JPS626049B2 - - Google Patents
Info
- Publication number
- JPS626049B2 JPS626049B2 JP52160632A JP16063277A JPS626049B2 JP S626049 B2 JPS626049 B2 JP S626049B2 JP 52160632 A JP52160632 A JP 52160632A JP 16063277 A JP16063277 A JP 16063277A JP S626049 B2 JPS626049 B2 JP S626049B2
- Authority
- JP
- Japan
- Prior art keywords
- suspension
- earth
- steel sheet
- auger
- hardening agent
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Description
【発明の詳細な説明】
本発明は砂礫地盤における土留壁工法に関する
ものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an earth retaining wall construction method on sandy and gravel ground.
一般に市街地に地下鉄等の地下構築物を建設す
るに際しては、掘削に先立つて、鋼矢板、H型鋼
等で土留壁を構築し、掘削に伴う周辺地盤の崩壊
や沈下を防止しなければならないが、鋼矢板やH
型鋼を通常の落錘打込法や振動打込法で打込むと
騒音や振動が激しく、近隣家屋に被害を及ぼす。
このため予めオーガーで地中に穿孔してH型鋼等
を建て込んだり、或いは軟弱地盤ではオーガーで
掘削した孔壁の崩壊を防止するためにオーガーロ
ツドを引抜くに際して、ロツド先端からセメント
ミルクやベントナイト液或いは両者の混合液を注
入し、オーガーロツドの引抜き完了后直ちにH鋼
を建て込む方法やコンクリートの地下連続壁を設
けたりする方法が行われている。 Generally, when constructing underground structures such as subways in urban areas, it is necessary to construct earth retaining walls using steel sheet piles, H-shaped steel, etc. prior to excavation to prevent the surrounding ground from collapsing or subsidence due to excavation. Sheet piles and H
Driving shaped steel using the normal falling weight driving method or vibration driving method produces intense noise and vibration, which can cause damage to neighboring houses.
For this reason, it is necessary to drill into the ground with an auger in advance and erect H-beams, etc., or in soft ground, to prevent the wall of the hole excavated with an auger from collapsing, when pulling out the auger rod, cement milk or bentonite liquid is poured from the tip of the rod. Alternatively, a method is used in which a mixture of the two is injected and H steel is erected immediately after the auger rod has been pulled out, or a concrete underground continuous wall is installed.
然しながら、オーガーロツドの先端からセメン
トミルクやベントナイトを注入するのはH型鋼を
親杭とするいわゆる横矢板土留壁のように一定間
隔にH型鋼を建て込む場合は穿孔→注入→建込→
穿孔という順序で作業は進められるが、鋼矢板の
ように連続して建込まなければならないものに対
しては先行して穿孔注入を終つた個所の硬化剤が
凝結してある程度の強度を発揮しなければ隣接し
て後から穿孔するオーガーロツドが先行掘削孔側
に滑り垂直な施工が困難となる。地盤が砂礫等の
固い土質の場合は特にその危険度が大きい。さら
に、地盤中に大きな礫を含んでいる場合や地下水
が伏流水となつて流れている場合にはコンクリー
トの地下連続壁の施工も非常に困難であり、往々
にして施工不可能の場合が多いので、このような
地盤に止水性を有する土留壁を施工することは殆
んど不可能か或いは経済的に非常に高価なものと
なつている。例えば第1図に示す如くアースオー
ガーによる穿孔と鋼矢板の建込みを連続して行う
場合、まず孔を順次穿孔する。この場合図中1,
2,3,4はアースオーガーによつて穿孔した
後、硬化剤を注入した孔を示し6,7,8は上記
1,2,3までの孔に建込みを終了した鋼矢板を
示す。5は次に穿孔する孔の位置を示したもので
あり、9は次いで建込まれる鋼矢板を示す。 However, injecting cement milk or bentonite from the tip of the auger rod requires drilling → pouring → erection → when erecting H-shaped steel at regular intervals like a so-called horizontal sheet retaining wall with H-shaped steel as the parent pile.
