- Publication number
- JPS6051219A JPS6051219A JP15744083A JP15744083A JPS6051219A JP S6051219 A JPS6051219 A JP S6051219A JP 15744083 A JP15744083 A JP 15744083A JP 15744083 A JP15744083 A JP 15744083A JP S6051219 A JPS6051219 A JP S6051219A
- Authority
- JP
- Japan
- Prior art keywords
- sand
- tube
- water
- pipe
- sand pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/10—Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
- E02D3/106—Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains by forming sand drains containing only loose aggregates
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
Description
【発明の詳細な説明】
本発明は軟弱地盤中に砂若しく tel:その類似物に
よる締固め杭を造成する技術に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a technique for constructing compacted piles in soft ground using sand or its analogues.
砂杭造成用中空管の引抜き工程において、管内の砂面に
圧気を作用させるとともに、管の下端部に設けた砂強制
排出兼締固め部材を作動させて、締固め砂杭を造成する
技術は、既知であるが、本発明は、この際の圧気の圧力
と砂強制排出兼締固め部材の押力が砂の排出と締固めに
有効に作用するようにしたものであって、その構成上の
特徴は、工法としては、抄造成用の中空管を引抜きつつ
、中空管内の砂面に圧気を作用させるとともに、中空管
の下端部の砂強制排出兼締固め部材を作動させて、締固
め砂杭を造成する過程において、砂強制排出兼締固め部
材の作動域の下方の管内砂を水で飽和させる点であシ、
装置としては、上端部に管内圧気装置を設けた砂杭造成
用中空管の下端部外周に強制上下動機構で作動される砂
強制排出兼締固め部材を設け、その外側を蔽う外管を砂
強制排出兼締固め部材の作動域の下方まで延長し、この
延長部に管内に向う水噴射ノズルを設けた点である。Technology for creating compacted sand piles by applying pressure to the sand surface inside the pipe and activating the sand forced discharge and compaction member installed at the lower end of the pipe during the drawing process of hollow pipes for sand pile construction. is known, but the present invention is such that the pressure of the air and the pushing force of the sand forced discharge/compaction member effectively act on the discharge and compaction of sand. The above feature is that the construction method involves pulling out the hollow tube for papermaking, applying pressure to the sand surface inside the hollow tube, and activating the sand forced discharge and compaction member at the lower end of the hollow tube. , In the process of creating a compacted sand pile, the sand in the pipe below the operating area of the forced sand discharge and compaction member is saturated with water.
The device consists of a hollow tube for sand pile construction with an internal pressure air device installed at the upper end, a forced sand discharge and compaction member operated by a forced vertical movement mechanism on the outer periphery of the lower end, and an outer tube that covers the outside of the hollow tube. It extends below the operating area of the sand forced discharge and compaction member, and a water injection nozzle directed into the pipe is provided in this extension.
以下、図面を参照しつつ本発明を具体的に説明する。The present invention will be specifically described below with reference to the drawings.
図において、lは砂杭造成用中空管、2は貫入機、3は
ホッパ、4は気密弁、5は圧縮空気供給管、6は排気管
、7は強制上下動機(1り(例えば、油圧ピストン・シ
リンダ装置)、8は砂強制排出兼締固め部材、9は外管
である。In the figure, l is a hollow pipe for sand pile construction, 2 is a penetrating machine, 3 is a hopper, 4 is an airtight valve, 5 is a compressed air supply pipe, 6 is an exhaust pipe, 7 is a forced vertical machine (for example, (hydraulic piston/cylinder device), 8 is a sand forced discharge/compaction member, and 9 is an outer pipe.
外管9は、従来のとの種装済におけるそれよpも長く、
砂強制排出兼締固め部月8の作動域の下方壕で延びてお
り、lOはその延長部に設けた水噴射ノズルである。The outer tube 9 is longer than that of the conventional seeded one,
It extends in the trench below the working area of the sand forced discharge and compaction section 8, and IO is a water injection nozzle installed in the extension.
水噴射ノズル10は外管9の周方向に間隔をあけて複数
個設けられ、その噴射方向は外管9の内方に水平若しく
は斜め下向きである。なお、水噴射ノズル10は円環パ
イプに設けた噴射孔であっても構わない。A plurality of water injection nozzles 10 are provided at intervals in the circumferential direction of the outer tube 9, and the water injection direction is horizontal or diagonally downward inward of the outer tube 9. Note that the water injection nozzle 10 may be an injection hole provided in an annular pipe.
水噴射ノズルIOからは砂杭造成時にタンク11からポ
ンプ12で流路13を経て送られる水を噴出させるが、
砂杭造成時には、砂杭造成用中空管l(以下、単に中空
管1という)を引抜きつつ、気密弁4を閉じ、圧縮空気
供給管5から中空管l内に圧縮空気を送って、中空管1
内の砂を加圧するとと中空管1の下端から外管9内に砂
の強制排出を行っているから、前述の水はこの砂に向っ
て噴射され、これを飽和状態にする。The water jet nozzle IO spouts water that is sent from the tank 11 through the channel 13 by the pump 12 during sand pile construction.
