JPS6040428A - Installation work of caisson - Google Patents
Installation work of caissonInfo
- Publication number
- JPS6040428A JPS6040428A JP14647783A JP14647783A JPS6040428A JP S6040428 A JPS6040428 A JP S6040428A JP 14647783 A JP14647783 A JP 14647783A JP 14647783 A JP14647783 A JP 14647783A JP S6040428 A JPS6040428 A JP S6040428A
- Authority
- JP
- Japan
- Prior art keywords
- caisson
- ground
- piles
- pile
- guide holes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009434 installation Methods 0.000 title claims description 18
- 238000000034 method Methods 0.000 claims abstract description 19
- 239000004576 sand Substances 0.000 claims abstract description 15
- 238000010276 construction Methods 0.000 claims description 24
- 239000007787 solid Substances 0.000 claims description 4
- 239000000945 filler Substances 0.000 claims description 3
- 238000005192 partition Methods 0.000 abstract description 6
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 5
- 238000009991 scouring Methods 0.000 abstract description 3
- 239000004575 stone Substances 0.000 description 12
- 230000000694 effects Effects 0.000 description 2
- 239000002245 particle Substances 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000003643 water by type Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/02—Caissons able to be floated on water and to be lowered into water in situ
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
Abstract
Description
【発明の詳細な説明】
本発明は、海洋及び港湾等にケーソンタイプの構築物を
構築するに際して、工期、工費等に大きく影響するケー
ソンの据付工事を海象には余り影響されないで実施する
ことのできるケーン/の据付工法に関するものである。[Detailed Description of the Invention] The present invention makes it possible to carry out caisson installation work, which greatly affects the construction period, construction cost, etc., without being affected by sea conditions. This concerns the installation method of the cane.
防波堤、岸壁、腹岸、係船施設等をケーソン工法により
構築する海工事において実施されるケーソンの据付は、
従来の据付工法に従って次のように実施されてきた。す
なわち、石運船やガツト船等によって運搬された石材を
基礎捨石として投入し、潜水士により基礎捨石の均しを
行なってケーソンの据付基礎とし、ケーソンを上記基礎
捨石上に載置し、次いでガツト船等によって運搬された
砂等を中詰めし、中詰めされた砂等(以下、中詰め砂と
言う〕の上部に蓋コンクリートを載直し、ケーソン囲p
の水中に露出する基礎捨石上に根固方塊や被覆石を置き
、最後に既に載置した蝋コンクリートの上部に上部コン
クリートを打設していたのである。ケーソンの従来の据
付工法fc実施する場合、基礎捨石を設計位置に正確に
投入する作業や潜水士による基礎捨石の均し作業は波や
潮流の影響を受け易く、特に海象条件の厳しい例えば大
水深の海域においては、上記基礎捨石の投入作業は不正
確となると共に均し作業は危険ですらあり、加えて水深
約20.以上の場所では均し作業の能率が非常に低下し
てし1う。更にケーソンの据伺には、ケーソンを基礎捨
石上に載置する1〜1.5日の工程の後に、波によるケ
ーソンの移動を防止するために直ちに中詰め砂の投入及
び蓋コンクリートの載置の1〜1.5日の工程にとりか
からなければならず、これらの工程を合計2〜6日のう
ちに連続して実施する必要があった。しかしながら、ケ
ーソンの据付が可能なように2〜3日間静穏に連続する
海象の出現率は極めて低い。従ってケーソンの従来の据
付工法によれば、2〜6日間静穏に連続すると予知され
た日が到来する1ではケーソンの据付工事を開始するこ
とができず、ケーソンの据付がおくれることによって構
築工事全体の工期が長くなり、工費をも増加させていた
。Caisson installation carried out in marine construction work to construct breakwaters, quays, berths, mooring facilities, etc. using the caisson construction method is as follows:
The installation was carried out as follows according to the conventional installation method. In other words, stones transported by stone transport ships, Gatsuto ships, etc. are put in as foundation rubble, the foundation rubble is leveled by divers and used as the foundation for installing the caisson, the caisson is placed on the foundation rubble, and then the foundation rubble is leveled by divers. Sand, etc. transported by a Gatsuto ship, etc. is filled into the filling, and the lid concrete is re-placed on top of the filled sand, etc. (hereinafter referred to as filling sand), and the caisson enclosure is closed.
