JPS584006A - Continuous type bridge using prestressed steel beam - Google Patents

Continuous type bridge using prestressed steel beam

Info

Publication number
JPS584006A
JPS584006A JP9830581A JP9830581A JPS584006A JP S584006 A JPS584006 A JP S584006A JP 9830581 A JP9830581 A JP 9830581A JP 9830581 A JP9830581 A JP 9830581A JP S584006 A JPS584006 A JP S584006A
Authority
JP
Japan
Prior art keywords
concrete
girder
steel
span
prestressed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP9830581A
Other languages
Japanese (ja)
Other versions
JPS5832243B2 (en
Inventor
斎藤道生
渡辺滉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KAWATA KOGYO KK
Original Assignee
KAWATA KOGYO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KAWATA KOGYO KK filed Critical KAWATA KOGYO KK
Priority to JP9830581A priority Critical patent/JPS5832243B2/en
Publication of JPS584006A publication Critical patent/JPS584006A/en
Publication of JPS5832243B2 publication Critical patent/JPS5832243B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 レス鋼桁を用いた連続型式橋梁に関するものであるO 橋梁用架数桁として、鋼桁に予め前たわみ荷重を与えて
おいて引張側となる下7ランジに該下7ランジを包むよ
うなコンクリートを打設し、このコンクリートの硬化後
鋳たわみ荷重を解除して鋼桁の復元力により下7ランジ
コンクリートにプレストレス応力を導入するようKした
通称プレビームと称されるプレストレス鋼桁は既に公知
である(41公紹n−to参コ参号)0 このようなプレストレス鋼桁を現場において架設したの
ちウェブコンクリート及び床版コンクリ−Fの打設を行
って鋼桁を完全Kmンクリートにより被覆した桁はプレ
ビーム合成桁と称されている・このプレビーム合成桁ば
下フランジコンクリートと床版コンクリートとが鋼桁と
合成されているために曲げ剛直が大きくなり、通常の合
成桁よりも桁高を低くすることができるという点で、桁
高制限を受けるような橋梁の施工に対しては極めて有利
である。また鋼桁自体が露呈してぃな−ために塗装等の
維持管理が不要であること、騒音が生じないこと、耐火
性を有することなどの利点を有する。
[Detailed Description of the Invention] This relates to a continuous type bridge using a steel girder.As a bridge girder, a pre-deflection load is applied to the steel girder in advance, and the lower seven lunges on the tension side are Commonly known as a pre-beam, concrete is placed to surround the 7th lunge, and after the concrete hardens, the casting deflection load is released and prestress stress is introduced into the lower 7th lunge concrete using the restoring force of the steel girder. Prestressed steel girders are already known (41 Publication n-to Sanco Reference No.) 0 After erecting such prestressed steel girders on-site, web concrete and slab concrete F are placed, and the steel A girder whose girder is completely covered with Km concrete is called a pre-beam composite girder.Since the lower flange concrete and slab concrete of this pre-beam composite girder are composited with the steel girder, the bending stiffness is increased, Since the girder height can be lower than that of composite girders, it is extremely advantageous for constructing bridges that are subject to girder height restrictions. In addition, since the steel girder itself is not exposed, it has the advantage of not requiring maintenance such as painting, making no noise, and being fire resistant.