The work proceeds in the order of drilling, but for items such as steel sheet piles that must be erected continuously, the hardening agent that has been poured into the holes will solidify in advance and provide a certain level of strength. If not, the adjacent auger rod that will be drilled later will slide toward the preceding drilling hole, making it difficult to perform vertical construction. This is particularly dangerous if the ground is hard, such as sand and gravel. Furthermore, in cases where the ground contains large gravel or where groundwater flows as underground water, it is extremely difficult to construct an underground concrete wall, and in many cases it is impossible. Therefore, it is almost impossible or economically very expensive to construct a water-stopping earth retaining wall on such ground. For example, when drilling with an earth auger and erecting steel sheet piles are performed consecutively as shown in FIG. 1, the holes are first drilled in sequence. In this case, 1 in the figure,
Reference numerals 2, 3, and 4 indicate holes into which a hardening agent was injected after drilling with an earth auger, and reference numerals 6, 7, and 8 indicate steel sheet piles that have been filled in the holes 1, 2, and 3 mentioned above. 5 indicates the position of the next hole to be drilled, and 9 indicates the steel sheet pile to be built next.
鋼矢板は互にセクシヨン部分10によつてジヨ
イントしなければならないので鋼矢板9を建込む
前に隣接した次の孔5の穿孔を終了していなけれ
ば、鋼矢板9の建込後においてはオーガーロツド
が鋼矢板9のセクヨン部10′に接触するので、
5の穿孔ができない。 Since the steel sheet piles must be jointed to each other by the section portions 10, if the drilling of the next adjacent hole 5 is not completed before the steel sheet pile 9 is erected, the auger rods will not be formed after the steel sheet pile 9 is erected. comes into contact with the section section 10' of the steel sheet pile 9, so
5 cannot be drilled.
このような鋼矢板の建込みには二つ以上のオー
カー孔を先行して穿孔しなければならないことが
分るが、硬化剤としてはセメントミルクを用い連
続して工事を施工する場合は先に穿孔した孔4の
硬化剤がまだ固結しない内に次の孔5を穿孔する
とオーガーロツドは周辺地盤より軟かい孔4の側
に滑り、正しい位置に孔5の穿孔を行うことがで
きなくなり、特に基礎地盤が砂礫質等の固い場合
には特にその傾向が大きい。 It is understood that two or more ocher holes must be drilled in advance when constructing such steel sheet piles, but if cement milk is used as a hardening agent and construction is to be carried out consecutively, it is necessary to drill two or more ocher holes first. If the next hole 5 is drilled before the hardening agent in the drilled hole 4 has yet solidified, the auger rod will slide to the side of the hole 4 which is softer than the surrounding ground, making it impossible to drill the hole 5 in the correct position. This tendency is particularly strong when the foundation ground is hard, such as sandy gravel.
このため連続して何本かの鋼矢板を1日のうち
に建込むためには第2図の如く1本置きにオーガ
ーで複数個の孔の穿孔を行い、セメント注入を行
いセメントの硬化をまつてその翌日に中間孔の穿
孔及び注入を行い、そのあとから鋼矢板を順次建
込む方方法が行われる。 Therefore, in order to erect several steel sheet piles in a row in one day, as shown in Figure 2, it is necessary to drill multiple holes with an auger every other sheet, inject cement, and allow the cement to harden. The next day, the intermediate holes are drilled and poured, and then the steel sheet piles are erected one after another.
然しながらこのような従来の方法では穿孔及び
注入と矢板の建込み作業との順序関係及び時間的
な制約が非常に大きいため、作業の施工性が非常
に悪くなる。即ち、セメントミルク或いはベント
ナイトとの混合懸濁液は時間の経過と共に強度が
発現するので、穿孔、注入後、雨天その他の作業
上の理由で後続の矢板建込みが数日遅れるとセメ
ントミルクの強度が大きくなり矢板の建込みが不
可能となるか振動打込み或いは強力なジヤツキに
よる建込みが必要となる。 However, in such a conventional method, the order of drilling and pouring and the erection of sheet piles and the time constraints are very large, so the workability of the work is very poor. In other words, the strength of cement milk or a mixed suspension with bentonite develops over time, so if the subsequent sheet pile erection is delayed for several days after drilling, pouring, rain or other operational reasons, the strength of cement milk will deteriorate. becomes large, making it impossible to erect the sheet pile, or erecting it by vibration driving or strong jacking becomes necessary.
