JPS59426A - Slope protection work - Google Patents

Slope protection work

Info

Publication number
JPS59426A
JPS59426A JP10938882A JP10938882A JPS59426A JP S59426 A JPS59426 A JP S59426A JP 10938882 A JP10938882 A JP 10938882A JP 10938882 A JP10938882 A JP 10938882A JP S59426 A JPS59426 A JP S59426A
Authority
JP
Japan
Prior art keywords
formwork
slope
mortar
concrete
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10938882A
Other languages
Japanese (ja)
Other versions
JPS6160207B2 (en
Inventor
Shingen Nagaoka
信玄 長岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FURII KOGYO KK
Original Assignee
FURII KOGYO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FURII KOGYO KK filed Critical FURII KOGYO KK
Priority to JP10938882A priority Critical patent/JPS59426A/en
Publication of JPS59426A publication Critical patent/JPS59426A/en
Publication of JPS6160207B2 publication Critical patent/JPS6160207B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

PURPOSE:To make easier the protection work of slope by a method in which cement mortar is placed into a formwork pipe made up by setting an upper formwork on a lower formwork partly buried in cement mortar, etc., sprayed on a slope, and then the upper formwork is removed. CONSTITUTION:In a formwork pipe 1 consisting of upper and lower formworks 11 and 14, L-shaped couplers 13 are formed throughout the whole length of the lower ends of side plates 12 facing the formwork 11. The width of the formwork 14 of the same length as the formwork 11 is matched with the interval between the plates 12 and coupling pieces 15 are vertically erected in mutually facing manner throughout the whole length in the longitudinal direction of the formwork 14. The pieces 15 are projected from concrete 5 sprayed with a given width on a slope A, part of the formwork 14 is buried, iron bars 2 are set, and the couplers 13 are fitted into the pieces 15 to set the formwork 11. Then, cement mortar 4 is placed into the pipe 1 and hardened, the formwork 11 is removed, and concrete structure C is constructed. In the next place, the structure C is likewise constructed.

Description

【発明の詳細な説明】 この発明は、法面保護工法に関するものである。[Detailed description of the invention] This invention relates to a slope protection method.

従来、法面保護の方法としてモルタル吹付工法、石積工
法、コンクリート擁壁工法、法枠工法、アンカニ法が存
在するが、これら工法はいずれも各々欠点を有する。
Conventionally, methods for protecting slope surfaces include mortar spraying, masonry, concrete retaining wall, slope framing, and Ankani method, but each of these methods has its own drawbacks.

すなわちモルタル吹付工法では耐久力がなく、石積工法
、コンクリート擁壁工法は作業に多大の労力を要し、危
険を供い、かつ施工費が高い。
In other words, the mortar spraying method lacks durability, and the masonry construction method and concrete retaining wall construction method require a great deal of labor, are dangerous, and have high construction costs.

また、法枠工法を施工する場合、一般的に切取法面は凹
凸がはげしく、斜面での作業となるため型枠の組立てに
時間、費用を要しかつ、型枠組立てに熟練工を要する。
Furthermore, when constructing the slope method, the cut slope is generally very uneven and the work is performed on a slope, so it takes time and money to assemble the formwork, and skilled workers are required to assemble the formwork.

この発明は以上のような欠点を改善するため釦なされた
ものであシ、この発明にかかる法面に法枠を形成し、法
面の安定を図るものである。
This invention has been made in order to improve the above-mentioned drawbacks, and aims to stabilize the slope by forming a slope frame on the slope according to the invention.

しかし、従来の法枠工法とは全く新たな方法で法枠の施
工を行うもので、施工が容易で工期を大幅に短縮でき、
工事費を安価にすることができる法面保護工法を提供す
ることを目的とする。
However, this method is completely new to the conventional method of constructing the slope, and it is easy to construct and can significantly shorten the construction period.
The purpose is to provide a slope protection construction method that can reduce construction costs.

また、施工に一度使用した部材を反復して使用可能で、
施工費を低順にすることのできる法面保護工法を提供す
ることを目的とする。
In addition, parts used once for construction can be used repeatedly,
The purpose is to provide a slope protection method that can reduce construction costs.

次に図示する実施例に基づき発明の詳細な説明する。Next, the invention will be described in detail based on the illustrated embodiments.

