JPS60250194A - Shield tunnel partial enlarging construction method - Google Patents
Shield tunnel partial enlarging construction methodInfo
- Publication number
- JPS60250194A JPS60250194A JP59104978A JP10497884A JPS60250194A JP S60250194 A JPS60250194 A JP S60250194A JP 59104978 A JP59104978 A JP 59104978A JP 10497884 A JP10497884 A JP 10497884A JP S60250194 A JPS60250194 A JP S60250194A
- Authority
- JP
- Japan
- Prior art keywords
- segment
- shield tunnel
- enlarged
- earth anchor
- section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims description 20
- 238000000034 method Methods 0.000 claims description 8
- 230000003014 reinforcing effect Effects 0.000 claims 1
- 238000009412 basement excavation Methods 0.000 description 7
- 239000012779 reinforcing material Substances 0.000 description 5
- 239000000126 substance Substances 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 230000002787 reinforcement Effects 0.000 description 3
- 238000002347 injection Methods 0.000 description 2
- 239000007924 injection Substances 0.000 description 2
- 239000007788 liquid Substances 0.000 description 2
- 230000002093 peripheral effect Effects 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000002411 adverse Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000007790 scraping Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は、シールドトンネルの断面を部分的に拡大する
ためのシールドトンネル部分拡大工法に関するものであ
る。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a shield tunnel partial expansion method for partially expanding the cross section of a shield tunnel.
(従来の技術)
最近、シールドトンネル内に超高圧電カケ−プルを配線
する例が多くなってきている。この場合、′屯カケーブ
ルの接続部は他のケーブル断面より大きな断面を要する
ため、従来は立坑内ですべての接続処理を行なっていた
。ところが、シールドトンネルは近年増々大深度化の傾
向にあり、その為、立坑を設置する方法は多額の工費が
かかり、たとえ深度の小さいシールドトンネルの場合て
あっても地表面の条件、例えば、交通量、道路幅員等に
より施工が困難を極める場合が多くなっているのが現況
である。(Prior Art) Recently, there have been many cases in which ultra-high voltage electric cables are wired inside shield tunnels. In this case, since the connecting part of the tunnel cable requires a larger cross section than the other cable cross sections, conventionally all connections have been made within the shaft. However, in recent years, shield tunnels have tended to become deeper and deeper, and the method of installing vertical shafts requires a large amount of construction costs. The current situation is that construction is often extremely difficult due to the amount of road, road width, etc.
(発明が解決しようとする問題点)
そこで、シールドトンネルの部分拡大を行な°う工法が
種々提案されるに至っているが、これらの工法は施工延
長が極めて短い区間において、いずれも特殊な機械や装
置を用いて行なうもので、施工方法も複雑であり、工事
費も高価で、かつ工期も長くなるため、はとんど利用さ
れていないのが実情である。(Problem to be solved by the invention) Therefore, various construction methods have been proposed for partially enlarging the shield tunnel, but these construction methods require special machinery in sections where the construction length is extremely short. The construction method is complicated, the construction costs are high, and the construction period is long, so it is rarely used.
(発明の目的)
本発明は、以上の点に鑑み案出されたもので、シールド
トンネル内の作業のみでシールドトンネルの断面を容易
に拡大でき、かつ、安価に施コーすることかできるシー
ルドトンネル部分拡大工法を提供することを目的とする
ものである。(Object of the Invention) The present invention has been devised in view of the above points, and is a shield tunnel that allows the cross section of the shield tunnel to be easily expanded by only working inside the shield tunnel, and that can be coated at low cost. The purpose is to provide a partial expansion method.
