JPS6149018A - Construction of sand pile by casing shorten than improved length - Google Patents
Construction of sand pile by casing shorten than improved lengthInfo
- Publication number
- JPS6149018A JPS6149018A JP16996184A JP16996184A JPS6149018A JP S6149018 A JPS6149018 A JP S6149018A JP 16996184 A JP16996184 A JP 16996184A JP 16996184 A JP16996184 A JP 16996184A JP S6149018 A JPS6149018 A JP S6149018A
- Authority
- JP
- Japan
- Prior art keywords
- casing
- sand
- length
- pipe
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/10—Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
- E02D3/106—Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains by forming sand drains containing only loose aggregates
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
Description
【発明の詳細な説明】
■ 発明の目的
産業上の利用分野
本発明方法は、軟弱地盤改良工事の際に用いられる地盤
中に多数のサンドパイル等を造成する施工法に関するも
のである。DETAILED DESCRIPTION OF THE INVENTION ■Objective of the invention Industrial field of application The method of the present invention relates to a construction method for creating a large number of sand piles etc. in the ground used in soft ground improvement work.
従来の技術
水深Aの底の軟弱地盤に対して深さBの多数のサンドパ
イルを施して地盤改良を行うとき、従来の施工法では、
ケーシングを水底地盤の杭底深度まで打込んだ状態で、
ケーシング上部が水面上にあるような長さ、すなわち、
少くともA十Bの長さを有するケーシングを使用してい
たから、(イ)ケーシングに大きな浮力が掛かり、その
浮力打消しのため貫入機を重くする必要があり、貫入装
置が全体的((長大で重量があるものになるので振動機
または衝撃機に大容量のものを要する。((ロ)貫入装
置のガイドリーダーも、それに見合って堅固で大きなも
のを用意しなければならない。(・・)貫入装置を吊下
げ、吊−ヒげるウィンチの容量も、これに見合った大き
さが必要。(ニ)その結果、施工機の安定性に問題が生
じるから可及的に大型機を導入・することを要する。と
云った非効率的で不経済な施工を強いられていた。Conventional technology When performing ground improvement by applying a large number of sand piles at depth B to soft ground at the bottom of water depth A, conventional construction methods:
With the casing driven to the depth of the pile bottom in the underwater ground,
the length such that the top of the casing is above the water surface, i.e.
Since a casing with a length of at least A x B was used, (a) a large buoyant force was applied to the casing, and it was necessary to make the penetrating machine heavier to cancel out the buoyant force, and the penetrating machine as a whole ((long and Since it is heavy, a vibrator or impact machine with a large capacity is required. ((b) The guide leader of the penetration device must also be strong and large. (...) Penetration The capacity of the winch to suspend and lift the equipment needs to be large enough to accommodate this. (d) As a result, problems arise with the stability of the construction machine, so a large machine should be introduced as much as possible. Inefficient and uneconomical construction was required.
また、陸上におけるサンドパイルによる軟弱地盤改良工
事のときも、従来、ケーシングの長さは少くとも杭底深
度Bよりも長いものを使用しているから、その質量が大
きく、上述の不都合を避けることができず、(ホ)ケー
シングを適当長引抜いて生じる空隙部にケーシング内に
供給した砂等を排出し、次いでケーシングを再貫入して
排出砂等を締固め地盤中に膨出させる操作ザイル、いわ
ゆるコンポーザエ法を順次上方向に繰返す工法とが、ケ
ーシングに設けた振動体、スクリュー、上下作動押出し
機構等により、ケーシング下端から軟弱地盤中に砂等を
強制的に排出・押出し、かつ突固めする操作サイクルを
繰返す工程においては、サンドパイルの造成、特に径を
拡大したパイルの造成のために大きな駆動エネルギーが
必要になる。In addition, when performing soft ground improvement work using sand piles on land, conventionally, the length of the casing is at least longer than the pile bottom depth B, so the mass is large and the above-mentioned disadvantages can be avoided. (e) An operating pile that discharges the sand, etc. supplied into the casing into the void created by pulling out the casing for an appropriate length, and then re-penetrates the casing and bulges the discharged sand, etc. into the compacted ground; This is a construction method in which the so-called Composer method is repeated upward in sequence, and sand, etc., is forcibly discharged and pushed out from the bottom of the casing into the soft ground using a vibrating body installed in the casing, a screw, a vertically operating extrusion mechanism, etc., and then compacted. In the process of repeated operation cycles, a large amount of driving energy is required to create sand piles, especially to create piles with enlarged diameter.
さらに、上述のパイル造成用の砂等は、一旦はケーシン
グ上端のホッパー進運び上げてケーシング内に補給する
ものであるから、(へ)ケーシングの長さが長いときに
は高い場所に持上げる作業が必要になり、昇降パケット
を用いる〃バッチ式〃にしろ、圧送パイプを用いる〃リ
アルタイム式〃にしろ、その為に相当の動力を要するも
のとなる。Furthermore, the sand, etc. for building the pile mentioned above is once transported up to the hopper at the top of the casing and refilled inside the casing, so (f) when the length of the casing is long, it is necessary to lift it to a high place. Therefore, whether it is a "batch type" using elevating packets or a "real time type" using a pressure pipe, a considerable amount of power is required.
そこで最近では、その対策として、水底地盤改良工法と
しては、ケーシングの長さを地盤改良深さBよりもやや
長めにし、水深Aの分はバイブロハンマーを備えた衝撃
伝達杆の長さでカバーするとか、ケーシング内に補給す
る砂等のホッパー取付位置は可及的低位置に設けるなど
して、貫入装置の質量を少さくシ、その駆動エネルギー
の低減を図るとか、リーダーの強度を貫入装置の重量に
マツチさせ、また、衝撃伝達杆とケーシングとの相法
= 4−
互固定位置を可変にすることによって、リーダーの長さ
く高さ)を短かく、軽量化するなどの水中ドレーン杭打
設方法(特公昭49−1084号公報参照)が提案さ扛
ている。Recently, as a countermeasure for this, an underwater soil improvement method has been developed in which the length of the casing is made slightly longer than the soil improvement depth B, and the length of the water depth A is covered by the length of an impact transmission rod equipped with a vibrohammer. For example, the hopper for replenishing sand etc. into the casing can be mounted as low as possible to reduce the mass of the penetrating device and its driving energy. Driving underwater drain piles by matching the weight and changing the mutual fixing position of the impact transmission rod and casing to shorten the length and height of the leader and reduce weight. A method (see Japanese Patent Publication No. 49-1084) has been proposed.