The foundation blocks and covering stones were placed on top of the foundation rubble exposed in the water, and finally the upper concrete was poured on top of the wax concrete that had already been placed. When implementing the conventional caisson installation method (FC), the work of accurately inserting the foundation rubble into the designed position and the work of leveling the foundation rubble by divers are susceptible to the effects of waves and currents, especially in severe sea conditions such as deep water. In these waters, the work of putting in the foundation rubble is inaccurate and the leveling work is even dangerous, and in addition, the water depth is about 20. In the above locations, the efficiency of leveling work will be greatly reduced. Furthermore, during the caisson installation, after the 1 to 1.5 day process of placing the caisson on the foundation rubble, filler sand is immediately poured and capping concrete is placed to prevent the caisson from shifting due to waves. 1 to 1.5 days, and these steps had to be carried out consecutively within a total of 2 to 6 days. However, the incidence of continuous calm sea conditions for 2 to 3 days to allow caissons to be installed is extremely low. Therefore, according to the conventional caisson installation method, it is not possible to start the caisson installation work on the day 1 when it is predicted that there will be continuous calm for 2 to 6 days. This lengthened the overall construction period and increased construction costs.
また、ケーソンの上記従来の据伺工法による場合は良質
の基礎捨石を大量に使用することになり、そのため、石
材の運搬懺が嵩んで工事費を増大させるばかりでなく、
陸上運搬によるダンプ公害等の建設公害や大量の6月の
海中投入による海域汚濁問題を引き起こす恐れもあった
。In addition, when using the above-mentioned conventional survey method for caissons, a large amount of high-quality foundation rubble is used, which not only increases the construction cost due to the bulk of the stone transport path.
There was also the risk of causing construction pollution such as dump pollution caused by land transport, and ocean pollution problems due to the large amount of water being dumped into the sea in June.
本発明者らはケーソンの従来の据伺工法の持つ上記種々
な欠点を解消し、海象には余り影響されないで据付が可
能で基礎捨石等の6拐の使用量が少なく現場施工の簡単
な据付工法を提供することを目的に鋭意検討した詰呆、
ケーソンの鉛直方向への移動は自由であるが水平方向へ
の移動を防止するようにパイルをケーソンに貫通せしめ
てその先端部を地盤に打ち込む工法により目的を達成で
きることを究明して本発明を成した。The present inventors solved the above-mentioned drawbacks of the conventional caisson construction method, and achieved a system that allows installation without being affected by sea conditions, uses only a small amount of foundation rubble, etc., and is easy to install on-site. Tsumezu, which has been carefully studied with the aim of providing construction methods,
The present invention was achieved by discovering that the object can be achieved by a construction method in which the caisson is free to move vertically but is prevented from moving horizontally by passing a pile through the caisson and driving its tip into the ground. did.
すなわち本発明は、ケーソンの堅壁内に複数個のパイル
ガイド孔を鉛直方向に予め貫通させて設け、上記ケーソ
ンを水中の平坦な地盤上に載置し、次いで複数個のパイ
ルをそれぞれ上記パイルカイト孔を遊嵌状に貫通せしめ
てその先端部を上記地盤中に打ち込んだ後、任急の時間
経過後にケーソン中への中詰め砂投入、蓋コンクリート
の載置及び上部コンクリート打ちを行なうことを特徴と
するケーソンの据付工法に関するものである。′以下、
本発明工法を図面を用いて詳細に説明する。That is, in the present invention, a plurality of pile guide holes are vertically penetrated in advance in the hard wall of a caisson, the caisson is placed on flat ground underwater, and then a plurality of piles are inserted into the pile guide holes, respectively. The feature is that after a hole is loosely inserted through the hole and its tip is driven into the ground, filling sand is poured into the caisson, cover concrete is placed, and the upper part is poured after a certain period of time has elapsed. This is related to the installation method of caisson. 'below,
The construction method of the present invention will be explained in detail using the drawings.
第1図は本発明工法に使用するケーソンの1例の平面図
中央縦;祈面図、第2図は第1図のA−A線断面図、第
6図は本発明工法の実施状態を示す第2図におけるB、
−B線断面説明図である。Figure 1 is a plan view of one example of a caisson used in the construction method of the present invention; B in FIG. 2 shown,
-B line cross-sectional explanatory diagram.
