JPS62121237A - Equipment foundation construction method - Google Patents

Equipment foundation construction method

Info

Publication number
JPS62121237A
JPS62121237A JP26169785A JP26169785A JPS62121237A JP S62121237 A JPS62121237 A JP S62121237A JP 26169785 A JP26169785 A JP 26169785A JP 26169785 A JP26169785 A JP 26169785A JP S62121237 A JPS62121237 A JP S62121237A
Authority
JP
Japan
Prior art keywords
foundation
floor
equipment
equipment foundation
blocks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP26169785A
Other languages
Japanese (ja)
Other versions
JPH0699939B2 (en
Inventor
Toshiyuki Takahashi
利幸 高橋
Tadahiko Nishina
仁科 忠彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP60261697A priority Critical patent/JPH0699939B2/en
Publication of JPS62121237A publication Critical patent/JPS62121237A/en
Publication of JPH0699939B2 publication Critical patent/JPH0699939B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PURPOSE:To shorten the term of construction, by casting floor concrete, after a foundation-setting trestle is set on the floor bottom section, reinforcements are arranged on the floor, and an apparatus foundation block is set on the trestle. CONSTITUTION:After a foundation-setting trestle 2 is set on a floor bottom section 1, reinforcements 3a, 3b are arranged on the floor. Then, after a prefabricated apparatus-foundation block 4 is set on the trestle 2, floor concrete 5 is cast.

Description

【発明の詳細な説明】 〔発明の利用分野〕 本発明は、機器基礎建設方法に係り、特にモータや発電
機のような回転機の土台、あるいは制御室のように床ピ
ット(凹み)を設けてその中にケーブルを布設配線する
盤上台などのコンクリート基礎建設方法に関する。
[Detailed Description of the Invention] [Field of Application of the Invention] The present invention relates to a method for constructing a foundation for equipment, and in particular, for the construction of a foundation for a rotating machine such as a motor or generator, or a floor pit (concavity) such as in a control room. This article relates to a method for constructing a concrete foundation, such as a board platform, in which cables are laid and routed.

〔発明の背景〕[Background of the invention]

原子力発電所の中央制御室は、近年、建屋容積縮小化、
プラント全体配置の適性化のために、従来の制御建屋内
に設置する方式から、原子炉建屋内に設置する方式に変
わりつつある。さらに、原子炉建屋内に設置する場合の
中央制御室は、適正配置の観点から、上階に設置される
ことになる。
In recent years, the central control room of a nuclear power plant has been reduced in size,
In order to optimize the overall layout of the plant, the conventional method of installing it inside the control building is being replaced by a method of installing it inside the reactor building. Furthermore, when installed in a reactor building, the central control room will be installed on the upper floor from the viewpoint of appropriate layout.

従来は、中央制御室の建設工事を原子炉建屋とは別に先
行してできたのに対し、建設工事は、通常、下階から始
めるので、中央胴#室が原子炉建屋内に設置される場合
、原子炉建屋の建設工事がある程度進捗してからでない
と、中央制御室関係の工事が開始できない。一方、据付
を完了した設備はテストに入るが、この時点で中央制御
室は完成していなければならない。すなわち、中央制御
室工事は、全体工事工程のクリティカルパスになってき
ている。
In the past, construction work for the central control room could be done separately from the reactor building, but construction work usually starts from the lower floor, so the central control room is installed inside the reactor building. In this case, construction work related to the central control room cannot begin until the construction work of the reactor building has progressed to a certain extent. Meanwhile, the equipment that has been installed will begin testing, but at this point the central control room must be completed. In other words, central control room construction has become a critical path in the overall construction process.

同様な理由により、中央制御室から現場機器までのケー
ブル工事もクリティカルパスになってきているが、これ
に対しては、例えば、特開技報81−3228号にある
ように、集合端子盤を設置し、中央制御室内の配線を現
場機器と集合端子盤間のケーブル工事から分離して、後
者の先行工事を可能にしている。
For similar reasons, cable construction from the central control room to field equipment is also becoming a critical path. The wiring inside the central control room is separated from the cable work between field equipment and the collective terminal board, making it possible to carry out advance work on the latter.

