JPS6037346A - Connection of precast concrete beam and pillar - Google Patents
Connection of precast concrete beam and pillarInfo
- Publication number
- JPS6037346A JPS6037346A JP14472083A JP14472083A JPS6037346A JP S6037346 A JPS6037346 A JP S6037346A JP 14472083 A JP14472083 A JP 14472083A JP 14472083 A JP14472083 A JP 14472083A JP S6037346 A JPS6037346 A JP S6037346A
- Authority
- JP
- Japan
- Prior art keywords
- column
- concrete
- steel
- precast concrete
- concrete beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000011178 precast concrete Substances 0.000 title claims description 12
- 229910000831 Steel Inorganic materials 0.000 claims description 28
- 239000010959 steel Substances 0.000 claims description 28
- 239000004567 concrete Substances 0.000 claims description 22
- 238000005304 joining Methods 0.000 claims description 4
- 238000000034 method Methods 0.000 claims description 4
- 239000000463 material Substances 0.000 description 12
- 238000010276 construction Methods 0.000 description 3
- 238000007796 conventional method Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
Landscapes
- Joining Of Building Structures In Genera (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
本発明はプレキャストコンクリート梁をコンクリート柱
にプレストレス導入によシ剛接合する技術に関するもの
である。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a technique for rigidly joining a precast concrete beam to a concrete column by introducing prestress.
プレキャストコンクリート梁をコンクリート柱にプレス
トレス導入により剛接合することは一般に行われている
が、従来法では、コンクリート柱が既製と現場打ちの倒
れの場合も、コンクリート柱内にシースを埋設するとと
もに、このシースとプレキャストコンクリート梁内のシ
ースをコンクリートが入らないように接続する作業を必
要としている。しかし、鉄筋類やセパレータ、スペーサ
ー等が入りくんでいる接合部においてシースのセットや
接続を確実に行うことは仲々大変であって、これが従来
法の1つの問題点になっている。It is common practice to rigidly connect a precast concrete beam to a concrete column by introducing prestress, but in the conventional method, even if the concrete column is ready-made or cast-in-place, a sheath is buried within the concrete column and It is necessary to connect this sheath to the sheath inside the precast concrete beam to prevent concrete from entering. However, it is difficult to reliably set and connect the sheath at joints where reinforcing bars, separators, spacers, etc. are involved, and this is one problem with the conventional method.
本発明は、前記問題点の解決と建築物全体の工期短縮に
つながるプレキャストコンクリート梁と柱の接合方法を
提供することを目的としており、その構成上の特徴は、
鉄骨柱に取付けたブラケット上にプレキャストコンクリ
ート梁の端部を載置し、プレキャストコンクリート梁が
転倒しないように仮止めするとともに、プレキャストコ
ンクリート梁内のシースに挿通したPC鋼材の端に、鉄
骨柱を貫通するアンボンド鋼材の端部を接続し、この状
態で床コンクリートと共に柱コンクリートを打設し、柱
コンクリートが所定強度に硬化した後、アンボンド鋼材
を緊張して、その端部を柱コンクリートに定着する点に
ある。The present invention aims to provide a method for joining precast concrete beams and columns that will solve the above problems and shorten the construction period of the entire building, and its structural features are as follows:
Place the end of the precast concrete beam on the bracket attached to the steel column, temporarily secure the precast concrete beam to prevent it from falling over, and attach the steel column to the end of the PC steel material inserted through the sheath inside the precast concrete beam. Connect the ends of the unbonded steel materials that pass through, and in this state, cast column concrete together with the floor concrete. After the column concrete has hardened to the specified strength, tension the unbonded steel materials and fix the ends to the column concrete. At the point.
以下、図示の一実施態様に基いて本発明を具体的に説明
する。Hereinafter, the present invention will be specifically explained based on one embodiment shown in the drawings.
図において、1はブレキャストコンクリート梁(以下、
PC梁という)であシ、その内部には複数本のシース2
が埋設され、その各々にPC鋼材3が挿入されている。In the figure, 1 is a precast concrete beam (hereinafter referred to as
It is called a PC beam), and inside it there are multiple sheaths 2.
are buried, and a PC steel material 3 is inserted into each of them.
また、PCC10端には、下縁と上縁近くにそれぞれ短
いT形材4,5が基部をコンクリートに埋込んで取付け
られている。Further, short T-shaped members 4 and 5 are attached to the end of the PCC 10 near the lower edge and upper edge, respectively, with their bases embedded in concrete.