また、ケーシングから排出した砂等を軟弱地盤中に膨出
させ、径の大きなパイルを造成する方法として輸送用流
体に砂等を混合し、それらがケーシング内を流通すると
きに砂等を分離させることによってケーシングに砂等の
補給をすると共に、前記流体の圧力を制御することによ
って、ケーシング下端から地盤中に排出する砂等に圧力
を加え、土圧に対抗して強制的IC押出し、締固めして
、造成パイル径を制御するようにして、ケーシングの駆
動エネルギーを節約し、経済的効果を得ようとする砂杭
造成工法(特開昭53−125309号公報または特開
昭53−145311号公報参照)も公開されている。In addition, as a method of creating large-diameter piles by bulging sand discharged from the casing into soft ground, sand, etc. is mixed with transportation fluid, and the sand, etc. is separated as it flows through the casing. By this, the casing is replenished with sand, etc., and by controlling the pressure of the fluid, pressure is applied to the sand, etc. discharged from the lower end of the casing into the ground, and forced IC extrusion and compaction are performed against the earth pressure. A sand pile construction method (JP-A-53-125309 or JP-A-53-145311) aims to save driving energy of the casing and obtain economic effects by controlling the pile diameter. (see official bulletin) are also published.
しかし、いずれにしても従来工法は、貫入装置における
ケーシングの長さが地盤改良深さBよりも実用上幾分か
長いものを使用しているのが現状であり、その為、程度
の差はあっても前述(イ)〜(へ)項に挙げた問題点を
解消することができなかったし、その解決策として前述
Bの長さよりも短い丈のケーシングを使用するという技
術思想を提案するものは無かった。However, in any case, in the conventional method, the length of the casing in the penetration device is actually somewhat longer than the ground improvement depth B, and therefore the difference in degree is Even if there were, we could not solve the problems listed in items (a) to (f) above, and as a solution, we propose the technical idea of using a casing with a length shorter than the length of B above. There was nothing.
当該発明が解決しようとする問題1、
そこで本発明方法は、斜上、従来のサンドパイル造成工
法における前述不都合点を解消かつ改善し得る新規な施
工方法を提供しようとするものである。Problem 1 to be Solved by the Invention Therefore, the method of the present invention attempts to provide a new construction method that can eliminate and improve the above-mentioned disadvantages of the conventional sand pile construction method.
(B) 発明の構成
問題点を解決するための手段
本発明方法は、
(1)軟弱地盤の所定深さにサンドパイルを打設する工
法において、地盤貫入用ケーシングを上端面閉塞形であ
って軸方向長さを地盤の改良深さに相当する長さよりも
短かくすると共に、その上部位置に設けた貫入手段との
間を動力伝達杆により連結し、前記ケーシング内部に、
輸送流体と共に、これに混入した砂等を補給するパイプ
と、同ケーシング内で砂等を分離した前記流体を排出す
るためのパイプまたはケーシング内部圧力を調節する流
体供給用パイプを連通して成り、所定深さ迄貫入したケ
ーシングの引抜きにより、その下方地盤中に生じる空隙
部に、ケーシング内に補給された砂等を排出・充填する
ことを特徴とする改良長さよりも短かいケーシングです
/ドパイル等を施工する方法。(B) Means for Solving the Constituent Problems of the Invention The method of the present invention is as follows: (1) In a method of driving a sandpile at a predetermined depth in soft ground, the casing for ground penetration is of a closed type at the upper end. The axial length is made shorter than the length corresponding to the soil improvement depth, and the penetration means provided at the upper position is connected by a power transmission rod, and inside the casing,
A pipe for replenishing sand, etc. mixed with the transportation fluid, and a pipe for discharging the fluid from which sand, etc. has been separated in the same casing, or a fluid supply pipe for adjusting the internal pressure of the casing, are connected to each other, This is an improved casing that is shorter than the improved length, characterized by draining and filling the void created in the ground below by pulling out the casing that has penetrated to a predetermined depth. How to construct.
(2)動力伝達杆の長さは少くとも、地盤改良深さまた
は地盤改良深さに水深を加えた長さからケーシングの軸
方向長さを差引いた長さよりも長くしたことより成る上
記第(1)項記載の、改良長さよりも短かいケーシング
でサンドパイ/l’ll’ii工する方法。(2) The length of the power transmission rod is at least longer than the soil improvement depth or the soil improvement depth plus the water depth minus the axial length of the casing. 1) Method of sand pie/l'll'ii work with a casing shorter than the improved length.
(3)砂等は、砂、砂利、砕石、鉱さい、石灰、セメン
ト等の砂類似粒状材の−っまたは、それらの混合物で、
これに対する輸送流体は圧縮空気を用いることより成る
」−配植(1)、(2)項記載の、改良長さよりも短か
いケーシングでサンドパイル等を施工する方法。(3) Sand, etc. refers to sand-like granular materials such as sand, gravel, crushed stone, slag, lime, cement, etc., or a mixture thereof;
The transport fluid for this consists of using compressed air.'' - A method of constructing sand piles, etc. with a casing shorter than the improved length, as described in sections (1) and (2).
(4)砂等は、砂、砂利、砕石、鉱さい等の砂類似粒状
材の一つまたは、それらの混合物で、輸送流体は少量の
水を用いることより成る上記第(1)、(2)項記載の
、改良長さよりも短かいケーシングでサンドパイル等を
施工する方法。(4) The sand, etc. is one of sand-like granular materials such as sand, gravel, crushed stone, ore slag, or a mixture thereof, and the transport fluid is a small amount of water. A method of constructing sand piles, etc. using a casing shorter than the improved length described in Section 1.
