JPS5930880B2 - How to make a sunken burial box - Google Patents
How to make a sunken burial boxInfo
- Publication number
- JPS5930880B2 JPS5930880B2 JP53094542A JP9454278A JPS5930880B2 JP S5930880 B2 JPS5930880 B2 JP S5930880B2 JP 53094542 A JP53094542 A JP 53094542A JP 9454278 A JP9454278 A JP 9454278A JP S5930880 B2 JPS5930880 B2 JP S5930880B2
- Authority
- JP
- Japan
- Prior art keywords
- steel plate
- concrete
- box
- submerged box
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【発明の詳細な説明】
本発明は、沈埋トンネル用の沈埋函の製作方法に関する
。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of manufacturing an immersed box for an immersed tunnel.
沈埋トンネル用の沈埋函のあるものは、巾30乃至40
m、長さ120m程度にも及ぶ大形で、重量は1万トン
近くに及ぶので、大規模な専用ドックを構築するか、造
船用ドックを使用せねばならず、使用ドック、進水、等
につき困難な問題をかかえている。Those with immersed boxes for immersed tunnels have a width of 30 to 40 mm.
As it is a large ship with a length of approximately 120 m and a weight of nearly 10,000 tons, it is necessary to construct a large-scale dedicated dock or use a shipbuilding dock. We are facing a difficult problem.
従来は、ドックを利用して、全コンクリート製沈埋函を
製作し、その硬化なまって進水させる方法が考えられ、
実施もされたが、同沈埋函製作のためには永い日数を要
するため、ドックの稼動効率悪く、トンネル工事期間は
のび、沈埋函の費用、引いてはトンネル工事費用が嵩む
欠点がある。Conventionally, the method used was to use a dock to manufacture an all-concrete immersed box and then launch it into the water after it had hardened.
Although this method has been implemented, it takes a long time to manufacture the immersed boxes, which results in poor dock operation efficiency, prolongs the tunnel construction period, and increases the cost of the immersed boxes and, by extension, the tunnel construction costs.
上記工法に代って、沈埋函の外被を鋼殻とし、ドックで
まづ鋼殻を造り、それを進水させ、その目的のために準
備された岸壁へ曳航し撃留して、下床版、中壁、側壁、
天井床版等順次コンクリート打設して、沈埋函を完成さ
せる方法が採られるに至り、永(重数を要するコンクリ
ートの打設、およびその硬化をドック以外の個所で実施
する事によって、ドックの稼動率を高めると共に、鋼殻
は沈埋後において、トンネルの防水ならびに地震への対
策となって甚だ有効と考えられた。Instead of the above construction method, the outer jacket of the immersed box is made of a steel shell, the steel shell is first built at the dock, the shell is launched, it is towed to a quay prepared for that purpose, it is held there, and the shell is lowered. Floor slabs, middle walls, side walls,
A method of completing the immersed box by sequentially pouring concrete such as ceiling slabs was adopted, and by placing heavy concrete and hardening it at a location other than the dock, it became possible to In addition to increasing the operating rate, the steel shell was considered to be extremely effective as a waterproofing and earthquake countermeasure for the tunnel after it was buried.
この鋼殻工法の初期のものむζ鋼殻は全閉構造で、撃留
岸壁おいては、鋼殻の底鋼板に作用する浮力によって鋼
殻に不同変形をきたし、またコンクリート打設に当って
は、コンクリートは重量が重(、かつ打設時には強度が
全(無い事により、更に鋼殻に二次の不同変形をきたす
ので、鋼殻の強度の強化や、コンクリート打設個所を細
分割し打設の順序を調整する事により不同変形の発生を
極力逓減する配慮も必要とする。The ζ steel shell used in the early stages of this steel shell construction method had a completely enclosed structure, and at the holding quay, the buoyancy acting on the bottom steel plate of the steel shell caused uneven deformation of the steel shell, and during concrete pouring. Concrete is heavy (and does not have full strength at the time of pouring), which further causes secondary nonuniform deformation of the steel shell. Consideration must also be given to reducing the occurrence of uneven deformation as much as possible by adjusting the order of pouring.