この発明に係る法面保護工法は組立て自在の型枠パイプ
を法面に配置し、型枠パイプ内にコンクリートあるいは
モルタルを打設し、コンクリート構造物を構築すること
を特徴とする。
The slope protection method according to the present invention is characterized in that a formwork pipe that can be assembled freely is placed on the slope, concrete or mortar is poured into the formwork pipe, and a concrete structure is constructed.

〔1〕 型枠パイプ 型枠パイプ1は上部型枠11および下部型枠14に分割
し九ものを組み立てることによって構成する。上部型枠
11は断面路コ状の部材であるが、その他山形、半円形
勢種々の形状が採用可能である。上部型枠11は鋼板の
他、合成樹脂、木岬様々な材質のものが採用できる。
[1] Formwork Pipe The formwork pipe 1 is constructed by dividing into an upper formwork 11 and a lower formwork 14 and assembling nine parts. The upper formwork 11 is a member having a curved cross section, but various other shapes such as a chevron shape and a semicircular shape can be adopted. The upper formwork 11 can be made of various materials such as steel plate, synthetic resin, and wooden cape.

上部型枠11はその相対向する側板12,12の下端全
長に断面り字形の係止部13.13を相対向して形成す
る。
The upper formwork 11 has opposing side plates 12, 12 with locking portions 13, 13 having an L-shaped cross section formed over the entire length of the lower ends thereof.

下部型枠14は長方形の鋼板であってその全長は上部型
枠11の全長と同じに形成し、その幅は上部型枠11の
側板間の間隔と一致させる。この下部型枠14の長手方
向全長には係止片15゜15を相対′向して垂直に起立
する。
The lower formwork 14 is a rectangular steel plate, and its total length is made to be the same as that of the upper formwork 11, and its width is made to match the interval between the side plates of the upper formwork 11. A locking piece 15.15 is vertically erected along the entire length of the lower formwork 14 in a direction opposite to each other.

その細工部型枠14としてはエキスバンドメタル等の部
材によって形成することも可能である。
The work part formwork 14 can also be formed from a member such as expanded metal.

これは後に述べるように下部型枠14をモルタル或いは
コンクリートに一部埋設するとき、モルタル等との定着
が良好となるようするものである。
This is to ensure that when the lower formwork 14 is partially buried in mortar or concrete, as will be described later, it will be well anchored to the mortar or the like.

従って鋼板の場合であれば、第1図のごとく孔16を多
数開設しておくことも考えられる。
Therefore, in the case of a steel plate, it is conceivable to open a large number of holes 16 as shown in FIG.

〔2〕 下部型枠の固定 この発明にかかる法面保護工法の施工にあたって、まず
下部型枠14を複数本法面に固定する。
[2] Fixing of lower formwork In implementing the slope protection method according to the present invention, first, a plurality of lower formworks 14 are fixed to the slope.

下部型枠14は地山に一定幌だけモルタル或いはコンク
リート5を吹付け、このモルタル等5に一部を埋設して
固定する。係止片15,150みは幾らかモルタル等上
に突出するようにして設置する。凹凸のある地山にモル
タル等5を吹付けた後下部型枠14を設置するため、下
部型枠14の屈曲もなくなシ、後に上べる上部型枠を設
置しても、下部型枠14と上部型枠間に隙間が発生する
ことがなくなる。
The lower formwork 14 is fixed by spraying a certain amount of mortar or concrete 5 onto the ground, and partially burying it in the mortar or the like 5. The locking pieces 15, 150 are installed so as to protrude somewhat above the mortar or the like. Since the lower formwork 14 is installed after spraying mortar etc. 5 on the uneven ground, there is no bending of the lower formwork 14, and even if the upper formwork that can be climbed later is installed, the lower formwork There will be no gap between the 14 and the upper formwork.

下部型枠14は法面に公知の方法で埋設、固定した後ア
ンカの上部を下部型枠14の適宜間隔離して側設した孔
から突出せしめ、モルタル等5の硬化後、アンカ3の上
部に刻設したネジにナツトを嵌合する等の手段によって
下部型枠14を固定する。
After the lower formwork 14 is buried and fixed on the slope by a known method, the upper part of the anchor is made to protrude from a hole provided on the side of the lower formwork 14 at an appropriate distance, and after the mortar etc. 5 has hardened, it is placed on the upper part of the anchor 3. The lower formwork 14 is fixed by means such as fitting nuts into carved screws.