(5)輸送流体排出パイプまたは流体供給パイプの中途
に、圧力調整手段を挿入し、前記手段を制御することに
よりケーシング内部圧力を調節し、地盤土壌中に排出さ
れる砂等により形成されたパイルの直径または密度を制
御することよりなる上記第(])〜(4)項記載の、改
良長さよりも短かいケーシングでパイル等を施工する方
法。(5) A pressure regulating means is inserted in the middle of the transportation fluid discharge pipe or fluid supply pipe, and the internal pressure of the casing is adjusted by controlling the means, and the pile is formed by sand etc. discharged into the ground soil. A method of constructing piles or the like with a casing shorter than the improved length, as described in items (]) to (4) above, which comprises controlling the diameter or density of the casing.
にががる。bitter.
つまり、従来工法におけるケーシングの機能は、軟弱地
盤中に孔を明けることおよびその内部に収容した砂等を
地盤土壌から保護することに重点が置かれ、そのためケ
ーシングの長さが改良施工長Bよりも長いものを使用し
ていたものと解される。In other words, the function of the casing in conventional construction methods is focused on making a hole in soft ground and protecting the sand, etc. stored inside the hole from the ground soil, so the length of the casing is longer than the improved construction length B. It is understood that a long one was also used.
水上施工の際は、その長さに水深A分の長さが加わるの
で、さらに大きなものとなり、前述のような問題が目立
つようになっていた。そこで本発明方法の基本的技術思
想は、ケーシングに砂等の保護管としての機能を求める
よりも、むしろ砂等の排出管としての機能を重視し、そ
のためにケーシングに対し、流体に混入して補給される
砂等の分離に必要な程度のスペースと軸方向長さの確保
および所要径のサンドパイル造成に要する直径を備える
ことが求められている。When construction is carried out over water, the length corresponding to the water depth A is added to the length, so the length becomes even larger, and the above-mentioned problems become more noticeable. Therefore, the basic technical idea of the method of the present invention is that rather than requiring the casing to function as a protection pipe for sand, etc., it emphasizes its function as a discharge pipe for sand, etc. It is required to ensure sufficient space and axial length to separate the sand, etc. to be replenished, and to provide a diameter necessary to create a sandpile of the required diameter.
本発明方法においては砂等が排出管としてのケーシング
壕で何等かの手段で補給されればサンドパイルを造成す
るために充分である。In the method of the present invention, it is sufficient to create a sand pile if sand or the like is replenished by some means through the casing trench serving as a discharge pipe.
作 用
(イ) ドライ施工法
ケーシング下端深度を深度計を用いて検出しながら地盤
中、所定深さまでケーシングを貫入した後、砂等を圧縮
空気にのせ補給パイプを通じてケーシング内上部に搬送
し、そこで空気と分離させる。分離した砂等はケーシン
グ下部に収容・補給され、圧縮空気は排出または回収パ
イプから回収する。Operation (a) Dry construction method After penetrating the casing into the ground to a predetermined depth while detecting the depth of the lower end of the casing using a depth gauge, sand, etc. is placed on compressed air and transported to the upper part of the casing through a supply pipe, where it is Separate from air. Separated sand, etc. is stored and replenished in the lower part of the casing, and compressed air is discharged or recovered from the recovery pipe.
このようにしてケーシング内を圧気状態に保持しながら
、ケーシングを徐々に引抜くことにより、その下端に収
容されている砂等を地盤中に排出する一方、引続いてケ
ーシング内に砂等を補給し、かくしてケーシング下端部
抜かれた跡にサンドパイルが形成される。その際、ケー
シングの下端開口部から地盤中に排出される砂量は、砂
面計を用いて検出することができる。上述のような操作
を地表付近壕で行うことにより、所定深さのサンドパイ
ルを造成する。このほか、ケーシングを一定長引抜いた
後、適当深さ再貫入させ、以後、それらの操作を繰返し
て行う、いわゆるコンポーザエ法とかケーシングは徐々
に引抜きながらも、ケーシング下部内に設けた強制駆動
機構により砂排出兼締固め部材を」二、下動させてサン
ドパイルを造成する方法もある。In this way, by gradually pulling out the casing while maintaining the inside of the casing in a pressurized state, the sand, etc. stored in the lower end of the casing is discharged into the ground, while the sand, etc. is subsequently replenished into the casing. However, a sandpile is formed at the site where the lower end of the casing has been pulled out. At this time, the amount of sand discharged into the ground from the lower end opening of the casing can be detected using a sand level meter. By performing the above operations in a trench near the ground surface, a sandpile of a predetermined depth is created. In addition, there is the so-called composite method, in which the casing is pulled out for a certain length, then re-penetrated to an appropriate depth, and these operations are repeated. There is also a method of creating a sand pile by moving the sand discharge/compaction member downward.
これらの施工法では砂等を補給パイプを通してケーシン
グ内に気送し、排出パイプによって圧縮空気を排気する
が、この際、排気パイプの回収空気圧を制御することに
より、圧気されたケーシング下端での空気圧を、管下端
深度における土圧(水底地盤面の改良にあっては水深分
の水圧と水底地盤面下管下端深度迄の土圧とを加えた圧
力)に対応させることにより、造成パイル径の制御を行
う。すなわち、管下端での空気圧を、管下端深度におけ
る主働土圧を越え、受働土庄未満に抑えることにより、
管径分のサンドパイルを造成し、また、管下端での空気
圧を、管下端深度における主働土圧以上に調°整するこ
とにより、管径分より拡大した径のサンドパイルを造成
することができる。In these construction methods, sand, etc. is fed into the casing through a supply pipe, and compressed air is exhausted through an exhaust pipe. At this time, by controlling the recovery air pressure of the exhaust pipe, the air pressure at the lower end of the pressurized casing By making it correspond to the earth pressure at the depth of the lower end of the pipe (in the case of improving the water bottom ground surface, the pressure that is the sum of the water pressure for the water depth and the earth pressure up to the depth of the lower end of the pipe below the water bottom ground surface), the diameter of the constructed pile can be adjusted. Take control. In other words, by suppressing the air pressure at the bottom end of the pipe to exceed the active earth pressure at the depth of the bottom end of the pipe and below the passive earth pressure,
By creating a sandpile equal to the diameter of the pipe and adjusting the air pressure at the bottom end of the pipe to be greater than the active earth pressure at the depth at the bottom end of the pipe, it is possible to create a sandpile with a diameter larger than the diameter of the pipe. can.