さらに又、セメントミルクの強度が周辺地盤の
強度より大きくなると、鋼矢板は建込みに際して
逆に周囲の地盤の方に流れ易くなり、オーガー掘
削による矢板建込みと云う本来の目的を失うこと
になる。 Furthermore, if the strength of the cement milk becomes greater than the strength of the surrounding ground, the steel sheet piles will tend to flow toward the surrounding ground during erection, and the original purpose of building sheet piles by auger excavation will be lost. .
即ち本発明は予めアースオーガー等にて地中に
穿孔して穿孔個所の地盤を緩めると共に、オーガ
ーロツドを引抜きながらロツド先端から硬化剤懸
濁液を孔中に注入して土を硬化剤懸濁液と置換
え、その中に鋼矢板を挿入してこれを繰り返して
連続させ地中に土留壁を形成させる土留工法にお
いて、硬化剤懸濁液として凝結遅延剤を適量添加
した半水石膏と精製粘土の懸濁液、或いはこれに
ポルトランドセメントを適量混入した懸濁液を用
いることにより、硬化剤の凝結開始時間を任意に
設定し、しかも所望の初期強度に達した後の経時
的強度増進を非常に緩慢なものにすることによつ
て、爾後の鋼矢板の建込み作業及びオーガー掘削
の施工性を高めると共に騒音、振動を伴わないよ
うになしたのである。 That is, in the present invention, a ground auger or the like is used to drill into the ground in advance to loosen the ground at the location of the hole, and while the auger rod is being pulled out, a hardening agent suspension is injected into the hole from the tip of the rod to transform the soil into a hardening agent suspension. In the earth retaining method, in which a steel sheet pile is inserted into the pile and this is repeated continuously to form an earth retaining wall underground, a mixture of hemihydrate gypsum and purified clay with an appropriate amount of setting retardant added as a hardening agent suspension is used. By using a suspension or a suspension in which an appropriate amount of Portland cement is mixed, it is possible to arbitrarily set the setting start time of the hardening agent and to greatly increase the strength over time after the desired initial strength is reached. By making it slow, it was possible to improve the workability of subsequent steel sheet pile erection work and auger excavation, and to avoid noise and vibration.
本発明において「オーガーロツドを引抜きなが
らロツドの先端から硬化剤懸濁液を注入し、その
中え鋼矢板を挿入する工法」は、PIP工法として
公知であり、止水壁造成工法(特開昭51−131117
号)が提案されている。本発明は硬化剤懸濁液と
して凝結遅延剤、半水石膏、天然又は精製粘土の
混合物、或いはこれにポルトランドセメントの混
入した懸濁液を用いることを新しい1つの要件と
する。 In the present invention, the ``method of injecting a hardening agent suspension from the tip of the rod while pulling out the auger rod, and inserting a steel sheet pile inside'' is known as the PIP method, and is a water-stop wall construction method (Japanese Patent Laid-Open No. 51 −131117
No.) has been proposed. A new requirement of the present invention is the use of a set retarder, gypsum hemihydrate, a mixture of natural or purified clay, or a suspension thereof mixed with Portland cement, as the hardening agent suspension.
次に石こう懸濁液を用いた止水壁成工法(特開
昭52−152610号)も公知である。この先行技術は
石こう懸濁液にセメントおよび/またはベントナ
イトを添加した懸濁液を用いるもので、ベントナ
イトは高価であるから工費が極めて高くなるが、
本発明では取扱いが容易で安価な粘土を用いるこ
とにより、工費の節約をはかつたものである。さ
らに本発明は先行技術にない凝結遅延剤を懸濁液
に加えており、これにより数日を経過した後でも
鋼矢板を建込むことができるので、鋼矢板の建込
み作業が施工しやすくなる。 Next, a water stop wall construction method using a gypsum suspension (Japanese Unexamined Patent Publication No. 152610/1982) is also known. This prior art uses a suspension made by adding cement and/or bentonite to a gypsum suspension, and since bentonite is expensive, the construction cost is extremely high.