When constructing a sand pile, the airtight valve 4 is closed while pulling out the hollow pipe l for sand pile construction (hereinafter simply referred to as hollow pipe 1), and compressed air is sent into the hollow pipe l from the compressed air supply pipe 5. , hollow tube 1
When the sand inside is pressurized, the sand is forcibly discharged from the lower end of the hollow tube 1 into the outer tube 9, so the water mentioned above is injected toward the sand and saturates it.
このようにして、砂強制排出兼締固め部材8の作動域の
下方の外管9内の砂は、間隙が水で満たされた状態で上
方から押され、順次、外管9の下端から地盤中に排出さ
れてゆく。In this way, the sand in the outer tube 9 below the operating area of the sand forced discharge/compaction member 8 is pushed from above with the gap filled with water, and the sand is sequentially pushed from the lower end of the outer tube 9 to the ground. It is expelled inside.
水噴射ノズルlOからの加水量は必要最小限に止めるこ
とが好ましいが、そのだめには加水量を次のようにして
制御すればよい。It is preferable to keep the amount of water added from the water injection nozzle lO to the minimum necessary, but if this is not possible, the amount of water added may be controlled as follows.
中空管1の下端から排出される単位時間当りの砂量をΔ
SLとし、単位時間当シの加水量をΔQとしたとき、
ΔQ=ム5LxK K:砂の間隙比に基づく常数となる
ようにΔQを制御するのであるが、ΔSLはいわゆる砂
面計14により検出し、ΔQは流路13に設けた流量計
15で検出し、これらの検出信号を計器16に送シ、そ
こから出される制御信号により、流路13に設けた制御
弁17を制御する。The amount of sand discharged from the lower end of hollow tube 1 per unit time is Δ
When SL is the amount of water added per unit time and ΔQ is the amount of water added per unit time, ΔQ is controlled so that it becomes a constant based on the pore ratio of sand. ΔSL is detected by a so-called sand level meter 14. However, ΔQ is detected by a flow meter 15 provided in the flow path 13, these detection signals are sent to a meter 16, and a control valve 17 provided in the flow path 13 is controlled by a control signal issued from there.
なお、中空管1内の砂がなくなると、中空管1の引抜き
を一旦停止し、気密弁4を開いてホッパ3よシ中空管1
内に砂を補給するが、このような時には、切換弁18を
制御して加水を停止させる。When the sand in the hollow tube 1 is gone, the drawing of the hollow tube 1 is temporarily stopped, the airtight valve 4 is opened, and the hollow tube 1 is removed from the hopper 3.
Sand is replenished into the tank, but in such a case, the switching valve 18 is controlled to stop adding water.
前述のように、本発明工法でしょ、砂杭造成工程におい
て、砂強制排出兼締固め部材の作動域の下方の管内砂を
水で飽和させているので、圧気の圧力はこの加水砂層に
対して作用することになり、空気洩れが生じないで有効
な加圧がなされ、また、加水砂層の部分で水によシ管壁
との摩擦が低減され、砂強制排出兼締固め部材の押力が
加水砂層に対して有効に作用し、しかも、砂強制uト出
兼締固め部材の作動域の砂は自然含水比状態であり、そ
の強制排出と締固めには何等支障は生じない。また、本
発明装置は、これを用いることによシ前述の工法を適確
に実施することができるものである。As mentioned above, in the method of the present invention, during the sand pile construction process, the sand in the pipe below the operating area of the forced sand discharge and compaction member is saturated with water, so the pressure of the pressurized air is applied to this hydrated sand layer. As a result, effective pressurization is achieved without air leakage, and the friction between the hydrated sand layer and the water drainage pipe wall is reduced, and the pushing force of the sand forced discharge and compaction member is reduced. It acts effectively on the hydrated sand layer, and moreover, the sand in the operating area of the forced sand ejection and compaction member has a natural water content, and there is no problem in its forced ejection and compaction. Moreover, by using the apparatus of the present invention, the above-mentioned construction method can be carried out appropriately.
