JPS6128046B2 - - Google Patents

Info

Publication number
JPS6128046B2
JPS6128046B2 JP2713179A JP2713179A JPS6128046B2 JP S6128046 B2 JPS6128046 B2 JP S6128046B2 JP 2713179 A JP2713179 A JP 2713179A JP 2713179 A JP2713179 A JP 2713179A JP S6128046 B2 JPS6128046 B2 JP S6128046B2
Authority
JP
Japan
Prior art keywords
ground
casing
existing pile
existing
softened
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP2713179A
Other languages
Japanese (ja)
Other versions
JPS55119825A (en
Inventor
Kunimitsu Yamada
Hidenori Kodera
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2713179A priority Critical patent/JPS55119825A/en
Publication of JPS55119825A publication Critical patent/JPS55119825A/en
Publication of JPS6128046B2 publication Critical patent/JPS6128046B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

【発明の詳細な説明】 この発明は、既設杭の抜去方法に関し、特に、
既設杭の周囲にケーシングを打ち込むとともに、
該ケーシングの内側に固化剤を含んだ液を噴出し
て、ケーシング内側の地盤を軟化し、以つて、既
設杭の抜去を容易にするとともに、既設杭跡に軟
化地盤を充填して空洞を完全に埋戻す。
[Detailed Description of the Invention] The present invention relates to a method for removing existing piles, and in particular,
In addition to driving casing around the existing piles,
A liquid containing a solidifying agent is ejected inside the casing to soften the ground inside the casing, making it easier to remove the existing piles, and filling the remains of the existing piles with the softened soil to completely fill the cavity. backfill.

都市開発に伴つて、既設建造物の撤去跡に新た
建造物を構築することが多い。そして、既設建造
物に用いられた既設杭は、その耐力不足その他の
理由により抜去して新たな杭、連続地中壁等を施
工することが行われる。
With urban development, new buildings are often constructed on the site of demolished existing buildings. Existing piles used in existing buildings are removed due to lack of bearing capacity or other reasons, and new piles, continuous underground walls, etc. are constructed.

従来、こうした既設杭を抜去する方法は、各種
提供されてはいるが、既設杭を抜去した後の既設
杭跡の空洞には、山砂、砂等の粒状体またはセメ
ントモルタルを充填して埋戻していた。しかしな
がら、この埋戻しによると、充分に埋戻すことが
難かしく、結局空洞が残つてしまうため、地盤の
耐力を低下させる結果となり、また、コンクリー
トモルタルの充填では、その硬化により地盤が高
強度になつて、以後の新しい杭の建込みやその他
の施工に支障を生じる結果となる。
Conventionally, various methods have been provided for removing existing piles, but after removing the existing piles, the cavities at the site of the existing piles are filled with granular materials such as mountain sand, sand, or cement mortar. I was putting it back. However, with this backfilling, it is difficult to backfill sufficiently and ends up leaving a cavity, which reduces the bearing strength of the ground.Furthermore, filling with concrete mortar increases the strength of the ground due to its hardening. This will result in problems with the subsequent erection of new piles and other construction work.

そこで、この発明は、従来のかかる欠点を除去
するために提供されたものであり、その目的は、
既設杭跡たる空洞を完全に埋戻すことにあり、ま
たその目的は、前記埋戻した跡地での地盤掘削等
を容易にすることにあり、さらにその目的は、既
設杭の抜去も容易にすることにある。
Therefore, the present invention was provided in order to eliminate such drawbacks of the conventional technology, and its purpose is to:
The purpose is to completely backfill the cavity where the existing pile remains, and the purpose is to facilitate ground excavation, etc. in the backfilled site, and the purpose is also to facilitate the removal of the existing pile. There is a particular thing.