The present invention aims to save construction costs by using clay that is easy to handle and inexpensive. Furthermore, the present invention adds a setting retardant to the suspension, which is not found in the prior art, and this makes it possible to erect steel sheet piles even after several days have passed, making the work of erecting steel sheet piles easier. .
本発明は上述の欠点をなくし、硬化剤懸濁液の
凝結時間を任意に設定して所要強度を短時間に発
現させ、オーガーによる穿孔を連続して施工でき
るようにして穿孔、注入の作業と鋼矢板建込み作
業を相互に併行して進め得るようにすると共に硬
化剤懸濁液の所要強度が短時間に発現した後は、
その後の時間の経過による強度の増進を非常に緩
慢な状態にして、鋼矢板建込が数日或いは1週間
位遅れても建込み作業には何等支障を来たさない
よう硬化剤の選定及び配合を行い、市街地におけ
る土留作業を砂礫質の地盤でも無騒音、無振動に
施工することを可能にしたものである。 The present invention eliminates the above-mentioned drawbacks, sets the coagulation time of the hardener suspension arbitrarily to develop the required strength in a short time, and enables continuous drilling with an auger, thereby reducing the work of drilling and pouring. After the steel sheet pile erection work can proceed in parallel with each other and the required strength of the hardener suspension is achieved in a short time,
The hardening agent was selected so that the strength would increase very slowly over time, so that even if the steel sheet pile erection was delayed by several days or a week, the erection work would not be affected in any way. This combination has made it possible to carry out earth retaining work in urban areas without noise or vibration, even on sandy and gravelly ground.
なおベントナイトは山形県、群馬県等の鉱山で
採掘し、これを粉砕して袋詰めにしたもので極め
て高価である。このベントナイトは膨潤性、増粘
性、液性限界が優れており、ノーケーシング工法
で溝を掘削する場合には不可欠であるが、その膨
潤性のため本発明の土留壁工法では作業性が良く
ない。これに対し本発明は作業場所によつては直
ぐ近くで入手できる天然粘土を用い、作業場所が
市街地又はその周縁のため天然粘土を入手しにく
い場合は天然粘土を篩に通して袋詰めした精製粘
土を用いる。これらの天然又は精製粘土は極めて
安価であり、しかも粘土を石膏、セメント等と混
合した硬化剤懸濁液は初期強度の発現が早く、そ
の後の強度増進が緩慢である。従つてベントナイ
トに比較して作業性が著るしく優れている。 Note that bentonite is mined in mines in Yamagata Prefecture, Gunma Prefecture, etc., and is crushed and packed into bags, which is extremely expensive. This bentonite has excellent swelling properties, thickening properties, and liquid property limits, and is essential when excavating trenches using the no-casing construction method.However, due to its swelling properties, workability is not good in the earth retaining wall construction method of the present invention. . In contrast, the present invention uses natural clay that is available nearby depending on the work location, and if the work location is in an urban area or its surrounding area and it is difficult to obtain natural clay, the natural clay is purified by passing it through a sieve and packing it into bags. Use clay. These natural or purified clays are extremely inexpensive, and hardener suspensions made by mixing clay with gypsum, cement, etc. develop initial strength quickly, but the subsequent increase in strength is slow. Therefore, it has significantly better workability than bentonite.
