JPS6110678A - Controller of wire arranging machine - Google Patents
Controller of wire arranging machineInfo
- Publication number
- JPS6110678A JPS6110678A JP12842084A JP12842084A JPS6110678A JP S6110678 A JPS6110678 A JP S6110678A JP 12842084 A JP12842084 A JP 12842084A JP 12842084 A JP12842084 A JP 12842084A JP S6110678 A JPS6110678 A JP S6110678A
- Authority
- JP
- Japan
- Prior art keywords
- reinforcing bars
- reinforcing bar
- reinforcing
- reinforcement
- amount
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Manipulator (AREA)
- Load-Engaging Elements For Cranes (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
〔発明の利用分野〕
本発明は、鉄筋を縦横に重ねて配置する配筋機を制御す
る配筋機の制御装置に関する。DETAILED DESCRIPTION OF THE INVENTION [Field of Application of the Invention] The present invention relates to a control device for a reinforcement arrangement machine that controls a reinforcement arrangement machine that arranges reinforcing bars vertically and horizontally one on top of the other.
(発明の背景〕
鉄筋コンクリート工事におい−Cは、鉄筋を所定の形態
に組合わせてコンクリートが流し込まれる。(Background of the Invention) In reinforced concrete construction, concrete is poured by combining reinforcing bars into a predetermined form.
このような鉄筋の組合わせ形態において極めて多く用い
られるのが、鉄筋を一定間隔に縦横に重ねて配置する形
態である。以下、このような形態を第2図により説明す
る。A very frequently used combination of reinforcing bars is one in which the reinforcing bars are stacked vertically and horizontally at regular intervals. Hereinafter, such a configuration will be explained with reference to FIG. 2.
第2図は長尺部材の配置形態の一例を示す説明図で、こ
の第2図は原子力発電所の基礎工事における配置形態を
示している。この図において、1は床、2はコンクリー
トブロック等がら成るうま、3.4.5,6.7は長尺
部材例えば鉄筋、8゜9は鉄筋どうしを締結する結束線
である。FIG. 2 is an explanatory diagram showing an example of the arrangement of elongated members, and this FIG. 2 shows the arrangement in foundation work of a nuclear power plant. In this figure, 1 is a floor, 2 is a column consisting of concrete blocks, etc., 3, 4, 5, 6, 7 are elongated members such as reinforcing bars, and 8.9 is a binding wire for connecting the reinforcing bars.
この第2図に示すような基礎工事にあっては次のように
して床1上にうま2、鉄筋3.4.5゜6.7等が配置
される。即ち、予め形成された強固な床l上に、例えば
等間隔にうま2を配置し、このうま2の上に鉄筋3(こ
の鉄筋を特に段取筋と称する)を配置する0次にこの段
取筋3の上に、当該段取筋3に直交するように鉄筋4.
5を配置し、これらの鉄筋4.5と段取筋3とを結束綿
8で縛結する。なお、鉄筋4.5は鉄筋4.5の縛結部
が一直線になることによるコンクリートの強度低下を防
ぐために、例えば図示のように交互にずらして千鳥状に
配置される。そして、このような鉄筋4,5の配置が終
了すると一点鎖線で例示する鉄筋6.7を鉄筋4.5と
同様に配置した後、鉄筋6,7を結束線9によって鉄筋
4.5のそれぞれに締結する作業がおこなわれる。以下
同様にしてうま2上に1段目の鉄筋が配置される。In the foundation work as shown in Fig. 2, the horses 2, reinforcing bars 3, 4, 5, 6, 7, etc. are placed on the floor 1 as follows. That is, on a strong floor l formed in advance, for example, horses 2 are placed at equal intervals, and reinforcing bars 3 (these reinforcing bars are especially called setup bars) are placed on top of these horses 2. A reinforcing bar 4. is placed on the setup bar 3 so as to be perpendicular to the setup bar 3.
5 are placed, and these reinforcing bars 4.5 and setup bars 3 are tied together with binding cotton 8. The reinforcing bars 4.5 are arranged in a staggered manner, for example, as shown in the figure, in order to prevent the strength of the concrete from decreasing due to the binding portions of the reinforcing bars 4.5 being aligned in a straight line. When the arrangement of the reinforcing bars 4 and 5 is completed, the reinforcing bars 6.7 illustrated by the dashed line are arranged in the same manner as the reinforcing bars 4.5, and then the reinforcing bars 6 and 7 are connected to each of the reinforcing bars 4.5 using binding wires 9. Work will be carried out to conclude the agreement. Thereafter, the first reinforcing bars are placed on the horse 2 in the same manner.
次いで図示しないが、鉄筋4,5,6.7等の上に、か
つ、これらの鉄筋4.5,6.7等に直交するように、
すなわち段取筋3に平行となるように2段目の鉄筋が配
置され、それぞれ結束線で締結される。このようにして
1組目の格子構造ができ上がる。その後、上記と同様に
1組目の格子構造の上に2組目の格子構造を作る。以下
、順次複数組の積層格子構造が作られ、その上にコンク
リートが流し込まれて基礎が完成する。Next, although not shown, on the reinforcing bars 4, 5, 6.7, etc., and perpendicular to these reinforcing bars 4.5, 6.7, etc.,
That is, the reinforcing bars in the second stage are arranged parallel to the setup bars 3, and each is fastened with a binding wire. In this way, the first set of lattice structures is completed. Thereafter, a second set of lattice structures is created on top of the first set of lattice structures in the same manner as above. After that, multiple sets of laminated lattice structures are built one after another, and concrete is poured on top of them to complete the foundation.
ところで、上述した基礎工事における配筋作業は従来、
人力によっておこなわれているが、第1図に例示するよ
うな原子力発電所のように強固な基礎を作る場合には、
鉄筋3,4.5.6.7等は例えば、直径が約50m、
長さが約10m、重量が約150 kgのように径寸法
が大きく、かつ重量の重いものを使用せざるを得ない。By the way, the reinforcement work in the foundation construction mentioned above has traditionally been
This is done manually, but when building a strong foundation like a nuclear power plant as shown in Figure 1,
For example, reinforcing bars 3, 4, 5, 6, 7, etc. have a diameter of about 50 m,
It is necessary to use a large diameter and heavy one, with a length of about 10 m and a weight of about 150 kg.
したがって、1本の配筋作業を数人がかりでおこなって
いるのが実情である。それ故、この配筋作業は苛酷で、
かつ危険なものとなっており、また多くの労力を要し、
作業効率の向上を見込めない、そこでこのような欠点を
排除し、人手を要することなく自動的に配筋作業を行な
うことができる配筋機およびその制御¥twが検討され
ている。以下、図によりこの配筋機を説明する。Therefore, the reality is that several people are working on one bar arrangement. Therefore, this reinforcement work is tough,
It is also dangerous and requires a lot of effort.
Improvements in work efficiency cannot be expected.Therefore, a reinforcement arrangement machine and its control that can eliminate such drawbacks and automatically perform reinforcement work without requiring human labor are being considered. This reinforcement arrangement machine will be explained below with reference to figures.
第3図は上記配筋機の斜視図である0図で、10は本体
で、例えば下部にフレーム11およびこのフレーム11
に保持される履帯12を有する走行体13を有し、上部
に走行体13に対して旋回可能に設けた旋回体14を有
している。また15は旋回体14に設けた運転室、16
は走行体13上に配置した収容部、17はこの収容部1
6に収容される鉄筋である。FIG. 3 is a perspective view of the above-mentioned reinforcement arrangement machine, and 10 is a main body, for example, a frame 11 at the bottom and this frame 11
It has a traveling body 13 having a crawler belt 12 held by the vehicle, and has a revolving body 14 provided on the upper part so as to be able to turn relative to the traveling body 13. Further, 15 is a driver's cab provided in the revolving structure 14;
17 is a housing part arranged on the traveling body 13, and 17 is a housing part 1
This is a reinforcing bar housed in 6.