(発明の構成)
本発明は、シールドトンネル内の部分拡大区間の上部セ
グメントに開閉窓及びアースアンカー貫通孔を有するセ
グメントを使用し、拡大部施工時、前記貫通孔を介して
アースアンカーを打込むとともに前記開閉窓を開「1し
て」二部の地山をかき落し、前記アースアンカーをガイ
ドとして前記セグメントを上昇させ、そのあとの側壁部
に拡大セグメントを取付けてシールドトンネルを部分的
に拡大するように°したもので、特殊な機械や装置δを
使用することなくシールドトンネル内の作業のみでシー
ルドトンネルの断面を部分的に拡大施工することができ
る。(Structure of the Invention) The present invention uses a segment having an opening/closing window and an earth anchor through hole in the upper segment of a partially enlarged section in a shield tunnel, and when constructing the expanded part, an earth anchor is driven through the through hole. At the same time, the opening/closing window is opened and the second part of the ground is scraped off, the segment is raised using the earth anchor as a guide, and an enlarged segment is attached to the subsequent side wall to partially enlarge the shield tunnel. It is possible to partially enlarge the cross section of the shield tunnel by simply working inside the shield tunnel without using special machines or equipment δ.
(発明の効果)
本発明によると、施]二が極めて容易であるとともに上
部セグメントをそのまま拡大部に再使用できるため、経
済的であり、安価に施工することができ、しかも拡大部
が竪形の長円形断面となるため、外力に対する対抗力が
大きくなる。また拡大区間のセグメント組立を他の部分
と同様に行なうことができるため、シールド掘進時の掘
進速度に悪影響を及ぼさない等の効果を奏し得る。(Effects of the Invention) According to the present invention, the construction is extremely easy, and the upper segment can be reused as it is for the enlarged part, so it is economical and can be constructed at low cost.Moreover, the enlarged part has a vertical shape. Since it has an oval cross section, it has a large resistance to external forces. Further, since the segments of the enlarged section can be assembled in the same manner as other parts, it is possible to produce effects such as not adversely affecting the excavation speed during shield excavation.
(実施例)
第1図はシールI・トンネルの部分拡大区間のセグメン
トを示し、第2図はその側面図を示すもので、同区間の
セグメン)lはにセグメ:、<)2.Bセグメン)3.
Aセグメント主桁からなり、水平ピース間継手5及びリ
ング間、継手6によりシールド掘進時において一般に使
用されているセグメントと同様に組立てられるものであ
る。(Example) Fig. 1 shows a segment of a partially enlarged section of Seal I tunnel, and Fig. 2 shows a side view of the segment. B segment) 3.
It consists of an A-segment main girder, and is assembled in the same manner as segments commonly used during shield excavation, using joints 5 between horizontal pieces, and joints 6 between rings.
」二部に、B、Aの各セグメントは、それぞれスキンプ
レー(・7.セグメント主桁8.セグメント継手板9よ
り構成されており、そのうち上部セグメントを構成する
Bセグメント3及びAセグメント4には後述する開閉窓
10が設けられているとともにBセグメント3には後述
するアースアンカーの貫通孔11が設けられている。In the second part, each of the B and A segments is composed of a skin play (7. Segment main girder 8. Segment joint plate 9, of which the B segment 3 and A segment 4 that make up the upper segment An opening/closing window 10, which will be described later, is provided, and the B segment 3 is also provided with a through hole 11 for an earth anchor, which will be described later.
第3図は、拡大部の上部セグメントを上昇させる際、上
部セグメントの変形を防止するために使用する補強材1
2を示し、第4図はその側面図を示すもので、補強材1
2は外周面が上部セグメントの内面と同し曲率半径の主
桁13.同主格13間をつなぐつなぎ材14.主桁13
に設けられたアースアンカー貫通孔15及び座金16か
ら構成されている。Figure 3 shows the reinforcement 1 used to prevent deformation of the upper segment of the enlargement when it is raised.
2, and FIG. 4 shows its side view.
2 is a main girder 13 whose outer peripheral surface has the same radius of curvature as the inner surface of the upper segment. Connector 14 that connects the same nominative 13. Main girder 13
It is composed of an earth anchor through hole 15 and a washer 16 provided in the ground anchor.
なお、補強材は鋼材を使用するのが望ましく、本例では
角パイプを用いている。Note that it is desirable to use steel as the reinforcing material, and in this example, a square pipe is used.