(ロ) ウェット施工法
加水量を補給パイプを使用して流動状態のままケーシン
グ−F部迄送る。一方、流体供給用パイプから圧縮空気
を供給する場合もある。そのようにして、ケーシング内
に加水量を充填してから、ケーシングを徐々に引抜くこ
とにより、充填された加水量を、その下端から排出して
ゆき、地盤中に加水量によるサンドパイルを形成する。(b) Wet construction method The amount of water added is sent to the casing-F section in a fluid state using a replenishment pipe. On the other hand, compressed air may be supplied from a fluid supply pipe. In this way, by filling the casing with water and then gradually pulling out the casing, the filled water is discharged from the lower end, forming a sandpile in the ground due to the amount of water added. do.
特に〃飽和付近の含水比の加水量〃となるような加水量
とした加水量を用いたときは、振動等の外力を作用させ
ることによって流動状態を保持するから振動機(または
衝撃機)を作動させれば加水量を流体として取扱いでき
、ケーシング下端からの排出をスムーズに行うこと、な
らびに排出量の調節も容易になる。このような加水量に
よるサンドパイルは後に造成径が細まる心配がない。In particular, when the amount of water added is such that the water content ratio is near saturation, a vibrator (or impact machine) is used to maintain the fluid state by applying an external force such as vibration. When activated, the amount of water added can be handled as a fluid, allowing smooth discharge from the lower end of the casing and making it easier to adjust the amount of water discharged. There is no fear that the diameter of the sand pile created by adding water in this amount will become narrower later.
上述の場合、ケーシング下端部に一種の開閉弁を設け、
その開度調節によって排出流量を制御することも可能で
あり、また、そのような開閉弁を使用し、一旦弁を閉じ
てケーシング内に充填される加水量の上に流体供給パイ
プからの圧縮空気の調整圧を加え、開閉弁を開にするこ
とで、前記空気圧を加水量の排出流量制御の補助に使用
することもできる。In the above case, a kind of on-off valve is provided at the lower end of the casing,
It is also possible to control the discharge flow rate by adjusting the opening degree, and by using such an on-off valve, once the valve is closed, compressed air from the fluid supply pipe is added to the amount of water filled into the casing. The air pressure can also be used to assist in controlling the discharge flow rate of the amount of water added by applying the adjustment pressure and opening the on-off valve.
また、ケーシング内側水砂による管下端面の圧力と、流
体供給パイプによる圧縮空気圧の合計圧力を、管下端深
度における土圧に対応させ、合計圧力を管下端深度にお
けるゝ主働土圧を越え受働土圧未満に制御することによ
り、管径分のサンドパイルを造成し、管下端深度におけ
る受働土圧以上に制御することにより管径分より拡大し
たサンドパイルを造成することができる。In addition, the total pressure of the pressure on the lower end surface of the pipe due to water sand inside the casing and the compressed air pressure from the fluid supply pipe is made to correspond to the earth pressure at the depth of the lower end of the pipe, and the total pressure exceeds the active earth pressure at the depth of the lower end of the pipe and is By controlling the pressure to less than the passive earth pressure, it is possible to create a sandpile equal to the diameter of the pipe, and by controlling it to a level greater than or equal to the passive earth pressure at the depth of the lower end of the pipe, it is possible to create a sandpile larger than the diameter of the pipe.
なお、ウェット施工の場合は、前記のドライ施工のよう
な強制的砂排出兼締固め手段は不用であり、また、一般
にケーシングの再貫入は行われない。In addition, in the case of wet construction, there is no need for forced sand discharge and compaction means as in the dry construction described above, and the casing is generally not re-penetrated.
実施例 1
第1(a)図は、本発明方法を実施するための施工機(
本実施例では海上施工船)の概略側面図で、図中、1は
、上端閉塞形の円筒鋼管より成るケーシングを示し、そ
の内側空間は気送される砂等を気流から分離できるだけ
のスペースと軸方向長さとを備え、その長さは殆んど軟
弱地盤改良深さとは無関係である。また、その内径は造
成パイルの最大径の数分の−よりも大であるのが好まし
い。Example 1 Figure 1(a) shows a construction machine (
This is a schematic side view of a marine construction vessel (in this example, a marine construction vessel). In the figure, 1 indicates a casing made of a cylindrical steel pipe with a closed top end, and the inner space is large enough to separate sand, etc. to be pneumatically blown from the air flow. The length is almost independent of the soft ground improvement depth. Moreover, it is preferable that the inner diameter is larger than a fraction of the maximum diameter of the constructed pile.
下端開口は、ケーシング貫入操作時に地盤土壌が侵入し
ないよう開閉蓋を設けることもある。The lower end opening may be provided with an opening/closing lid to prevent ground soil from entering during the casing penetration operation.
2は、動力伝達杆で、貫入機3とケーシング1との間を
連結すると共に、貫入機3の振動をケーシング1に伝達
して間管を軟弱地盤中、所定深さ迄質入させる。その際
、貫入機3は地表または水面上に余裕を持って位置でき
る程度に伝達杆2の長さが定められている。同杆は、■
形鋼、H形鋼などの型鋼1だは鋼管であってよく、その
長さは最大池盤改良深さからケーシングの長さを差引い
たもの、水上施工の場合は、それに水深を加えた長さよ
りも若干長いものとするのが一般である。Reference numeral 2 denotes a power transmission rod that connects the penetrating machine 3 and the casing 1, and transmits the vibrations of the penetrating machine 3 to the casing 1 to pawn the pipe into soft ground to a predetermined depth. At this time, the length of the transmission rod 2 is determined to such an extent that the penetrating device 3 can be positioned above the ground or water surface with a sufficient margin. The same rod is ■
Shaped steel 1, such as shaped steel or H-shaped steel, may be a steel pipe, and its length is the maximum pond improvement depth minus the length of the casing, or in the case of construction over water, the length plus the water depth. Generally, it is slightly longer than that.