また、18は旋回体14に上下方向に回動可能に装着さ
れるブーム、19はこのブーム18に上下方向に回動可
能に装着されるアーム、20はアーム19の先端に装着
され、上下方向に回動可能なブラケット、21はこのブ
ラケット20に装着され、水平方向に回動可能な棒状体
である。また22は、一端が旋回体14に、他端がブー
ム18に連結され、ブーム18を回動させる油圧シリン
ダ、23は一端がブーム18に、他端がアーム19に連
結され、アーム19を回動させる油圧シリンダ、24は
一端がアーム19に、他端がブラケット20に連結され
、ブラケット20を回動させる油圧シリンダ、25は一
端がブラケット20に、他端が棒状体21に連結され、
棒状体21を回動させる油圧シリンダである。又26は
棒状体21の一方の端部に装着した送り装置で、鉄筋1
7の把持が可能で、かつ、鉄筋17を把持した状態で、
その軸心方向に送り出し可能になっている。27は棒状
体21の他方の端部に装着した送り量検出装置で、送り
装置26における把持機能と同等の把持機能を存すると
ともに、送り装置26によって送り出された鉄筋17の
送り量を検出し、信号を出力する。Further, 18 is a boom attached to the revolving body 14 so as to be rotatable in the vertical direction, 19 is an arm attached to the boom 18 so as to be rotatable in the vertical direction, and 20 is attached to the tip of the arm 19, and is attached to the top of the arm 19 in the vertical direction. A rotatable bracket 21 is attached to this bracket 20 and is a rod-shaped body that can be rotated in the horizontal direction. Further, 22 is a hydraulic cylinder whose one end is connected to the revolving structure 14 and the other end is connected to the boom 18 to rotate the boom 18; and 23 is connected to the boom 18 at one end and the arm 19 at the other end and rotates the arm 19. A hydraulic cylinder 24 for rotating the bracket 20 has one end connected to the arm 19 and the other end to the bracket 20, and a hydraulic cylinder 25 for rotating the bracket 20 has one end connected to the bracket 20 and the other end connected to the rod-shaped body 21.
This is a hydraulic cylinder that rotates the rod-shaped body 21. Further, 26 is a feeding device attached to one end of the rod-shaped body 21, and a feeding device 26 is used to feed the reinforcing bar 1.
7 and in a state where the reinforcing bar 17 is gripped,
It can be fed out in the axial direction. 27 is a feed rate detection device attached to the other end of the rod-shaped body 21, which has a gripping function equivalent to the gripping function in the feeder 26, and detects the feed rate of the reinforcing bar 17 sent out by the feeder 26; Output a signal.
なお上記した棒状体21およびブラケット20は、送り
装置26を上下方向および左右方向に回動可能に支持す
る支持部材を構成しており、又、この支持部材、アーム
19およびブーム18は、送り装置26を収容部16の
位置に移動させ、および該収容部16から離れた位置に
移動させる腕を構成している。The above-described rod-shaped body 21 and bracket 20 constitute a support member that rotatably supports the feed device 26 in the vertical and horizontal directions, and this support member, arm 19 and boom 18 support the feed device 26 in a rotatable manner. 26 to the position of the accommodating part 16 and to a position away from the accommodating part 16.
28は旋回体14を旋回させる旋回モータ、29は旋回
体14と走行体13との間の相対的な回転角度θを検出
する旋回角度検出器、30はブーム18の回転角度βを
検出するブーム角度検出器、31はアーム19とブーム
18との間の相対的な回転角度αを検出するアーノ、角
度検出器、32はアーム19とブラケット20との間の
相対的な回転角度γを検出するブラケット角度検出器、
33は棒状体21の中央部の回転角度φを検出する棒状
体角度検出器である。これら各角度検出器29゜30.
31,32.33はブーム18、アーム19等から成る
前記腕の可動部の作動量を検出する検出手段を構成して
いる。Reference numeral 28 denotes a rotation motor that rotates the revolving body 14, 29 a rotation angle detector that detects the relative rotation angle θ between the revolving body 14 and the traveling body 13, and 30 a boom that detects the rotation angle β of the boom 18. An angle detector 31 detects a relative rotation angle α between the arm 19 and the boom 18; an angle detector 32 detects a relative rotation angle γ between the arm 19 and the bracket 20; bracket angle detector,
33 is a rod-shaped body angle detector that detects the rotation angle φ of the central portion of the rod-shaped body 21. Each of these angle detectors is 29°30.
Reference numerals 31, 32, and 33 constitute detection means for detecting the amount of operation of the movable portion of the arm, which includes the boom 18, arm 19, and the like.
このように構成された配筋機による配筋作業は概路次の
ようにして行なわれる。即ち、先ず、図示しないクレー
ン等により、収容部16に鉄筋17が複数本収容される
。一方、第2図に示すように、基礎が形成される床1の
上にうま2が配置される。Reinforcement placement work using the reinforcement arrangement machine configured as described above is generally carried out as follows. That is, first, a plurality of reinforcing bars 17 are accommodated in the accommodation section 16 by a crane or the like (not shown). On the other hand, as shown in FIG. 2, a horse 2 is placed on a floor 1 on which a foundation will be formed.
次いで、走行体13を駆動し、うま2の近傍の所定の配
筋作業位置に至る。このときの配筋機の位置は第3図に
示す位置とは異なり、段取筋3の長手方向に対して直角
方向の位置にあり、その向きも段取筋3の長手方向に対
してほぼ直角の向きとされる。そして、当該位置におい
て、鉄筋17のうちの最先端の鉄筋が第3図に示すよう
に収容部16の前方位置に送り出される。次いで、油圧
シリンダ22,23.24が駆動され、ブーム18、ア
ーム19、ブラケット20が上下方向に回動し、棒状体
21に支持された送り装置26、送り量検出袋ff27
が収容部16の位置即ち、前方に送り出された鉄筋を把
持する位置に至る。なお、このとき送り装N26および
送り量検出装置27は鉄筋17の把持が可能な状態にな
ってい−る。この状態において上述の鉄筋は送り装置2
6および送り量検出装置27に把持される。次いで、油
圧シリンダ22.23.24および必要ならば油圧シリ
ンダ25が駆動され、これによって上述の鉄筋は収容部
16から取出され、うま2上に段取筋として配置される
。第3図に示す符号3はこのようにしてうま2上に配置
された段取筋を示している。Next, the traveling body 13 is driven to reach a predetermined reinforcement work position near the horse 2. The position of the reinforcement arrangement machine at this time is different from the position shown in Fig. 3, and is in a position perpendicular to the longitudinal direction of the setup reinforcement 3, and its orientation is also approximately relative to the longitudinal direction of the setup reinforcement 3. It is assumed to be oriented at right angles. Then, at this position, the most advanced reinforcing bar of the reinforcing bars 17 is delivered to the front position of the accommodating portion 16 as shown in FIG. Next, the hydraulic cylinders 22, 23, and 24 are driven, and the boom 18, arm 19, and bracket 20 are rotated in the vertical direction, and the feed device 26 supported by the rod-shaped body 21 and the feed amount detection bag ff27 are driven.
reaches the position of the accommodating portion 16, that is, the position where the reinforcing bar fed forward is gripped. At this time, the feed device N26 and the feed amount detection device 27 are in a state where they can grip the reinforcing bar 17. In this state, the above-mentioned reinforcing bars are
6 and the feed amount detection device 27. The hydraulic cylinders 22, 23, 24 and, if necessary, the hydraulic cylinder 25 are then actuated, so that the above-mentioned reinforcing bars are removed from the receptacle 16 and placed as a set-up bar on the horse 2. The reference numeral 3 shown in FIG. 3 indicates a setup line arranged on the horse 2 in this manner.