第5図及び第6図は拡大セグメントを示すもので、第5
図(a)及び第6図の左半分に示す拡大セグメント17
は、スキンプレート18.セグメントf桁19及びセグ
メント継手板20より構成され、第5図(b)及び第6
図の右半分に示す拡大セグメンj17aは、崩壊し易い
地山で積上げながら使用する高さの小さいセグメントで
、この場合スキンプレー1−18.セグメント主桁19
.セグメント継手板20及び水平ピース間継手21より
構成される。Figures 5 and 6 show enlarged segments;
Enlarged segment 17 shown in Figure (a) and left half of Figure 6
is skin plate 18. Consisting of segment f girder 19 and segment joint plate 20,
The enlarged segment j17a shown in the right half of the figure is a small-height segment that is used while piling up in a ground that is prone to collapse, and in this case, skin play 1-18. Segment main girder 19
.. It is composed of a segment joint plate 20 and a horizontal piece-to-piece joint 21.
第7図は開閉窓10を有するセグメントの平面図で、第
8図は第7図におけるA−A線矢現断面図である。FIG. 7 is a plan view of the segment having the opening/closing window 10, and FIG. 8 is a sectional view taken along the line A--A in FIG.
セグメント主桁8にはリング間継手ボルト穴22が設け
られ、セグメント継手板9にはピース間継手ナルト穴2
3が、スキンプレー・ドアの略中央にはボルト25及び
ナツト26を介して開閉可能な状態に窓24が設けられ
ている。The segment main girder 8 is provided with an inter-ring joint bolt hole 22, and the segment joint plate 9 is provided with an inter-piece joint bolt hole 2.
3, a window 24 is provided approximately in the center of the skin play door and can be opened and closed via a bolt 25 and a nut 26.
つぎに、第9図乃至第13図を参照してシールドトンネ
ルの部分拡大の施工要領を説明する。Next, the procedure for partially enlarging the shield tunnel will be explained with reference to FIGS. 9 to 13.
第9図の(a)は、拡大施工前のシールドトンネルの軸
方向断面図、(b)はそのA−A線及び(C)はB−B
線矢視断面図を示したものである。31は地山、32は
シールドトンネル−股部、33はシールドトンネル拡大
部、34は拡大部の」二部セグメント、35は拡大部の
下部セグメントであり、」二部セグメント34及び下部
セグメント35は、第1図及び第2図で既に説明した各
セグメントから構成されている。Figure 9 (a) is an axial cross-sectional view of the shield tunnel before expansion construction, (b) is its A-A line, and (C) is B-B.
It shows a cross-sectional view taken along the line. 31 is the ground, 32 is the shield tunnel-crotch part, 33 is the shield tunnel expansion part, 34 is the "two-part segment of the expansion part, 35 is the lower segment of the expansion part," the two-part segment 34 and the lower segment 35 are , the segments already explained in FIGS. 1 and 2.
まず、第10図の(a)と°そのA−A線及びB−B線
矢視断面図である(b)、(C)が示すように、拡大部
分区間に」二部セグメント34に設けられているアース
アンカー貫通孔11を通してアースアンカー38.を各
上部セグメント毎にそれぞれ平行に2木ずつ」ニブノへ
打込むとともに、薬液注入ゾーン37に薬液を注入し、
さらに、上部セグメント34の内側には補強材12を取
付ける。アースアンカー38の打込み及び薬液の注入は
坑内に据付けられたボ薬液注入はセグメントに設置しで
あるグラウトホールより行なえはよく、また補強材12
の取付けは、第14図及び第15図に示すように貫通孔
15にアースアンカー38を貫通させてナツト38によ
り固定すればよい。First, as shown in FIG. 10(a), and FIG. The earth anchor 38. into the nib knob in parallel for each upper segment, and inject the chemical into the chemical injection zone 37,
Furthermore, the reinforcement 12 is attached to the inside of the upper segment 34. Driving the earth anchor 38 and injecting the chemical liquid into the hole installed in the mine can be done through a grout hole installed in the segment, and the reinforcing material 12
For installation, the earth anchor 38 may be passed through the through hole 15 and fixed with a nut 38, as shown in FIGS. 14 and 15.