一方、図示の鉄骨柱6は、断面がH形(又は十字形、箱
形)で、その内側フランジ7の表面にはブラケット8が
取付けられている。On the other hand, the illustrated steel column 6 has an H-shaped (or cross-shaped, box-shaped) cross section, and a bracket 8 is attached to the surface of its inner flange 7.
本発明では、先ず、PCC10端部を鉄骨柱6のブラケ
ット8上に載置し、T形材4の露出部をブラケット8に
固着するとともに、T形材5の露出部を、T形材9を介
して鉄骨柱6の内側フランジ7に固着する。In the present invention, first, the end of the PCC 10 is placed on the bracket 8 of the steel column 6, the exposed part of the T-shaped member 4 is fixed to the bracket 8, and the exposed part of the T-shaped member 5 is fixed to the T-shaped member 9. It is fixed to the inner flange 7 of the steel column 6 via.
このよう圧して、PC梁lを転倒しない安定状態で鉄骨
柱6に仮止めするとともに、各PC鋼材3の露出端に対
向する位Mにおいて、外側から鉄骨柱6の外側フランジ
10と内側フランジ7を貫通して、アンボンド鋼材11
を差込み、その先端を、カップラー12を介してPC鋼
材3の端に接続する。By applying pressure in this way, the PC beam l is temporarily fixed to the steel column 6 in a stable state without falling over, and at the position M opposite to the exposed end of each PC steel member 3, the outer flange 10 and inner flange 7 of the steel column 6 are connected from the outside. Unbonded steel material 11
is inserted, and its tip is connected to the end of the PC steel material 3 via the coupler 12.
この状態で、床コンクリートと柱コンクリートの型枠組
立てや配筋等を行って、床コンクリート13と柱コンク
リート14f、打設する。In this state, formwork assembly and reinforcement for the floor concrete and column concrete are performed, and the floor concrete 13 and column concrete 14f are poured.
柱コンクIJ −) 14が所定強度に硬化した後、ア
ンボンド鋼材11を緊張し、その端部を、適宜の定着具
15を介して柱コンク’J −) 14に定着する。After the column concrete IJ-) 14 is hardened to a predetermined strength, the unbonded steel material 11 is tensioned and its end portion is fixed to the column concrete 'J-) 14 via an appropriate fixing device 15.
図示の場合は、PC鋼材3はPCC10製作段階で緊張
されており、シース3にはすでにグラウトが施されてい
るが、無緊張状態のPC@材3にアンボンド鋼材11を
接続し、アンボンド鋼材11の緊張によりPC鋼材3を
も緊張させる場合は、後でシース3内にグラウトを注入
することになる。In the illustrated case, the PC steel material 3 is tensioned at the PCC 10 manufacturing stage, and the sheath 3 has already been grouted. If the PC steel material 3 is also to be tensed by this tension, grout will be injected into the sheath 3 later.
本発明の接合方法は前述のようなものであり、その利点
としては次のような事項が挙げられる。The joining method of the present invention is as described above, and its advantages include the following.
柱部分のPC鋼材にアンボンド鋼材を用いたことにより
、この部分にシースを配設する必要がないから、先に述
べた従来法に比べて接合部の作業性が良好であり、施工
の確実性も大である。By using unbonded steel for the PC steel in the column, there is no need to install a sheath in this area, so the workability of the joint is better than with the conventional method mentioned earlier, and the construction is more reliable. is also large.
PC梁の端部を鉄骨柱に転倒しないように仮止めした状
態で床コンクリートと柱コンクリートを打設するので、
全体的工期の短縮が期待できる。Floor concrete and column concrete are poured with the ends of the PC beams temporarily secured to the steel columns to prevent them from falling over.
It is expected that the overall construction period will be shortened.
アンボンド鋼材の使用によシ、接合部にしん性が付与さ
れ、耐震上好ましい剛接合部が得られる。The use of unbonded steel imparts stiffness to the joint, resulting in a rigid joint that is favorable for earthquake resistance.