このような長所をもつプレビーム合成桁により橋梁を架
設する場合、単純支持型式とするか或は連続支持型式と
するかという点が考えられるが、連続支持型式の合成桁
の場合は、中間支点部付近に作用する負の曲はモーメン
トによる床版コンクリートのひ!割れという問題に対処
しなければならな−。この問題に対処するための処電と
しては、例えば正の曲はモーメント域に一時的な前荷重
を載架したり、或は中間支点をジヤツキアップさせたり
して一時的にψ間支点部の鋼桁上7ランジに引張応力を
与えておき、中間支点部材版コンクリートの打設硬化後
前記の前荷重を除去したり或はジヤツキダウンを行って
中間支点部材版コンクリ−)Kプレストレス応力を支え
るという方法がある。しかし乍らこのような中間支点部
付近の負のモーメントに伴う対策方法は、全て架設現場
において行わなければならずその方法も繁雑であるため
施工上かならずしも適切とは云えない点があり、このよ
うな理由から本発明において使用するプレストレス鋼桁
は前記のような長所を有しているにも拘らず連続支持型
式として架設されず、従来より単純支持型式の橋梁に多
く採用されていた。
When constructing a bridge using pre-beam composite girders that have these advantages, it is possible to consider whether to use a simple support type or a continuous support type, but in the case of a continuous support type composite girder, intermediate support The negative force acting near the concrete slab is due to the moment! We have to deal with the problem of cracking. To deal with this problem, for example, for positive curves, temporarily load the front load in the moment area, or jack up the intermediate support to temporarily reduce the steel at the ψ support. Tensile stress is applied to the 7 lunges on the girder, and after the concrete for the intermediate fulcrum member is placed and hardened, the above-mentioned preload is removed or jacked down to support the prestress stress of the concrete for the intermediate fulcrum member. There is a way. However, all countermeasures for negative moments near the intermediate support must be carried out at the construction site, and the methods are complicated, so they cannot necessarily be said to be appropriate for construction. For these reasons, although the prestressed steel girder used in the present invention has the above-mentioned advantages, it has not been constructed as a continuous support type, and has traditionally been used in simple support type bridges.

本発明は前記のような長所をもつプレストレス鋼桁によ
るプレビーム合成桁の利点をそのt−活かし、更に耐展
性とか車輛走向性などの点で有利な連続合成桁型式への
応用を図ることを目的としテ、中間支点部の床版コンク
リートのプレストレス応力導入手順が簡素化できるよう
Kした連続型式の橋梁を提供しようとするものであり、
正の曲げモーメントを受ける径間部には下7ランジにプ
レストレスコンクリートが設けられた通常のプレストレ
ス鋼桁による径間部材を架設し、負の曲はモーメントを
受ける中間支点部付近には予曲げKよる引張側に床版コ
ンクリートを打設して該コンクリートの硬化後予曲は荷
重を解除することKより床版コンクリートにプレストレ
ス応力が導入された変形プレストレス鋼桁による中間支
点部材を架設して、両鋼桁を連続型式に連結架設するこ
とを特徴としたものである。
The present invention aims to take advantage of the advantages of pre-beam composite girders made of prestressed steel girders, which have the above-mentioned advantages, and to further apply them to a continuous composite girder type that is advantageous in terms of malleability, vehicle running properties, etc. The purpose of this project is to provide a continuous type bridge that simplifies the procedure for introducing prestress stress into the concrete deck slab at the intermediate support.
Span members made of ordinary prestressed steel girders with prestressed concrete on the lower 7 lunges are installed in the spans that receive positive bending moments, and prestressed steel girders are constructed near the intermediate supporting points that receive moments for negative bends. Placing slab concrete on the tensile side due to bending K and releasing the pre-bending load after the concrete has hardened. The feature is that both steel girders are connected and constructed in a continuous manner.

次に本発明に係る連続型式橋梁の架設工程を図示の実施
例により詳記すれば、第1図a乃至Cは正の曲はモーメ
ントを受ける径間部に用いられるプレストレス鋼桁によ
る径間部材(1)の製作工程を示す側面図、第2図a乃
至eli負の曲げモーメントを受ける中間支点部に用い
られる変形プレストレス鋼桁による中間支点部材−)の
製作工程を示す側面図である。
Next, the construction process of a continuous type bridge according to the present invention will be described in detail with reference to the illustrated embodiment. FIG. 2 is a side view showing the manufacturing process of member (1); FIG. .