更に天井床版のコンクリート打設に当っては、型枠と鋼
殻の天井鋼板との間の狭い空間にコンクリートを充填す
るを要し工事に難渋し、更に加えて、前記打設コンクリ
ートの上面に浮上する有害な残滓レイタンスを除去する
事が構造上困難で、已むを得ず、該レイタンスを除去す
ることなく、前記コンクリートと鋼殻の天井鋼板との間
にモルタルを注入せねばならない破口にあり、更に密閉
に近い鋼殻の中に多量のコンクリートを打設することに
よるコンクリート硬化時の発熱により、鋼殻内作業は劣
悪な作業環境下にある等、多(の欠点がある。Furthermore, when pouring concrete for the ceiling slab, it is necessary to fill the narrow space between the formwork and the ceiling steel plate of the steel shell, making the work difficult. It is structurally difficult to remove the harmful residual laitance that floats to the surface, and it is unavoidable to inject mortar between the concrete and the ceiling steel plate of the steel shell without removing the laitance. There are many drawbacks, such as the fact that work inside the steel shell is a poor working environment due to the heat generated when the concrete hardens due to pouring a large amount of concrete into the nearly airtight steel shell.
上記の欠点に対して、特公昭50−29565号では、
前記の全閉式鋼殻に対して、上面開放型鋼殻とすること
により、前記工法における天井床コンクリート打設に当
っての、コンクリート充填の困難、レイタンスの除去、
劣悪作業環境等の欠点を排除し、青天井下で丁寧な打設
施工を可能とし、そのあとで鋼殻の天井鋼板の取付けと
、その下のコンクリート上面との間のモルタル充填をし
て沈埋函の岸壁での作業を終了とした。To address the above-mentioned drawbacks, in Japanese Patent Publication No. 50-29565,
By using an open-top steel shell as opposed to the fully enclosed steel shell described above, it is possible to eliminate difficulties in concrete filling and laitance when pouring concrete for the ceiling and floor using the above-mentioned construction method.
It eliminates drawbacks such as poor working environment and enables careful pouring work under blue ceilings.After that, the ceiling steel plate of the steel shell is installed and mortar is filled between the top surface of the concrete below and the immersed box is constructed. Work on the quay has been completed.
上述の諸改善にもかかわらず、下床版コンクリート打設
に当っての鋼殻の原鋼板の変形の障害は依然未解消のま
ま残されている。Despite the above-mentioned improvements, the problem of deformation of the original steel plate of the steel shell during concrete pouring for the sub-slab still remains unresolved.
本発明は、前記の未解消の障害を解決し、併せて所要鋼
材量を大巾に節約して、より安価にして上品質の沈埋函
を提供せんとするもので、鋼構造並に製作手順の改善に
より目的を達した。The present invention aims to solve the above-mentioned unresolved obstacles, and at the same time, to provide a high-quality immersed burial box at a lower cost by significantly reducing the amount of steel required, and by improving the steel structure and manufacturing process. The objective was achieved by improving the
その要点は、沈埋函を水上にて製作するに当り、先ずド
ックの底面上に原鋼板を水密かつ水平に配設し、工型断
面形桁のウェブの両側面に柱状の抗曲材を設け、沈埋函
内側の抗曲材の下部にスタッドジベルを多数植設したブ
ラケット状の連結装置を装着した側桁を構成し、前記原
鋼板の両側に前記側桁を配置し、前記■型断面形桁の下
フランジと原鋼板とを水密に溶接し、前記原鋼板の長手
方向にバルクヘッドを設げ鋼殻を形成し、次いで該鋼殻
の原調板上に下床版コンクリートを打設し、該下底板コ
ンクリートの硬化をまって生成品の沈埋函を進水させ、
その後沈埋函構成に必要な中壁、側壁、天井床版等のコ
ンクリート打設の工程を行なうこととした。The key point is that when producing a submerged box on the water, first the raw steel plates are placed watertight and horizontally on the bottom of the dock, and column-shaped bending members are installed on both sides of the web of the cross-section shaped girder. , constructing a side girder equipped with a bracket-like connecting device with a number of stud dowels planted in the lower part of the bending member inside the submerged box, placing the side girder on both sides of the raw steel plate, and forming the side girder with the ■-shaped cross section. The lower flange of the girder and the raw steel plate are watertightly welded, a bulkhead is provided in the longitudinal direction of the raw steel plate to form a steel shell, and then concrete for the lower deck is poured on the master plate of the steel shell. , wait for the concrete of the lower base plate to harden, and then launch the immersed product into a submerged box;
After that, we decided to perform the process of pouring concrete for the inner walls, side walls, ceiling slabs, etc. necessary for the immersed box structure.
