JPS5934332A - Caisson work - Google Patents
Caisson workInfo
- Publication number
- JPS5934332A JPS5934332A JP14372782A JP14372782A JPS5934332A JP S5934332 A JPS5934332 A JP S5934332A JP 14372782 A JP14372782 A JP 14372782A JP 14372782 A JP14372782 A JP 14372782A JP S5934332 A JPS5934332 A JP S5934332A
- Authority
- JP
- Japan
- Prior art keywords
- cell
- construction
- steel plate
- underwater
- see
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/08—Lowering or sinking caissons
- E02D23/10—Caissons filled with compressed air
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
本発明は、橋梁基礎、−海洋玉串など、水中にコンクリ
ート構慮吻を1池工する吸に用いら21.る浩咽工法に
関する。DETAILED DESCRIPTION OF THE INVENTION The present invention is applicable to the construction of concrete structures in one pond, such as bridge foundations and ocean tamagushi. Concerning the drilling method.
この種の工法としては、オープンケーソン工法。This type of construction method is the open caisson construction method.
ニューマヂツクケーソン工法1M音矢叡井尚工法などか
知らγしている。これらの工法σ、)甲でニューマチツ
クケーソン工法、オープンケーソン工法は上1jls構
造か大規模な荷重の場合に多く適用される。I don't know about the New Majik caisson construction method, 1M Otoya Ai Takashi construction method, etc. These construction methods σ,) A: Pneumatic caisson construction method and open caisson construction method are often applied in cases of upper 1jls structure or large-scale loads.
とくに、水深の大きい河川、ン母中や波浪の生ずる場p
liなどで締切工費か著しく高い場合、ケーソンを曳航
し、つり下げて施工でさる。このうち、オープンケーソ
ン工法は地盤条件のよい場合に適用Tることができ、ニ
ューマチックケーソン工法に比べて低コストであるか、
土石増など、沈設に際して1櫂晋切のある場合には不適
であり、水中でのコンクリート構造物施工には条件かき
びしい。こノ点、ニューマチックケーソン工法では、−
気圧下ではあるか、ドライで作業でき、施工が確実であ
り、工程が立てや丁い長所かある。しかし、水中l施工
であるため築島し、あるいは恢細切りTるなどの仮設備
を必要とする。Especially in deep rivers, rivers, and areas where waves occur.
If the cost of cofferdam construction is extremely high, such as with a li, the caisson can be towed and suspended for construction. Among these, the open caisson method can be applied when the ground conditions are good, and it is lower cost than the pneumatic caisson method.
It is unsuitable for cases where a single paddle is required to sink the soil, such as when adding soil and stones, and the conditions are difficult for constructing concrete structures underwater. In this regard, in the pneumatic caisson construction method, -
It has the advantage of being able to work under atmospheric pressure or dry conditions, ensuring reliable construction, and having a vertical or precise process. However, since it is an underwater construction, temporary equipment such as building an island or cutting it into small pieces is required.
本発明は上記事情にもとづいてな2r1シたもので、筒
状の鋼板セルを水中地盤に打設し、止血を取り付は気蜜
状態としπ後、内部気圧を水深比以上にし茫ドライの状
態を保ちつつ、水中基礎の施工を行うことにより、大か
がすな仮設備ご不要とし、作業工程の短縮を計/;3な
どの利益かある浩−工法を提供しようとするものである
。The present invention is based on the above-mentioned circumstances, and is a 2r1 improvement, in which a cylindrical steel plate cell is cast into the underwater ground, and after the hemostasis is installed in an airy state, the internal pressure is set to be higher than the water depth ratio and the water is dry. By constructing underwater foundations while maintaining the same condition, we aim to eliminate the need for large-scale temporary equipment and shorten the work process by providing a construction method with benefits such as: .