一方、集合端子盤と中央制御室制御盤間の配線について
は、第6図に示すように、盤11の基礎ブロック1によ
って床ピツトを形成し、この中にケーブルトレイ9を設
け、プレハブケーブル12を盤下部から立ち上げ、ケー
ブル布設を合理化している。
On the other hand, for wiring between the collective terminal board and the central control room control board, as shown in FIG. is launched from the bottom of the panel, streamlining cable installation.

こうした制御室の基礎工事に関しては、さらに例えば、
特開昭52−21592号にあるように、コンクリート
柱と工学鋼を組み合わせて行う方法がある。
Regarding the basic construction of the control room, for example,
As described in Japanese Patent Application Laid-open No. 52-21592, there is a method of combining concrete columns and engineering steel.

この方法では、盤の基礎となるコンクリート柱の設定は
、床コンクリート打設後しこ、一つ一つ見枠を組んでな
されていた。コンクリート柱は中央制御室全体で約10
0個にものぼるため、盤基礎の位置および高さの調整や
ケーブルトレイの布設を含め、中央制御室基礎工事が、
工程上のクリティカルパスになってきており、その工数
低減および工期短縮が重要な課題となってきている。
In this method, the concrete pillars that serve as the foundation for the board were set one by one after the floor concrete was poured, and the frames were constructed one by one. There are approximately 10 concrete pillars in the central control room.
As the number of pieces reached 0, the foundation work for the central control room, including adjusting the position and height of the panel foundation and laying the cable tray, was
It has become a critical path in the process, and reducing the number of man-hours and construction period has become an important issue.

また、モータや発電機等の回転機器の基礎土台は、耐震
動性および強度の点から、コンクリート土台が用いられ
ているが、従来の床コンクリート打設後に土台を作成す
る方法では、基礎ブロックを−っ−っ形成するため手間
がかかり、養生と仕上げを含め、コンクリート床引き渡
し後、基礎完成まで約2ケ月を要し、機器に接続される
配管の工事を遅らせる原因になっている。
In addition, concrete foundations are used as foundations for rotating equipment such as motors and generators due to their earthquake resistance and strength, but the conventional method of creating foundations after pouring concrete for the floor does not require foundation blocks. - It takes time to form the concrete floor, and it takes about two months to complete the foundation after handing over the concrete floor, including curing and finishing, which causes delays in the construction of the piping connected to the equipment.

〔発明の目的〕[Purpose of the invention]

本発明の目的は、機器コンクリート基礎工事を短期間で
完了できる機器基礎建設方法を提供することである。
An object of the present invention is to provide an equipment foundation construction method that allows equipment concrete foundation work to be completed in a short period of time.

〔発明の概要〕[Summary of the invention]

本発明の特徴は、現場工事と並行して機器基礎ブロック
を作成しておき、床コンクリート打設前に、設定用架台
にこの基礎ブロックを載せて位置設定を行い、しかるの
ち、床コンクリートを打つ点にある。このように、基礎
ブロックを前もって作成しておくと、現場でのコンクリ
ート打設が1回で済み、基礎工事の工期が大幅に短縮さ
れる。
A feature of the present invention is that equipment foundation blocks are created in parallel with on-site construction, and before the floor concrete is poured, the foundation blocks are placed on a setting frame to set the position, and then the floor concrete is poured. At the point. By preparing the foundation blocks in advance in this way, only one concrete pouring is required on site, significantly shortening the foundation construction period.

〔発明の実施例〕[Embodiments of the invention]

以下、実施例に基づき、本発明の詳細な説明する6 第1図は1本発明による機器基礎建設方法の一実施例を
示すフロー図である。
Hereinafter, the present invention will be described in detail based on examples.6 FIG. 1 is a flowchart showing an embodiment of the equipment foundation construction method according to the present invention.

ステップAにおいて、床下部1が建設された時点で、基
礎設定用架台あるいは枠2を搬入し、設置する。本架台
は、機器基礎の高さおよび位置を設定するためのもので
ある。
In step A, when the lower part of the floor 1 is constructed, a foundation setting frame or frame 2 is brought in and installed. This frame is used to set the height and position of the equipment foundation.

ステップBにおいては、床配筋3a、3bを施行する。In step B, floor reinforcements 3a and 3b are installed.

ステップCでは、予め作成した機器基礎ブロック4を搬
入し、設定用架台上に設置する。
In step C, the equipment foundation block 4 prepared in advance is carried in and installed on a setting pedestal.