次いで走行体13を駆動して、例えば当該走行体13が
段取筋3上に位置するようにする。この状態(第3図に
示す状態)において上述のように収容部16の鉄筋のう
ちの最先端の1本が送り出される。そして、上述のよう
にブーム18、アーム19、ブラケット20を適宜回動
させ、送り装置26および送り量検出装置27によって
、上述のように送り出された鉄筋17を把持させた後、
ブーム18、アーム19、ブラケット20を回動させ、
把持した鉄筋17が先に配置した段取筋3の上に、かつ
直交するように位置決めする。この状態において送り装
置26を駆動させ、所定量送られたところで送り装!2
6および送り量検出装置27による把持を解除する。第
2図に示す符号4はこのようにして段取筋3上に配置さ
れた鉄筋を示している。次に同様の操作によって一点鎖
線で示す鉄筋5が段取筋3上に、かつ、鉄筋4に対して
ずらして配置される。PI、Pア、P、は段取筋3上に
配置される鉄筋の位置を示し、各位置P 1.Pt 、
Ps・・・・・・間の距離は、ある定められた一定距離
となっている。以上の動作を繰り返すことにより配筋作
業が行なわれる。Next, the traveling body 13 is driven so that, for example, the traveling body 13 is positioned on the setup strip 3. In this state (the state shown in FIG. 3), the most advanced one of the reinforcing bars in the housing section 16 is fed out as described above. Then, as described above, the boom 18, arm 19, and bracket 20 are rotated as appropriate, and the reinforcing bar 17 sent out as described above is gripped by the feeding device 26 and the feeding amount detection device 27, and then
Rotate the boom 18, arm 19, and bracket 20,
The gripped reinforcing bars 17 are positioned above and orthogonally to the previously placed setup bars 3. In this state, the feeding device 26 is driven, and when it has been fed a predetermined amount, the feeding device is ready! 2
6 and the gripping by the feed amount detection device 27 is released. Reference numeral 4 shown in FIG. 2 indicates a reinforcing bar placed on the setup bar 3 in this manner. Next, the reinforcing bars 5 shown by the dashed-dotted line are placed on the setup bars 3 and shifted with respect to the reinforcing bars 4 by a similar operation. PI, Pa, P indicate the positions of reinforcing bars placed on the setup bar 3, and each position P1. Pt,
The distance between Ps... is a certain fixed distance. Reinforcement work is performed by repeating the above operations.
なお、収容部16内の鉄筋17のうち最先端にある鉄筋
を1本だけ前方に送り出す装置、およびこの送り出され
た1本の鉄筋を送り装置26と送り量検出装置27によ
り把持する機構等の詳細は、特願昭59−13469号
の明細書および図面に開示されている。It should be noted that a device for feeding forward only one of the most advanced reinforcing bars among the reinforcing bars 17 in the housing section 16, and a mechanism for gripping this fed-out single reinforcing bar by the feeding device 26 and the feed amount detection device 27, etc. Details are disclosed in the specification and drawings of Japanese Patent Application No. 59-13469.
さて、次に、このような配筋mに対して上記動作を行な
わせるため、現在検討中の制御装置について説明する。Now, next, a control device currently under consideration will be described in order to cause the above-mentioned operations to be performed on such reinforcement m.
第4図は当該制御装置のブロック図である0図で、第3
図に示す部分と同一部分を示すブロック′には同一符号
を付して説明を省略する。35は旋回モータ28の駆動
を制御するサーボ弁、36はブームシリンダ22の駆動
を制御するサーボ弁、37はアームシリンダ23の駆動
を制御するサーボ弁、38はブラケットシリンダ24の
駆動を制御するサーボ弁、39は棒状体シリンダ25の
駆動を制御するサーボ弁、40は送り装置26を駆動す
る送り装置モータである。50は配筋機の動作を制御す
る制御部であり、間隔設定部51、本数設定部52、記
憶部53および演算・制御部54で構成され、又、各設
定部51.52は例えばスイッチで構成されている0間
隔設定部51には互いに平行に配置される鉄筋相互間の
ある定められた距離、即ち、第3図に示す位置P+ 、
Pg 、Pa・・・・・・間の距離が設定される。本数
設定部52には互いに平行に配置される鉄筋の本数が設
定される。記憶部53には、演算・制御部54で演算処
理された値等が記憶される。演算・制御部54について
は後述する。55は教示信号を出力する教示部である。FIG. 4 is a block diagram of the control device, and the third
Blocks indicating the same parts as those shown in the figure are designated by the same reference numerals, and the explanation thereof will be omitted. 35 is a servo valve that controls the drive of the swing motor 28; 36 is a servo valve that controls the boom cylinder 22; 37 is a servo valve that controls the arm cylinder 23; 38 is a servo that controls the bracket cylinder 24. The valve 39 is a servo valve that controls the drive of the rod-shaped body cylinder 25, and 40 is a feed device motor that drives the feed device 26. Reference numeral 50 denotes a control section that controls the operation of the reinforcement arrangement machine, and is composed of an interval setting section 51, a number setting section 52, a storage section 53, and an arithmetic/control section 54, and each setting section 51, 52 is configured with a switch, for example. The zero spacing setting section 51 has a predetermined distance between reinforcing bars arranged parallel to each other, that is, the position P+ shown in FIG.
The distance between Pg, Pa... is set. The number of reinforcing bars arranged parallel to each other is set in the number setting section 52. The storage unit 53 stores values and the like that have been processed by the calculation/control unit 54. The calculation/control unit 54 will be described later. 55 is a teaching section that outputs a teaching signal.
演算・制御部54および記憶部53は例えばマイク西コ
ンピュータで構成される。The calculation/control unit 54 and the storage unit 53 are configured by, for example, a microphone computer.
この制御装置を用いた配筋作業の動作を説明するに先立
ち、演算・制御部54における演算を第5図(a)、
(b)を参照しながら説明する。前述の配筋作業の説
明から明らかなように、段取筋3上に最初に配置すべき
鉄筋の位?tP+が定まれば、以後に配置される鉄筋の
位置Pt、Ps・・・・は順次所定間隔ずつずらしてゆ
けば得られることになる。そこで、位i&P+に鉄筋を
配置するためには、配筋機の特定個所、例えば、把持さ
れた鉄筋における送り装置26と送り量検出装置27と
の間の中心点(鉄筋中心点)をどのような位置に移動さ
せればよいかが問題となり、この位置が決定されれば、
以後の各位置は所定間隔ずつずらして得られることにな
る。そして、この最初の位置は、当該特定個所(以後、
この個所をさきに例示した鉄筋中心点とする)の三次元
空間の座標として表現することができる。鉄筋中心点の
位置は、配筋機の各回転駆動部により変化するので、そ
の座標も当該回転駆動部の動きを考慮しなければならな
い。このような回転駆動部の動きを判り易く示すには、
JIS規格BO138r産業用ロボット記号」に準拠し
た形で表わすのが便利である。Before explaining the operation of reinforcement work using this control device, the calculations in the calculation/control unit 54 are shown in FIG. 5(a).
This will be explained with reference to (b). As is clear from the explanation of the reinforcement work described above, where should the reinforcing bar be placed first on the setup bar 3? Once tP+ is determined, the positions Pt, Ps, etc. of reinforcing bars to be placed thereafter can be obtained by sequentially shifting them by predetermined intervals. Therefore, in order to place the reinforcing bars at position i&P+, how should the center point (the reinforcing bar center point) between the feeding device 26 and the feeding amount detection device 27 of the grasped reinforcing bars be set at a specific location of the reinforcing machine, for example? The question is whether to move it to a certain position, and once this position is determined,
Each subsequent position will be obtained by shifting by a predetermined interval. Then, this initial position is the specific location (hereinafter referred to as
This point can be expressed as coordinates in a three-dimensional space (assuming that this point is the center point of the reinforcing bar shown earlier). Since the position of the reinforcing bar center point changes depending on each rotary drive unit of the reinforcement arrangement machine, its coordinates must also take into account the movement of the rotary drive unit. To clearly show the movement of such a rotary drive unit,
It is convenient to represent it in accordance with the JIS standard BO138r industrial robot symbol.