本発明工法を実施するには、先ずケーソン1の堅壁転向
すなわち側壁1a′内や隔壁1a/7内に複数個のパイ
ルガイド孔1bを鉛直方向に予め貫通させて設けておく
。パイルガイド孔1bの位置は特に限定する必要はない
が、第2図に示す如く堅壁1aの交差部すなわち(側壁
1a′と側壁1a’t、(側壁1a′と隔壁1a”)+
及び(隔壁1a/7と隔壁1a〃)の各交差部の壁厚を
大きくしてパイルガイド孔1bを設けるのが好ましい。In order to carry out the construction method of the present invention, first, a plurality of pile guide holes 1b are vertically penetrated and provided in advance in the solid wall of the caisson 1, that is, in the side wall 1a' or in the partition wall 1a/7. The position of the pile guide hole 1b does not need to be particularly limited, but as shown in FIG.
It is preferable to increase the wall thickness at each intersection of (the partition wall 1a/7 and the partition wall 1a) and provide the pile guide hole 1b.
第2図では全交差部にパイルガイド孔1bが設けられて
いるが、必ずしも全交差部を利用する必要になく、ケー
ソン1の製作時又はパイル2の打ち込み時において成る
可く平均に散在するように複数位置の交差部を選べば良
い。In Fig. 2, the pile guide holes 1b are provided at all intersections, but it is not necessary to use all the intersections, and the pile guide holes 1b are provided as evenly as possible during the manufacturing of the caisson 1 or the driving of the piles 2. All you have to do is select intersections at multiple locations.
このように準備したケーソン1を水中の地盤6上の所定
位置に載置する。ケーソン1の載置に際し、地盤6が平
坦な場合には、地盤6をそのままケーソンの基礎として
利用し、不陸(平坦でない部分ンがわずかに存在する場
合はその不陸部分に手を加えて直接に修正して平坦にし
ケーソン1の基礎として利用する。若し不陸が甚だしい
状態のときは、地盤6上に砂、小砂利、小砕石等の粒径
の小さい石材4を投入して不陸を修正して平坦にしケー
ソン1の基礎として利用するが、小砕石以下の粒径の小
さい石材4を使用するため、均し作業は容易であり、パ
イルの打ち込みに支障とならず、また基礎捨石に比べて
使用石材量が大幅に少なくて済む。このようにしてケー
ソン1を地盤6上の所定位置に載置したら、次いで第6
図の如く核数個のパイル2をそれぞれパイルガイド孔1
bを遊嵌状に、すなわちパイルガイド孔1bの内径より
小さな直径のパイルを使用して両者間に間隙を設けた状
態で貫通せしめてその先端部ンaを地盤6中に打ち込む
。このような状態においては、ケーソン1が波や潮流に
より水平方向の押圧力を受けてもケーソン1は複数本の
パイル2により水平面上で位置固定されているから少し
も滑動したり転倒することがない。そしてケーソン1の
自重により更には波や潮流による洗掘作用も加わってケ
ーソン1が沈下する場合、複数本のパイル2がケーソン
1のパイルガイド孔1bに遊嵌状に貫通していることに
より、ケーソン1は少しも傾くことなくその1壕の優勢
を維持してパイル2にガイドされて鉛直方向にのみ沈下
するから不等沈下は全く起らない。パイル2は上記の如
くケーソン1の滑動、転倒及び不等沈下を防止する作用
をするものであるから、地盤6中に打ち込葦れる先端部
2aの根入長は上記諸作用に必要な長さであれば良く、
支持杭のような長さを必要としない。また・2イル2の
径。The caisson 1 prepared in this way is placed at a predetermined position on the ground 6 underwater. When placing the caisson 1, if the ground 6 is flat, use the ground 6 as it is as the foundation of the caisson. It is directly corrected and flattened to be used as the foundation for the caisson 1. If the ground is extremely uneven, stones 4 with small particle diameters such as sand, small gravel, and crushed stones are poured onto the ground 6 to make it flat. The land is corrected and flattened to be used as the foundation for the caisson 1. Since stones 4 with a small particle size smaller than small crushed stones are used, the leveling work is easy and does not interfere with driving piles, and the foundation The amount of stone used is significantly less than that of rubble.Once the caisson 1 is placed in the predetermined position on the ground 6 in this way, the caisson 6
As shown in the figure, several piles 2 are connected to each pile guide hole 1.