最後にステップDにおいて、床コンクリートを打設し、
基礎工事を完了させる。
Finally, in step D, the floor concrete is poured,
Complete foundation work.

なお、ステップBとCとを逆にしても、本発明の利点が
変わらないのは、明らかである。
It is clear that even if steps B and C are reversed, the advantages of the present invention will not change.

第2図は機器基礎ブロック4の一例を示すものである。FIG. 2 shows an example of the equipment basic block 4. As shown in FIG.

第2図(a)はブロック外観図、(b)はブロックの断
面図である。基礎ブロック4は。
FIG. 2(a) is an external view of the block, and FIG. 2(b) is a sectional view of the block. Basic block 4 is.

配筋22が下部にはみ出ており、床コンクリート5と結
合する構造となっている。ここでは、直線状のものを例
示しであるが、アングル状であってもよいことはもちろ
んである。また、機器を固定するためのボルト21が埋
め込まれており、その一部がブロック上部につき出てい
る。図示しない機器とブロック4とはボルト21−によ
り結合される。
The reinforcing bars 22 protrude from the bottom and are connected to the floor concrete 5. Here, a linear shape is shown as an example, but it goes without saying that an angular shape may also be used. Further, bolts 21 for fixing the equipment are embedded, and a portion of the bolts protrudes from the top of the block. A device (not shown) and the block 4 are connected by bolts 21-.

第3図は機器基礎ブロック4の他の例である。FIG. 3 shows another example of the equipment basic block 4.

第3図において、ブロック上部には埋込金物31があり
、機器とは溶接により結合される。
In FIG. 3, there is an embedded metal fitting 31 in the upper part of the block, which is connected to the equipment by welding.

第1図の例は、1つの基礎ブロック4について示したも
のであるが、基礎が複数である場合は、複数の基礎ブロ
ック4を一体化して搬入・設定することもできる。第4
図は、一体化した基礎ブロックの外観を示す一例である
9図において、基礎ブロック4a、4b、4c、4d、
4e、4fは、埋込金物31a、31b、31c、31
d。
The example in FIG. 1 is shown for one foundation block 4, but if there are multiple foundations, the multiple foundation blocks 4 may be brought in and set up as one. Fourth
In Figure 9, which is an example of the appearance of integrated foundation blocks, foundation blocks 4a, 4b, 4c, 4d,
4e, 4f are embedded metal parts 31a, 31b, 31c, 31
d.

3Le、31fにおいてビーム41と溶接で結合されて
いる。
3Le and 31f are connected to the beam 41 by welding.

基礎ブロック搬入時には、これらを一体化したままクレ
ーン42で吊り下げで搬入し、設定用架台2の七に設定
する。この場合には、床コンクリート打設後ビーム41
を取りはずし、基礎工事を完成させる。
When carrying in the foundation blocks, they are carried in by being suspended by a crane 42 while being integrated, and set at the 7th position of the setting frame 2. In this case, after placing the floor concrete, the beam 41
Removed and completed the foundation work.

このようにすると、基礎ブロック間の寸法を高精度に維
持できる。第4図の例は、6個のブロックを一体化して
いるが、ブロックの数はいくつであっても、同様に搬入
し、設定できる。
In this way, the dimensions between the foundation blocks can be maintained with high precision. In the example shown in FIG. 4, six blocks are integrated, but any number of blocks can be brought in and set in the same way.

なお、第3図の埋込金物を備えた基礎ブロックではなく
、第2図のボルトを用いる基礎ブロックについて、第4
図のようにビームで一体化し、搬入・設定する場合、ボ
ッL l−21をビームへの取り付けにも兼用できるこ
とはいうまでもない。
In addition, regarding the foundation block that uses the bolts shown in Figure 2 instead of the foundation block with the embedded metal fittings shown in Figure 3,
It goes without saying that when the parts are integrated with a beam as shown in the figure and transported and set up, the box L1-21 can also be used for attachment to the beam.

以上は、設定用架台設定後、基礎ブロックを搬入し設定
する例であるが、第5図のように、基礎ブロック4a、
4bを設定用架台2と一体化させておき、クレーン42
で搬入し設定する方法もある。この場合には、搬入も一
回で済む利点がある。
The above is an example of carrying in and setting the foundation block after setting the setting frame, but as shown in FIG. 5, the foundation block 4a,
4b is integrated with the setting frame 2, and the crane 42
There is also a way to import and configure it. In this case, there is an advantage that the product only needs to be transported once.

