JPS6023521A - Construction work of concrete pile - Google Patents

Construction work of concrete pile

Info

Publication number
JPS6023521A
JPS6023521A JP12938083A JP12938083A JPS6023521A JP S6023521 A JPS6023521 A JP S6023521A JP 12938083 A JP12938083 A JP 12938083A JP 12938083 A JP12938083 A JP 12938083A JP S6023521 A JPS6023521 A JP S6023521A
Authority
JP
Japan
Prior art keywords
pile
piles
excavated
hole
tip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP12938083A
Other languages
Japanese (ja)
Inventor
Shinichi Yamato
真一 大和
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Asahi Kasei Corp
Asahi Chemical Industry Co Ltd
Original Assignee
Asahi Chemical Industry Co Ltd
Asahi Kasei Kogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Chemical Industry Co Ltd, Asahi Kasei Kogyo KK filed Critical Asahi Chemical Industry Co Ltd
Priority to JP12938083A priority Critical patent/JPS6023521A/en
Publication of JPS6023521A publication Critical patent/JPS6023521A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/26Placing by using several means simultaneously

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PURPOSE:To permit the settlement of a concrete pile without causing any damage to the pile by a method in which the pile is settled while giving vertical vibrations to the pile into an excavated pit where the ground is made sludgy by stirring in advance. CONSTITUTION:The ground is excavated by an earth auger 2, and the soil is made sludgy with groundwater, etc., by stirring it by a non-spiral shaped blade 3. When the tip of the auger 2 reaches the bearing subsoil, cement milk is jetted from the tip of the auger 2 to form a cement milk-sludge 4 mixed lump 5 near the bottom of the pit. A pile 6 is then settled into the sludge 4 while applying vertical vibration to the pile 6 by a vibrator 7.

Description

【発明の詳細な説明】 本施工法はコンクリート<いの施工方法に関し、更に詳
しくは予め掘削I−泥土化された掘削孔内にくいを沈設
するコンクリート(いの施工方法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present construction method relates to a method for constructing concrete, and more specifically, to a method for constructing concrete by depositing a slag in an excavated hole that has been turned into mud in advance.

従来、ゾレオーガ等で掘削し、泥土化された掘削孔内に
コンクリート<いを沈設する工法は提案されていたが、
いずれの工法においても孔内の泥土がくいの貫入により
締め固まり、その結果くいが貫入不能となったり、くい
が破断したりしてくい沈設が不可能なことが多かった。
Previously, a method of excavating with a Zoleauger and depositing concrete into the muddy hole had been proposed;
In either method, the mud in the hole becomes compacted due to the penetration of the piles, and as a result, the piles become unable to penetrate or break, making it often impossible to sink the piles.

本工法は予め掘削攪拌し泥土化された掘削孔内にくいを
沈設するとぎに生じていた従来のこれ等の欠点を解消し
たものであり、上下動の振動をくいに与えながらくいを
沈設すると驚くべきことに従来の工法の如きくいの貫入
による泥土の締め固まり現象やくいの破断現象が発生し
ないことを見出し、本発明を完成したのである。即ち、
本発明は、予め掘削攪拌し泥土化された掘削孔内に上下
動の振動をくいに与えながらくいを沈設するコンクリー
トくいの施工方法である。
This method eliminates these drawbacks of the conventional method, which occurs when a pile is placed in an excavated hole that has been previously excavated and stirred to become muddy soil. The present invention was completed based on the discovery that the compaction of mud and the breaking of piles do not occur as in conventional construction methods due to the penetration of piles. That is,
The present invention is a method for constructing concrete piles, in which the piles are placed in an excavated hole that has been previously excavated and stirred to become muddy soil, while applying vertical vibration to the pile.

本発明によるくいの沈設すべき孔の掘削およびその攪拌
による泥土化にあたっては、例えば第1図に示す様にア
ースオーガー2により予め地盤1を掘削し、アースオー
ガー2につげられた非ラセン状の翼3で土を攪拌し、地
盤中の地下水などにより泥土化する。この際水分が不足
するときなどは必要に応じオーが一先端より水やベント
ナイト液等の泥水を噴射しながら地盤1を掘削すること
が好ましく、また掘削時には土をほとんど孔外に排出し
ないことが好ましい。この様にしてオーが一先端が支持
地盤に達するまで掘削する。また、第2図の様に泥土化
された孔内にくいを沈設する前にオーが一先端よりセメ
ントミルクを噴出して掘削孔内の先端部付近をセメント
ミルクと泥土4との混合体5とするとともに′、オーガ
ー引き上げ時にはできる限り排土を少なくする。
When excavating a hole in which a pile is to be deposited according to the present invention and turning it into mud by stirring, for example, as shown in FIG. The soil is stirred by the blade 3 and turned into mud by groundwater in the ground. At this time, if there is a lack of water, it is preferable to excavate the ground 1 while spraying water or muddy water such as bentonite liquid from one tip of the oar as necessary.Also, it is preferable that almost no soil be discharged outside the hole during excavation. preferable. Excavate in this manner until one end of the drill reaches the supporting ground. In addition, as shown in Fig. 2, before sinking the muddy hole in the hole, cement milk is spouted from one tip of the drill and the vicinity of the tip of the hole is mixed with a mixture 5 of cement milk and mud 4. At the same time, when pulling up the auger, reduce soil removal as much as possible.