すなわち、この出願は、既設杭1の周囲に、該
既設杭1を囲むように筒状のケーシング2を打ち
込み、且つ既設杭1とケーシング2との間に、固
化剤を含んだ液を噴出して、ケーシング2内側の
地盤を軟化し、しかる後、既設杭1を抜去すると
ともに軟化地盤3を既設杭1跡に充填し、さら
に、軟化地盤3の上方に形成される地表近傍の空
隙に土砂4等を充填することを特徴とする既設杭
の抜去方法を特定発明するとともに、既設杭1の
周囲に、該既設杭1を囲むように筒状のケーシン
グ2を打ち込みながら、既設杭1とケーシング2
との間に、ケーシング2内側に内方に向けて設け
たノルズ5から、固化剤を含んだ液を噴出し、ケ
ーシング2とノルズ5との適宜上下動を繰返して
次第に一定深度までケーシング2内側の地盤を軟
化し、しかる後既設杭1を抜去するとともに軟化
地盤3を既設杭1跡に充填し、さらに、軟化地盤
3の上方に形成される地表近傍の空隙に土砂4等
を充填することを特徴とする既設杭の抜去方法を
併合発明とする。
That is, in this application, a cylindrical casing 2 is driven around an existing pile 1 so as to surround the existing pile 1, and a liquid containing a solidifying agent is spouted between the existing pile 1 and the casing 2. Then, the ground inside the casing 2 is softened, and then the existing piles 1 are removed, the softened ground 3 is filled into the remains of the existing piles 1, and the void near the ground surface formed above the softened ground 3 is filled with earth and sand. In addition to specifically inventing a method for removing existing piles, which is characterized by filling the existing piles with 2
A liquid containing a solidifying agent is ejected from the nozzle 5 provided inward inside the casing 2, and the casing 2 and the nozzle 5 are repeatedly moved up and down to gradually reach a certain depth inside the casing 2. After that, the existing piles 1 are removed, the softened ground 3 is filled into the remains of the existing piles 1, and the void near the ground surface formed above the softened ground 3 is filled with earth and sand 4, etc. A method for removing existing piles characterized by the following is defined as a combined invention.

つぎに、これら発明を、添付図面にもとづいて
詳細に説明する。
Next, these inventions will be explained in detail based on the accompanying drawings.

第1図は、既設杭1が既設されたままの状態を
示し、該既設杭1の周囲に、これを囲むように筒
状のケーシング2を打ち込む。第2図は、ケーシ
ング2の打ち込み途中の状態を示すが、ケーシン
グ2の内側には、注入パイプ6が固着され、その
ノルズ5から固化剤を含んだ液を既設杭1に向け
て噴出する。ケーシング2には振動が与えられて
次第に下方に打ち込まれるが、該ケーシング2の
上下動を適宜繰り返しながら順次下降する。ケー
シング2と注入パイプ6とは同時に運動すること
は勿論である。
FIG. 1 shows the existing pile 1 still in place, and a cylindrical casing 2 is driven around the existing pile 1 so as to surround it. FIG. 2 shows a state in which the casing 2 is being driven in. An injection pipe 6 is fixed to the inside of the casing 2, and a liquid containing a solidifying agent is spouted from the nozzle 5 toward the existing pile 1. The casing 2 is given vibration and is gradually driven downward, but the casing 2 gradually descends while repeatedly moving up and down as appropriate. Of course, the casing 2 and the injection pipe 6 move simultaneously.

そして、ノルズ5から噴出する前記液により地
盤を軟化させる。これにより、既設杭1と地盤と
のフリクシヨンは大幅に低下する。液は、その噴
出により地盤を形成する土の粒子間に充分に浸透
し、且つ、その噴出圧力により土と液とが充分に
混合されて、軟化地盤には流動性が生じる。
Then, the liquid spouted from the nors 5 softens the ground. As a result, the friction between the existing pile 1 and the ground is significantly reduced. The liquid sufficiently penetrates between the soil particles that form the ground due to the jetting, and the soil and the liquid are sufficiently mixed by the jetting pressure, resulting in fluidity in the softened ground.