b is loosely fitted, that is, using a pile having a smaller diameter than the inner diameter of the pile guide hole 1b, the pile is passed through with a gap provided between the two, and its tip a is driven into the ground 6. In such a state, even if the caisson 1 is subjected to horizontal pressing force due to waves or currents, the caisson 1 is fixed in position on the horizontal plane by the plurality of piles 2, so it will not slide or fall at all. do not have. When the caisson 1 sinks due to its own weight and the scouring action of waves and currents, the plurality of piles 2 penetrating the pile guide holes 1b of the caisson 1 in a loose-fitting manner will cause the caisson 1 to sink. Caisson 1 does not tilt in the slightest and maintains the predominance of that 1 trench and is guided by pile 2 and sinks only in the vertical direction, so unequal settlement does not occur at all. Since the pile 2 functions to prevent the caisson 1 from sliding, overturning, and uneven settlement as described above, the rooting length of the tip portion 2a driven into the ground 6 is the length necessary for the above-mentioned functions. It's fine if it's
Does not require the same length as support piles. Also, the diameter of 2 il 2.
長さ、断面性能、及び本数は、予想されるケーンン据付
時の波茜、設計波高及びケーソンの形状によp定められ
る。The length, cross-sectional performance, and number of canes are determined by the expected wave depth at the time of cane installation, design wave height, and caisson shape.
このようにしてケーソン1を載置しパイル2を打設する
工程の施工が終れば、次に砂等5の中詰め。When the construction process of placing the caisson 1 and driving the pile 2 is completed in this way, the next step is filling with sand or the like 5.
蓋コンクリート6の載置及び上部コンクリート7打ち等
の、施工に着手することになるが、本発明方法において
は上記の如くパイル2の打設により砂等5の中詰めが未
施工の状態でもケーソン1は全く安定に保たれているた
め、ケーソン1の載置及びパイル2の打設終了の所要日
数合計1.5〜2日後、砂等5の投入や蓋コンクリート
6の載置の工程に直ちに着手する必要はなく、海象状態
その他の事情でケーソン1の載置及びパイル2の打設の
工程が終了後一旦工手を中断し、海象の回復を待つ時間
等の任意の時間経過後に砂等50投入や蓋コンクリート
6の載置の工程にうつることができる。従って本発明方
法によれば、静穏な海象が1.5〜2日連続すると予知
されたときにケーソン据付工事を開始することが出来る
のである。そしてこの程度の日数の静穏な海象状態は従
来の据付工法による場合に要求される静穏に連続する2
〜6日間と百5日数に比べてその出現率は遥かに高く、
ケーソンの据付工期は海象にあ1り影響されることがな
い。ケーソン1はその載置及び砂等5の投入に伴って沈
下し、その後に波や潮流の洗掘作用により徐々に沈下は
継続するが、パイル2の効果によってこれらの沈下は等
沈下であり、一定量沈下すれば地盤の支持力と釣り合っ
てやがて沈下は終烟する。また中詰め砂5の上部に蓋コ
ンクリート6を載置した後に、上部コンクリート7を従
来工法と同様に打設すれば良いが、上部コンクリ−ドア
の打設時に沈下分を補なって設計高が確保できるように
上部コンクリート7を嵩上げしておくことが好ましい。Construction work such as placing the lid concrete 6 and pouring the upper concrete 7 will begin. However, in the method of the present invention, the caisson can be constructed even if the filling with sand, etc. 5 has not been completed by placing the pile 2 as described above. 1 is kept completely stable, so after a total of 1.5 to 2 days required for placing the caisson 1 and completing the pouring of the pile 2, the process of adding sand etc. 5 and placing the cover concrete 6 was started immediately. There is no need to start work, but due to sea conditions or other circumstances, after the process of placing caisson 1 and pouring pile 2 is completed, the work is temporarily suspended, and sand, etc. 50 and the process of placing the lid concrete 6. Therefore, according to the method of the present invention, caisson installation work can be started when it is predicted that calm sea conditions will continue for 1.5 to 2 consecutive days. And this level of calm sea conditions for several days is continuous with the calm required for conventional installation methods.