以下本発明を第1図の実施例に基づいて説明す
れば、まず所望地盤にアースオーガー工法にて所
望の孔1を穿孔する。目標深度まで穿孔した後ア
ースオーガーロツドを引き抜くがこの場合アース
オーガーロツドの先端より凝結遅延剤を適量添加
した半水石膏と天然又は精製粘土の懸濁液或いは
これにポルトランドセメントを適量混入した懸濁
液を注入する。即ち該懸濁液を注入しつつオーガ
ーロツドを引き抜いて穿孔内の土砂を硬化剤懸濁
液と置き換え、そして次にこの穿孔内に注入した
懸濁液が所望の初期強度に達した時点で先にあけ
た孔1と隣接した次の孔2を同様にしてアースオ
ーガーにて穿孔しオーガーロツドの引抜時硬化剤
懸濁液を注入する。さらに孔2の硬化剤の硬化後
第三番目の孔3を穿孔し、その中に懸濁液を注入
する。このようにして順次穿孔すると共に少くと
も第二番目の孔の穿孔及び注入が終了すれば第一
番目の孔1の硬化物内に所望の鋼矢板6を建て込
む。又第三番目の孔3の穿孔及び注入を終われば
次に第二番目の孔2の硬化物内に鋼矢板7を建て
込む。このようにして穿孔及び注入の終つた一つ
手前の孔に鋼矢板を建て込み連続して土留壁を構
築していく。この場合穿孔と懸濁液の注入は複数
個連続して行いその後に鋼矢板を建て込むことも
可能である。 The present invention will be described below based on the embodiment shown in FIG. 1. First, a desired hole 1 is bored in a desired ground using the earth auger method. After drilling to the target depth, the earth auger rod is pulled out. In this case, a suspension of hemihydrate gypsum and natural or purified clay, to which an appropriate amount of setting retardant has been added, or an appropriate amount of Portland cement is mixed in from the tip of the earth auger rod. Inject the suspension. That is, the auger rod is withdrawn while the suspension is being injected to replace the soil in the borehole with a hardener suspension, and then, when the suspension injected into the borehole has reached the desired initial strength, The next hole 2 adjacent to the drilled hole 1 is similarly drilled with an earth auger, and the hardening agent suspension is injected when the auger rod is pulled out. Furthermore, after the curing agent in hole 2 has hardened, a third hole 3 is bored and the suspension is injected into it. In this way, the holes are drilled one after another, and when at least the second hole has been drilled and the injection is completed, the desired steel sheet pile 6 is built into the hardened material of the first hole 1. Further, after the drilling and injection of the third hole 3 is completed, the steel sheet pile 7 is then built into the hardened material of the second hole 2. In this way, a steel sheet pile is placed in the hole one hole before the completion of drilling and injection, and an earth retaining wall is constructed continuously. In this case, it is also possible to perform the drilling and injection of the suspension several times in succession and then erect the steel sheet piles.
第3図はセメント、半水石膏(以下石膏と称す
る)、水、粘土の組み合せとその硬化物の一軸圧
縮強度(以下単に強度という)を比較したもので
あり、これをグラフを以て示したのが第4図であ
る。粘土には粒径の微細なベントナイトと粒径の
粗いニユー粘土およびみの粘土(以下精製粘土と
総称する)を比較した。石膏とセメントを混合し
た懸濁液の場合第4図に示すように短時間で硬化
が始まるため、施工に当り混練終了後より注入完
了までの時間を見込んで硬化を遅延させる必要が
ある。 Figure 3 compares the unconfined compressive strength (hereinafter simply referred to as strength) of a combination of cement, hemihydrate gypsum (hereinafter referred to as gypsum), water, and clay and the cured product, and this is shown graphically. FIG. We compared bentonite, which has a fine particle size, and new clay and mino clay, which have coarse particle sizes (hereinafter collectively referred to as refined clay). In the case of a suspension of mixed gypsum and cement, hardening begins in a short period of time as shown in Figure 4, so it is necessary to delay the hardening in consideration of the time from the end of kneading to the completion of injection during construction.
第3図のCに示した懸濁液に凝結遅延剤の添加
量を変化させることにより、第5図に示すように
硬化の開始を調節することが可能となる。 By varying the amount of setting retarder added to the suspension shown in FIG. 3C, it is possible to adjust the onset of curing as shown in FIG.
通常穿孔内に注入する懸濁液は第5図のb又は
Cが適当であるがさらに強度を必要とするか又は
長期強度が不要の場合など目標強度に合わせて第
3図E又はFの如く配合を若干変更し、これに石
膏の量に見合う凝結遅延剤を添加した懸濁液を用
いる。 Normally, suspensions injected into the borehole are suitable for suspensions b or C in Figure 5, but if higher strength is required or long-term strength is not required, use the suspension as shown in Figure 3 E or F according to the target strength. The formulation is slightly changed, and a suspension is used in which a set retarder is added in proportion to the amount of gypsum.