〔発明の効果〕〔Effect of the invention〕

本発明の方法によれば、次の効果が得られる。 According to the method of the present invention, the following effects can be obtained.

1、機器基礎建設現場における機器基礎土台の配筋施工
、型枠施工および成形や表面仕上げ等の作業が不要とな
り、これらに替わる基礎ブロック作成を現場建設工事と
並行して行うことが可能となるため、現地作成工数を大
幅に低減し。
1. Work such as reinforcement construction, formwork construction, molding, and surface finishing of the equipment foundation foundation at the equipment foundation construction site is no longer necessary, and it becomes possible to create alternative foundation blocks in parallel with the on-site construction work. This greatly reduces the number of on-site production steps.

工期を短縮できる。特に、ブロック位置およびその高さ
の設定および調整は、従来量も工数を必要としていた部
分であるが、本発明の基礎ブロック一体化設定方法によ
れば、建設現場でのこうした調整作業を大幅に減らすこ
とができンる。
Construction period can be shortened. In particular, setting and adjusting the block position and its height is a part that conventionally requires a lot of man-hours, but according to the foundation block integrated setting method of the present invention, such adjustment work at the construction site can be greatly reduced. It can be reduced.

2、基礎ブロックやトレイブロックおよび基礎設定用架
台の作成あるいはそれらの一体化製作は、工場で実施で
きるため、加工や溶接が容易になり、これらの製作コス
ト低減および品質向上が可能となる。特に、その数が多
い基礎ブロックは標準化することにより、入社生産が可
能となり、大幅なコストダウンが図れる。
2. Since the foundation blocks, tray blocks, and foundation setting frames or their integrated manufacturing can be carried out in a factory, processing and welding are facilitated, making it possible to reduce manufacturing costs and improve quality. In particular, by standardizing the basic blocks, which have a large number of them, on-site production becomes possible, resulting in significant cost reductions.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明による機器基礎建設方法の施工手順を示
すフロー図、第2図は機器を基礎土台にボルトで固定す
る方式のプレキャスト基礎ブロックを示す図、第3図は
同じく埋込金物で固定する方式の基礎ブロックを示す図
、第4図は複数のプレキャスト基礎ブロックをビームで
一体化し、クレーンで吊り下げて設定用架台に載せる作
業状況を示す図、第5図は基礎ブロックと設定用架台と
を一体化し、クレーンで搬入する作業状況を示す図、第
6図は集合端子盤周りの配線の様子を示す図である。 1・・・床下部、2・・・基礎設定用架台、3・・・床
配筋、4・・・プレキャスト基礎ブロック、5・・・床
コンクリート、9・・・ケーブルトレイ、11・・・集
合端子盤、12・・・プレハブケーブル、21・・・機
器固定用ボルト、22・・・基礎ブロック配筋、31・
・・埋込金物、41・・・ビーム、42・・・クレーン
Fig. 1 is a flowchart showing the construction procedure of the equipment foundation construction method according to the present invention, Fig. 2 is a diagram showing a precast foundation block in which equipment is fixed to the foundation foundation with bolts, and Fig. 3 is a diagram showing a precast foundation block in which equipment is fixed to the foundation foundation with bolts. Figure 4 is a diagram showing a foundation block that is fixed in place. Figure 4 is a diagram showing how multiple precast foundation blocks are integrated with a beam, suspended by a crane, and placed on a setting frame. Figure 5 is a diagram showing a foundation block and a setting frame. FIG. 6 is a diagram showing the state of the wiring around the collective terminal board. 1... Lower floor, 2... Frame for foundation setting, 3... Floor reinforcement, 4... Precast foundation block, 5... Floor concrete, 9... Cable tray, 11... Collective terminal board, 12... Prefabricated cable, 21... Equipment fixing bolt, 22... Foundation block reinforcement, 31.
...embedded hardware, 41...beam, 42...crane.