水中でも使用可能な貫入機とした場合は、水深部は加え
なくてもよい。伝達杆2の断面積は必要強度にもよるが
、あまり大でない方が好ましく鋼管を使用する場合は上
下端を開放する。つ丑り、伝達杆2の地盤への貫入によ
って、地盤中に無用の孔を明け、そこの土壌を側方に押
出すことが少ないのが望ましい〔第2(b)区点線表示
部参照〕。If the penetration machine is designed to be usable underwater, there is no need to add a depth section. The cross-sectional area of the transmission rod 2 depends on the required strength, but it is preferable that it is not too large.If a steel pipe is used, the upper and lower ends should be open. It is desirable that penetration of the transmission rod 2 into the ground does not create unnecessary holes in the ground and push the soil there to the side. [Refer to section 2 (b) Dotted line display] .
3は貫入機で、通常、動力伝達杆2の上端部に固着され
るが、第11b)図に示すように伝達杆2との間の相対
的固着位置を変更可能にして、後述リーダーの長さを短
かくする手段もある。貫入機3には振動機または衝撃機
を使用するのが一般である。Reference numeral 3 denotes a penetrating machine, which is normally fixed to the upper end of the power transmission rod 2, but as shown in Fig. 11b), the relative fixing position between it and the transmission rod 2 can be changed, and the length of the leader described later can be changed. There are also ways to shorten the length. Generally, a vibrator or an impact machine is used as the penetrating machine 3.
4は、1゛1人機:つ、これに連結する伝達杆2および
ケー/ングlを上、下方向に案内・支持するリーダーで
、木、+4施例では作業船の一側に立設されている、勿
論、陸に細工の際にはタローラークレ−7に設けられる
1、リーダー4の丈、すなわち長さは、少くともケー/
ング1の・h11方向長さ、動力伝達杆2、貫入機3お
よび緩衝器5を直列に連結した長さよりも長くなければ
ならず、その頂端に滑車を軸支して、緩衝器5に取Uけ
た滑車を介し、前記部材1〜3および5より成る貫入装
置に連結したワイヤロープを、これに掛渡し、その他端
を別に設置したウィンチドラムに結んで、貫入装置をリ
ーダー4 K rr3つて一ヒ、下方向に吊上げ、吊下
げ可能にしである。い したがって、ガイドリーダー4
は、少くとも地盤改良深さと同じ長さのケーシングの重
量を支持する必要がなく、これに対応して構造・強度の
レベルを下げることができるのでリーダーを軽量にする
ことが可能であり、この点は水上施工の際には、加えて
水性分のケーシング重量を支持することを要しないため
、特に大きな効果を奏する。さらに、第1(b)図に示
すように貫入機3と伝達杆2との固着位置を変更するこ
とができるようにしておけば、リーダー4の丈を、ケー
シング1の軸方向長さに伝達杆2等の長さを加えたもの
よりも短かくすることが可能になるので、さらに小型化
することができ、施工機の安定性、操縦性を良好にする
ばかりか施工機全体を小型化することも可能になる。水
中貫入機を使用する場合は、リーダーは水中まで伸ばす
ことになるが、安定性の点ではさらに向上する。4 is a leader that guides and supports the transmission rod 2 and the cable ring 1 connected to this in the upward and downward directions; it is made of wood, and is installed on one side of the work boat in the +4 example. Of course, when working on land, the length of the leader 4 provided on the tall roller clay 7, at least the length of the case/
The length of the ring 1 in the ・h11 direction must be longer than the length of the power transmission rod 2, the penetrator 3, and the shock absorber 5 connected in series, and a pulley is pivotally supported at the top of the rod and attached to the shock absorber 5. A wire rope connected to the penetrating device consisting of the members 1 to 3 and 5 is looped through the U-shaped pulley, and the other end is tied to a separately installed winch drum, so that the penetrating device is connected to the leader 4Krr3. hi, lift it downwards so that it can be hung. Therefore, guide leader 4
This makes it possible to make the leader lighter as it does not need to support the weight of a casing of at least the same length as the soil improvement depth, allowing for a correspondingly lower level of structure and strength. This is especially effective when performing construction on water, since it is not necessary to additionally support the weight of the water-based casing. Furthermore, as shown in FIG. 1(b), if the fixed position between the penetrator 3 and the transmission rod 2 can be changed, the length of the leader 4 can be transmitted to the axial length of the casing 1. Since it is possible to make it shorter than the length of the rod 2 etc., it can be further downsized, which not only improves the stability and maneuverability of the construction machine, but also reduces the size of the construction machine as a whole. It will also be possible to do so. If a submersible penetrator is used, the leader will extend into the water, providing even greater stability.
以上、説明したように貫入装置全体の重量を軽くするこ
とができたから、同装置を駆動するための貫入機3の容
量とかウィンチのパワーなどを、これに応じて小さくす
ることができ、また駆動エネルギーを節減することがで
きる。As explained above, since the weight of the entire penetrating device can be reduced, the capacity of the penetrating device 3 and the power of the winch for driving the device can be reduced accordingly, and the driving force can be reduced accordingly. Energy can be saved.
なお、水上施工の場合はケーシングが施工改良長よりも
短かく、それから生じる浮力の大きさをセーブすること
ができるから、その分だけ駆動力を小さくすることが可
能である。In addition, in the case of construction on water, the casing is shorter than the construction improvement length, and the magnitude of the buoyancy generated from it can be saved, so it is possible to reduce the driving force by that amount.
5は、緩衝器であって、コイルスプリング、ゴムなどを
組合わ拷て制振機構を構成したものであり、貫入機3か
らの振動・衝撃がワイヤ・ロープを介してリーダー4に
伝わらないよう遮断する作用を受持つ。Reference numeral 5 denotes a shock absorber, which constitutes a vibration damping mechanism by combining coil springs, rubber, etc., and prevents vibrations and shocks from the penetrator 3 from being transmitted to the leader 4 via the wire rope. It has the function of blocking.