第11ii4に示す如く径間部材(1)は、公知のプレ
ストレス鋼桁の製作と同様K11作される。即ち同図a
の如く鋼桁(1)、K予めキャンバーを与えておき、次
に同図すの如く該鋼桁(1)、に両熾を支持した状態で
キャンバ−を打消すような前たわみ荷重(プレ7レクシ
目ン)釘を与える。この状態で第1図〇の如く鋼桁(1
)、の引張側となる下7ランジ(J) K 桁違結端部
(41)を残してコンクリート(j)を打設し、該コン
クリ−) (j)が所定強度に達した時点で助たわみ荷
重Ptを解除し、鋼桁の復元力によって下7ランジコン
クリート(j) Kプレストレス応力を導入する。
As shown in No. 11ii4, the span member (1) is made of K11, similar to the production of known prestressed steel girders. That is, figure a
A camber is applied to the steel girder (1) and K in advance as shown in the figure, and then a forward deflection load (pre-loading) is applied to the steel girder (1) to cancel the camber with the steel girder (1) supporting both sides as shown in the figure. 7) Give a nail. In this state, the steel girder (1
), concrete (j) is poured leaving the lower 7-lunge (J) K girder unconnected end (41) on the tensile side, and when the concrete (j) reaches the specified strength, it is The deflection load Pt is released, and the lower 7 lunge concrete (j) K prestress stress is introduced by the restoring force of the steel girder.

第一図に示す中間支点部材(λ)は、基本的には前記の
径間部材(1)の製作と変りはないが、この場合は前た
わみ荷重Pfを与える鋼桁(コ)、の上下7ランジ(4
)(7)の位置が、前記径間部材用プレストレス鋼桁(
1)、とは逆になるように配置されている。即ち第コ図
aK示す如く鋼桁口)、は当初下7ランジ(7)を上向
IKIIIi、この状態で第2図すの如く上7ランジ(
≦)が引張側となるような前たわみ荷重Pfを与える0
次にこの段階で引張側の上フランジ(t)に桁連結端部
(9)を残して床版コンクリート(t)を打設し、と9
コンクリート(1)が所定強度に達した時点で前記前た
わみ荷重Pfを解除し、鋼桁(コ)、の復元力により床
版コンクリ−) (r) Kプレストレス応力を導入す
る0次に第2図dの如く′床版コンクリート(t)と同
様桁連結趨部(デ)を残して吟ニブコンクリート(10
)及び下7ランジ(7)にコンクリート(l/)を打設
し、コンクリ−) (7)(lの(//)Kより主要部
鋼桁が被覆された合成部材とする。勿論これらのウェブ
コンクリート(/の及び下7ランジコンクリー)(//
)にはプレストレスは導入されていない。このようにし
て製作された変形プレストレス鋼桁による中間支点部材
(λ)は、#!λ図eの如く桁の上下を回転して正しい
位置に戻され、架設迄fストックされる。
The intermediate fulcrum member (λ) shown in Figure 1 is basically manufactured in the same way as the span member (1) described above, but in this case, the steel girder (K) that applies the forward deflection load Pf is used above and below the 7 lunges (4
) (7) is located on the prestressed steel girder for span members (
1), are arranged in the opposite way. In other words, the steel girder opening (as shown in Fig. aK) initially moves the lower 7 langes (7) upward IKIIIi, and in this state the upper 7 langes (7) as shown in Fig. 2.
≦) gives a forward deflection load Pf such that it becomes the tension side 0
Next, at this stage, slab concrete (t) is poured leaving the girder connection end (9) on the upper flange (t) on the tension side, and 9
When the concrete (1) reaches a predetermined strength, the pre-deflection load Pf is released and the zero-order prestress stress is introduced into the floor slab concrete (r) by the restoring force of the steel girder (r). As shown in Fig. 2 d, the girder connecting ridges (d) were left in place like the slab concrete (t), and the ginnib concrete (10
) and the lower 7 langes (7), concrete (l/) will be poured to form a composite member with the main steel girder covered from (//) K of (l). Web Concrete (/'s and lower 7 range concrete) (//
), no prestress is introduced. The intermediate support member (λ) made of the deformed prestressed steel girder manufactured in this way is #! As shown in Figure λ, the girder is rotated up and down and returned to the correct position, and then stocked until it is erected.