次いで、ナ・ント26を取外して上部セグメント34の
窓24を開口し、」一部の地山31をかき落しながらナ
ツト38を回軸して補強材12とともに上部セグメント
34を上昇させる。Next, the nut 26 is removed, the window 24 of the upper segment 34 is opened, and the upper segment 34 is raised together with the reinforcing material 12 by rotating the nut 38 while scraping off some of the ground 31.
第11図(a)は一部の上部セグメント34を上記によ
り所定位置まで上昇させ、そのあとに拡大セグメント1
7を取付けた状態のトンネル軸方向断面図を示したもの
である。又(b)、、(’C)は(a)におけるA−A
線及びB−B線矢視断面図を示したものである。FIG. 11(a) shows that some of the upper segments 34 are raised to a predetermined position as described above, and then the enlarged segment 1
7 is a cross-sectional view of the tunnel in the axial direction in a state where it is attached. Also, (b), , ('C) is A-A in (a)
3 shows a cross-sectional view taken along the line and the line B-B.
この作業は、拡大部区間を同時に施工するのではなく適
当な間隔、例えば本例のように1リングおきに施工し、
安全を確保しながら実施される。This work is not done in the enlarged section at the same time, but at appropriate intervals, for example, every other ring as in this example.
This will be carried out while ensuring safety.
なお、掘削は人力若しくは小型ブレーカ−な使用すれは
よい。また崩壊し易い地山の場合には安全のため、高さ
の小さい拡大セグメン)17aを積」−げなから実施す
ることができる。Note that excavation can be done manually or by using a small breaker. In addition, in the case of a rock that is prone to collapse, for safety reasons, it is possible to carry out the process by stacking enlarged segments (17a) with a small height.
第12図(a)は、拡大区間全部の上部セグメント34
を所定位置まで」二部させ、拡大セグメン)17の増刊
けを完了した状態を示すトンネル軸方向断面図であり(
b)と(C)はそのA−A線、B−B線矢視断面図であ
る。FIG. 12(a) shows the upper segment 34 of the entire enlarged section.
It is a sectional view in the tunnel axial direction showing a state in which the enlarged segment) 17 has been expanded in two parts to a predetermined position.
b) and (C) are cross-sectional views taken along line AA and line BB.
このように」二部セグメント34を所定位置まで上昇さ
せた後、第13図 (a)のトンネル軸方向断面1Δと
そのA−A線及びB−B線矢視断面図(b)、CC)が
示すように上部セグメント34の内周面付近でアースア
ンカー38を切断し、補強材12を取外すことによりシ
ールドトンネル拡大部の一次覆工か完了し、その後、コ
ンクリートを打設して二次覆工を行なうことにより拡大
部の施工が完了する。After raising the two-part segment 34 to a predetermined position in this way, the tunnel axial cross section 1Δ in FIG. As shown in Figure 3, the earth anchor 38 is cut near the inner peripheral surface of the upper segment 34 and the reinforcing material 12 is removed to complete the primary lining of the shield tunnel expansion section, and then concrete is poured and the secondary lining is completed. Construction of the enlarged section will be completed by carrying out this work.
以上に述べたシールドトンネル部分拡大工法によると以
下のような数々の効果を得ることができる。According to the shield tunnel partial expansion construction method described above, the following numerous effects can be obtained.
(1)シールド掘進時に使用したセグメントをそのまま
拡大部に再使用できるため経済的である。(1) It is economical because the segments used during shield excavation can be reused as they are for the expansion part.
(2)拡大部が竪形の長円形断面となるため外力に対す
る対抗力が大きくなり、拡大部の施工を経済的にできる
。(2) Since the enlarged section has a vertical oval cross section, the resistance to external forces is increased, making construction of the enlarged section economical.
(3)シールド掘進時に拡大部のセグメント組立を通常
のセグメントと同様に組立てることができるためシール
ド掘進速度に何らの影響を与えない。(3) During shield excavation, the segments of the enlarged portion can be assembled in the same way as normal segments, so the shield excavation speed is not affected in any way.