6は、ケーシングlの上端内側に連通した砂等の補給パ
イプで、別に設けた気送手段にのせて砂、砂利、砕石、
鉱さい、石灰またはセメントのような砂類似粒状材の一
つまたは混合物をケーシングl内に送込み、その空間で
気粒分離し、砂等はケーシングlの下端開口部付近に堆
積、補給する3゜そのため補給バイブロの開口端をケー
シング1内に深く貫入させるとか、管内に螺旋状に流入
するようにするとか、フィルクーを設けるなどして、気
粉分離作用を促進させ、かつ、その作用を確実なものと
している。一方、砂等を分離した圧縮空気は、同じくケ
ーシングl上端に連通ずる排出(回収)パイプ7によっ
て管外に回収する。排出パイプ7には、その中途に圧力
調整弁を挿入して排気圧を制御できるようにしである。6 is a supply pipe for sand, etc. that communicates with the inside of the upper end of the casing l, and is used to supply sand, gravel, crushed stone, etc. on a separately provided air supply means.
One or a mixture of sand-like granular materials such as slag, lime or cement is fed into the casing l, air particles are separated in that space, and sand, etc. is deposited and replenished near the lower end opening of the casing l. Therefore, by making the open end of the replenishment vibro deeply penetrate into the casing 1, by making it flow into the pipe in a spiral shape, by providing a filter, etc., it is possible to promote the air particle separation effect and to ensure its effect. I take it as a thing. On the other hand, the compressed air from which sand and the like have been separated is recovered outside the pipe through a discharge (recovery) pipe 7 that also communicates with the upper end of the casing l. A pressure regulating valve is inserted in the middle of the exhaust pipe 7 so that the exhaust pressure can be controlled.
これらのバイブロ、7は、いずれもケーシングl上端に
至るまでは動力伝達杆2に沿わせたり、内部に設置する
ことおよび鋼管を用いるとメンテナンスが楽になる。そ
れ以後、供給#、寸での経路は可焼性のあるパイプを用
いる。Maintenance of these vibros 7 can be facilitated by placing them along the power transmission rod 2 up to the upper end of the casing l or installing them inside the vibro, and by using steel pipes. From then on, the supply route uses combustible pipes.
8は作業船、9は水底地盤面、W、Lは水面を示す。8 indicates a work boat, 9 indicates the water bottom ground surface, and W and L indicate the water surface.
第2図は、本発明方法の工程を示すもので、そのfa)
は、貫入装置を水底の軟弱地盤中の所定深さ捷で貫入し
たところ、(b)はサンドパイル造成工程完了時の状態
である。第2(a)図において、動力伝達杆2に鋼管を
用いたときは、その上、下端を開放して浮力を生じない
ようにするとか、引抜き時には積極的に空気を導入して
、貫入した土壌を、う捷く原地盤中に戻すこともできる
。なお、図ではケーシングが二本、伝達杆2に対称的に
連結されているが、ケーシング1の数は一本でもよく、
数にとられれない。ただし、平面上でみて貫入機3に対
してケーシングの支持位置がバランスしていなければな
らないのは当然である。FIG. 2 shows the steps of the method of the present invention, its fa)
(b) shows the state at the completion of the sandpile creation process, when the penetration device was penetrated to a predetermined depth into the soft ground at the bottom of the water. In Fig. 2(a), when a steel pipe is used for the power transmission rod 2, the lower end is opened to prevent buoyancy, or air is actively introduced during extraction to prevent penetration. It is also possible to return the soil to the eroded original ground. In addition, in the figure, two casings are symmetrically connected to the transmission rod 2, but the number of casings 1 may be one,
It cannot be taken as a number. However, it goes without saying that the supporting position of the casing must be balanced with respect to the penetrating machine 3 when viewed from above.
第・2(b)図は、排出パイプに挿入した圧力調整弁を
調節することによってケーシング1下端開口部における
空気圧を、管下端深度における主働土圧を越え受働土圧
未満に制御しつつ、徐々にケーシングを引上げることに
よって、はぼ管径針のサンドパイルを造成したところを
示すもので、勿論、その操作中、ケーシング内に砂等の
気送、補給を絶やさないようにしなければならない。そ
の際、空気圧を受動土圧以」二に制御することによって
管径よりも拡大した径のサンドパイルを造成することが
できるから、ケーシング1の径を相対的に細くすること
が可能であり、つまりは、ケーシングの質量をより小さ
くすることができる。したがって、特定径のケーシング
を用い、複数棟の径のサンドパイルを、それぞれ造成可
能となる。Figure 2(b) shows that by adjusting the pressure regulating valve inserted in the discharge pipe, the air pressure at the lower end opening of the casing 1 is gradually controlled to exceed the active earth pressure at the depth of the lower end of the pipe and to be less than the passive earth pressure. This figure shows the construction of a sandpile for the hollow tube diameter needle by pulling up the casing.Of course, during this operation, it is necessary to keep pneumatically feeding and replenishing the casing with sand, etc. At that time, by controlling the air pressure to a level greater than the passive earth pressure, it is possible to create a sandpile with a diameter larger than the pipe diameter, so it is possible to make the diameter of the casing 1 relatively thin. In other words, the mass of the casing can be made smaller. Therefore, using a casing with a specific diameter, it is possible to create sandpiles each having a plurality of diameters.
なお、造成されたサンドパイルは、ドライ砂によって形
成されるから、初期吸水量において優れていると共に造
成時においても締固めによって砂の間隙比を小さくする
ことができ、締固めサンドパイルを造成することができ
る。前述施工中、使用済みの圧縮空気は排出パイプ7に
よって回収されるから、水域を汚濁するおそれはない。Furthermore, since the created sand pile is made of dry sand, it has an excellent initial water absorption capacity, and the pore ratio of the sand can be reduced through compaction during construction, creating a compacted sand pile. be able to. During the above-mentioned construction, the used compressed air is collected by the discharge pipe 7, so there is no risk of polluting the water area.
実施例 2
第1(a)図中、砂等の補給バイブロを用いて、ケーシ
ング1内に加水量を流動状態のまま供給する。Example 2 In FIG. 1(a), water is supplied into the casing 1 in a fluid state using a replenishing vibro such as sand.