上記の製作工程により得られた径間部材(1)及び中間
支点部材−)の架設は、第3図a乃至(iK示す順序に
より行われる。即ちまず第J図aのように仮ペン) (
/J)等により径間部材(/l及び中間支点部材(λ)
の桁連結端部付近、を夫々支持し、径間部材の桁連結端
部(≠)と予め露出しておいた中間支点部材(J) 1
7) 桁連結端部(9)とを夫々スプライスプレート(
13)及び高力ボルトを用いてしっかりと連結する。
The span member (1) and the intermediate fulcrum member (-) obtained by the above manufacturing process are constructed in the order shown in Fig. 3a to (iK. That is, first, as shown in Fig. Ja, the temporary pen) (
/J), etc. to create a span member (/l) and an intermediate fulcrum member (λ).
The girder connecting end (≠) of the span member and the intermediate fulcrum member (J) 1 exposed in advance support the vicinity of the girder connecting end of the span member.
7) Attach the girder connecting end (9) to the splice plate (
13) and securely connect using high-strength bolts.

次に第3図b’に示すように中間支点部材<2)の中央
部下面を中間支承前(/参)Kより支持し、同時に仮ペ
ン) (/J)を撤去して連続桁とする。しかるのち第
3図OK示すように径間部材(1)及び中間支点部材(
コ)Kおける鋼桁の露出している桁連結、端部(4=)
(9)の下7ランジ(J)(7) K 、下7ランジ間
詰めコンクリート(lj)を打設する。上記の間詰めコ
ンクリ−) (13)の硬化後置後に第3図dに示すよ
うに、径間部材(/)の上7ランジ(Za)の床版コン
クリ−) (/7)を、桁連結端部(ゲ)上はもとより
中間支点部材(2)の桁連結端部(9)の上7ランジ(
≦)をも被覆して中間支点部材(2)の床版コンクリー
ト(t)と接する位置まで打設し、また径間部材(1)
Kおけるウェブにウェブコンクリート(n)を床版コン
クリートと同様中間支点部材(コ)のウェブコンクリー
ト(lのと接する位置まで打設する。従ってこの段階で
鋼材(1)、(λ)、が全てコンクリートにより被覆さ
れた形の連続桁が完成し、これ以後の地覆、高欄、舗装
等の後死荷重或は車幅等の活荷重は下7ランジプレスト
レスコンクリーF及び床版コンクリートとが鋼桁と合成
された連続合成桁に作用すること\なる。
Next, as shown in Fig. 3 b', the central lower surface of the intermediate support member <2) is supported from the front intermediate support (/J), and at the same time, the temporary pen (/J) is removed to form a continuous girder. . After that, the span member (1) and the intermediate fulcrum member (
e) Exposed girder connection and end of steel girder in K (4=)
(9) Lower 7 lunge (J) (7) K, pour the lower 7 lunge filler concrete (lj). After curing of the above filler concrete (13), as shown in Figure 3d, the floor slab concrete (/7) of the upper 7 lunges (Za) of the span member (/) is installed. Not only the top of the connecting end (ge) but also the top 7 langes of the girder connecting end (9) of the intermediate fulcrum member (2).
≦), and cast the intermediate support member (2) to the position where it contacts the floor slab concrete (t), and also cover the span member (1).
Place the web concrete (n) on the web at K in the same way as the slab concrete until it touches the web concrete (l) at the intermediate support member (C). Therefore, at this stage, all of the steel members (1) and (λ) The continuous girder covered with concrete has been completed, and the subsequent dead loads such as ground covering, handrails, pavement, etc., or live loads such as vehicle width, etc., will be handled by the lower 7 lunge prestressed concrete F and the slab concrete. It acts on the continuous composite girder combined with the girder.

本発明に係る連続型式橋梁′は上記の如き構造よりなり
、次の如き利点を有する。
The continuous type bridge according to the present invention has the structure described above and has the following advantages.