第5図(a)、 (b)は当該記号を用いて示した配
筋機の平面図および側面図である。図で、第3図に示す
部分と同一部分には同一符号が付され、又、表示されて
いる各角度はさきの角度検出器の説明で述べたと同一の
文字が使用されている。座標原点0は配筋機の履帯12
の下面が接触する面と旋回体14の旋回中心とが交わる
位置に定められ、当該面上にX軸セよび2軸が、又、原
点を通り当該面と直交してy軸が定められている。図に
示す各文字は次の値を表わしている。FIGS. 5(a) and 5(b) are a plan view and a side view of a reinforcement arrangement machine indicated using the symbols. In the figure, parts that are the same as those shown in FIG. 3 are given the same reference numerals, and each angle shown has the same letters as described in the description of the angle detector above. The coordinate origin 0 is the track 12 of the reinforcement machine
The center of rotation of the revolving body 14 intersects the surface that the lower surface of the rotating body 14 contacts, and the X-axis and two axes are determined on this surface, and the y-axis is determined to pass through the origin and orthogonally cross the surface. There is. Each character shown in the figure represents the following value.
Loiブームフート高さ
り、:旋回中心とプームフートとの距離■、2:棒状体
21の回転中心と鉄筋中心点との距離
β、;プーム18の長さ
EA :アーム19の長さ
lG ニブラケット20の回転中心と棒状体21の回転
中心との距離
そして、配筋機を操作して最初の鉄筋を位Hp。Loi boom foot height, : Distance between center of rotation and boom foot ■, 2: Distance β between center of rotation of rod-like body 21 and reinforcing bar center point; Length of boom 18 EA : Length of arm 19 lG of bracket 20 Distance between the center of rotation and the center of rotation of the rod-shaped body 21, and then operate the reinforcement machine to place the first reinforcing bar at the position Hp.
に配置する姿勢としたときの前記各回転角度を、角度θ
5.β1.α1.γ3.φ1とすると、そのときの鉄筋
中心点の座標x、l )’+ + z、は次式で表
わされる。The above-mentioned rotation angles when the posture is arranged as
5. β1. α1. γ3. When φ1 is assumed, the coordinates x, l )'+ + z of the reinforcing bar center point at that time are expressed by the following equation.
X+= (L++(j!s cosβ+’ + I A
Qinα1′+IGcosγ、’+L2cosγ羞”
cosφ1))cosθI
V +” Lo+ l1m sinβ、’ −IAco
sc?t′十j!、sinγ、’+ Lzsinγl”
CO3φ罵2+= iL++(j!Icosβ、’+l
、、sinα1′斗j!c C03T +’ + LI
Cogγ1”cosφI))・5ine宜
ただし、
β、′=β1−没一
α、′−α、+β8′−号
T I’ =号十α1′−11
である。X+= (L++(j!s cosβ+' + I A
Qinα1′+IGcosγ,'+L2cosγ shyness”
cosφ1)) cosθI V +” Lo+ l1m sinβ,' −IAco
sc? t'tenj! , sinγ, '+ Lzsinγl''
CO3φ abuse 2+= iL++(j!Icosβ,'+l
,,sinα1′toj! c C03T +' + LI
Cogγ1"cosφI))・5ine, where β,'=β1-minus1α,'-α,+β8'-No.TI'=No.10α1'-11.
次に、このようにして得られた鉄筋中心点の最初の位置
(X+ 、 y+ 、Z+ )から、当該鉄筋中心点
を所定間隔したけずらすための各回転角度を、角度θ2
.φ7.α2.β2.γ2とすると、これらの角度は次
式により演算される。Next, each rotation angle for shifting the reinforcing bar center point by a predetermined interval from the initial position (X+, y+, Z+) of the reinforcing bar center point obtained in this way is calculated by the angle θ2
.. φ7. α2. β2. Assuming γ2, these angles are calculated by the following equation.
θ3=jan−’ ((L++ R@ cosβ1′+
らsinα、′→It a cos r +’) ・s
inθ、 −Lsin(θ1+φ1))/(L1+らc
osβ、’+#As1nα、”+II c cos T
+’)・cosθ1−Lcos(θ1+φI))φ2
−θ1+φI−θ2
αt=cos−’(j! H” + 12 A” −X
” −Y”)/ 21 E・ lA
β7−β、’+4−
γ、=β、′+αz rt’
ただし、
βt’=sin−’(j+Bt−jlA”+X”+Y”
)/ 2 j!mfy1171−jan−’X/ Y
γ1′=12′
X=AIIcosβ2’ + A a cos(π−α
、−βt’)Y ” j! m sinβ2’
j! A 5in(n −αz −β、′)である
。演算・制御部54では、前記演算式による演算を行な
い、鉄筋の配置位置および当該配置位置に鉄筋を置くべ
く、鉄筋中心を移動させるための各回転駆動部の回動す
べき角度がそれぞれ算出される。θ3=jan-' ((L++ R@cosβ1'+
rasinα, ′→It a cos r +′) ・s
inθ, −Lsin(θ1+φ1))/(L1+ et c
osβ,'+#As1nα,”+II c cos T
+')・cosθ1−Lcos(θ1+φI))φ2
-θ1+φI-θ2 αt=cos-'(j! H" + 12 A" -X
"-Y") / 21 E・lA β7-β,'+4- γ,=β,'+αz rt' However, βt'=sin-'(j+Bt-jlA"+X"+Y"
) / 2 j! mfy1171-jan-'X/ Y γ1'=12'X=AIIcosβ2' + A a cos(π-α
, -βt')Y ” j! m sinβ2'
j! A 5in(n −αz −β,′). The calculation/control unit 54 performs calculations based on the above-mentioned calculation formula, and calculates the placement position of the reinforcing bars and the angle at which each rotary drive unit should rotate to move the center of the reinforcing bars in order to place the reinforcing bars at the placement positions. Ru.
さて、ここで、第4図に示す制御装置を用いた配筋作業
の動作を第6図に示すフローチャートを参照しながら説
明する。Now, the operation of reinforcement work using the control device shown in FIG. 4 will be explained with reference to the flowchart shown in FIG. 6.
まず、間隔設定部51に鉄筋相互間の定められた所定の
間隔りが設定される(手順S+)。この場合、間隔りは
各座標軸x、 y、 z方向の変化の成分ΔX、Δ
y、Δ2の関数として設定されるが、第3図に示すよう
に配筋してゆくときには、変化の成分ΔX、Δy、Δ2
は一定となり、がっ、1つの作業サイクル内においてy
軸方向には変位しないので、Δy=oであり、又、ΔX
、Δ2は、L2−Δx2+Δz2の関係を満足する。シ
タがって、この場合には、Lt=Δx2+Δz寞の関係
を満足するΔX、△2、およびΔy=oを与えうる間隔
りが設定されることになる。次いで、平行に配置される
べき鉄筋の本数が本数設定部52に設定される0次に、
収容部I6の鉄筋17のうちの最先端の鉄筋が1本だけ
前方に送り出される。First, a predetermined interval between reinforcing bars is set in the interval setting section 51 (step S+). In this case, the spacing is the component of change in each coordinate axis x, y, z direction ΔX, Δ
It is set as a function of y, Δ2, but when arranging reinforcement as shown in Fig. 3, the components of change ΔX, Δy, Δ2
is constant, and within one work cycle y
Since there is no displacement in the axial direction, Δy=o, and ΔX
, Δ2 satisfy the relationship L2−Δx2+Δz2. Therefore, in this case, intervals are set that can provide ΔX, Δ2, and Δy=o that satisfy the relationship Lt=Δx2+Δz寞. Next, the number of reinforcing bars to be arranged in parallel is set in the number setting section 52,
Only one of the most advanced reinforcing bars of the reinforcing bars 17 in the accommodation portion I6 is sent forward.