第2図はオーガーを引き上げた掘削孔を示すものである
Figure 2 shows the drilled hole with the auger pulled up.

第2図から明らかな様に、本工法は従来のセメントミル
ク工法等のゾレオーが−1法と異り、掘削孔内の土は軟
弱化するのみで、その土を掘削孔内にできる限り残し、
掘削孔の崩壊を防止するもので、できる限り排土するこ
とを目的とした従来の埋込み杭工法とは異るものである
As is clear from Figure 2, this method differs from the conventional cement milk method and other ZOL-1 methods in that the soil in the borehole is only softened, leaving as much soil as possible inside the borehole. ,
This method prevents the collapse of the excavated hole, and is different from the conventional buried pile construction method, which aims to remove as much soil as possible.

第3図はくい6を掘削孔内に沈設している状態を示すも
ので、くい頂部に上下動の振動機7を設置することによ
り(い6に上下動の振動を与え泥土中を沈設させる。こ
の場合、振動機としては鋼矢板の打込みに用いる振動機
と同様のものを用いれば十分である。
Figure 3 shows the state in which the pile 6 is sunk into the excavated hole.A vertical vibration vibrator 7 is installed at the top of the pile (the pile 6 is given vertical vibration to sink it into the muddy soil). In this case, it is sufficient to use a vibrator similar to that used for driving steel sheet piles.

くい6の沈設を更に効果的にするには、くい先端を開放
にしたり、くい先端部を第5図(11に示す様な錐状に
するとよい。第5図+21 、 (31は開放したくい
の先端状態の例である。くい先端を開放にするとくいの
掘削孔内への貫入性が向上するのみでなく、掘削孔白土
をくい中空部へ入れることができるので、くい挿入によ
る掘削孔白土の外部への排出量を軽減できるという効果
も有している。
In order to make the sinking of the pile 6 more effective, it is recommended to make the tip of the pile open or to make the tip of the pile cone-shaped as shown in Figure 5 (11). This is an example of the state of the tip of the pile.If the tip of the pile is open, it not only improves the ability of the pile to penetrate into the excavation hole, but also allows the white soil of the excavation hole to be inserted into the hollow part of the pile. It also has the effect of reducing the amount of water released to the outside.

くい先端が支持地盤に達したならば、十分支持地盤にく
いを貫入させて沈設を終了し、くい頂部に設置した振動
機7をとりはずし第4図に示す様に施工を完了する。
When the tip of the pile reaches the supporting ground, the pile is sufficiently penetrated into the supporting ground to complete the sinking, and the vibrator 7 installed at the top of the pile is removed to complete the construction as shown in Figure 4.

本発明においてはこの様にくい回転装置などの大規模な
装置は必要とせず、くいを破損することもなく、また従
来工法では不可能と考えられていたくいの貫入による泥
土の締め固まりがなく、くいをトラブルなく沈設できる
方法を提供するものである。
The present invention does not require large-scale equipment such as difficult rotating equipment, does not damage piles, and does not cause compaction of mud due to pile penetration, which was thought to be impossible with conventional construction methods. To provide a method for sinking piles without any trouble.

実施例と比較例 くいの長さ20mの地盤に施工した例を示すくいの種類
 既製コンクリートくい くいの外径 40! 施工方法、および結実 施工法I(従来工法) 掘削攪拌し泥土化された掘削孔内にくいを圧入した。2
本施工したが、いずれも圧入のみでは途中で貫入不能と
なり、支持層までくいを沈設することはできなかった。
Examples and Comparative Examples Examples of piles installed in the ground with a pile length of 20 m Types of piles External diameter of ready-made concrete piles 40! Construction method and construction method I (conventional construction method) The sludge was pressed into the borehole, which had been turned into mud by excavation and stirring. 2
Although this work was carried out, it became impossible to penetrate the piles by press-fitting alone, and it was not possible to sink the piles all the way to the support layer.

施工法■(従来工法) 掘削攪拌し泥土化した掘削孔内にくいを回転しながら沈
設した。3本施工したが、うち2本は回転力により施工
中くいが破損した。
Construction method ■ (Conventional method) The soil was excavated and agitated, and the mud turned into mud was deposited in the hole while rotating. Three piles were constructed, but two of the piles were damaged during construction due to rotational force.

支持層まで沈設できた杭の施工時間は掘削に要した時間
35分、およびくい沈設に要した時間は40分であった
The construction time for the pile that could be sunk to the support layer was 35 minutes for excavation and 40 minutes for sinking the pile.