本発明に石膏、セメント、精製粘土を用いる理
由は用いる材料の組合せによつて初期強度および
その発現に要する時間、および長期強度の発現状
況を異らしめるためである。例えばベントナイ
ト、セメント系の場合には日数の経過に伴う強度
の増進が著しいが石膏、セメント系の場合には強
度増進が非常に緩慢である。又、初期強度として
は2〜3Kg/cm2程度のものが望ましいが本発明の
石膏、セメント系の場合には凝結遅延剤の添加量
を適当に設定することによる第5図の如く1〜5
時間位の範囲で容易に所要強度を得ることができ
る。 The reason why gypsum, cement, and purified clay are used in the present invention is that the initial strength, the time required to develop it, and the state of development of long-term strength can be varied depending on the combination of materials used. For example, in the case of bentonite and cement-based materials, the strength increases significantly over time, but in the case of gypsum and cement-based materials, the strength increases very slowly. In addition, it is desirable that the initial strength is about 2 to 3 kg/cm 2 , but in the case of the gypsum or cement system of the present invention, it can be increased to 1 to 5 kg/cm 2 as shown in Fig. 5 by appropriately setting the amount of setting retarder added.
The required strength can be easily obtained within a range of about hours.
ベントナイトを用いた場合はベントナイトの膨
潤性のために硬化剤懸濁液の流動性が非常に悪く
なり施工性に欠ける。流動性を良くするために添
加する水の量を増やすと初期強度の発現が遅く、
第4図におけるA,Bの如く10時間程度経過して
始めて強度を発現し、24時間後に2Kg/cm2程度の
強度を得るがその後の強度増進が非常に大きいた
め、鋼矢板の建込み或いは隣接穿孔時間が24時間
前後に限定されてしまう。第4図Dの如くセメン
ト、石膏、ベントナイトの懸濁液を用いると初期
強度の発現は早くなるが24時間以後における強度
増進は同じく大きいため後続鋼矢板建込作業は24
時間以内に限定される。 When bentonite is used, the fluidity of the curing agent suspension is extremely poor due to the swelling properties of bentonite, resulting in a lack of workability. If you increase the amount of water added to improve fluidity, the development of initial strength will be delayed.
As shown in A and B in Fig. 4, strength is developed only after about 10 hours, and after 24 hours, strength of about 2 kg/cm 2 is obtained, but since the increase in strength after that is very large, it is difficult to build up steel sheet piles or Adjacent drilling time is limited to around 24 hours. As shown in Figure 4D, when a suspension of cement, gypsum, and bentonite is used, the initial strength develops quickly, but the increase in strength after 24 hours is also large, so the subsequent steel sheet pile erection work is carried out at 24 hours.
Limited within hours.
石膏、セメント、精製粘土の場合には初期強度
の発現が早く、その後の強度増進がきわめて緩慢
であるため、鋼矢板の建込み作業が非常に楽にな
る。さらに又凝結遅延剤の適量添加により凝結開
始時期をコントロールできるので穿孔注入作業の
施工性を高めることができる。第4図Eの場合は
硬化剤懸濁液として石膏のみを精製粘土と水に添
加した場合であり、初期強度を最も早く得ること
ができ、その後は全く強度の増進を見ないことが
分る。 In the case of gypsum, cement, and refined clay, the initial strength develops quickly and the subsequent increase in strength is extremely slow, making the work of erecting steel sheet piles very easy. Furthermore, by adding an appropriate amount of a setting retarder, the timing of the start of setting can be controlled, thereby improving the workability of drilling and pouring work. In the case shown in Figure 4E, only gypsum is added as a hardening agent suspension to purified clay and water, and it can be seen that the initial strength can be obtained the earliest, and there is no increase in strength after that. .