この方法によると、鋼殻の原鋼板はドックの底面に支え
られて平坦に配設されており、下床版コンクリートを打
設しても、その重量によって変形することはな(、剛性
の大きい■聖断面形状の鋼桁と、剛性の大きい下床版コ
ンクリートとの結合にシャーコネクタ機能を備えたブラ
ケット状の連結装置を配置することにより、該結合部に
発生する該鋼桁が吃水線下の水圧で沈埋函内方へ押され
る事による彎曲力と、沈埋函の天井床版や側壁の重さを
下床版コンクリートに伝達する剪断力とに対して結合を
強化して剛性の強い沈埋函とし、かつ原鋼板に対して強
度への貢献を免することにより鋼材量の節減を可能とし
た。According to this method, the raw steel plates of the steel shell are supported by the bottom of the dock and are laid flat, so even when the sub-floor concrete is poured, they will not deform due to the weight of the sub-floor concrete. ■ By arranging a bracket-like connecting device with a shear connector function to connect the steel girder with a cross-sectional shape and the highly rigid sub-slab concrete, the steel girder generated at the joint will be below the water line. The immersion box has strong rigidity by strengthening the bond against the bending force caused by the water pressure pushing the immersion box inward and the shearing force that transfers the weight of the ceiling slab and side walls of the immersion box to the concrete subfloor slab. It is possible to reduce the amount of steel by making it a box and not contributing to the strength of the original steel plate.
本発明の方法の詳細を、図示の実施例について以下に説
明する。Details of the method of the invention are described below with reference to illustrated embodiments.
第1図は沈埋函の天井の一部を破砕した概略斜視図で、
1は沈埋函の運搬、沈設、隣接面との結合等工事手順の
ためのものでトンネル開通時は撤去されているバルクヘ
ッド、2は下床版、3は側壁、4は天井床版を示す。Figure 1 is a schematic perspective view of a partially fragmented ceiling of the immersed box.
1 shows the bulkhead, which was removed when the tunnel was opened for construction procedures such as transporting, sinking, and connecting the immersed box to the adjacent surface, 2 shows the lower floor slab, 3 shows the side wall, and 4 shows the ceiling slab. .
第2図は本発明の方法による製作途中の沈埋函の横断面
の部分図、第3図は第2図の左下部の拡大図である。FIG. 2 is a partial cross-sectional view of a submerged burial box in the process of being manufactured by the method of the present invention, and FIG. 3 is an enlarged view of the lower left part of FIG. 2.
ドックの底面5上の適宜な間隔片6の上に、溶接して水
密に一体とした原鋼板Iを水平に配−置する。Raw steel plates I, which are welded and watertightly integrated, are placed horizontally on the bottom surface 5 of the dock at appropriate spacing pieces 6.
ウェブ9、下フランジ10、上フランジ11よりなる■
型断面形桁のウェブ9の両側面に柱状の抗曲材12を設
け、沈埋函内側の抗曲材12の下部に、シャーコネクタ
の役目をするスタッドジベル14’d!J植設したブラ
ケット状の連結装置13を装着した側桁8を構成して前
記原鋼板70両側に配置し、下フランジ10の端と、原
鋼板7の端とを溶接目15により水密になるように溶接
する。Consisting of web 9, lower flange 10, and upper flange 11■
Column-shaped bending members 12 are provided on both sides of the web 9 of the type cross-section type girder, and a stud dowel 14'd that serves as a shear connector is installed at the bottom of the bending members 12 inside the submerged box. A stringer 8 equipped with a bracket-shaped connecting device 13 planted in J is constructed and placed on both sides of the raw steel plate 70, and the end of the lower flange 10 and the end of the raw steel plate 7 are made watertight by the weld seam 15. Weld as shown.