前記の如〈従来の連続合成桁型式の橋梁架設に際しては
、中間支点部材近に生ずる負の曲はモーメントによる床
、版コンクリートのひ!割れ等の問題点があり、これを
解決するための方法としては、前記の如く正の曲げモー
メント域に一時的な前荷重を載荷したり、中間支点をジ
ヤツキアップさせたすして中間支点部鋼桁上7ランジに
引張応力を与え、中間支点部材版コンクリート打設して
、その硬化後前荷重除去、支点のジヤツキダウンにより
中r[fl 支点部床版コンクリートにプレストレス応
力を与えるという手順によるため、現場施工の面で著し
い繁雑さを有していたOしかるに本発明に係る連続型式
橋梁では、プレストレス鋼桁の基本原理を中間支点部材
(コ)K応用して、前荷重を与えられた鋼桁の引張側に
床版コンクリート(r)を打設して前荷重を解除する仁
とによって該床版7ンクリー) (r)にプレストレス
応力を導入するものであり、この床版コンクリート<r
)のプレストレス導入作業は予め桁架設の前段階即ち作
業性の良好な工場内や現場ヤード内において部材単位に
行われるので、施工性が極めて良好であり、しかも術部
材の架設R#では径間部材(ハと中間支点部材(2)を
単に連結するだけで足りるため、総体的に中間支点部分
の負の曲げモーメント対策が著しく簡素化されるという
利点を有する。
As mentioned above, when constructing a conventional continuous composite girder type bridge, the negative bending that occurs near the intermediate supporting member is due to the bending of the floor and concrete slab due to the moment. There are problems such as cracking, and methods to solve this problem include applying a temporary preload in the positive bending moment region as described above, or jacking up the intermediate support, and then increasing the strength of the steel girder at the intermediate support. Because the procedure is to apply tensile stress to the upper 7 lunges, pour concrete for the intermediate fulcrum member slab, remove the preload after it hardens, and apply prestress stress to the middle r [fl fulcrum slab concrete by jacking down the fulcrum. However, in the continuous type bridge according to the present invention, the basic principle of prestressed steel girder is applied to the intermediate supporting member (K), and the construction is extremely complicated in terms of on-site construction. By pouring slab concrete (r) on the tension side of the girder and releasing the preload, prestress stress is introduced into the slab (7) (r), and this slab concrete < r
) prestress introduction work is carried out in advance for each member at the stage prior to girder erection, i.e. in a factory or on-site yard where workability is good, so workability is extremely good. Since it is sufficient to simply connect the intermediate member (C) and the intermediate fulcrum member (2), there is an advantage that countermeasures against negative bending moments at the intermediate fulcrum portion are significantly simplified overall.

また本発明の橋梁においては、径間部材(1)及び中間
支点部材−)ともその構成部材として鋼桁(/l、(J
)1を有し、しか1夫身の部材(1)(λ)は予めプレ
ストレス応力の導入が所定部分に導入されているもので
あり、これらのプレストレス応力の導入された部材間の
連続が構成部材としての鋼桁の連結により確実且容易に
行えるという利点を有する。
In addition, in the bridge of the present invention, both the span member (1) and the intermediate support member -) are steel girders (/l, (J
) 1, and the member (1) (λ) that has only one member has prestress stress introduced into a predetermined part in advance, and there is a continuity between the members to which these prestress stresses have been introduced. This has the advantage that this can be done reliably and easily by connecting steel girders as structural members.

また中間支点部材(2)は所定の長さをもつ鋼桁(コ)
、をもとに構成され、この中間支点部材(12)の両端
が径間部材(1)と連結されるため、この連結部分を曲
はモーメントの符号が変る曲けの大きくない区間に設定
できるとと\なり、耐荷力士の問題はなく、連続桁の曲
げモーメント分布に応じた極めて合理的な構造型式とす
ることかで−きる。
In addition, the intermediate fulcrum member (2) is a steel girder (co) with a predetermined length.
, and both ends of this intermediate fulcrum member (12) are connected to the span member (1), so this connected part can be set in a section where the bend is not large and the sign of the moment changes. Therefore, there is no problem with load-bearing strength, and it is possible to create an extremely rational structural type that corresponds to the bending moment distribution of the continuous girder.