以下、本発明の工法を基礎杭打設と併用した実施例につ
いて図面?i:参照しつつ具本的に説明する。The following are drawings of examples in which the construction method of the present invention is used in conjunction with foundation pile driving. i: Explain in detail with reference.
先づ、癲工丁べき水中地盤に対して、コンクリート+J
′cなどの基礎杭lの打設を行う(第1図参照)。First, concrete + J should be added to the underwater ground.
Driving foundation piles such as 'c' (see Figure 1).
次に筒状の鋼板セル2を曳ルし、吊持して、施工場所に
もkらし、鋼板セル2上端に設けたフレーム8に設[6
したバイブロハンマー4で、上記鋼板セル2をIJ設し
、根入れを行う(第2図参照ン。このQ合、r設の事情
を保つkめ、上記バイブロハンマーは互いに連動される
ように連動装V(を設けるとよい。次〔、鋼板セルz内
でLit要の掘削を行い、ディープウェル5t−i霞し
T:俊、均しコンクリ−)Aを水中で1廂工丁金(第3
図参照)。吹に陸上にて予めh“q或ざn7’フーチン
グの鉄筋または鉄骨Biクレーン船にて上記コンクリー
トA上に設置4丁ゐ(第弘図a照)。そして、上記’d
d4仮セル2に村して無61F15よびロック鉗取付け
る(第5図参照)。この状態で、画数セル2内は大気と
遮断2!lシるので、ディープウェル5で排水を開すし
π俊、コンプレツサなどでセル2内圧を上昇させ水深圧
に対応させつつ、セル2内の水を抜く (第6図6照)
。こ乙によって、セル2内はドライGこなる。υζにフ
ーチングコンクリートOを施工しく第7図参照)、立上
りコンクリ−)Dfi:施工する (第3図1釦。次に
セル2内部に、注水し、内部圧力を常圧にし、テイープ
ウエル排水を中止する(第9図参照)。そして、最後に
゛フーチング上部より鋼板セル2を切り履し、鋼板セル
2および魚6などをクレーン船にて吊り上げ撤去°fる
。同じくディープウェル5も撤去Tる。次に立上りコン
クリート上部を施工Tる(第lO図系照)。この場合、
鋼板セル2の一部を切り離Tために、予め、上記鋼板セ
ル2を容易に分離できる構成にして置くとよい。Next, the cylindrical steel plate cell 2 is pulled, suspended, placed at the construction site, and installed on the frame 8 provided at the upper end of the steel plate cell 2.
The above-mentioned steel plate cell 2 is IJ-set and embedded using the vibro-hammer 4 (see Fig. 2).In order to maintain this Q- and R-setting situation, the above-mentioned vibro-hammers are interlocked so that they are interlocked with each other. Next, excavate the required Lit in the steel plate cell z, and place the deep well 5t-i haze T: leveled concrete) A in water. 3
(see figure). In advance, on land, the reinforcing bars with h'q or n7' footings or steel frame Bi cranes are installed on the above concrete A (see Figure A).Then, the above 'd
d4 Attach the blank 61F15 and locking forceps to the temporary cell 2 (see Figure 5). In this state, the inside of stroke number cell 2 is blocked from the atmosphere 2! 1, so open the drain in deep well 5 and use a compressor to increase the internal pressure of cell 2 to correspond to the water depth pressure while draining the water in cell 2 (see Figure 6).
. Due to the heat, there is a dry G inside cell 2. Construct footing concrete O on υζ (see Fig. 7), standing concrete) Dfi: Construct (1 button in Fig. 3).Next, pour water into cell 2, bring the internal pressure to normal pressure, and stop tape well drainage. (See Figure 9).Finally, the steel plate cell 2 is cut from the upper part of the footing, and the steel plate cell 2, fish 6, etc. are lifted and removed by a crane boat.Deep well 5 is also removed in the same way. Next, construct the upper part of the rising concrete (see Figure 10).In this case,
In order to cut off a portion of the steel plate cell 2, it is preferable that the steel plate cell 2 be configured in advance so that it can be easily separated.