また、このときアンカ3に第1次緊張を与えて崩壊し易
い法面を一時的に支えることが可能である。
Moreover, at this time, it is possible to apply primary tension to the anchor 3 to temporarily support a slope that is prone to collapse.

〔3〕 鉄筋の配筋 下部型枠14上に鉄筋2を配筋する。鉄筋2はあらかじ
め鉄筋2数本を下部型枠14上に載置可能な形状のもの
を配設するようにすれは配筋が容易である。
[3] Rebar arrangement Reinforcement bars 2 are arranged on the lower formwork 14. The reinforcing bars 2 can be arranged easily if a shape that allows several reinforcing bars to be placed on the lower formwork 14 is provided in advance.

例えば、4本の鉄筋2を平行にして四角形の粋筋によっ
て一体に結合してもよい。
For example, the four reinforcing bars 2 may be made parallel and connected together by a square bar.

〔4〕 上部型枠の設置 下部型枠14上に上部型枠11を設置する。上部型枠1
1の側板12,12の係止部13.13を下部型枠の係
止片15.15に嵌合して設置する。従って鉄筋2は上
部型枠11および下部型枠14によって構成される型枠
パイプ1内に収納されることになる。
[4] Installation of upper formwork The upper formwork 11 is installed on the lower formwork 14. Upper formwork 1
The locking portions 13.13 of the side plates 12, 12 of No. 1 are fitted into the locking pieces 15.15 of the lower formwork. Therefore, the reinforcing bars 2 are housed in the formwork pipe 1 constituted by the upper formwork 11 and the lower formwork 14.

上部型枠11は、開設した孔にアンカ3の上部を挿嵌し
て、上部型枠11上面に突出せしめ、ナツト等によ漫固
定する。
The upper part of the anchor 3 is inserted into the opened hole in the upper formwork 11 so that it protrudes from the upper surface of the upper formwork 11, and is widely fixed with nuts or the like.

〔5〕 モルタル等の打設 この型枠パイプ1内にコンクリートあるいはモルタル4
を打設する(第3図)。
[5] Casting mortar etc. Concrete or mortar 4 is placed inside this formwork pipe 1.
(Fig. 3).

型枠パイプ1の下端にあたるところには基礎コンクリー
ト6を施工しておき、コンクリートあるいはモルタル4
を上方から型枠パイプ1内に流し込む。コンクリートあ
るいはモルタル4は低スランプのものでなく、上方から
下方に流れ型枠パイプ1内に充満する。
A foundation concrete 6 has been constructed at the bottom end of the formwork pipe 1, and concrete or mortar 4
is poured into the formwork pipe 1 from above. The concrete or mortar 4 is not of low slump and flows from top to bottom and fills the formwork pipe 1.

下部型枠14は地山に吹付けたモルタル又はコンクリー
ト等上に設置して屈曲しないようにしであるため、下部
型枠14と上部型枠11間に隙間が生じることなく型枠
パイプ1内のモルタル等が流出することがなくなる。
The lower formwork 14 is installed on mortar or concrete sprayed on the ground to prevent it from bending, so there is no gap between the lower formwork 14 and the upper formwork 11, and the inside of the formwork pipe 1 is Mortar etc. will not flow out.

〔6〕 上部型枠の取り外し モルタル4等が硬化した後上部型枠11を取り外すとコ
ンクリート構造物Cが構築されることになる。
[6] Removal of the upper formwork After the mortar 4 and the like have hardened, the upper formwork 11 is removed, and the concrete structure C is constructed.

取り外した上部型枠11は、次の施工に反復して使用可
能となり、工事費を安価にすることができる。
The removed upper formwork 11 can be used repeatedly for the next construction, and construction costs can be reduced.

このコンクリート構造物Cのアンカ3に第2次緊張を与
えれば崩壊し易い法面に抵抗することができる。
By applying secondary tension to the anchors 3 of this concrete structure C, it is possible to resist slopes that are prone to collapse.