また架設時の桁取扱いも従来のプレストレス鋼桁による
単純型式の橋梁の場合と比較してそれ程繁雑でなく架設
作業を安全に行いつる外、同規模のプレストレス鋼桁に
よる単純型式の橋梁と比較して経済性、耐震性、車輛走
行性、美観等の点で優れており、モーメントバランスが
良くなることから桁高/支間比を単純型式橋梁の’/、
?fPら\。
In addition, the handling of girders during erection is not as complicated as in the case of a simple type bridge with conventional prestressed steel girders, and the erection work can be carried out safely. It is superior in terms of economy, earthquake resistance, vehicle drivability, aesthetics, etc. compared to that of a simple type bridge, and its moment balance is better, so the girder height/span ratio is lower than that of a simple type bridge.
? fP et al.

程度にすることができ、極めてスレンダーな美しい橋梁
とすることができるという効果を有するものである。
This has the effect that it can be made into a very slender and beautiful bridge.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図a乃至Cは本発明に係る橋梁の径間部材の製作工
程を示す側面図、第一図a乃至eは同じく中間支点部材
の製作工程を示す側面図、第3図a乃至dは桁の架設工
程を示す側面図、′第参図は第1図CのIV−P/線に
おける断面図、第5図は第2図eのv−v線における断
面図である。 図において、 (1)・・・径間部材、(2)・・・中間支点部材、(
31(7)・・・下フランジ、(+’)(9)・・・桁
連結端部、(j)’ Crt)・・・下7ランジコンク
リート、(≦1 (/1>・・・上7ランジ、(zl 
(/7)・・・床版コンクリート、(/の(1g)−・
・ウェブコンクリート、(/、2)・・・仮ベント、(
/J)・・・スプライスプレー11(/4I)・・・中
間支承、(tS)・・・間詰めコンクリート。 特許出願人 川田工業株式会社 3 第夕図 −3:
Figures 1a to 1C are side views showing the manufacturing process of the bridge span member according to the present invention, Figure 1a to e are side views showing the manufacturing process of the intermediate support member, and Figures 3a to d are side views showing the manufacturing process of the intermediate support member. A side view showing the process of constructing the girder, Figure 1 is a sectional view taken along the line IV-P/ in FIG. 1C, and FIG. 5 is a sectional view taken along the line v-v in FIG. 2e. In the figure, (1)...Span member, (2)...Intermediate fulcrum member, (
31 (7)...Lower flange, (+') (9)...Girder connection end, (j)' Crt)...Lower 7 lunge concrete, (≦1 (/1>...Top) 7 lunges, (zl
(/7)...Slab concrete, (/of (1g)--
・Web concrete, (/, 2)...Temporary vent, (
/J)... Splice spray 11 (/4I)... Intermediate bearing, (tS)... Filling concrete. Patent applicant: Kawada Kogyo Co., Ltd. 3 Figure 3:

Claims (1)

【特許請求の範囲】[Claims] L 正の曲げモーメンFを受ける径間部には鋼桁下7ラ
ンジに打設されたコンクリートにプレストレス応力が与
えられた通常のプレストレス鋼桁による径間部材を架設
し、負の曲げモーメントを受けろ中間支点部材近には鋼
桁の予曲げKよる引張側7ランジに床版コンクリ−Fを
打設して諌コンクリート硬化後予曲は荷重を解除するこ
とにより床版コンクリートにプレストレス応力が与えら
れ、且つ下7ランジには非プレストレスコンクリートが
設けられた変形プレストレス鋼桁による中間支点部材を
架設し、両帯部材を連結して連続桁としての架設に代え
、径間部材に床版コンクリート及びウェブコンクリート
を打設して最終的に鋼桁の全てをコンクリートにより被
覆したことを特徴とするプレストレス鋼桁を用いた連続
型式橋梁。
L In the span part that receives the positive bending moment F, a span member made of a normal prestressed steel girder is constructed by applying prestress stress to the concrete placed in the lower 7 flanges of the steel girder, and the span part receives the negative bending moment F. Concrete deck F is placed near the intermediate supporting member of the steel girder on the tensile side 7 of the pre-bending K, and after the concrete has hardened, the pre-bending is done by releasing the load and applying prestress stress to the concrete deck. In addition, an intermediate support member made of a deformed prestressed steel girder with non-prestressed concrete provided on the lower 7 lunges was erected, and both band members were connected to create a span member instead of being constructed as a continuous girder. A continuous type bridge using prestressed steel girders characterized by pouring slab concrete and web concrete and finally covering all of the steel girders with concrete.
JP9830581A 1981-06-26 1981-06-26 Continuous type bridge using prestressed steel girders Expired JPS5832243B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9830581A JPS5832243B2 (en) 1981-06-26 1981-06-26 Continuous type bridge using prestressed steel girders