なお、上記の実j池例では、セル2内酷の土層にディー
プウェル5をe置し、浮力を生じぎせないようにしたか
、lIg礎仇1と鋼板セル2の下部とを接続する方法も
ある。また、アースアンカーでセル2′?i−抑える方
法もある。また、この実施例ではフーチングの鉄筋ある
いは鉄骨Bを予め陸上で構築し、これケクレーン船でセ
ル2内に降ろし耐が、現場において構築してもよいこと
勿論である。In addition, in the above example of the actual pond, the deep well 5 was placed in the soil layer inside the cell 2 to prevent buoyancy from occurring, or the foundation 1 and the lower part of the steel plate cell 2 were connected. There is a way. Also, cell 2' with earth anchor? i-There is also a way to suppress it. Further, in this embodiment, the reinforcing bars or steel frame B of the footing may be constructed in advance on land, and then lowered into the cell 2 by a crane ship, and the structure may of course be constructed at the site.
本発明は、以上詳述したように、筒状の鋼板セルを水中
地盤にわ収し、上蓋を取り付は気缶吠態としS俊、内部
気圧を水深上以上にしたドライの状態を保ぢつつ、水中
基礎の施工を行うことを特徴とする。その結果、次のよ
うな効果か得ら2’L心。As described in detail above, the present invention is to maintain a dry state by placing a cylindrical steel plate cell in underwater ground, attaching the top cover in an open position, and keeping the internal pressure above the water depth. However, it is characterized by the construction of underwater foundations. As a result, you will get the following effects: 2'L heart.
111フーチングコンクリートかドライ施工できるので
品質の長い構造物となる。111 footing can be constructed using concrete or dry construction, resulting in a long-lasting structure.
(2) ニューマチツクケーソン工法のような染詩、
仮輔切などの大がかりな仮設備を必要としない。(2) Dyed poems such as the pneumatic caisson method,
There is no need for large-scale temporary equipment such as temporary cutting.
(3) 支持層か深くても、基礎杭か施工でさる範四
迄なら、施工かuf tkltである。(3) No matter how deep the supporting layer is, if it is up to the level of foundation pile construction, it is construction or uf tklt.
(4)南欧セルの一部を切馳Tことで、フーチングと一
本化Tるので、地盤への横抵抗か増大し、耐層上6有利
である。(4) By cutting out a part of the southern European cell, it becomes integrated with the footing, increasing the lateral resistance to the ground, which is advantageous in terms of layer resistance.
第1図ないし第fO図は本発明の1咎ルく工法(/J
−実地例を順序に図解する側面概略図である。
2・・・・・・鋼板セル、4・・・・・・バイブロハン
マー、5・・・・ディープウェル、IS・・・・・無、
。Figures 1 to 3 show the first construction method of the present invention (/J
- side schematic diagrams illustrating the practical example in sequence; 2...Steel plate cell, 4...Vibrohammer, 5...Deep well, IS...None,
.