〔7〕 以−ヒのよう六作業によって、法面にコンクリ
ート構造物Cを構築するが、法枠として格子状に構造物
Cを形成することも可能である。
[7] Although the concrete structure C is constructed on the slope by the above-mentioned six operations, it is also possible to form the structure C in a lattice shape as a slope.

既設のコンクリート構造物Cに対し交差する方向に型枠
を組み立てコンクリートあるいはモルタルを打設する。
Formwork is assembled in a direction crossing the existing concrete structure C, and concrete or mortar is poured.

すなわち、第4図に示すようにコンクリート構造物Cに
対し直角で法面に対し平行に貫通する横筋7を配設し、
横筋7の両側に平行に型枠8を設置する。
That is, as shown in Fig. 4, horizontal reinforcements 7 are provided that penetrate the concrete structure C at right angles and parallel to the slope.
Formwork 8 is installed parallel to both sides of the horizontal reinforcement 7.

型枠8は金網、鋼板、合成樹脂、紙等によって構成し、
その間隔はスペーサによって保持し、アンカ3によって
法面に設置固定する。
The formwork 8 is made of wire mesh, steel plate, synthetic resin, paper, etc.
The distance between them is maintained by spacers, and the anchors 3 are used to install and fix them on the slope.

この型枠8間にモルタルあるいはコンクリートを打設し
、たて梁とよと梁が連続した格子状のコンクリート構造
物Cとして法枠を施工する。
Mortar or concrete is poured between the formworks 8, and a legal frame is constructed as a concrete structure C in the form of a lattice with continuous vertical beams.

型枠パイプIKよって構成したたて梁は主土庄に抵抗し
、小規模な土圧は型枠8によって構成したよと梁によっ
て抵抗するための構造としてすぐれている。
The vertical beam formed by the formwork pipe IK resists the main soil pressure, and the structure is excellent because the beam formed by the formwork 8 resists small-scale earth pressure.

この発明にかかる法面保護工法は、以上のような構成を
有するため以下のような効果を得ることができる。
Since the slope protection method according to the present invention has the above configuration, it can obtain the following effects.

■ 型枠パイプを組み合せるだけでよいから、現場での
型枠の組立てが省力化され工期が著しく短縮できる。
■ Since it is only necessary to combine the formwork pipes, the assembly of the formwork on site is labor-saving and the construction period can be significantly shortened.

@ コンクリートあるい紘モルタルを型枠パイプ内に流
し込み打設するものであるから、吹付けの場合より著し
く作業時間を短縮できる。
@ Because concrete or mortar is poured into the formwork pipe, the work time can be significantly reduced compared to spraying.

θ コンクリート等硬化後解体した型枠パイプはさらに
次の施工に使用できるため、工事費を安価にすることが
可能である。
θ Formwork pipes that are dismantled after hardening of concrete can be used for further construction, making it possible to reduce construction costs.

[相] 下部型枠は地山に吹付けたモルタル等上に一部
埋設して設置するため屈曲することがなくなシ上部型枠
を設置したときモルタル郷が隙間から流出してしまうこ
とがなく、施工に無駄がなくなる。
[Phase] The lower formwork is partially buried above the mortar sprayed into the ground, so it does not bend, and when the upper formwork is installed, the mortar will not flow out through the gap. This eliminates waste during construction.

さらK、この発明は長大法面の保護工法として電極めて
有効である。
Additionally, this invention is extremely effective as a protection method for long slopes.

山等を切り崩し長大法面を形成する場合、第5図に示す
ように現状の地山Aを計画掘削線Bに沿って上方から段
階的に法面a、b、・・・eを徐々に形成する方法が採
用されている。
When cutting down a mountain or the like to form a long slope, as shown in Figure 5, slopes a, b, ... e are gradually cut from the top of the existing ground A along the planned excavation line B. A method of forming is adopted.

このような工法において問題となるのは法枠工法、コン
クリート擁壁工法、モルタル吹付工法、アンカニ法等の
法面保護工法を施工する以前の地山のゆるみである。
The problem with these construction methods is the loosening of the ground prior to the construction of slope protection methods such as the slope construction method, concrete retaining wall method, mortar spraying method, and Ankani method.

すなわち法面a、b、・・・eを上方から順々に形成す
るに際し、初期の地山のゆるみが生じ、下方の法面形成
作業中に地山の崩壊が発生するととがある。
That is, when forming the slopes a, b, .