本発明による時はアースオーガーによる穿孔及
び注入が終了するのに引続いて隣接位置の穿孔注
入を行うことが可能であり、アースオーガーによ
る作業に追随しながら鋼矢板の建込みを行うこと
ができ、さらに又何らかの都合により建込みが遅
れ数日を経過した後においても硬化剤の強度増進
が小さいので容易に建込むことができる。 According to the present invention, it is possible to perform drilling and injection at an adjacent position immediately after the completion of drilling and injection by the earth auger, and it is possible to erect steel sheet piles while following the work by the earth auger. Furthermore, even after several days have elapsed due to a delay in construction due to some reason, the hardening agent can easily be installed because the strength increase is small.
このように本発明による時は特に砂礫質の地盤
で地下水流のある個所においても無振動、無騒音
で鋼矢板打込み作業を施工することができ、建設
公害を排除すると共に従来非常にコスト高となる
か或いは施工不可能とされた地盤条件での土留壁
工事を容易に行うことができる利点がある。 As described above, according to the present invention, steel sheet pile driving work can be carried out without vibration or noise, especially in areas with gravelly ground and underground water flow, eliminating construction pollution and eliminating construction costs that were conventionally extremely expensive. There is an advantage that earth retaining wall construction can be easily carried out under ground conditions that are considered to be difficult or impossible.
さらに本発明においては安価で取扱いの容易な
粘土を用いるから、土留壁工事を極めて安価に施
工しかつその作業性の向上をはかりうる効果があ
る。 Furthermore, since clay is used in the present invention, which is inexpensive and easy to handle, it is possible to construct earth retaining walls at a very low cost and to improve workability.
第1図、第2図は土留壁工法におけるその施工
順序を示す平面図、第3図は硬化剤懸濁液を構成
する物質の配合割合と経時的強度を示す比較図、
第4図は第3図のグラフ図、第5図は硬化剤懸濁
液中の凝結遅延剤量による一軸圧縮強度変化を示
したグラフ図である。
1,2,3,4,5は孔、6,7,8,9は鋼
矢板、10はジヨイント部。
Figures 1 and 2 are plan views showing the construction order in the earth retaining wall construction method, Figure 3 is a comparison diagram showing the blending ratio of substances constituting the hardening agent suspension and the strength over time;
FIG. 4 is a graph of FIG. 3, and FIG. 5 is a graph showing changes in uniaxial compressive strength depending on the amount of setting retarder in the hardening agent suspension. 1, 2, 3, 4, and 5 are holes, 6, 7, 8, and 9 are steel sheet piles, and 10 is a joint part.
Claims (1)
して穿孔個所の地盤を緩めると共に前記アースオ
ーガーロツドを引抜きつつアースオーガーロツド
の先端より硬化剤懸濁液を注入しながらオーガー
ロツドを引抜いて硬化剤を土と置き換え、先に明
けた孔に隣接した次の孔を同様にしてアースオー
ガーで穿孔し、アースオーガーロツドの引抜時硬
化剤懸濁液を注入し、これを繰り返して硬化剤懸
濁液が注入された孔を連続して形成し、この連続
して形成され硬化剤懸濁液が注入されている孔に
所望の鋼矢板を順次連続させて建て込んで地中に
土留壁を形成させる土留壁工法において、凝結遅
延剤を適量添加した半水石膏と天然又は精製粘土
の懸濁液、或いはこれにポルトランドセメントを
適量混入したる硬化剤懸濁液を用いることによ
り、硬化剤の凝結開始時間を任意に設定し、所望
の初期強度に達した後の経時的強度増進を緩慢な
らしめることによつて、爾后の鋼矢板の建込み、
オーガー掘削の施工性を高め、騒音、振動の随伴
をなくすることを特徴とする土留壁工法。1. Drill a hole in the desired ground using an earth auger or the like to loosen the ground at the drilling location, and while pulling out the earth auger rod, inject a hardening agent suspension from the tip of the earth auger rod, and then pull out the auger rod to harden it. Replace the agent with soil, drill the next hole adjacent to the previously drilled hole with the earth auger in the same way, inject the hardener suspension when the earth auger rod is pulled out, and repeat this process to increase the hardener suspension. Form a series of holes into which the suspension is injected, and build an earth retaining wall into the ground by sequentially erecting desired steel sheet piles into these continuously formed holes into which the hardening agent suspension is injected. In the earth retaining wall construction method, by using a suspension of hemihydrate gypsum and natural or purified clay to which an appropriate amount of a setting retardant has been added, or a hardening agent suspension in which an appropriate amount of Portland cement is mixed, the hardening agent can be reduced. By arbitrarily setting the setting start time and slowing down the increase in strength over time after reaching the desired initial strength, the subsequent erection of steel sheet piles,