そして、ブーム18、アーム19、ブラケット2゜が操
作され、棒状体21に支持された送り装置26および送
り量検出装置27が、前記送り出された鉄筋を把持する
位置に至り、当該鉄筋を把持する(手順Ss)。次いで
、ブーム18、アーム19、ブラケット20を操作し、
鉄筋を位WPIに置くための位置まで鉄筋を運ぶ(手順
s4)。この状態で、送り装置26を駆動して鉄筋を所
定長さだけ送り(千鳥状に配置するため)、次いで送り
装置26および送り量検出装置27による鉄筋の把持を
解除し、鉄筋は位置P、に置かれる(手順SS)。Then, the boom 18, the arm 19, and the bracket 2° are operated, and the feeding device 26 and the feeding amount detection device 27 supported by the rod-shaped body 21 reach a position where they grip the fed-out reinforcing bar, and grip the reinforcing bar. (Step Ss). Next, operate the boom 18, arm 19, and bracket 20,
The reinforcing bars are carried to the position where they are placed at the WPI (step s4). In this state, the feeding device 26 is driven to feed the reinforcing bars by a predetermined length (to arrange them in a staggered manner), and then the reinforcing bars are released from the feeding device 26 and the feeding amount detection device 27, and the reinforcing bars are moved to position P. (Step SS).
ここで、教示部55により演算・制御部54に教示信号
が出力されて手順S6が実行される。即ち、演算・制御
部54では、教示信号が入力されると、そのときの姿勢
における各角度検出器29゜30.31.32.33お
よび送り量検出装置27の検出信号を入力し、この検出
値に基づいて、鉄筋中心点の座標”l + 7+ l
z+が前述の式にしたがって演算される。得られた
値xl r yI + Zrは位置P、に対応する
腕の姿勢データとして、鉄筋の送り量(この値をDとす
る)とともに記憶部53に記憶される(手順St)。以
後、段取筋3上に等間隔に鉄筋を自動配筋する動作が開
始される(手順Ss)。Here, a teaching signal is outputted from the teaching section 55 to the arithmetic/control section 54, and step S6 is executed. That is, when the teaching signal is input, the calculation/control unit 54 inputs the detection signals of the angle detectors 29, 30, 31, 32, and 33 and the feed amount detection device 27 in the posture at that time, and calculates the detection signal. Based on the value, the coordinates of the reinforcing bar center point “l + 7 + l
z+ is calculated according to the above formula. The obtained value xl r yI + Zr is stored in the storage unit 53 as arm posture data corresponding to the position P, together with the feed amount of the reinforcing bar (this value is set as D) (step St). Thereafter, an operation for automatically arranging reinforcing bars at equal intervals on the setup bars 3 is started (step Ss).
手順S、において、演算・制御部54からは、各サーボ
弁35〜39に対して指令信号が出力され、これに応じ
て旋回体14、ブーム18、アーム19等が駆動され、
自動的に次の鉄筋が収容部16から取り出される。次に
、演算・制御部54において、鉄筋中心点を、座標xI
+ yl、Zlから所定間隔したけずらした新たな配
筋位置が演算されるとともに、この新たな位置とするに
は、各角度θ、φ、α、β、Tをどのような角度にすれ
ばよいかが演算される(手順S1゜)。これらの演算は
、さきに記憶部53に記憶された値Xl+y++2+お
よび間隔設定部51に設定された間隔りに基づき行なわ
れ、又、各角度の演算は前記式にしたがって実行される
。次いで、手順S1゜により得られた角度θ2.α2.
β2.γ2.φtと各角度検出器で検出された現在角度
との偏差が演算・制御部54において演算され、その偏
差は対応するサーボ弁に出力される。これにより、鉄筋
中心点は新たな所定位置まで移動し、これとともに鉄筋
もその位置まで運ばれる(手順S++)。In step S, the calculation/control unit 54 outputs a command signal to each servo valve 35 to 39, and the rotating body 14, boom 18, arm 19, etc. are driven in accordance with the command signal.
The next reinforcing bar is automatically taken out from the storage section 16. Next, in the calculation/control unit 54, the reinforcing bar center point is determined at coordinates xI
+ A new reinforcement position shifted by a predetermined interval from yl and Zl is calculated, and what angles θ, φ, α, β, and T should be set to achieve this new position. Whether it is good or not is calculated (step S1°). These calculations are performed based on the value Xl+y++2+ previously stored in the storage section 53 and the interval set in the interval setting section 51, and the calculation of each angle is performed according to the above formula. Next, the angle θ2. obtained by step S1°. α2.
β2. γ2. The deviation between φt and the current angle detected by each angle detector is calculated in the calculation/control unit 54, and the deviation is output to the corresponding servo valve. As a result, the reinforcing bar center point is moved to a new predetermined position, and the reinforcing bar is also transported to that position (step S++).
次いで手順Sl□に移り、演算・制御部54からの指令
により、送り装置26は鉄筋を前回の送り方向とは反対
方向に送り量りだけ移動させ、この状態で鉄筋に対する
把持が解除される。解除された鉄筋は第3図の一点鎖線
で示されるように、鉄筋5として位置P、に配置され、
その配置は最初に配置された鉄筋4に対して千鳥状とな
る。Next, the process moves to step Sl□, and in response to a command from the arithmetic/control unit 54, the feeding device 26 moves the reinforcing bar by the feeding distance in the direction opposite to the previous feeding direction, and in this state, the grip on the reinforcing bar is released. The released reinforcing bars are placed at position P as reinforcing bars 5, as shown by the dashed line in FIG.
The arrangement is staggered with respect to the reinforcing bars 4 placed first.
次の手順Sl、においては、記憶部53に記憶されてい
る数1に1を加算して記憶された本数を2とする。即ち
、鉄筋4.5の2本が記憶されたことになる。次いで、
手順S14において、演算・制御部54では記憶部53
に記憶された本数が取り出され、この本数と本数設定部
52に設定された本数との比較が行なわれる。比較の結
果、設定された本数に達していなければ、再び手順S、
に戻り、以下、配置された鉄筋の本数が設定された本数
に達するまで、同様の手順で自動的に配筋作業が実行さ
れることになる。In the next step Sl, 1 is added to the number 1 stored in the storage unit 53 to make the stored number 2. In other words, two reinforcing bars 4.5 are stored. Then,
In step S14, the calculation/control unit 54 stores the memory unit 53.
The number stored in is retrieved, and this number is compared with the number set in the number setting section 52. As a result of the comparison, if the set number has not been reached, repeat step S.
Returning to , the reinforcement work will be automatically executed in the same manner from now on until the number of placed reinforcing bars reaches the set number.
以上述べたような検討中の配筋機およびその制御装置に
より、配筋作業が自動的に実施され、これにより、人手
による配筋作業を排除し、安全に作業を行なうことがで
き、かつ、作業効率を向上させることができる。The reinforcement machine and its control device under consideration as described above automatically perform reinforcement work, thereby eliminating manual reinforcement work and making it possible to perform the work safely. Work efficiency can be improved.
ところで、このような配筋機により配筋作業を実施する
場合、前述のように千鳥状に配筋する必要があるときに
は、収容部16から所定の位置まで鉄筋を搬送した後、
把持している鉄筋を一旦所定量だけ横送りしてから下に
置いて配筋しなければならない、このような横送りを実
施することにより、鉄筋自体は横送りされた側において
相当量たわむこととなる。したがって、たわんだ鉄筋の
端部はすでに配置されている鉄筋に衝突し、又は当該鉄
筋の下方にもぐり込む状態となり、その状態で横送りを
継続すると当該鉄筋を押圧することにより結束線8をゆ
るめ、又は切断し、すでに配置されている鉄筋の位置を
ずらしてしまうおそれがある。そしそ、このような事態
が生じると、作業員は、ずれた鉄筋を元の位置に戻し、
再度結束線8を縛結し直すという補修作業を行なわねば
ならず、作業能率は著しく低下することになる。By the way, when carrying out reinforcement work using such a reinforcement arrangement machine, when it is necessary to arrange the reinforcement in a staggered manner as described above, after conveying the reinforcing bars from the storage section 16 to a predetermined position,
The reinforcing bars that are being gripped must be moved horizontally by a predetermined amount and then placed below for reinforcing. By carrying out such horizontal feeding, the reinforcing bars themselves will flex by a considerable amount on the side that has been side-feeded. becomes. Therefore, the end of the bent reinforcing bar collides with the reinforcing bar that has already been placed or goes under the reinforcing bar, and if the traverse feed is continued in this state, the binding wire 8 is loosened by pressing the reinforcing bar, and Otherwise, there is a risk of cutting and shifting the position of the reinforcing bars that have already been placed. When a situation like this occurs, workers return the displaced reinforcing bars to their original positions.