施工法■ 本発明工法により施工した。5本施工し、いずれも支持
層まで沈設することができた。施工時間は掘削に要した
時間は約35分、およびくい沈設に要した時間は約20
分であった。
Construction method■ Construction was carried out using the construction method of the present invention. We constructed 5 pipes and were able to sink all of them to the supporting layer. Construction time was approximately 35 minutes for excavation and approximately 20 minutes for sinking piles.
It was a minute.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はアースオーが−による地盤掘削を示す断面図、
第2図は第1図におけるアースオーガを引き抜いた掘削
孔の断面図、第3図はくいを掘削図である。 1・・・地盤 2・・・アースオーガー 3・・・非ラセン状の翼 4・・・泥土 5・・・セメントミルクと泥土の混合体6・・・コンク
リート<−1 7・・・上下動の振動機 特許出願人 旭化成工業株式会社 第4図 手続補正書彷力 昭和58年11月2日 特許庁長官 若杉和夫 殿 1、事件の表示 昭和58年特許願第129380号2
、発明の名称 コンクリートくいの施工方法 3、?ili正をする者 事件との関係 特許出願人 大阪府大阪市北区堂島浜1丁目2番6号4、補正命令の
日付 昭和58年10月 1日 (発送日5B、10.25)
5、補正の対象 明細書「図面の簡単な説明」の欄 6、補正の内容 (1)、明細書第6頁第3行、[示す断面図であり。第
5FI!J」を[示す断面図、第4図はくいの沈設を終
了した勧1孔の断面図、第5図」と補正する。 以 上
Figure 1 is a cross-sectional view showing ground excavation by Earth-O.
FIG. 2 is a sectional view of the excavation hole from which the earth auger in FIG. 1... Ground 2... Earth auger 3... Non-helical blades 4... Mud 5... Mixture of cement milk and mud 6... Concrete <-1 7... Vertical movement Vibrator patent applicant: Asahi Kasei Kogyo Co., Ltd. Figure 4 Procedural amendment letter: November 2, 1980 Commissioner of the Japan Patent Office Kazuo Wakasugi 1, Indication of case: 1988 Patent Application No. 129380 2
, Name of invention Concrete pile construction method 3, ? Relationship with the Ili Correction Case Patent applicant: 1-2-6-4 Dojimahama, Kita-ku, Osaka-shi, Osaka Prefecture, date of amendment order: October 1, 1980 (shipment date: 5B, 10.25)
5. Column 6 of the specification to be amended, "Brief explanation of the drawings," Contents of amendment (1), page 6, line 3 of the specification, [This is a sectional view shown] 5th FI! Correct ``J'' to ``Cross-sectional view shown in Figure 4 and Figure 5 showing a cross-sectional view of the first hole where piles have been placed.''that's all

Claims (1)

【特許請求の範囲】[Claims] 予め掘削攪拌し泥土化された掘削孔内に上下動の振動を
くいに与えながらくいを沈設することを特徴とするコン
クリートくいの施工方法
A method for constructing concrete piles, which is characterized by depositing piles in an excavated hole that has been previously excavated and stirred to become muddy soil while applying vertical vibration to the pile.
JP12938083A 1983-07-18 1983-07-18 Construction work of concrete pile Pending JPS6023521A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12938083A JPS6023521A (en) 1983-07-18 1983-07-18 Construction work of concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12938083A JPS6023521A (en) 1983-07-18 1983-07-18 Construction work of concrete pile

Publications (1)

Publication Number Publication Date
JPS6023521A true JPS6023521A (en) 1985-02-06

Family

ID=15008145

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12938083A Pending JPS6023521A (en) 1983-07-18 1983-07-18 Construction work of concrete pile

Country Status (1)

Country Link
JP (1) JPS6023521A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08209696A (en) * 1995-02-03 1996-08-13 Fumio Kinoshita Pile burying method for foundation pile and burying attachment and pile burying device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08209696A (en) * 1995-02-03 1996-08-13 Fumio Kinoshita Pile burying method for foundation pile and burying attachment and pile burying device

Similar Documents

Publication Publication Date Title
JP2002155530A (en) Embedding method and tip metal fitting of existing pile
JP2731806B2 (en) Construction method of soil cement composite pile
JP4074198B2 (en) How to remove existing piles
JPS6023521A (en) Construction work of concrete pile
JPH0536565B2 (en)
JPH0656015B2 (en) Pile inside digging method
JP3673171B2 (en) Concrete pile setting method
JPS62253817A (en) Burying work of custom-made concrete pile with expanded head
GB2137678A (en) Method and apparatus for pile construction
JPS60115718A (en) Laying of pile
JPH0627405B2 (en) Ready-made pile burying method
JPH0442493B2 (en)
JPH0325121A (en) Sinking of pile in inner drilling pile method
JPS6286223A (en) Settlement work of prefabricated pile
JPS6023522A (en) Construction work of concrete pile
JPH08199567A (en) Construction method of pile
JPS58120918A (en) Burying method for pile
JPS6130090B2 (en)
JPS6131246B2 (en)
JPS6043490B2 (en) Pile driving method
JPS62202118A (en) Burying work of pile
JPH0121288B2 (en)
JPS61117323A (en) Method of burying ready-made pile
JPH0240152Y2 (en)
JPH0442356Y2 (en)