そのようにして、ケーシング内に加嶽槃を充填し、ケー
シングを徐々に引抜くことにより充填された加水量をケ
ーシング1内から排出してゆき、地盤中にサンドパイル
を形成する。一方、流体排出パイプ7から圧縮空気をケ
ーシング1内に供給して、その圧力を充填された加水量
の上に加え、ケーシング1を引」−げるときに地盤中に
排出する加水量の量を調節することが可能で、なお、前
記圧縮空気はケーシング内の加水砂上面に作用するだけ
で外部に洩れることはないから、水域汚濁のおそれはな
い。In this way, the casing is filled with water, and by gradually pulling out the casing, the filled water is discharged from the casing 1, forming a sandpile in the ground. On the other hand, compressed air is supplied into the casing 1 from the fluid discharge pipe 7, and the pressure is applied to the amount of added water that is filled, and the amount of added water that is discharged into the ground when the casing 1 is pulled out. Furthermore, since the compressed air only acts on the upper surface of the hydrated sand in the casing and does not leak to the outside, there is no risk of polluting the water area.
特に、〃□飽和付近の含水比の加水量〃となるような加
水量の加水量は振動等の外力を作用させて流動状態を保
持することができるのでケーシング引上げ操作に加えて
振動機を作動させれば加水量を流動体として地盤中に排
出することができ、上述圧縮空気の圧力を制御して管径
よりも拡大した径を有するサンドパイルを造成すること
ができる。In particular, when the amount of water added is such that the water content ratio is near saturation, the fluid state can be maintained by applying an external force such as vibration, so a vibrator is activated in addition to the casing lifting operation. By doing so, the amount of added water can be discharged into the ground as a fluid, and by controlling the pressure of the compressed air mentioned above, it is possible to create a sandpile having a diameter larger than the pipe diameter.
(C)発明の効果
以上のとおりであるから本発明方法によれば、ケーシン
グの軸方向長さと直径が造成サンドパイルの長さや径に
比べて小さいため、それらの構成部材としている貫入装
置の重量が軽くでき、それに基いて、
(1)貫入装置を駆動する貫入機のパワーが小さくて済
む。(C) Effects of the Invention As described above, according to the method of the present invention, the axial length and diameter of the casing are smaller than the length and diameter of the created sandpile, so the weight of the penetration device that is a component of the casing is smaller. (1) The power of the penetrating machine that drives the penetrating device can be small.
(2)貫入装置吊上げ、吊下けのためのウィンチの動力
が節約できる。(2) The power of the winch for lifting and hanging the penetration device can be saved.
(3)貫入装置を吊上げ、案内するリーダーの構造を弱
化、軽量化することができる。(3) The structure of the leader that lifts and guides the penetration device can be weakened and lightened.
(4)そのため施工機の安定性を良好にし、かつ小型化
を可能とする。(4) Therefore, the stability of the construction machine is improved and it is possible to downsize the construction machine.
ケーシングを砂排出管として使用し、その軸方向長さを
施工改良長よりも短かくしであるため、砂等のケーシン
グ内への運搬・補給を、すべて、または殆んど下方位置
に対して行うことができ、砂等の運搬のための動力を小
さくするのに有利である。Since the casing is used as a sand discharge pipe and its axial length is shorter than the construction improvement length, all or most of the sand, etc., is transported and supplied to the lower position. This is advantageous in reducing the power required to transport sand, etc.
さらに本発明方法で貫入機を水中式としたり、貫入機が
動力伝達杆の上端でなく、横側に着脱可能としたりした
場合は、リーダーの上部が不用となり、施工機の安定性
に寄与する。Furthermore, if the method of the present invention is used to make the penetrating machine underwater, or if the penetrating machine is detachable from the side of the power transmission rod instead of the top end, the upper part of the leader becomes unnecessary, which contributes to the stability of the construction machine. .
第1(a)図(ri、本発明方法を実施する施工機の概
略側面図、第1 +bj図は別の型の施工機の貫入装置
の正面図、第2図は、本発明方法の工程を示すもので、
その(ai図はケーシング貫入完了時における一部を断
面にした貫入装置の正面図、そのfb1図は同様、サン
ドパイル造成終了後の貫入装置を含めた一部切断正面図
を示す。
1・・ケーシング、2・・・動力伝達杆、3・・・貫入
機、4・・・ガイドリーダー、5・・・緩衝器、6・・
・補給パイプ、7・・・排出パイプ、8・・・作業船、
WXL・・・水面。Figure 1(a) (ri) is a schematic side view of a construction machine that carries out the method of the present invention, Figure 1+bj is a front view of a penetration device of another type of construction machine, and Figure 2 shows the steps of the method of the present invention. It shows
The (ai figure) is a partially cutaway front view of the penetrating device when the casing penetration is completed, and the fb1 figure is a partially cutaway front view including the penetrating device after sandpile creation is completed.1. Casing, 2... Power transmission rod, 3... Penetrator, 4... Guide leader, 5... Buffer, 6...
・Supply pipe, 7... Discharge pipe, 8... Work boat,
WXL...Water surface.
Claims (5)
法において、地盤貫入用ケーシングを、上端面閉塞形で
あつて軸方向長さを地盤の改良深さに相当する長さより
も短かくすると共に、その上部位置に設けた貫入手段と
の間を動力伝達杆により連結し、前記ケーシング内部に
輸送流体と共に、これに混入した砂等を補給するパイプ
と、同ケーシング内で砂等を分離した前記流体を排出す
るためのパイプまたはケーシング内部圧力を調節する流
体供給用パイプを連通して成り、所定深さ迄貫入したケ
ーシングの引抜きにより、その下方地盤中に生じる空隙
部に、ケーシング内に補給された砂等を排出・充填する
ことを特徴とする改良長さよりも短かいケーシングでサ
ンドパイル等を施工する方法。(1) In a method of driving sand piles at a predetermined depth in soft ground, the ground penetration casing has a closed top end and an axial length shorter than the length corresponding to the soil improvement depth. At the same time, a power transmission rod connects the penetrating means provided at the upper part of the casing with a pipe for replenishing the transport fluid and sand mixed in the casing, and separating the sand, etc. within the casing. A pipe for discharging the fluid or a fluid supply pipe for adjusting the internal pressure of the casing is connected, and when the casing that has penetrated to a predetermined depth is pulled out, a void created in the ground below is filled with the inside of the casing. A method of constructing sand piles, etc. with a casing shorter than the improved length, characterized by discharging and filling the supplied sand, etc.