第1図はPC梁の端部を鉄骨柱に仮止めした状態図、第
2図はPC鋼材の接続部の拡大断面図である。
図中、l・・・PC梁、2・・・シース、3・・・PC
鋼材、6・・・鉄骨柱、11・・・アンボンド鋼材、・
・・・・・。
特許出願人・ 7ドウ建研株式会社
代理人弁理士 染 谷 廣 司Fig. 1 is a diagram showing the end of a PC beam temporarily fixed to a steel column, and Fig. 2 is an enlarged cross-sectional view of the connection part of the PC steel material. In the figure, l...PC beam, 2...sheath, 3...PC
Steel material, 6... Steel column, 11... Unbonded steel material,
・・・・・・. Patent applicant: Hiroshi Sometani, patent attorney representing 7Do Kenken Co., Ltd.
Claims (1)
ート梁の端部を載置し、プレキャストコンクリート梁が
転倒しないように仮止めするとともに、プレキャストコ
ンクリート梁内のシースに挿通したPC@材の端に、鉄
骨柱を貫通するアンボンド鋼材の端を接続し、この状態
で床コンクリートと共に柱コンクリートを打設し、柱コ
ンクリートが所定強度に硬化した後、アンボンド鋼材を
緊張して、その端部を柱コンクリートに定着することを
特徴とするプレキャストコンクリート梁と柱の接合方法
。Place the end of the precast concrete beam on the bracket attached to the steel column and temporarily secure the precast concrete beam so that it does not fall over. Connect the ends of the unbonded steel that penetrate through the column, and in this state, cast the column concrete together with the floor concrete. After the column concrete has hardened to the specified strength, tension the unbonded steel and fix the end to the column concrete. A method for joining precast concrete beams and columns.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14472083A JPS6037346A (en) | 1983-08-08 | 1983-08-08 | Connection of precast concrete beam and pillar |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14472083A JPS6037346A (en) | 1983-08-08 | 1983-08-08 | Connection of precast concrete beam and pillar |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6037346A true JPS6037346A (en) | 1985-02-26 |
| JPH0256452B2 JPH0256452B2 (en) | 1990-11-30 |
Family
ID=15368737
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP14472083A Granted JPS6037346A (en) | 1983-08-08 | 1983-08-08 | Connection of precast concrete beam and pillar |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6037346A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP0476327A1 (en) | 1990-08-20 | 1992-03-25 | Fuji Photo Film Co., Ltd. | Data-retainable photographic film product and process for producing color print |
| JP2007191865A (en) * | 2006-01-17 | 2007-08-02 | Shimizu Corp | Prestressed precast concrete member and bonded structure and prestressed precast concrete member |
-
1983
- 1983-08-08 JP JP14472083A patent/JPS6037346A/en active Granted
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP0476327A1 (en) | 1990-08-20 | 1992-03-25 | Fuji Photo Film Co., Ltd. | Data-retainable photographic film product and process for producing color print |
| JP2007191865A (en) * | 2006-01-17 | 2007-08-02 | Shimizu Corp | Prestressed precast concrete member and bonded structure and prestressed precast concrete member |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0256452B2 (en) | 1990-11-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3992401B2 (en) | Seismic reinforcement method for existing buildings with RC seismic walls | |
| JP2885055B2 (en) | Construction method of frame with precast members | |
| JPH05340031A (en) | Prestressed concrete girder and its manufacture | |
| JPH0610420A (en) | Method for connecting precast concrete member | |
| JP2831934B2 (en) | How to build substructure | |
| JPH0256452B2 (en) | ||
| JPS59192145A (en) | Fixing of iron pillar | |
| JPH07292770A (en) | Connective structure between corner post and beam | |
| JPH02221535A (en) | Connecting structure for pillar and beam | |
| JPH11181807A (en) | Construction method for underground story | |
| JP2001254519A (en) | Reinforcement structure and method using steel plate with joint bars | |
| JP2928941B2 (en) | Beam-column connection structure | |
| JPS61229070A (en) | Connection of reinforced concrete structure | |
| JPH0441733B2 (en) | ||
| JP2893406B2 (en) | Precast concrete beam-column joining method | |
| JPH11181880A (en) | Connection structure of steel members with closed section | |
| JPH0366878A (en) | Construction method of precast columns and beams and precast shear walls | |
| JP2833764B2 (en) | Pillar fixing method for steel columns | |
| JPH10325212A (en) | Precast column body for constituting steel encased reinforced concrete column | |
| JP2907038B2 (en) | Joint structure and joining method between precast beam and column | |
| JPH02248543A (en) | Connecting method for precast concrete column | |
| JPS61109842A (en) | Column/beam connection method | |
| JPS60253636A (en) | Building structure | |
| JPH04353149A (en) | Precast reinforced concrete beams and their connection method | |
| JPH0453223B2 (en) |