An earth retaining wall construction method that improves the workability of auger excavation and eliminates accompanying noise and vibration.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16063277A JPS5490815A (en) | 1977-12-27 | 1977-12-27 | Method of constructing sand guard wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16063277A JPS5490815A (en) | 1977-12-27 | 1977-12-27 | Method of constructing sand guard wall |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5490815A JPS5490815A (en) | 1979-07-18 |
| JPS626049B2 true JPS626049B2 (en) | 1987-02-07 |
Family
ID=15719118
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP16063277A Granted JPS5490815A (en) | 1977-12-27 | 1977-12-27 | Method of constructing sand guard wall |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5490815A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH01115962U (en) * | 1988-01-31 | 1989-08-04 |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS62189217A (en) * | 1986-02-15 | 1987-08-19 | Kajima Corp | Sheathing work |
| JP5367537B2 (en) * | 2009-10-30 | 2013-12-11 | 鹿島建設株式会社 | Construction method and structure of steel pipe sheet pile |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| PL97947B3 (en) * | 1974-06-18 | 1978-03-30 | Politechnika Krakowska | FOUR-STROKE MULTIPLE CYLINDER COMBUSTION ENGINE WITH SPARK IGNITION |
| JPS5113117A (en) * | 1974-07-22 | 1976-02-02 | Nishikawa Gomu Kogyo Kk | Kochikubutsuno mejisetsugokoho |
| JPS52152610A (en) * | 1976-06-14 | 1977-12-19 | Obayashi Gumi Kk | Method of building water stop or sheathing wall using gypsum suspended solution |
-
1977
- 1977-12-27 JP JP16063277A patent/JPS5490815A/en active Granted
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH01115962U (en) * | 1988-01-31 | 1989-08-04 |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5490815A (en) | 1979-07-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102124163B (en) | Method for constructing a chair-type, self-supported earth retaining wall | |
| US5378085A (en) | Methods for in situ construction of deep soil-cement structures | |
| CN103774675B (en) | Combined double-row-pile combined vertical prestress anchor rod supporting system and construction method thereof | |
| AU781819B2 (en) | Soil reinforcement method and apparatus | |
| US20020071725A1 (en) | Earth support and permanent structural foundation wall | |
| KR100947627B1 (en) | Reinforced grouting structure of tunnel and tunnel construction method using same | |
| KR20120079987A (en) | Method of pre-support tunneling reinforced by in-situ soil mixed with cement | |
| KR100762991B1 (en) | Ready-made pile filling method to fill high strength mortar | |
| JP3676441B2 (en) | Pit and construction method of basement using it | |
| JP2653731B2 (en) | Embankment slope steepening method | |
| Kazemian et al. | Assessment of stabilization methods for soft soils by admixtures | |
| CN106917402A (en) | A kind of CFG pile precast piles head and CFG pile construction methods | |
| RU2344230C2 (en) | Method of ground anchor installation and associated device | |
| JPS63110319A (en) | Stabilization work of banking | |
| KR100477357B1 (en) | Construction method for retaining of earth | |
| JP2005146756A (en) | Earth retaining wall construction method and earth retaining wall formed thereby | |
| JP2004124452A (en) | Foundation pile structure and construction method of foundation pile on supporting ground | |
| KR200354672Y1 (en) | Wall Structure by Steel-column Pile Recovery Process | |
| CN206570822U (en) | A kind of slope retaining structure being applied in Mud Ground | |
| JPH0280710A (en) | Preparing cast-in-place concrete pile | |
| KR101070372B1 (en) | Grout-type composite sheet pile and its construction method | |
| JPS615118A (en) | Formation work of over-all friction pile | |
| JP2026028359A (en) | Pile construction method | |
| Walker | DSM saves the dam | |
| JP2004278041A (en) | Impermeable wall construction method |