Repair work must be carried out to re-tie the binding wire 8, resulting in a significant drop in work efficiency.
このような懸念を排除するには、横送りされる鉄筋の端
部がすでに配置されている鉄筋と接触しない充分の高さ
において横送りを実施すればよいのであるが、横送り終
了後に高い個所から鉄筋の把持を解除すると、解除され
た鉄筋はすでに配置された鉄筋上に落ちたときバウンド
して転がり、鉄筋の配置位置が大きく狂い、人手による
正しい位置への戻し作業が必要になるばかりでなく、鉄
筋の落下、バウンドおよび転がりは、予期しない事故を
発生するおそれがある。そして、これらの事態を避ける
ため、高い位置での楢送り終了後、棒状体21を再度移
動させて、これをできるだけ下方に位置せしめ、それか
ら鉄筋の把持を解除する操作を行なうことが考えられる
が、さらにこのような操作を行なうことは明らかに作業
能率の低下を招来することになる。In order to eliminate such concerns, it is sufficient to carry out cross-feeding at a sufficient height so that the end of the reinforcing bars to be cross-feed does not come into contact with the reinforcing bars that have already been placed. If you release the grip on the reinforcing bars, the released reinforcing bars will bounce and roll when they fall onto the reinforcing bars that have already been placed, causing the reinforcing bars to be placed in a greatly incorrect position, requiring manual work to return them to the correct position. If not, falling, bouncing and rolling reinforcing bars may cause unexpected accidents. In order to avoid these situations, it is conceivable to move the rod-shaped body 21 again after completing the feeding at a high position, position it as low as possible, and then perform an operation to release the grip on the reinforcing bar. Moreover, performing such an operation will obviously lead to a decrease in work efficiency.
本発明は、このような事情を考慮してなされたものであ
り、その目的は、鉄筋の横送りを最適位置で実施するこ
とができ、ひいては配筋能率を向上させることができ、
かつ、安全に配筋作業を行なうことができる配筋機の制
御装置を提供するにある。The present invention was made in consideration of such circumstances, and its purpose is to be able to carry out cross-feeding of reinforcing bars at optimal positions, thereby improving reinforcement efficiency.
Further, it is an object of the present invention to provide a control device for a reinforcement arrangement machine that can safely perform reinforcement work.
上記の目的を達成するため、本発明は、鉄筋の横送り装
置と横送り量の検出装置とを支持体で支持し、鉄筋の横
送り量と当該鉄筋により定まる値とに基づいてその鉄筋
のたわみ量を演算し、一方、前記支持体の特定個所とそ
の鉄筋が配置される面との高さを演算し、この高さと前
記たわみ量とを比較し、その比較の結果に応じて支持体
の高さを制御するようにしたことを特徴とする。In order to achieve the above object, the present invention supports a reinforcing bar transverse feed device and a transverse feed amount detection device with a support, and detects the reinforcing bar based on the transverse feed amount of the reinforcing bar and a value determined by the reinforcing bar. The amount of deflection is calculated, and on the other hand, the height between a specific part of the support and the surface on which the reinforcing bar is placed is calculated, this height is compared with the amount of deflection, and the support is adjusted according to the result of the comparison. The feature is that the height is controlled.
以下、本発明を図示の実施例に基づいて説明する。 Hereinafter, the present invention will be explained based on illustrated embodiments.
第1図は本発明の実施例に係る配筋機の制御装置のブロ
ック図である。図で、第4図に示す部分と同一部分には
同一符号を付して説明を省略する。FIG. 1 is a block diagram of a control device for a reinforcement arrangement machine according to an embodiment of the present invention. In the figure, parts that are the same as those shown in FIG. 4 are given the same reference numerals, and description thereof will be omitted.
なお、本体10においては、送り装置モータ40、送り
装?&26および送り量検出装置27のみを示し、他の
装置およびそれらと演算・制御部54との接続について
は図示が省略されている。57は鉄筋が横送りされたと
き、そのたわみ量を所定の式(後述)にしたがって演算
するたわみ量演算部である。58は、たわみ量演算部5
7で演算されたたわみ量と、鉄筋中心点の高さとを入力
し、その偏差を出力する比較器である。In addition, in the main body 10, the feed device motor 40, the feed device? &26 and the feed amount detection device 27 are shown, and illustrations of other devices and their connections with the arithmetic/control unit 54 are omitted. Reference numeral 57 denotes a deflection calculation section that calculates the deflection amount of the reinforcing bar according to a predetermined formula (described later) when the reinforcing bar is fed laterally. 58 is the deflection amount calculation unit 5
This is a comparator that inputs the deflection amount calculated in step 7 and the height of the reinforcing bar center point, and outputs the deviation.
次に、たわみ量演算部57の演算を第7図に示すたわみ
量の説明図を参照しながら説明する。第7図で、17は
収容部16から取り出されて把持された鉄筋、21は棒
状体、26rは棒状体21に支持された送り装W26の
一対のローラ、27rは同じく棒状体21に支持された
送り量検出装置27の一対のローラである。鉄筋17は
一対のローラ26rと他の一対のローラ27rとで挟着
支持されており、一対のローラ26rの一方が結合され
ている送り装置モータ40の回転により、例えば図の右
方向に横送りされる。図は、鉄筋17が右方向に横送り
されている状態を示す。この横送りにより、他の一対の
ローラ27rも回転し、その回転数を検出することによ
り鉄筋17の横送り量りが検出されるecOは鉄筋中心
点である。Next, the calculation by the deflection amount calculating section 57 will be explained with reference to the diagram for explaining the deflection amount shown in FIG. In FIG. 7, reference numeral 17 denotes a reinforcing bar taken out from the storage section 16 and held, 21 denotes a rod-shaped body, 26r denotes a pair of rollers of the feeding device W26 supported by the rod-shaped body 21, and 27r denotes a pair of rollers also supported by the rod-shaped body 21. This is a pair of rollers of the feed amount detection device 27. The reinforcing bar 17 is sandwiched and supported between a pair of rollers 26r and another pair of rollers 27r, and is horizontally fed, for example, to the right in the figure, by rotation of a feeder motor 40 to which one of the pair of rollers 26r is connected. be done. The figure shows a state in which the reinforcing bars 17 are being fed laterally to the right. Due to this lateral feeding, the other pair of rollers 27r also rotate, and by detecting their rotational speed, the amount of lateral feeding of the reinforcing bar 17 is detected. ecO is the reinforcing bar center point.
なお、図のように鉄筋を把持した場合、鉄筋はローラ2
6r、27r間で掻く僅かたわみ、点C0もローラ26
r、27rの把持点を結ぶ直線上から微小間隔だけずれ
るが、この、ずれは無視することができる。Gは配筋機
の履帯12の下面と同一の平面、即ち鉄筋17が配置さ
れる平面を示す。Note that when gripping the reinforcing bars as shown in the figure, the reinforcing bars are held by roller 2.
Slight deflection between 6r and 27r, point C0 is also caused by roller 26
Although it deviates by a minute interval from the straight line connecting the gripping points of r and 27r, this deviation can be ignored. G indicates the same plane as the lower surface of the crawler track 12 of the reinforcement arrangement machine, that is, the plane on which the reinforcing bars 17 are arranged.