注入パイプ6やノルズ5の数は、既設杭1の寸
法、地盤の性状等により適宜決定される。また、
図示の例では注入パイプ6がケーシング2に固着
されるが、これらは、夫々独立した構造をもつも
のでもよい。この場合には、両者の運動は必ずし
も前記のように同期しなくてもよい。しかしなが
ら、前記のように注入パイプ6がケーシング1内
に固着されておれば、ケーシング1のみの打ち込
み作業により、同時に注入パイプ6も地盤内に突
入できる利点がある。
The number of injection pipes 6 and nols 5 is appropriately determined depending on the dimensions of the existing piles 1, the properties of the ground, etc. Also,
In the illustrated example, the injection pipe 6 is fixed to the casing 2, but these may have independent structures. In this case, the movements of both do not necessarily have to be synchronized as described above. However, if the injection pipe 6 is fixed in the casing 1 as described above, there is an advantage that the injection pipe 6 can also be plunged into the ground at the same time by driving only the casing 1.

第3図は、既設杭1の下端部まで地盤の軟化が
進んだ状態を示す。そこで既設杭1を抜去する。
この抜去は、既設杭1の周囲の地盤がすでに軟化
しているためフリクシヨンが低下しているから、
極めて容易になし得る。
FIG. 3 shows a state in which the ground has softened to the lower end of the existing pile 1. Therefore, the existing pile 1 is removed.
This removal is because the ground around the existing pile 1 has already softened and the friction has decreased.
It can be done very easily.

既設杭1を抜去した後に、ケーシング2内は軟
化地盤3のみとなる。そして、軟化地盤3には前
記の通り流動性が生じているため、既設杭1の存
在した既設杭1跡たる空洞には、その抜去ととも
に周囲の軟化地盤3が流入して充填される。この
ときの軟化地盤3の空洞への流入は、既設杭1の
抜去に伴い、既設杭1跡の圧力が低下するため、
該低圧部へ吸い込まれる如くに軟化地盤3は流入
する。かくして、前記圧力の変化と、軟化地盤3
の自重とにより前記空洞の充填は円滑になされ
る。これは、一旦空洞が形成された後に充填され
るものではなく、事実上空洞が形成される前に、
既設杭の抜去に伴つて充填される。
After removing the existing pile 1, only the softened ground 3 remains inside the casing 2. Since the softened ground 3 has fluidity as described above, the surrounding softened ground 3 flows in and fills the cavity where the existing pile 1 was located as soon as the existing pile 1 was removed. At this time, the softened ground 3 flows into the cavity because the pressure at the site of the existing pile 1 decreases as the existing pile 1 is removed.
The softened ground 3 flows as if being sucked into the low pressure area. Thus, the change in pressure and the softening of the ground 3
Due to its own weight, the cavity is smoothly filled. This is not something that is filled once the cavity is formed, but is actually filled before the cavity is formed.
It will be filled when the existing piles are removed.

したがつて、一旦形成された空洞に充填するこ
ととは異つて、空洞が残存することはない。
Therefore, unlike filling a cavity once formed, no cavity remains.

既設杭1を抜去すると、該既設杭1の容積に相
当する容積の空隙が地表近傍に形成される。した
がつて、この空隙には、第4図の如く土砂4等を
充填する。このときには、ハンデイなバイブレー
タを使用するだけで土砂4の充填は完了する。け
だし、深度が小であるからである。
When the existing pile 1 is removed, a void with a volume corresponding to the volume of the existing pile 1 is formed near the ground surface. Therefore, this void is filled with earth and sand 4, etc., as shown in FIG. At this time, filling with the earth and sand 4 is completed by simply using a handy vibrator. This is because the depth is small.