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9830581A JPS5832243B2 (en) 1981-06-26 1981-06-26 Continuous type bridge using prestressed steel girders

Publications (2)

Publication Number Publication Date
JPS584006A true JPS584006A (en) 1983-01-11
JPS5832243B2 JPS5832243B2 (en) 1983-07-12

Family

ID=14216208

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9830581A Expired JPS5832243B2 (en) 1981-06-26 1981-06-26 Continuous type bridge using prestressed steel girders

Country Status (1)

Country Link
JP (1) JPS5832243B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59218991A (en) * 1983-01-14 1984-12-10 ウエスチングハウス・エレクトリック・コーポレーション Reactor structure
KR100793157B1 (en) 2006-12-21 2008-01-10 주식회사 포스코 Continuous fabrication method using pre-stressed parent cement girders
KR100840190B1 (en) 2007-12-10 2008-06-23 노윤근 Connection method of i-beam segment with prestressed steel composite flange for continuous bridge

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59218991A (en) * 1983-01-14 1984-12-10 ウエスチングハウス・エレクトリック・コーポレーション Reactor structure
KR100793157B1 (en) 2006-12-21 2008-01-10 주식회사 포스코 Continuous fabrication method using pre-stressed parent cement girders
KR100840190B1 (en) 2007-12-10 2008-06-23 노윤근 Connection method of i-beam segment with prestressed steel composite flange for continuous bridge

Also Published As

Publication number Publication date
JPS5832243B2 (en) 1983-07-12

Similar Documents

Publication Publication Date Title
CN101080534B (en) Manufacturing method for prestressed steel composite girder
US2786349A (en) Prestressed concrete building
KR20030014686A (en) Method of constructing simple and continuous composite bridges
CN1222672C (en) Flat soffit, doubly prestressed, composite, roof-ceiling construction for large span industrial buildings
JPS584004A (en) Construction of prefabricated prestressed steel beam
JPS6282147A (en) Novel prestressed synthetic beam and its construction
CA2114263A1 (en) Method of post-tensioning steel/concrete truss before installation
CN217652103U (en) Novel precast concrete frame beam
JPS61176706A (en) Structure of concrete floor panel and its construction
JPS5832243B2 (en) Continuous type bridge using prestressed steel girders
JP2838608B2 (en) Connection structure of girder and steel beam
CN213390771U (en) Welding-free laminated plate
JP2000104219A (en) Construction method of composite truss bridge
CN213390768U (en) Bottom plate for assembling type concrete prestress overlapping
JPS584005A (en) Construction of connected beam by prestressed steel beam
KR20230064863A (en) A method of manufacturing a double-flanged I-girder to prevent lateral buckling
JP2007046277A (en) Bridge girder construction method
JPH116296A (en) Concrete casting method
CN120311581B (en) Pedestrian suspension link arch bridge and construction method thereof
JPH01137034A (en) Structure of composite building structure
KR20000058716A (en) Multi-span continuous composite construction that integrates beams and piers and lowers and raises end points
Girgis Optimization of spliced precast concrete I-girder superstructures
HK40101205A (en) Composite rcc deck and prestressed parabolic bottom chord underslung open web steel girder bridge superstructure
CN119434513A (en) A kind of local prestressed support-free prefabricated floor and construction method thereof
JPS6059383B2 (en) Construction method for steel reinforced concrete structures