(4)アースアンカーをガイドとして」一部セグメント
を上昇させるので施工が極めて容易である。(4) Construction is extremely easy because some segments are raised using the earth anchor as a guide.
(5)特殊な機械、装置を必要としないため施工コス]
・が低廉である。(5) Construction cost as no special machinery or equipment is required]
・It is inexpensive.
第1図は、セグメントの断面図、
第2図は、第1図の側面図。
第3図は、補強材の断面図。
第4図は、第3図の側面図、
第5図(a)、、(b)は、それぞれ拡大セグメントの
断面図、
第6図は、左半分が第5図(a)に示した拡大セグメン
ト、右半分が第5図(b)に示した拡大セグメントの側
面図、
第7図は、開閉窓を有するセグメントの平面図、
第8図は、第7図のA−A線矢視断面図、第9図乃至第
13図は、拡大部の施工要領説明図で、それぞれの(a
)はシールドトンネルの軸方向断面図、(b)はそのA
−A線及び(C)はB−B線矢視断面を示す図、
第14図は、第11図のC部拡大図、
m15図は、第10図の平面図である。
1・・・セグメント、10・・・開閉窓。
11・・・アースアンカー貫通孔、12・・・補強材。
15・・・アースアンカー貫通孔。
17.17a・・・拡大セグメント、31・・・地山。
32・・・シールドトンネル一般6B 。
33・・・シールドトンネル拡大部。
34・・・」二部セグメント、37・・・薬液注入ゾー
ン。
38・・・アースアンカー、38・・・ナツト。
出願人 株式会社熊谷組
代理人 弁理±9船 橋 國則
第13図
(a)
第14図
(b) (c)
第15図FIG. 1 is a sectional view of the segment, and FIG. 2 is a side view of FIG. 1. FIG. 3 is a sectional view of the reinforcing material. Fig. 4 is a side view of Fig. 3, Figs. 5(a) and 5(b) are cross-sectional views of the enlarged segments, and Fig. 6 is an enlarged view of the left half shown in Fig. 5(a). Segment, the right half is a side view of the enlarged segment shown in FIG. 5(b), FIG. 7 is a plan view of the segment having an opening/closing window, and FIG. 8 is a cross section taken along line A-A in FIG. 7. Figures 9 to 13 are explanatory diagrams of the construction procedure for the enlarged section, and each (a
) is an axial cross-sectional view of the shield tunnel, and (b) is its A
-A line and (C) are views showing cross sections taken along the line B-B; FIG. 14 is an enlarged view of section C in FIG. 11; and FIG. 15 is a plan view of FIG. 10. 1...Segment, 10...Opening/closing window. 11... Earth anchor through hole, 12... Reinforcement material. 15...Earth anchor through hole. 17.17a... Expanded segment, 31... Rock. 32...Shield tunnel general 6B. 33... Shield tunnel expansion part. 34..." two-part segment, 37... chemical liquid injection zone. 38...Earth Anchor, 38...Natsuto. Applicant: Kumagai Gumi Co., Ltd. Attorney: ±9 Funabashi Kuninori Figure 13 (a) Figure 14 (b) (c) Figure 15
Claims (1)
に開閉窓及びアースアンカー貫通孔を有するセグメント
を使用し、拡大部施主時、前記貫通孔を介してアースア
ンカーを打込むとともに前記開閉窓を開口して上8tの
地山をかき落し、前記アースアンカーをガイドとして前
記上部セグメン゛1・をJJIさせ、そのあとの側壁部
に拡大セグメントを取付けてシールドトンネルを部分的
に拡大することを特徴とするシールドトンネル部分拡大
工法。 2、上部セグメント内側にはナツトを介して補強材を取
付けることを特徴とする特許請求の範囲第1項記載のシ
ールドトンネル部分拡大°工法。 3、前記」二部セグメントの上昇にともない高さの小さ
い拡大セグメントを複数個積上げながら取付けることを
特徴とする特許請求の範囲第1項記載のシールドトンネ
ル部分拡大工法。 4、拡−大部施工は拡大区間内において適当な間隔毎に
行なうことを特徴とする特許請求の範囲第1項記載のシ
ールドトンネル部分拡大工法6[Claims] A segment having an opening/closing window and an earth anchor through hole is used in the upper segment of the partially enlarged section in the shield tunnel, and when the enlarged part is installed, the earth anchor is driven through the through hole and Open the operable window and scrape off the top 8 tons of ground, use the earth anchor as a guide to JJI the upper segment 1, and then attach an enlarged segment to the side wall to partially enlarge the shield tunnel. A shield tunnel partial expansion method that is characterized by: 2. The method for enlarging a portion of a shield tunnel according to claim 1, wherein a reinforcing member is attached to the inside of the upper segment via a nut. 3. The shield tunnel partial expansion construction method according to claim 1, characterized in that as the two-part segment rises, a plurality of small-height expansion segments are stacked and attached. 4. Shield tunnel partial expansion construction method 6 as set forth in claim 1, characterized in that construction of the expansion section is carried out at appropriate intervals within the expansion section.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP59104978A JPS60250194A (en) | 1984-05-24 | 1984-05-24 | Shield tunnel partial enlarging construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP59104978A JPS60250194A (en) | 1984-05-24 | 1984-05-24 | Shield tunnel partial enlarging construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS60250194A true JPS60250194A (en) | 1985-12-10 |