この方法で用いる固化剤としては、セメント等
が考えられる。セメントは軟化地盤と混合されて
低強度に地盤を固結する程度に用いる。また、既
設杭1の容積が大なる場合には、これを抜去する
ことによつて軟化地盤3が不足することを防止す
るため、二水石膏、ベントナイトモルタル等を用
いて増量材とする。
Cement and the like can be considered as the solidifying agent used in this method. Cement is mixed with the softened ground and used to solidify the ground to a low strength level. In addition, if the volume of the existing pile 1 is large, in order to prevent the softened ground 3 from becoming insufficient due to its removal, dihydrate gypsum, bentonite mortar, etc. are used as a bulking material.

前記土砂4の充填は、ケーシング2の抜去の前
後を問わないが、ケーシング2の抜去前になせ
ば、地表近傍の地盤の崩落等を防止し得るから好
適である。
The filling of the earth and sand 4 can be done before or after the removal of the casing 2, but it is preferable to fill it before the removal of the casing 2 because this can prevent the ground from collapsing near the ground surface.

なお、この方法により埋戻された地盤の圧縮強
度は1〜3Kg/cm2程度であることが次回の掘削等
のために好適である。
Note that it is preferable that the compressive strength of the ground backfilled by this method is about 1 to 3 kg/cm 2 for the next excavation, etc.

以上から明らかなように、この発明によれば、
既設杭の抜去に伴い、該抜去により生ずる内部圧
の低下と軟化地盤の自重とにより、既設杭跡たる
空洞を完全に埋戻すことができるとともに、該埋
埋戻後の地盤の強度を適当にすることができるた
め、その地盤掘削等の作業を容易にすることがで
きる。また、この発明によれば別段の工程を加え
ることなく既設杭へのフリクシヨンを低下し得る
から、その抜去も極めて容易となる効果がある。
As is clear from the above, according to this invention,
As the existing piles are removed, the internal pressure that occurs due to the removal decreases and the weight of the softened ground makes it possible to completely backfill the cavity where the existing piles remained, and to maintain the strength of the ground after the backfilling. Therefore, work such as ground excavation can be facilitated. Furthermore, according to the present invention, the friction on the existing pile can be reduced without adding any additional steps, and therefore the removal of the existing pile can be made extremely easy.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は、この発明の一実施例を示すものであ
り、第1図は、既設杭の既設状態を示す断面図、
第2図は、ケーシングを打込み且つ地盤を軟化す
る途中の断面図、第3図は、ケーシングの打込み
および地盤軟化が終了した状態の断面図、第4図
は、既設杭を抜去して、上部に土砂を充填した状
態の断面図、第5図は、第3図の5−5線断面拡
大図である。 なお、図中1は、既設杭、2は、ケーシング、
3は、軟化地盤、4は、土砂、5は、ノルズであ
る。
The drawings show one embodiment of the present invention, and FIG. 1 is a sectional view showing an existing state of an existing pile;
Figure 2 is a cross-sectional view of the state in which the casing is driven and the ground is softened, Figure 3 is a cross-sectional view of the state where the casing has been driven and the ground softened, and Figure 4 is the upper part after the existing pile has been removed. FIG. 5 is an enlarged cross-sectional view taken along the line 5-5 in FIG. 3. In addition, in the figure, 1 is the existing pile, 2 is the casing,
3 is softened ground, 4 is earth and sand, and 5 is nors.

Claims (1)