又、hは点C0の面Gからの垂直高さ、2.は鉄筋17
の張出し量、12はローラ26r、27rによる鉄筋1
7の把持間隔、δはたわみ量である。Also, h is the vertical height of point C0 from plane G, 2. is reinforcing bar 17
The amount of overhang, 12 is the reinforcing bar 1 by rollers 26r and 27r.
7 is the gripping interval and δ is the amount of deflection.
なお、第7図では鉄筋17のたわみは拡大して図示され
ている。In addition, in FIG. 7, the deflection of the reinforcing bar 17 is illustrated in an enlarged manner.
このような鉄筋17のたわみ量δは次式で表わされる。The amount of deflection δ of the reinforcing bar 17 is expressed by the following equation.
δ=Wj!+(3pI’+6J+”Jt At3)/
24ETここで、
E:鉄筋17の縦弾性係数
l;鉄筋17の断面2〜モーメント
W:鉄筋17の単位長さ当りの重量
である。なお、張出し量1重については、鉄筋17を収
容部16から取り出したとき、当該鉄筋17は両方向に
同一量だけ張出した状態でローラ26r。δ=Wj! +(3pI'+6J+”Jt At3)/
24ET Here, E: longitudinal elastic modulus l of the reinforcing bar 17; cross section 2~moment W of the reinforcing bar 17: weight per unit length of the reinforcing bar 17. In addition, regarding the overhang amount of 1 layer, when the reinforcing bar 17 is taken out from the storage part 16, the reinforcing bar 17 is moved to the roller 26r in a state where it is overhanging by the same amount in both directions.
27rに挟持されるので、鉄筋17の全長が判っておれ
ば送りilDから演算することができる。27r, so if the total length of the reinforcing bar 17 is known, it can be calculated from the feed ilD.
次に、本実施例の動作を説明する。ローラ26rおよび
ローラ27rで収容部16の鉄筋17が把持された後、
棒状体21における点coは演算された新しい位置まで
移動せしめられる0次いで、ローラ26rが駆動され、
鉄筋17が横送りされる。送り量検出装置27はその検
出した送り量を演算・制御部54に出力する。演算・制
御部54ではこの送り量に基づいて張出しllj!、が
演算されるとともに、この値11と、予め記憶部53に
記憶されている前記値E、It w、l12とがたわみ
量演算部57に出力される。たわみ量演算部57では、
これらの値に基づいてたわみ量δが演算され、このたわ
み量δは比較器58に出力される。Next, the operation of this embodiment will be explained. After the reinforcing bars 17 of the housing section 16 are gripped by the rollers 26r and 27r,
The point co on the rod-shaped body 21 is moved to the calculated new position.Then, the roller 26r is driven,
The reinforcing bars 17 are fed laterally. The feed amount detection device 27 outputs the detected feed amount to the calculation/control unit 54. The calculation/control unit 54 overhangs llj! based on this feed amount. is calculated, and this value 11 and the values E, Itw, l12 previously stored in the storage section 53 are output to the deflection amount calculation section 57. In the deflection amount calculation section 57,
The amount of deflection δ is calculated based on these values, and this amount of deflection δ is output to the comparator 58.
一方、演算・制御部54からは比較器58に対して点C
0のy軸方向の値、即ち現在の高さhが出力される。比
較器58では値りと値りとの偏差Δhが演算され、演算
された偏差Δhは演算・制御部54に出力される。On the other hand, the calculation/control unit 54 sends a signal to the comparator 58 at point C.
A value of 0 in the y-axis direction, ie, the current height h, is output. The comparator 58 calculates the deviation Δh between the two values, and the calculated deviation Δh is output to the calculation/control unit 54.
演算・制御部54では、入力された偏差Δhと、予め設
定されて記憶部53に記憶されている値にとを比較し、
両者に差がある場合には、Δh=にとするように、本体
10の必要な駆動部に対して制御信号を出力する。即ち
、Δh>kである場合には点C0を下げるように、又、
Δh<kである場合には点CI、を上げるように各サー
ボ弁36゜37.38に制御信号が出力される。なお、
上記設定値には、配筋機の各部のガタ、演算精度等を考
慮して定められた値であり、くれにより鉄筋17の先端
部分が、既に配置されている黙筋に衝突し、又はその下
にもぐり込む事態を確実に防止している。The calculation/control unit 54 compares the input deviation Δh with a value set in advance and stored in the storage unit 53,
If there is a difference between the two, a control signal is output to the necessary driving section of the main body 10 so that Δh=. That is, if Δh>k, lower the point C0,
If Δh<k, a control signal is output to each servo valve 36°37.38 to raise point CI. In addition,
The above setting values are determined by taking into consideration the looseness of each part of the reinforcement arrangement machine, calculation accuracy, etc., and the tip of the reinforcing bar 17 collides with the already placed silent reinforcement due to looseness, or It definitely prevents the situation from falling under.
上記の動作は、鉄筋17の横送りが実施されている間常
に行なわれており、横送り量が増加してたわみ量が大き
くなり、鉄筋17の先端が下がって偏差Δhが小さくな
り、これが設定値により小さくなると、演算・制御部5
4からは点c0の位置を上げる信号が出力され、高さh
が大きくなって偏差Δhも大きくなり設定値にと等しく
なる。The above operation is always performed while the reinforcing bar 17 is being traversed, and the amount of lateral feeding increases, the amount of deflection increases, the tip of the reinforcing bar 17 lowers, and the deviation Δh decreases, which changes the setting. When the value becomes smaller, the calculation/control unit 5
4 outputs a signal to raise the position of point c0, increasing the height h
becomes larger, and the deviation Δh also becomes larger and becomes equal to the set value.
偏差Δhが設定値により大きくなると逆の動作が行なわ
れて点C0の位置を下げ、偏差Δhを小さくして、Δh
=にとする。このように、鉄筋17の横送り側の先端位
置は、常に既設の鉄筋より高い位置にあり、かつ、既設
の鉄筋との高さの差は微小である。そして、横送りが終
了したとき、直ちに鉄筋17の把持を解除すれば、鉄筋
17のバウンドは抑えられ、バウンドにより鉄筋17が
転がったりすることはなく、鉄筋17は正しい位置に配
置されることになる。When the deviation Δh becomes larger than the set value, the opposite operation is performed, lowering the position of point C0, reducing the deviation Δh, and increasing Δh.
= to be. In this way, the end position of the reinforcing bar 17 on the traverse feed side is always at a higher position than the existing reinforcing bar, and the difference in height from the existing reinforcing bar is minute. If the grip on the reinforcing bar 17 is immediately released when the traverse feed is completed, the bouncing of the reinforcing bar 17 will be suppressed, the reinforcing bar 17 will not roll due to the bouncing, and the reinforcing bar 17 will be placed in the correct position. Become.
このように、本実施例では、鉄筋の横送り作業中、鉄筋
のたわみ量を演算し、鉄筋のたわんだ方の先端が既設の
鉄筋より高い位置で、しかもその既設の鉄筋に接近′し
た位置にあるように制御する構成としたので、横送りす
る鉄筋と既設の鉄筋との接触を防止することができ、こ
れにより既設の鉄筋の位置ずれ修正や結束線の再縛結等
の補修作業を不要として配筋作業の能率を向上すること
ができ、又、鉄筋の把持解除を横送り作業終了後直ちに
、かつ、低い位置で行なうことができ、これにより、再
度低い位置まで鉄筋を移動させる操作や鉄筋のバウンド
による配筋位置の修正作業が不要となって、この面から
も配筋作業の能率を向上させることができ、さらに、鉄
筋のバウンドによる危険も防止することができる。In this way, in this example, the amount of deflection of the reinforcing bars is calculated during the horizontal feeding work of the reinforcing bars, and the deflected tip of the reinforcing bars is located at a position higher than and close to the existing reinforcing bars. Since the configuration is configured to control as shown in Figure 1, it is possible to prevent the reinforcing bars that are being fed horizontally from coming into contact with the existing reinforcing bars, and this allows for repair work such as correcting the misalignment of the existing reinforcing bars or retying the binding wires. The efficiency of reinforcement work can be improved by eliminating the need for reinforcing bars, and the grip on reinforcing bars can be released immediately after the cross-feeding work is completed and at a lower position. This eliminates the need to correct the reinforcement position due to the bounce of the reinforcing bars, which improves the efficiency of the reinforcement work, and also prevents dangers due to the bounce of the reinforcing bars.