バルクヘッド1を原鋼板7の長手方向両端に設ける事に
より、本発明の構造の主要部の鋼殻がドック内にて完成
し、第4図の姿となる。By providing the bulkheads 1 at both ends of the raw steel plate 7 in the longitudinal direction, the steel shell, which is the main part of the structure of the present invention, is completed in the dock, resulting in the appearance shown in FIG. 4.
鋼殻が完成の上は、ドック内で、そのままの位置で、原
鋼板7上に、下床版コンクリート16のための鉄筋の施
工をした上で、コンクリートを打設して下床版2を構成
して、第5図の姿となる。After the steel shell is completed, reinforcing bars for the concrete 16 for the lower deck slab are placed on the original steel plate 7 in the same position in the dock, and concrete is poured to form the lower deck 2. The configuration is as shown in Figure 5.
下床版コンクリート16の硬化中の日数を活用して、下
床版コンクリート16に連設する中壁コンクリート17
および側壁コンクリート18のための鉄筋の施工を、事
情が許す範囲内でなるだけ工事を進めておくが工程進捗
上有効である。Taking advantage of the number of days that the lower floor concrete 16 is curing, the middle wall concrete 17 is connected to the lower floor concrete 16.
It is effective for the progress of the process to proceed with the construction of reinforcing bars for the concrete side walls 18 as much as possible within the circumstances.
下床版コンクリート16の硬化ヲ待って、コノ半成品の
沈埋函を進水させる。After waiting for the concrete 16 for the lower floor to harden, the semi-finished immersed container is launched.
この時の吃水は第6図に示す如(、鋼殻のみの重量相当
分の0,54mと下床版コンクリート分3.37mの合
計3.91mとなる。The stifling water at this time was as shown in Figure 6 (0.54 m corresponding to the weight of the steel shell alone and 3.37 m for the concrete of the lower deck, totaling 3.91 m.
回生成品の沈埋函を曳航して、両層のコンクリート打設
工事の準備ができている岸壁に至り、撃留する。The immersed box containing recycled products will be towed to the quay where preparations are being made for concrete pouring work on both layers, where it will be deported.
中壁コンクリート17の打設により、吃水は第7図に示
す如く、4.26mとなり、更に次工程の側壁コンクリ
ート18の打設により、吃水は第8図に示す如(,5,
34771と増加する。By placing the middle wall concrete 17, the hiccup will be 4.26 m as shown in Figure 7, and by pouring the side wall concrete 18 in the next step, the hiccup will be reduced to 4.26 m as shown in Figure 8.
It increases to 34,771.
天井床版コンクリ−)19の打設&ζ鋼殻の天井鋼板2
0の装着がない状態で実施されるので配筋並に打設、お
よびレイタンス除去を好環境下で丁寧に実施し、天井鋼
板20の装着、モルタルの充填により、吃水は第9図に
示す如<8.95mとなる。Ceiling floor slab concrete) 19 pouring & ζ steel shell ceiling steel plate 2
Since the work was carried out without the installation of steel reinforcing steel, reinforcement was laid and placed, and laitance was removed carefully in a favorable environment. By installing the ceiling steel plate 20 and filling with mortar, the dripping was eliminated as shown in Figure 9. <8.95m.
天井床版コンクリ−H9の打設工事用の支保工撤去、内
部清掃が終ると沈埋函は完成し、第10図の姿となり、
沈埋個所への曳航に対し待機する。After removing the support for pouring the concrete ceiling slab H9 and cleaning the inside, the immersed box was completed and looked like Figure 10.
Standby for towing to the buried site.