【特許請求の範囲】 1 既設杭の周囲に、該既設杭を囲むように筒状
のケーシングを打ち込み、且つ既設杭とケーシン
グとの間に、固化剤を含んだ液を噴出して、ケー
シング内側の地盤を軟化し、しかる後、既設杭を
抜去するとともに軟化地盤を既設杭跡に充填し、
さらに、軟化地盤の上方に形成される地表近傍の
空隙に土砂等を充填することを特徴とする既設杭
の抜去方法。 2 既設杭の周囲に、該既設杭を囲むように筒状
のケーシングを打ち込みながら、既設杭とケーシ
ングとの間に、ケーシング内側に内方に向けて設
けたノルズから、固化剤を含んだ液を噴出し、ケ
ーシングとノルズとの適宜上下動を繰返して次第
に一定深度までケーシング内側の地盤を軟化し、
しかる後既設杭を抜去するとともに軟化地盤を既
設杭跡に充填し、さらに、軟化地盤の上方に形成
される地表近傍の空隙に土砂等を充填することを
特徴とする既設杭の抜去方法。
[Scope of Claims] 1. A cylindrical casing is driven around the existing pile so as to surround the existing pile, and a liquid containing a solidifying agent is spouted between the existing pile and the casing, so that the inside of the casing is After that, the existing piles are removed and the softened ground is filled into the existing pile remains.
Furthermore, the method for removing existing piles is characterized by filling a void near the ground surface formed above the softened ground with earth and sand. 2. While driving a cylindrical casing around the existing pile so as to surround the existing pile, a liquid containing a solidifying agent is injected between the existing pile and the casing from a nozzle installed inside the casing facing inward. The ground inside the casing is gradually softened to a certain depth by repeatedly moving the casing and the nors up and down as appropriate.
Thereafter, the existing pile is removed, the existing pile remains are filled with softened ground, and the void near the ground surface formed above the softened ground is filled with earth and sand.
JP2713179A 1979-03-08 1979-03-08 Extracting method for existing pile Granted JPS55119825A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2713179A JPS55119825A (en) 1979-03-08 1979-03-08 Extracting method for existing pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2713179A JPS55119825A (en) 1979-03-08 1979-03-08 Extracting method for existing pile

Publications (2)

Publication Number Publication Date
JPS55119825A JPS55119825A (en) 1980-09-13
JPS6128046B2 true JPS6128046B2 (en) 1986-06-28

Family

ID=12212493

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2713179A Granted JPS55119825A (en) 1979-03-08 1979-03-08 Extracting method for existing pile

Country Status (1)

Country Link
JP (1) JPS55119825A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5071320B2 (en) * 2008-09-12 2012-11-14 株式会社大林組 How to pull out a pile

Also Published As

Publication number Publication date
JPS55119825A (en) 1980-09-13

Similar Documents

Publication Publication Date Title
KR101081343B1 (en) Compaction grouting system
CN107012861A (en) A kind of discrete material core expansive concrete stake and its construction method
KR101746654B1 (en) Method for constructing pile for reinforce of mine hole
JP2019015100A (en) How to remove the Yamato wall
JP4888293B2 (en) Earth retaining wall made of parent pile sheet pile, water stop structure of earth retaining wall made of parent pile side sheet pile, construction method of earth retaining wall made of parent pile side sheet pile, and retaining wall of earth retaining wall made of parent pile side sheet pile Water method
JPS6128046B2 (en)
JPH06228947A (en) Construction of landslide protection wall in ground filled up with wastes
JP2003221828A (en) Burying method of ready-made pile
JPS58189414A (en) Construction of sheathing wall
JP4872561B2 (en) Construction method of ready-made piles
CN206570789U (en) A kind of structure for being applied to build retaining wall in Mud Ground
JPH0280710A (en) Preparing cast-in-place concrete pile
JPS61134425A (en) Method of forming foundation pile
JP2002070003A (en) Construction method of pillar type underground diaphragm wall
JP2004124452A (en) Foundation pile structure and construction method of foundation pile on supporting ground
JPS615118A (en) Formation work of over-all friction pile
JPH0325121A (en) Sinking of pile in inner drilling pile method
JPS61211423A (en) Refilling method of excavated trench
JPS63197718A (en) Construction work of in-situ pile
JPH0442493B2 (en)
JPS60123619A (en) Block stay anchor and manufacture thereof
JPS6122089B2 (en)
JP2711029B2 (en) Soil improvement method of pile formation hollow moat
JPS63304821A (en) Construction work of underground continuous cut-off wall
JPS62174415A (en) Formation of in-situ pile