は地盤改良深さに水深を加えた長さからケーシングの軸
方向長さを差引いた長さよりも長くしたことより成る特
許請求の範囲第(1)項記載の、改良長さよりも短かい
ケーシングでサンドパイル等を施工する方法。(2) The length of the power transmission rod is at least longer than the soil improvement depth or the soil improvement depth plus water depth minus the axial length of the casing. A method of constructing sand piles, etc. using a casing shorter than the improved length as described in Scope (1).
ト等の砂類似粒状材の一つまたは、それらの混合物で、
これに対する輸送流体は圧縮空気を用いることより成る
特許請求の範囲第(1)、(2)項記載の、改良長さよ
りも短かいケーシングでサンドパイル等を施工する方法
。(3) Sand, etc. is one of sand-like granular materials such as sand, gravel, crushed stone, slag, lime, cement, etc., or a mixture thereof;
A method for constructing sand piles or the like with a casing shorter than the improved length, as set forth in claims (1) and (2), which comprises using compressed air as the transport fluid.
材の一つまたは、それらの混合物で、輸送流体は少量の
水を用いることより成る特許請求の範囲第(1)、(2
)項記載の、改良長さよりも短かいケーシングでサンド
パイル等を施工する方法。(4) The sand, etc. is one of sand-like granular materials such as sand, gravel, crushed stone, ore slag, or a mixture thereof, and the transport fluid is a small amount of water. (2
) method of constructing sand piles, etc. using a casing shorter than the improved length.
に、圧力調整手段を挿入し、前記手段を制御することに
よりケーシング内部の圧力を調節し、地盤土壌中に排出
される砂等により形成されるパイルの直径または密度を
制御することより成る特許請求の範囲第(1)〜(4)
項記載の、改良長さよりも短かいケーシングでサンドパ
イル等を施工する方法。(5) A pressure regulating means is inserted in the middle of the transportation fluid discharge pipe or the fluid supply pipe, and the pressure inside the casing is adjusted by controlling the means, and the casing is formed by sand etc. discharged into the ground soil. Claims (1) to (4) consist of controlling the diameter or density of the pile.
A method of constructing sand piles, etc. using a casing shorter than the improved length described in Section 1.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16996184A JPS6149018A (en) | 1984-08-16 | 1984-08-16 | Construction of sand pile by casing shorten than improved length |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16996184A JPS6149018A (en) | 1984-08-16 | 1984-08-16 | Construction of sand pile by casing shorten than improved length |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPS6149018A true JPS6149018A (en) | 1986-03-10 |
Family
ID=15896035
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP16996184A Pending JPS6149018A (en) | 1984-08-16 | 1984-08-16 | Construction of sand pile by casing shorten than improved length |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6149018A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH07158044A (en) * | 1993-12-09 | 1995-06-20 | Seiwa Kiko Kk | Sand ground liquefaction preventing work method |
| KR100492512B1 (en) * | 2005-03-15 | 2005-06-02 | (주)초석건설 | Crusher-stone drain pile method, crusher-stone compaction pile method of, using the auto pressurize device |
-
1984
- 1984-08-16 JP JP16996184A patent/JPS6149018A/en active Pending
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH07158044A (en) * | 1993-12-09 | 1995-06-20 | Seiwa Kiko Kk | Sand ground liquefaction preventing work method |
| KR100492512B1 (en) * | 2005-03-15 | 2005-06-02 | (주)초석건설 | Crusher-stone drain pile method, crusher-stone compaction pile method of, using the auto pressurize device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| RU2369690C2 (en) | Device and method of making building bearing piles from one or successive layers formed in ground rock | |
| EP2929093B1 (en) | Soil densification system and method | |
| KR101358622B1 (en) | Apparatus for constructing stone column by adding vertical impact with a cycle and method for constructing stone column by the apparatus | |
| CN113356190A (en) | Pile forming method for cast-in-place pile in karst development area | |
| EP1183426B1 (en) | Process and device for producing a pile in the earth | |
| US9062431B2 (en) | Device and method for soil compaction and/or soil stabilization | |
| CN112359815A (en) | Dry-type vibroflotation gravel pile for soft foundation treatment and construction method thereof | |
| JPS6149018A (en) | Construction of sand pile by casing shorten than improved length | |
| CN209958333U (en) | Geosynthetic flexible constraint pile construction pile machine | |
| CN108005055A (en) | Cavitation dynamic compaction method and complete set of soft soil foundation explosion point cavitation | |
| CN100412272C (en) | Concrete transplanting steel bar cage pile forming technical method of long screw hole drilling and center pump pressure | |
| CN104131562A (en) | Pile-forming construction equipment for composite foundation piles | |
| EP4103785B1 (en) | Method for introducing a soil penetrating tool into a soil and underground construction device | |
| CN100552148C (en) | Apparatus and method for constructing buttresses from one or successive intervals formed in a soil matrix | |
| CN1142344C (en) | Grouting equipment and pile making process of pump-grouting concrete | |
| JP4137744B2 (en) | Pile material supply device for ground improvement | |
| JPH04363410A (en) | Vibration compaction work method | |
| JP2891663B2 (en) | Ground improvement equipment | |
| CN217782011U (en) | Grid wrapping type bagged CFG pile | |
| JP2511067B2 (en) | Underwater sand pile driving method | |
| JP2942106B2 (en) | Sand pile creation method and its equipment | |
| CN100412273C (en) | Concrete pile construction method | |
| JP2602051B2 (en) | Underwater sand pile construction method | |
| JPH0229811B2 (en) | ||
| RU2027826C1 (en) | Device for ramming loose mixture when installing pile |