Claims (1)

【特許請求の範囲】 1、機器間配線等のための床ピツトを有する機器基礎を
建設する方法において A、床下部の上に基礎設定用架台を配置する段階と、 B、床配筋をする段階と、 C、予め作成した機器基礎ブロツクを前記架台上に設定
する段階と、 D、床コンクリートを打設する段階と、 からなることを特徴とする機器基礎建設方法。 2、特許請求の範囲第1項において、機器基礎ブロツク
が複数ある場合に、いくつかの機器基礎ブロツクと設定
用架台とを予め一体化し、上記A段階とC段階とを同時
に行うことを特徴とする機器基礎建設方法。 3、特許請求の範囲第1項において、機器基礎ブロツク
が複数ある場合に、いくつかのブロツクをビームにより
予め一体化し、同時に搬入・設定することを特徴とする
機器基礎建設方法。
[Scope of Claims] 1. A method for constructing an equipment foundation having a floor pit for inter-equipment wiring, etc., including the steps of A. arranging a foundation setting frame on the lower part of the floor, and B. arranging floor reinforcement. A method for constructing an equipment foundation, comprising the steps of: (C) setting a pre-prepared equipment foundation block on the pedestal; and (D) pouring floor concrete. 2. Claim 1 is characterized in that when there are a plurality of equipment foundation blocks, some of the equipment foundation blocks and the setting frame are integrated in advance, and the above steps A and C are performed simultaneously. equipment foundation construction method. 3. A method for constructing an equipment foundation according to claim 1, characterized in that, when there are a plurality of equipment foundation blocks, several of the blocks are integrated in advance by a beam, and are carried in and set at the same time.
JP60261697A 1985-11-21 1985-11-21 Equipment foundation construction method Expired - Lifetime JPH0699939B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60261697A JPH0699939B2 (en) 1985-11-21 1985-11-21 Equipment foundation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60261697A JPH0699939B2 (en) 1985-11-21 1985-11-21 Equipment foundation construction method

Publications (2)

Publication Number Publication Date
JPS62121237A true JPS62121237A (en) 1987-06-02
JPH0699939B2 JPH0699939B2 (en) 1994-12-12

Family

ID=17365454

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60261697A Expired - Lifetime JPH0699939B2 (en) 1985-11-21 1985-11-21 Equipment foundation construction method

Country Status (1)

Country Link
JP (1) JPH0699939B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014005621A (en) * 2012-06-22 2014-01-16 Kajima Corp Multifunctional rooftop foundation
JP2016199957A (en) * 2015-04-14 2016-12-01 戸田建設株式会社 Leading floor method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6268928A (en) * 1985-09-20 1987-03-30 Kajima Corp Construction for foundation for setting machine

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6268928A (en) * 1985-09-20 1987-03-30 Kajima Corp Construction for foundation for setting machine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014005621A (en) * 2012-06-22 2014-01-16 Kajima Corp Multifunctional rooftop foundation
JP2016199957A (en) * 2015-04-14 2016-12-01 戸田建設株式会社 Leading floor method

Also Published As

Publication number Publication date
JPH0699939B2 (en) 1994-12-12

Similar Documents

Publication Publication Date Title
JP5523179B2 (en) Building construction method and room module
KR20040016371A (en) Construction of high-rise building with large modular units
CN115270278B (en) BIM application and formwork construction technology of suspended chamfered terrace concrete structure
JPS62121237A (en) Equipment foundation construction method
JPH10311049A (en) Work executing method for turbine frame of steel plate concrete and locating jig for burying metal piece
JP3015415B2 (en) Nuclear power plant construction method
CN116876829A (en) A formwork system for modified polystyrene particle peripheral wall panels and its construction method
JPS6335931A (en) Construction of building of atomic power plant
JPH0996036A (en) Structure of wall material or floor material for construction
CN220908811U (en) Outer wall dismantling-free template system
JP2025024769A (en) Gate manufacturing method
JPH0665985A (en) Architectural wall material and manufacture thereof
JPH108725A (en) Constructing method for building frame
JP2000192664A (en) Method for construction of building
JPS6043547A (en) Mold frame and reinforcement iron integral assembling and constructing method
JPH02140339A (en) Structure of composite pc member
JPH04191698A (en) Installing method turbine foundation mold form and condenser
JPH01142150A (en) Flat slab construction method
JPS6113183A (en) Method of constructing mat for housing of nuclear reactor
JPH11124902A (en) Constructing of building using pc member
JPS6245837A (en) Construction work for foundation of turbine generator
JPS62182322A (en) Setting of apparatus
JPH11229408A (en) Installation method of apparatus
JPS63251546A (en) How to build concrete structures
JPS6329057B2 (en)