| JPH031479B2 JPH031479B2 (en) | 1991-01-10 |
Family
ID=14395180
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP59104978A Granted JPS60250194A (en) | 1984-05-24 | 1984-05-24 | Shield tunnel partial enlarging construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS60250194A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2009249985A (en) * | 2008-04-10 | 2009-10-29 | Kajima Corp | Abutting section structure between underground structural member and earth retaining cut-off wall |
| JP2012057466A (en) * | 2011-12-22 | 2012-03-22 | Kajima Corp | Contact part structure between underground structural member and earth-retaining cut-off wall |
-
1984
- 1984-05-24 JP JP59104978A patent/JPS60250194A/en active Granted
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2009249985A (en) * | 2008-04-10 | 2009-10-29 | Kajima Corp | Abutting section structure between underground structural member and earth retaining cut-off wall |
| JP2012057466A (en) * | 2011-12-22 | 2012-03-22 | Kajima Corp | Contact part structure between underground structural member and earth-retaining cut-off wall |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH031479B2 (en) | 1991-01-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO2006057545A1 (en) | Tunnelling method using pre-support concept and an adjustable apparatus thereof | |
| JPS60250194A (en) | Shield tunnel partial enlarging construction method | |
| JP2942779B1 (en) | Underground wall construction method | |
| JP3948655B2 (en) | Construction method of retaining wall and underground structure | |
| JPH02200917A (en) | Landslide suppressing well cylinder and its building method | |
| CN210460663U (en) | A detachable steel corrugated plate enclosure wall | |
| JPH0257163B2 (en) | ||
| JP6729902B1 (en) | Construction method of soil cement continuous wall | |
| JPS6117696A (en) | Construction of underground head | |
| JP3076827B2 (en) | Seismic support pile | |
| JPH0351415A (en) | Constructing method for underground continuous wall | |
| JPS61186623A (en) | Method of building foundation of building | |
| JPS62178620A (en) | Formation of improved angular ground | |
| JP2675858B2 (en) | Vertical shaft excavation method | |
| JPS63247423A (en) | Underground continuous wall usable as structure base and its construction | |
| JPH03206213A (en) | Construction method of earth support | |
| JPH0960471A (en) | Wall body for shield tunneling method | |
| CN107059839A (en) | A kind of construction method of armored concrete waveform sheet pile underground structure | |
| JPH0523629Y2 (en) | ||
| JPH06220841A (en) | Construction method of continuous underground wall using steel pipe pile | |
| JPH0860650A (en) | Excavation method | |
| JP2777539B2 (en) | Tunnel connection method and tunnel connection segment | |
| JPS62236916A (en) | Treater for extra-banking portion of in-situ concrete pile | |
| JPH0317398A (en) | Construction of roof for underground structure | |
| JP2777540B2 (en) | Tunnel connection method and tunnel connection segment |