Claims (1)
密状態とした後、内部気圧を水深比以上にしたドライの
状態を保ちつつ、水中基礎の施工After pouring a planar rice cell into the underwater ground and making the upstream part airtight, construct the underwater foundation while maintaining a dry state with internal pressure greater than the water depth ratio.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14372782A JPS5934332A (en) | 1982-08-19 | 1982-08-19 | Caisson work |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14372782A JPS5934332A (en) | 1982-08-19 | 1982-08-19 | Caisson work |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5934332A true JPS5934332A (en) | 1984-02-24 |
| JPS6143493B2 JPS6143493B2 (en) | 1986-09-27 |
Family
ID=15345592
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP14372782A Granted JPS5934332A (en) | 1982-08-19 | 1982-08-19 | Caisson work |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5934332A (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH02104229A (en) * | 1988-10-13 | 1990-04-17 | Shiitex:Kk | Fish culture device of automatic feeding and oxygenating |
| CN102619231A (en) * | 2012-03-15 | 2012-08-01 | 中冶天工上海十三冶建设有限公司 | Underground water pressure reducing valve |
| CN107642101A (en) * | 2017-09-27 | 2018-01-30 | 中铁二十局集团第工程有限公司 | A kind of rocky bed steel cofferdam back cover leak stopping and guarded drainage construction method |
| CN113668587A (en) * | 2021-09-03 | 2021-11-19 | 中建安装集团南京建设有限公司 | Construction method suitable for excavation and pressure sinking of deep and large open caisson of water-rich stratum |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS639987U (en) * | 1986-07-03 | 1988-01-22 | ||
| JPH04287U (en) * | 1990-04-19 | 1992-01-06 | ||
| CN102454167B (en) * | 2010-10-21 | 2015-09-02 | 五冶集团上海有限公司 | The construction method of especially big & deep open caisson |
-
1982
- 1982-08-19 JP JP14372782A patent/JPS5934332A/en active Granted
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH02104229A (en) * | 1988-10-13 | 1990-04-17 | Shiitex:Kk | Fish culture device of automatic feeding and oxygenating |
| CN102619231A (en) * | 2012-03-15 | 2012-08-01 | 中冶天工上海十三冶建设有限公司 | Underground water pressure reducing valve |
| CN107642101A (en) * | 2017-09-27 | 2018-01-30 | 中铁二十局集团第工程有限公司 | A kind of rocky bed steel cofferdam back cover leak stopping and guarded drainage construction method |
| CN107642101B (en) * | 2017-09-27 | 2020-01-07 | 中铁二十局集团第一工程有限公司 | Rock riverbed steel cofferdam bottom sealing and water drainage preventing construction method |
| CN113668587A (en) * | 2021-09-03 | 2021-11-19 | 中建安装集团南京建设有限公司 | Construction method suitable for excavation and pressure sinking of deep and large open caisson of water-rich stratum |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6143493B2 (en) | 1986-09-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US2895301A (en) | Stabilization of submarine raft foundations | |
| JPS60242219A (en) | Formation of offshore seabed mound | |
| JP4409357B2 (en) | Construction method for underwater foundation | |
| CA1247871A (en) | Marine template retaining wall and method of construction | |
| JP2000265474A (en) | Temporary cofferdam constructing method for construction | |
| JPS6143493B2 (en) | ||
| JP3518379B2 (en) | Construction method for underwater structures | |
| US2317016A (en) | Bridge foundation and method of making same | |
| JPS58143023A (en) | Caisson for pile supporting type breakwater | |
| JP2000290936A (en) | Construction method of pier footing and caisson for pier footing construction | |
| CN111576469A (en) | A new type of transmission line tower foundation and construction method | |
| JPH0381422A (en) | Caisson method | |
| JPH03275812A (en) | Foundation construction method for soft sea bottom ground | |
| JPS60215924A (en) | Settlement of steel skeleton for underwater foundation structure | |
| JPS58113423A (en) | Construction of cell-type underwater structure | |
| JPH0588326B2 (en) | ||
| JPS6340024A (en) | Pile-type caisson work | |
| JPS63219714A (en) | Breakwater, its construction, and concrete caisson therefor | |
| JP2512744B2 (en) | How to place underwater concrete | |
| JPS61155514A (en) | Mass concrete pouring method | |
| CN109403325A (en) | The more well foundations of major diameter steel reinforced concrete combinatorial cylinders distributing and its construction method | |
| JP3760329B2 (en) | Deep water intake equipment and method for forming the same | |
| JP2556380B2 (en) | Construction method of revetment structure | |
| CN109356187A (en) | Anchor-anchor composite foundation of suspension bridge suitable for deep-water soft soil area and its construction method | |
| CN116556400A (en) | A rapid construction method for caps in shallow coverage areas |