図面は装置発明の一実施例の説明図である。
図中、1・・・砂杭造成用中空管、4・・・気密弁、5
・・・圧縮空気供給管、7・・・強制」二下動tJ!宿
、8・・・砂強制排出兼締固め部材、9・・・外管、l
O・・・水噴射ノメル、・・・・・。
特許出願人 不動建設株式会社
代理人弁理士 染 谷 廣 司The drawing is an explanatory diagram of an embodiment of the device invention. In the figure, 1... Hollow pipe for sand pile construction, 4... Airtight valve, 5
... Compressed air supply pipe, 7... Forced 2 lower movement tJ! Accommodation, 8... Sand forced discharge and compaction member, 9... Outer pipe, l
O...Water injection nomel... Patent applicant: Fudo Construction Co., Ltd. Representative patent attorney: Hiroshi Sometani
Claims (1)
に圧気を作用させるとともに、中空管の下端部の砂強制
排出兼締固め部材を作動させて、締固め砂杭を造成する
過程において、砂強制排出兼締固め部材の作動域の下方
の管内砂を水で飽和させることを特徴とする砂杭造成工
法。 2)上端部に管内圧気装置を設けだ砂杭造成用中空管の
下端部外周に、強制上下動機構で作動される砂強制排出
兼締固め部材を設け、その外側を蔽う外管を砂強制排出
兼締固め部材の作動域の下方まで延長し、この延長部に
管内に向う水噴射ノズルを設けたことを特徴とする砂杭
造成装置。[Claims] 1) While pulling out a hollow pipe for constructing a sand pile, pressurized air is applied to the sand surface inside the hollow pipe, and a sand forced discharge and compaction member at the lower end of the hollow pipe is operated. , a sand pile construction method characterized by saturating the sand in the pipe below the operating area of the sand forced discharge and compaction member with water in the process of constructing the compacted sand pile. 2) A pressure air device inside the pipe is installed at the upper end.A forced sand discharge and compaction member operated by a forced vertical movement mechanism is installed on the outer periphery of the lower end of the hollow pipe for sand pile construction. 1. A sand pile construction device, which extends below the operating area of a forced discharge/compaction member, and is provided with a water injection nozzle directed into the pipe at this extension.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP15744083A JPS6051219A (en) | 1983-08-29 | 1983-08-29 | Method and apparatus for formation of sand pile |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP15744083A JPS6051219A (en) | 1983-08-29 | 1983-08-29 | Method and apparatus for formation of sand pile |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6051219A true JPS6051219A (en) | 1985-03-22 |
| JPH0341609B2 JPH0341609B2 (en) | 1991-06-24 |
Family
ID=15649690
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP15744083A Granted JPS6051219A (en) | 1983-08-29 | 1983-08-29 | Method and apparatus for formation of sand pile |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6051219A (en) |
Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5098109A (en) * | 1973-12-29 | 1975-08-04 | ||
| JPS5443287A (en) * | 1977-09-13 | 1979-04-05 | Dainippon Ink & Chem Inc | Production of water-soluble modified resin with high storage stability at low temperatures |
-
1983
- 1983-08-29 JP JP15744083A patent/JPS6051219A/en active Granted
Patent Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5098109A (en) * | 1973-12-29 | 1975-08-04 | ||
| JPS5443287A (en) * | 1977-09-13 | 1979-04-05 | Dainippon Ink & Chem Inc | Production of water-soluble modified resin with high storage stability at low temperatures |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0341609B2 (en) | 1991-06-24 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US3817040A (en) | Pile driving method | |
| US4397588A (en) | Method of constructing a compacted granular or stone column in soil masses and apparatus therefor | |
| US4697953A (en) | Method and apparatus for subsequent underground sealing | |
| EP1881113A2 (en) | Suction arrangement for an anchorage in the seabed and method of operation | |
| JPH0341609B2 (en) | ||
| KR20230039970A (en) | the improved grout rapid-set injection device with slime emission and pressure control | |
| JP4990687B2 (en) | Sand discharge method in reclaimed compressed sand pile construction method | |
| US4659257A (en) | Method for making a hole in the ground, and hollow body open at the lower and upper sides and adapted for use in this method | |
| US3712067A (en) | Method and an apparatus for compacting a loosely packed layer of earth | |
| JP3584201B2 (en) | Sand pile forming equipment | |
| JPS594718A (en) | Jet injection device | |
| JPS6124489B2 (en) | ||
| JP2535484B2 (en) | Ogre drain placing device | |
| JP2535485B2 (en) | Sand drain placing device | |
| CN223974579U (en) | Grouting pile device for multiple pressurization in soft foundation | |
| JPH08333991A (en) | Filler supply device to tail seal part in shield machine | |
| JP2000144710A (en) | How to improve the ground | |
| RU2030524C1 (en) | Device for cleaning drain wells and pipelines | |
| JP2000192445A (en) | Consolidation method in soft ground | |
| CN115613546A (en) | A continuous post-grouting device for precise positioning of steel pipe piles | |
| JPS60488B2 (en) | Powder material pile construction method with improved air pressure efficiency | |
| JPS5850216A (en) | Improving work of soft ground | |
| JPS6026717A (en) | Sand pile former | |
| JPH04128415A (en) | Method and device for improving ground | |
| KR930002970B1 (en) | Timbering covering layer construction method |