本発明の構造によると、鋼殻を構成する側桁8と、下床
版コンクリート16とを、連結装置13により強固に連
結して沈埋函の剛性の中心とし、原鋼板7は、下床版コ
ンク!J−)16打設時の下型枠の役目と、防水のため
の役目を中心とし、強度に期待するところが少いので、
左程厚い鋼板を必要とせず、天井鋼板20に至っては型
枠の役目もない事より、むしろこれを排して、天井床版
コンクリート19に防水施工をもって代替することすら
も可能である。According to the structure of the present invention, the side girder 8 constituting the steel shell and the concrete lower deck 16 are firmly connected by the connecting device 13 to serve as the center of rigidity of the submerged box, and the raw steel plate 7 is connected to the concrete lower deck 16. Conch! J-)16 It mainly serves as the lower formwork during pouring and for waterproofing, and there are few expectations for its strength.
There is no need for a thick steel plate, and the ceiling steel plate 20 does not serve as a formwork, and it is even possible to eliminate it and replace it with the ceiling slab concrete 19 by waterproofing.
以上の如くであるので、本発明の構造によると、先行技
術の場合と比較して、鋼材所要量において、試設計では
、40〜50%の節約が可能となる。As described above, according to the structure of the present invention, it is possible to save 40 to 50% in the amount of steel required in the trial design compared to the case of the prior art.
本発明の方法によると、原鋼板7の変形に対しての配慮
を全く無用とするため、原鋼板7の厚さを薄くする事を
許し、下床版コンクリート16の打設にあたり、打設コ
ンクリートの重量による原鋼板7の二次変形防止のため
の打設個所を細分してその打設順序を調整する等の配慮
を無用とし、先行技術の鋼殻を上面開放型とする事によ
る利点と相俟って、沈埋函製作手間を大きく改善するこ
とができる。According to the method of the present invention, in order to completely eliminate the need to consider the deformation of the raw steel plate 7, the thickness of the raw steel plate 7 is allowed to be reduced, and when pouring concrete for the sub-slab 16, The advantages of using the prior art steel shell as an open-top type eliminates the need to subdivide the pouring locations and adjust the pouring order in order to prevent secondary deformation of the raw steel plate 7 due to the weight of Together, the time and effort required to produce immersed boxes can be greatly improved.
第1図は沈埋函の概略の斜視図、第2図は本発明の方法
による沈埋函の横断面の部分図、第3図は第2図の左下
隅部の拡大図、第4図乃至第10図沈埋函製作工程の説
明図。
1・・・バルクヘッド、2・・・下床版、3・・・側壁
、4・・・天井床版、5・・・ドックの底面、6・・・
間隔片、7・・・原鋼板、8・・・側桁、9・・・ウェ
ブ、10・・・下フランジ、11・・・上フランジ、1
2・・・抗曲材、13・・・連結装置、14・・・スタ
ットジヘル、15・・・溶接目、16・・・下床版コン
クリート、17・・・中壁コンクリート、18・・・側
壁コンクリート、19・・・天井床版コンクリート、2
0・・・天井鋼板。FIG. 1 is a schematic perspective view of the immersed burial box, FIG. 2 is a partial cross-sectional view of the immersed burial box made by the method of the present invention, FIG. 3 is an enlarged view of the lower left corner of FIG. 2, and FIGS. Figure 10 is an explanatory diagram of the submerged box manufacturing process. 1... Bulkhead, 2... Lower floor slab, 3... Side wall, 4... Ceiling floor slab, 5... Bottom of dock, 6...
Spacing piece, 7... Raw steel plate, 8... Side girder, 9... Web, 10... Lower flange, 11... Upper flange, 1
2... Resistance bending material, 13... Connecting device, 14... Studgeher, 15... Welding seam, 16... Subfloor slab concrete, 17... Middle wall concrete, 18... Side wall Concrete, 19...Ceiling slab concrete, 2
0...Ceiling steel plate.