The appearance rate is much higher than ~6 days and 105 days,
The caisson installation period is not affected by sea conditions. Caisson 1 sinks as it is placed and sand, etc. 5 is thrown in, and then it gradually continues to sink due to the scouring action of waves and currents, but due to the effect of pile 2, these sinks are equal sinks, Once the land subsides by a certain amount, it will be balanced by the supporting capacity of the ground and the subsidence will eventually stop. In addition, after placing the lid concrete 6 on top of the filler sand 5, the upper concrete 7 may be poured in the same manner as in the conventional construction method, but the design height is increased by compensating for the settlement when placing the upper concrete door. It is preferable to raise the height of the upper concrete 7 so that it can be secured.
尚、ケーソン1が載置される地盤6の洗掘を防止するた
めには第6図の如くケーソンの港外側と港内側とに根固
方塊等8を設置することが好ましい。In order to prevent the ground 6 on which the caisson 1 is placed from being scoured, it is preferable to install foundation blocks 8 on the outside and inside of the port of the caisson, as shown in FIG.
以上、本発明方法によればケーソンタイプの港湾構築物
を構築する場合に、ケーソンの基礎造りに基礎捨石を使
用せず粒径の小さい石材を使用し、ケーソンの堅壁を遊
嵌状に貫通せしめてパイルを地盤に打ち込んでケーソン
の水平上の位置を固定してケーソンの滑動、転倒、及び
不等沈下を防止することにより、地盤へのケーソン喚の
載置後、工事を中断することを可能とさせ、従って海象
によって余り影響されることなくケーソンの据付工事を
開始し、終了することが出来るのである。こΩように本
発明方法は工期を早め、石材量を少なくして工費を安く
シ、建築公害をなくせしめる価1直あるものである。As described above, according to the method of the present invention, when constructing a caisson-type port structure, stones with small grain size are used instead of foundation rubble for the foundation construction of the caisson, and the solid walls of the caisson are penetrated in a loose-fitting manner. By driving piles into the ground and fixing the horizontal position of the caisson to prevent the caisson from sliding, overturning, and uneven settling, it is possible to interrupt the construction work after the caisson is placed on the ground. Therefore, the caisson installation work can be started and completed without being significantly affected by sea conditions. Thus, the method of the present invention has the advantage of speeding up the construction period, reducing the amount of stone needed, lowering construction costs, and eliminating construction pollution.
第1図は本発明工法に使用するケーソンの1例の平面図
中央縦断面図、第2図は第1図のA−A線断面図、第5
図は本発明工法の実施状態を示す第2図におけるB−B
線断面説明図である。
1・・ケーソン
1a・・堅壁
1a′・・側壁
1a〃・・隔壁
1b・・パイルガイド孔
2・・パイル
2a・・先端部
6・・地盤
4・・粒径の小さい石材
5・・砂等
6・・蓋コンクリート
7・・上部コンクリート
8・・根固万塊等Fig. 1 is a plan view and center vertical sectional view of an example of a caisson used in the construction method of the present invention, Fig. 2 is a sectional view taken along the line A-A in Fig. 1, and Fig. 5
The figure is B-B in Figure 2 showing the implementation state of the method of the present invention.
It is a line cross-sectional explanatory drawing. 1...Caisson 1a...Solid wall 1a'...Side wall 1a...Partition wall 1b...Pile guide hole 2...Pile 2a...Tip 6...Soil 4...Small grain size stone 5...Sand, etc. 6. Lid concrete 7. Upper concrete 8. Negoma block, etc.
