) | Method and apparatus for constructing dam | |
| GB2003538A (en) | Improvements in building construction | |
| JPS579916A (en) | Foundation structure for building | |
| JPS57134663A (en) | Solar heat collecting device | |
| JPS5796134A (en) | Construction of working chamber in caisson | |
| JPS57140804A (en) | Press-injecting method for packing to under bottom plate of blast furnace bottom plate | |
| TR2024000109U5 (en) | SINGLE VERTICAL PLACEMENT SOLAR POWER PLANT BOTTOM CARRIER CONSTRUCTION SYSTEM | |
| JPS55105029A (en) | Sheathing of trench side wall | |
| JPS57184134A (en) | Construction of retaining wall by large-size blocks | |
| JPS57108320A (en) | Reinforcing wall for banking | |
| SU1201414A1 (en) | Foundation under metal column | |
| JPS5715728A (en) | Construction of foundation | |
| ES8101177A1 (en) | Formwork system (Machine-translation by Google Translate, not legally binding) | |
| GB1443871A (en) | Prefabricated concrete columns | |
| JPS57133921A (en) | Manufacture of pile | |
| JPS5454429A (en) | Floating precast concrete factory | |
| JPS5585737A (en) | Foundation work |