Claims (1)
面上に底鋼板な水密かつ水平に配設し、■型断面形桁の
ウェブの両側面に柱状の抗曲材を設け、沈埋函内側の抗
曲材の下部にスタンドジベルを多数植設したブラケット
状の連結装置を装着した側桁を構成し、前記底鋼板の両
側に前記側桁を配置し前記■型断面形桁の下フランジと
底鋼板とを水密に溶接し、前記底鋼板の長手方向にバル
クヘッドを設げ鋼殻を形成し、次いで該鋼殻の底鋼板上
に下床版コンクリートを打設し、該下床板コンクリート
の硬化をまって生成品の沈埋函を進水させ、その後沈埋
函構成に必要な中壁、側壁、天井床版等のコンクリート
打設の工程を行なうことを特徴とする沈埋函の製作方法
。1. When manufacturing a submerged box on the water, first, a steel plate bottom is placed watertight and horizontally on the bottom of the dock, and pillar-shaped bending members are installed on both sides of the web of the type cross-section girder. The side girder is equipped with a bracket-like connecting device with a number of stand dowels planted in the lower part of the inner bending member, and the side girder is arranged on both sides of the bottom steel plate, and the lower flange of the ■-shaped cross-section girder is constructed. and a bottom steel plate are welded watertightly, a bulkhead is provided in the longitudinal direction of the bottom steel plate to form a steel shell, and then a subfloor concrete is poured on the bottom steel plate of the steel shell, and the bottom steel plate is welded to the bottom steel plate in a watertight manner. 1. A method for producing a submerged box, which comprises: waiting for the submerged box to harden, then launching the product into the submerged box, and then carrying out the process of pouring concrete for the inner walls, side walls, ceiling slab, etc. necessary for constructing the submerged box.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP53094542A JPS5930880B2 (en) | 1978-08-04 | 1978-08-04 | How to make a sunken burial box |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP53094542A JPS5930880B2 (en) | 1978-08-04 | 1978-08-04 | How to make a sunken burial box |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5523211A JPS5523211A (en) | 1980-02-19 |
| JPS5930880B2 true JPS5930880B2 (en) | 1984-07-30 |
Family
ID=14113196
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP53094542A Expired JPS5930880B2 (en) | 1978-08-04 | 1978-08-04 | How to make a sunken burial box |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5930880B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6260579U (en) * | 1985-07-18 | 1987-04-15 |
-
1978
- 1978-08-04 JP JP53094542A patent/JPS5930880B2/en not_active Expired
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6260579U (en) * | 1985-07-18 | 1987-04-15 |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5523211A (en) | 1980-02-19 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104594500B (en) | Integrated slab column formwork structure system and construction method | |
| CN112323635A (en) | Construction method for cast-in-place wet joint and bridge structure | |
| CN114482304A (en) | Construction method of composite insulation board of building | |
| CN111411643A (en) | A construction method for a construction elevator foundation supported on a basement roof | |
| CN207812307U (en) | The construction system of Cable stayed Bridge Main Tower and steel anchor beam | |
| CN211849593U (en) | Anti device and anti system that floats of immersed tube lumen template | |
| JPS5930880B2 (en) | How to make a sunken burial box | |
| CN108570974A (en) | A kind of prefabricated fish pass slot of bottom plate | |
| CN107012985A (en) | A kind of prefabricated girder and the laminated floor slab construction technology containing the prefabricated girder | |
| CN110820805A (en) | Prefabricated assembly and cast-in-place mixed comprehensive pipe gallery construction method | |
| JPS5910240Y2 (en) | Immersed steel shell | |
| CN109914571A (en) | A kind of basement drainage ditch formwork system, casting system and construction method | |
| CN209082509U (en) | It is a kind of to fall to support the load bearing support structure of bracing members for underground structure deep basal pit | |
| JP3332595B2 (en) | How to make a caisson bottom plate | |
| JPS6128626A (en) | Construction of marine concrete structure on sea | |
| JP2000355910A (en) | Space truss with concrete extra form for civil engineering such as bridge floor | |
| CN117418477B (en) | Fish-bellied box girder anti-floating reinforcement template system and installation and construction method thereof | |
| CN223047934U (en) | Prestressed concrete T-beam wet joint formwork-free construction structure | |
| CN217420172U (en) | Floor slab shelving joint | |
| CN210857525U (en) | Connecting structure of building main body and exterior cladding panel | |
| CN215561861U (en) | Construction structure of integral abutment | |
| US3767154A (en) | Composite form | |
| JPH039251B2 (en) | ||
| CN213999876U (en) | A box girder casting platform | |
| CN119593350A (en) | Prefabricated wharf and construction method |