Claims (1)
方向に予め貫通させて設け、上記ケーソンを水中の平坦
な地盤上に載置し、次いで複数個のパイルをそれぞれ上
記パイルガイド孔を遊嵌状に貫通せしめてその先端部を
上記地盤中に打ち込んだ後、任意の時間経過後にケーソ
ン中への中詰め砂投入、*コンタリートの載置及び上部
コンクリート打ちを行なうことを特徴とするケーソンの
据付工法。 2 パイルガイド孔を堅壁の交差部に設けたケーソンを
使用する特許請求の範囲第1項に記載のケーソンの据伺
工伝。[Claims] 1. A plurality of pile guide holes are provided vertically in advance in the hard wall of the caisson, and the caisson is placed on flat ground underwater, and then the plurality of piles are inserted into the solid wall of the caisson, respectively. After passing through the pile guide hole loosely and driving its tip into the ground, fill the caisson with filler sand after a certain period of time, place the contourite, and pour the top concrete. A distinctive caisson installation method. 2. The caisson construction work according to claim 1, which uses a caisson in which pile guide holes are provided at intersections of hard walls.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14647783A JPS6040428A (en) | 1983-08-12 | 1983-08-12 | Installation work of caisson |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14647783A JPS6040428A (en) | 1983-08-12 | 1983-08-12 | Installation work of caisson |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPS6040428A true JPS6040428A (en) | 1985-03-02 |
Family
ID=15408522
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP14647783A Pending JPS6040428A (en) | 1983-08-12 | 1983-08-12 | Installation work of caisson |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6040428A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5441871A (en) * | 1977-08-26 | 1979-04-03 | Delalande Sa | Novel 55hydroxymethyloxazolidinons and its manufacture |
| JP2022089637A (en) * | 2020-12-04 | 2022-06-16 | 国立大学法人神戸大学 | Embedment type wharf wall |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS4963208A (en) * | 1972-10-18 | 1974-06-19 | ||
| JPS51142813A (en) * | 1975-06-04 | 1976-12-08 | Saito Kiyoshi | Caisson and method of executing filling same |
| JPS5383331A (en) * | 1976-12-28 | 1978-07-22 | Taisei Corp | Method of building underwater construction |
-
1983
- 1983-08-12 JP JP14647783A patent/JPS6040428A/en active Pending
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS4963208A (en) * | 1972-10-18 | 1974-06-19 | ||
| JPS51142813A (en) * | 1975-06-04 | 1976-12-08 | Saito Kiyoshi | Caisson and method of executing filling same |
| JPS5383331A (en) * | 1976-12-28 | 1978-07-22 | Taisei Corp | Method of building underwater construction |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5441871A (en) * | 1977-08-26 | 1979-04-03 | Delalande Sa | Novel 55hydroxymethyloxazolidinons and its manufacture |
| JP2022089637A (en) * | 2020-12-04 | 2022-06-16 | 国立大学法人神戸大学 | Embedment type wharf wall |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPS60242219A (en) | Formation of offshore seabed mound | |
| JPS6040428A (en) | Installation work of caisson | |
| JP2000290936A (en) | Construction method of pier footing and caisson for pier footing construction | |
| CN208472649U (en) | A kind of Gravity Type Casisson Berth structure setting friction pile in foundation | |
| JP2017160701A (en) | Installation method to water bottom of gravitational structure | |
| JPS62215727A (en) | Foundation work for structure | |
| CN212709903U (en) | Comb type slideway structure | |
| CN104727326B (en) | A kind of off-load method becoming water level structure | |
| JPS5862210A (en) | Construction of underwater dam structure | |
| KR102169627B1 (en) | Installation method of concrete sinker for floating structure | |
| JP2597878B2 (en) | Weir structure | |
| JP4776694B2 (en) | Harbor structure and method for constructing such a structure | |
| JP2630994B2 (en) | Construction method of quay using caisson | |
| JP3388416B2 (en) | Construction equipment for the layer for preventing the suction of landfill soil in reclaimed seawalls | |
| JPH05148830A (en) | Marine artificial ground and constructing method therefor | |
| JPS5944459B2 (en) | Construction method for offshore structures | |
| JPH04297619A (en) | Construction of underwater foundation | |
| JPH0161126B2 (en) | ||
| JP2652026B2 (en) | Quay construction method | |
| Bosman et al. | Design and construction of pleasure craft harbour–club Mykonos Langebaan | |
| Monroe | A feasibility study of a wave-powered device for moving sand | |
| JPS6134534B2 (en) | ||
| JPH05148829A (en) | Marine artificial ground and constructing method therefor | |
| JP2003003453A (en) | Hybrid artificial ground built in marine space and its construction method | |
| JPH05311667A (en) | Launching method for large caisson |