また初期のゆるみが長期的な斜面の安定に太きな影響を
与えることが判明しておシ、長期的な法面保護の上でも
初期の地山のゆるみを防止することが重要である。
It has also been found that initial loosening has a significant impact on long-term slope stability, and it is important to prevent early rock loosening for long-term slope protection.

この発明は、以上のように長大法面を形成する際におい
て法面作業中は地山の初期のゆるみを防止するとともに
、法面形成後は長期的な法面保護をなすことができ、法
面形成作業が極めて安全に    ・行え、工期短縮を
図ることが可能である長大法面の保護工法を提供するこ
とを目的とする。
As described above, when forming a long slope, this invention can prevent the initial loosening of the ground during the slope work, and can provide long-term slope protection after the slope has been formed. The purpose of this invention is to provide a protection method for long slopes that allows surface formation work to be carried out extremely safely and to shorten the construction period.

さらに、施工が容易で高度な熟練工を必要とせず、また
工程短縮と工事費の低減を図ることかできる長大法面保
護工法を提供することを目的とする0 次に、図に示す実施例に基づき発明の詳細な説明する。
Furthermore, the purpose is to provide a long slope protection construction method that is easy to construct, does not require highly skilled workers, and can shorten the process and reduce construction costs. The invention will be described in detail based on the following.

) (a)  法面形成と土留め 第5図において地山Aを切崩し長大法面Bを形成する場
合、斜面上方から切崩しを開始し7て法面a、b、・・
・eを徐々に段階的に形成していく。
) (a) Slope formation and earth retention In Figure 5, when cutting down rock mass A to form long slope B, start cutting from the top of the slope, and then create slopes a, b, etc.
- Gradually form e in a step-by-step manner.

この場合、切崩し、と同時に法面a、b、・・・eに土
留めを行う(第6図)。
In this case, earth retaining is performed on slopes a, b, . . . e at the same time as cutting down (Figure 6).

土留めは型枠ノ(イブ1の下部型枠14を既述のごとく
法面に設置し、アンカ3に第1次緊張を与えて土留めを
行う。下部型枠14は法面を押える支圧板として、地山
の初期ゆるみを防止する。
Earth retention is performed by installing the lower formwork 14 of the formwork (Eve 1) on the slope as described above, applying primary tension to the anchor 3, and performing earth retention. As a pressure plate, it prevents the initial loosening of the ground.

(b)  法面形成作業の続行 上方の法面aを土留めすれば法面aの崩壊が防止される
ため、下方の法面す、c、d、eの形成作業が安全かつ
迅速に行える(第6図)。従って、上方の法面の土留め
作業を順次行うとともに、下方の法面を順次繰返して形
成し、長大法面Bを形成する(第7図)。
(b) Continuation of slope formation work If the upper slope a is earth-retained, slope a will be prevented from collapsing, so the work to form the lower slopes S, c, d, and e can be done safely and quickly. (Figure 6). Therefore, the earth retaining work for the upper slope is performed sequentially, and the lower slope is formed repeatedly to form the long slope B (FIG. 7).

〔C〕 コンクリート等の打設 上記の支圧板として使用した下部型枠14に既述したよ
うに鉄筋2.上部型枠11を組み型枠パイプ1を構成し
、モルタルあるいはコンクリート4を上方から流し込み
コンクリート構造物Cを構築する。
[C] Casting of concrete, etc. As described above, reinforcing bars 2. An upper formwork 11 is assembled to form a formwork pipe 1, and mortar or concrete 4 is poured from above to construct a concrete structure C.

コンクリート構造物Cの構築は土留め作業、法面形成作
業と平行して行うことが可能である。
The construction of the concrete structure C can be performed in parallel with the earth retaining work and the slope forming work.

(d)  上部型枠の取外し 型枠パイプ1内のモルタルあるいはコンクリート4が硬
化した後、上部型枠11を取外すとコンクリート構造物
Cが構築されることになる。
(d) Removal of the upper formwork After the mortar or concrete 4 in the formwork pipe 1 has hardened, the upper formwork 11 is removed and the concrete structure C is constructed.

このコンクリート構造物Cのアンカ3に第2次緊張を与
えれば、法面の安定を図ることができる。
By applying secondary tension to the anchors 3 of this concrete structure C, the slope can be stabilized.