なお、上記実施例の説明では、たわみ量演算部および比
較器を個別に設ける例について説明したが、演算・制御
部にこれらの機能をもたせることもできる。In addition, in the description of the above embodiment, an example in which the deflection amount calculation section and the comparator are provided separately has been described, but it is also possible to provide these functions to the calculation/control section.
以上述べたように、本発明では、鉄筋の横送りにおける
たわみ量を演算し、このたわみ量と横送り装置を支持す
る支持体の特定位置の高さとを比較し、この比較の結果
に応じて前記特定位置の高さを制御するようにしたので
、横送りする鉄筋の先端が既設の鉄筋より高く、かつ、
当該既設の鉄筋に極めて接近した最適位置で横送りを行
なうことができ、これにより、横送りする鉄筋と既設鉄
筋との接触による後者の鉄筋の補修、バウンドによる鉄
筋の配置位置修正、横送り作業後の鉄筋の下げ操作を不
要として配筋作業の能率を向上させることができ、又、
鉄筋のバウンドによる危険を除くことができる。As described above, in the present invention, the amount of deflection during cross-feeding of reinforcing bars is calculated, this amount of deflection is compared with the height of a specific position of the support body that supports the cross-feed device, and according to the result of this comparison, the amount of deflection is calculated. Since the height of the specific position is controlled, the tip of the reinforcing bar to be fed laterally is higher than the existing reinforcing bar, and
Traversing can be carried out at an optimal position extremely close to the existing reinforcing bars, and this allows for repair of the latter reinforcing bars due to contact between the reinforcing bars to be transversely transported and existing reinforcing bars, correction of the reinforcing bar placement position due to bounce, and traversing work. It is possible to improve the efficiency of reinforcement work by eliminating the need to lower the reinforcing bars later, and
The danger caused by bouncing reinforcing bars can be eliminated.
第1図は本発明の実施例に係る配筋機の制御装置のブロ
ック図、第2図は鉄筋の配置形態を示す斜視図、第3図
は配筋機の斜視図、第4図は検討されている配筋機の制
御装置のブロック図、第5図(a)、 (b)はそれ
ぞれ記号化して示した配筋機の平面図および側面図、第
6図は第4図に示す制御装置を用いた配筋作業のフロー
チャート、第7図は鉄筋のたわみ量の説明図である。
3・・・段取筋、10・・・配筋機本体、14・・・旋
回体、16・・・収容部、18・・・ブーム、19・・
・アーム、20・・・ブラケット、21・・・棒状体、
26・・・送り装置、27・・・送り量検出器、29.
3(j、 31. 32゜33・・・角度検出器、
50・・・制御部、51・・・間隔設定部、52・・・
本数設定部、53・・・記憶部、54・・・演算・制御
部、55・・・教示部、57・・・たわみ量演算部、5
8・・・比較器。
第1図
第2図
!
第3図
第4図
第5図
tσノ
(b)
第6図
ド
[Fig. 1 is a block diagram of a control device for a reinforcement arrangement machine according to an embodiment of the present invention, Fig. 2 is a perspective view showing the arrangement form of reinforcing bars, Fig. 3 is a perspective view of the reinforcement arrangement machine, and Fig. 4 is a study. 5(a) and 5(b) are a plan view and a side view of the reinforcing bar arrangement machine shown in symbols, respectively, and FIG. 6 is a block diagram of the control device of the reinforcement arrangement machine shown in FIG. FIG. 7 is a flowchart of reinforcement work using the apparatus, and is an explanatory diagram of the amount of deflection of reinforcing bars. 3... Setup bar, 10... Reinforcement arrangement machine body, 14... Swivel body, 16... Accommodation section, 18... Boom, 19...
・Arm, 20... Bracket, 21... Rod-shaped body,
26... Feeding device, 27... Feeding amount detector, 29.
3(j, 31. 32°33... angle detector,
50... Control unit, 51... Interval setting unit, 52...
Number setting section, 53... Storage section, 54... Calculation/control section, 55... Teaching section, 57... Deflection amount calculation section, 5
8... Comparator. Figure 1 Figure 2! Figure 3 Figure 4 Figure 5 tσ (b) Figure 6 Do[
Claims (1)
装置により横送りされた量を検出する検出装置および前
記横送り装置と前記検出装置を支持する支持体を備えた
配筋機と、把持された鉄筋により定まる値および前記検
出装置により検出された値に基づいて当該鉄筋のたわみ
量を演算する第1の演算手段と、鉄筋の把持中心位置と
当該鉄筋が配置される面との間の高さを演算する第2の
演算手段と、前記第1の演算手段で演算された値と前記
第2の演算手段で演算された値とを比較する比較手段と
、この比較手段での比較に応じて前記把持中心位置の高
さを制御する制御手段とを設けたことを特徴とする配筋
機の制御装置。a cross-feeding device that grips and cross-feeds reinforcing bars, a detection device that detects the amount of cross-feed by the cross-feeding device, and a reinforcement arrangement machine that includes a support that supports the cross-feeding device and the detection device; between a first calculation means that calculates the amount of deflection of the reinforcing bar based on a value determined by the grasped reinforcing bar and a value detected by the detection device, and a grasping center position of the reinforcing bar and a surface on which the reinforcing bar is arranged; a second calculating means for calculating the height of the height, a comparing means for comparing the value calculated by the first calculating means and the value calculated by the second calculating means, and a comparison by the comparing means. A control device for a reinforcing bar arrangement machine, comprising: a control means for controlling the height of the gripping center position according to the height of the gripping center position.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12842084A JPS6110678A (en) | 1984-06-23 | 1984-06-23 | Controller of wire arranging machine |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12842084A JPS6110678A (en) | 1984-06-23 | 1984-06-23 | Controller of wire arranging machine |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPS6110678A true JPS6110678A (en) | 1986-01-18 |
Family
ID=14984319
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP12842084A Pending JPS6110678A (en) | 1984-06-23 | 1984-06-23 | Controller of wire arranging machine |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6110678A (en) |
-
1984
- 1984-06-23 JP JP12842084A patent/JPS6110678A/en active Pending
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5187958A (en) | Method of positioning a metal sheet for a sheetmetal working machine | |
| DE102018009169B4 (en) | Control device for limiting the speed of a robot | |
| KR101809325B1 (en) | A Wire net stacking machine | |
| DE102018111371A1 (en) | robot system | |
| KR102185189B1 (en) | Systme for auto-making of coaming | |
| KR20060096902A (en) | Robot controller and robot control method | |
| JP2021049567A (en) | Reinforcement assembly system | |
| JPS6110678A (en) | Controller of wire arranging machine | |
| JP7729771B2 (en) | Rebar Assembly System | |
| JPH0343310Y2 (en) | ||
| JPH0345477Y2 (en) | ||
| JPH0412347B2 (en) | ||
| JPH047322Y2 (en) | ||
| JP2723994B2 (en) | Gauging treatment method for bending equipment | |
| JPS6110679A (en) | Controller of wire arranging machine | |
| CN120500570A (en) | Reinforcing steel bar bundling device | |
| JPH0368985B2 (en) | ||
| JP2014157462A (en) | Loader position teaching device | |
| JP2022082091A (en) | Robot hand device | |
| JPH01159188A (en) | Method of controlling industrial robot | |
| JPH0563251B2 (en) | ||
| JP4164190B2 (en) | Work position deviation detection / correction apparatus and method, and storage medium | |
| JPH0445627B2 (en) | ||
| CN120380226A (en) | Reinforcing steel bar bundling device | |
| JP2790775B2 (en) | Automatic teaching method for plate material abutment position and apparatus therefor |