(e)  その他 上記したコンクリート構造物Cに既述した方法で型枠8
および横筋7を配設し、コンクリート等を打設すればた
て梁とよと梁が格子状に連続したコンクリート構造物C
を施工可能となる(第8図)。
(e) In addition, formwork 8 is constructed using the method already described for concrete structure C mentioned above.
By placing horizontal reinforcements 7 and pouring concrete, etc., a concrete structure C with continuous vertical beams in a lattice pattern can be created.
(Fig. 8).

この発明にかかる法面保−工法は以上のような構成を有
するため、長大法面を施工するに際しても以下のような
効果を得ることができる。
Since the slope protection construction method according to the present invention has the above configuration, the following effects can be obtained even when constructing a long slope.

■ 法面形成時は剛性の型枠パイプをアンカによつ1法
面に同定し支圧板として使用するから初期の地山のゆる
みを防止し、安全な作業が行える。
■ When forming a slope, a rigid formwork pipe is attached to an anchor and used as a bearing plate to prevent the initial loosening of the ground and ensure safe work.

0 また、この発明によれば道路法面、ダム法面はもち
ろん急傾斜地の斜面、緊急を要するガケ崩れ斜面にも適
用できるが、人家の密集した斜面などにも、特別の土留
仮設備が不要なため非常に有効である。
0 In addition, this invention can be applied not only to road slopes and dam slopes, but also to slopes of steep slopes and slopes that require emergency rock collapse, but it can also be applied to slopes with densely populated houses, etc., where special temporary earth retaining equipment is not required. Therefore, it is very effective.

[株] 法面を形成した後は、型枠パイプを使用してコ
ンクリート構造物Cを構築し、さらに第2次緊張を与え
て、法面の長期の保睦、安定化を図ることができる。
[Co., Ltd.] After forming the slope, concrete structure C is constructed using formwork pipes, and secondary tension can be applied to maintain and stabilize the slope over the long term. .

0 その他、既述したような作業の迅速性、工事費の低
廉化等同様な効果を得ることができる。
0 In addition, it is possible to obtain the same effects as described above, such as speed of work and lower construction costs.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明にかかる法面保鰻工法に使用する型枠
パイプの一実施例の斜視図、第2図は型枠パイプを組立
てた状態の斜視図、第3図は施工− 状態の説明図、第4図は施工状態の斜視図、第5図、第
6図、第7図は長大法面を施工する場合の施工順序説明
図、第8図は完成斜視図であみ。 1・・型枠パイプ、2・・鉄筋、 3・会アンカ、4,5・嗜モルタル、コンクリート、1
1・・上部型枠、14・・下部型棒、A・・地山、B・
・法面、C・・コンクリート構造物。
Fig. 1 is a perspective view of an embodiment of the formwork pipe used in the slope preservation method according to the present invention, Fig. 2 is a perspective view of the formwork pipe in an assembled state, and Fig. 3 is a perspective view of the formwork pipe in the assembled state. Explanatory drawings, Fig. 4 is a perspective view of the construction state, Figs. 5, 6, and 7 are explanatory drawings of the construction order when constructing a long slope, and Fig. 8 is a completed perspective view. 1. Formwork pipe, 2. Rebar, 3. Anchor, 4, 5. Mortar, concrete, 1
1. Upper formwork, 14. Lower mold rod, A. Earth, B.
・Slope, C... Concrete structure.

Claims (2)

【特許請求の範囲】[Claims] (1)地山に吹付けたモルタル又はコンクリートに下部
型枠を、一部を埋設して設置し、該下部型枠上に鉄筋を
配筋し更に上部型枠を設置して、上部型枠及び下部型枠
よりなる型枠パイプを組み合せて型枠パイプを構成し、
該型枠パイプ内にモルタルまたはコンクリートを打設し
てコンクリート構造物を構築し、その後型枠パイプの上
部型枠を取外すことを特徴とする法面保護工法。
(1) Install the lower formwork by partially burying it in mortar or concrete sprayed on the ground, arrange reinforcing bars on the lower formwork, and then install the upper formwork. and a formwork pipe consisting of a lower formwork are combined to form a formwork pipe,
A slope protection construction method characterized by constructing a concrete structure by pouring mortar or concrete into the formwork pipe, and then removing the upper formwork of the formwork pipe.
(2)長大法面を形成するに際し、既に形成した法面に
、地山に吹付けたモルタル等に一部埋設した下部型枠を
配設してアンカに第1次緊張を与え土留めす−るととも
K、法面形成作業を継続して行い長大法面全体を形成し
て順次土留めを行うとともに、前記下部型枠には順次上
部型枠を取付けて型枠パイプを構成し、モルタルあるい
はコンクリートを打設してコンクリート構造物を構築し
、モルタル等の硬化後上部型枠を取外しアンカに第2次
緊張を与えることを特徴とする法面保護工法。
(2) When forming a long slope, a lower formwork partially buried in mortar, etc. sprayed onto the ground is placed on the already formed slope to give primary tension to the anchor and retain the soil. - Tomo K, continue the slope forming work to form the entire long slope and sequentially perform earth retaining, and at the same time, sequentially attach upper formwork to the lower formwork to form a formwork pipe, A slope protection method characterized by constructing a concrete structure by pouring mortar or concrete, removing the upper formwork after the mortar has hardened, and applying secondary tension to the anchor.
JP10938882A 1982-06-25 1982-06-25 Slope protection work Granted JPS59426A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10938882A JPS59426A (en) 1982-06-25 1982-06-25 Slope protection work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10938882A JPS59426A (en) 1982-06-25 1982-06-25 Slope protection work

Publications (2)

Publication Number Publication Date
JPS59426A true JPS59426A (en) 1984-01-05
JPS6160207B2 JPS6160207B2 (en) 1986-12-19

Family

ID=14508964

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10938882A Granted JPS59426A (en) 1982-06-25 1982-06-25 Slope protection work

Country Status (1)

Country Link
JP (1) JPS59426A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02167928A (en) * 1988-08-10 1990-06-28 Ricoh Kensetsu Kk Reinforcing work for ground
JPH03161615A (en) * 1989-11-21 1991-07-11 Kensetsu Kiso Eng Kk Execution method of slope frame
JP2006132137A (en) * 2004-11-04 2006-05-25 Okabe Co Ltd Method and structure for stabilizing slope

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02167928A (en) * 1988-08-10 1990-06-28 Ricoh Kensetsu Kk Reinforcing work for ground
JPH03161615A (en) * 1989-11-21 1991-07-11 Kensetsu Kiso Eng Kk Execution method of slope frame
JP2006132137A (en) * 2004-11-04 2006-05-25 Okabe Co Ltd Method and structure for stabilizing slope

Also Published As

Publication number Publication date
JPS6160207B2 (en) 1986-12-19

Similar Documents

Publication Publication Date Title
JP3682588B2 (en) Building member connection structure of H-shaped steel continuous foundation beam
JP2769936B2 (en) Construction method of beams and slabs in underground skeleton construction
JPS6054459B2 (en) Slope protection method
JPS59426A (en) Slope protection work
US5558470A (en) System and method for adjustably anchoring traffic barriers and wall facing panels to the soldier beams of a wall
KR101483865B1 (en) Construction Method of Underground Structure using Composite Wale
JPS5841118A (en) Sheathing and protecting method for long-sized slope
JPH05112948A (en) Permanent form and foundation execution method using it
KR100389535B1 (en) subway open cut structure water proofing method and panel thereby
JPH10299003A (en) Foundation method using precast concrete members
JPS6290445A (en) Block for foundation and its manufacture
CN109868921A (en) A kind of filling wall for preventing from collapsing outside plane
JPH0467533B2 (en)
JP3171716B2 (en) Foundation construction method on inclined surface
JPS5833644A (en) Slope protection work
JPS6350491B2 (en)
JPS6253653B2 (en)
JPH03260222A (en) Construction of slope frame and block structure
JPH02266016A (en) Structural process of underground concrete body of building
JPH0359223A (en) Foundation constructing method for reinforced concrete building
JPS5919208B2 (en) Ground reinforcement method
JPH05125740A (en) Working of exterior retaining wall
JPH05112949A (en) Execution method of foundation
JP3289163B2 (en) How to build underground structures
JPH0376929A (en) Steel-framed foundation