JPS6318155B2 - - Google Patents
Info
- Publication number
- JPS6318155B2 JPS6318155B2 JP54003890A JP389079A JPS6318155B2 JP S6318155 B2 JPS6318155 B2 JP S6318155B2 JP 54003890 A JP54003890 A JP 54003890A JP 389079 A JP389079 A JP 389079A JP S6318155 B2 JPS6318155 B2 JP S6318155B2
- Authority
- JP
- Japan
- Prior art keywords
- diaphragm floor
- containment vessel
- reactor
- reactor containment
- diaphragm
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000010276 construction Methods 0.000 claims description 19
- 238000000034 method Methods 0.000 claims description 10
- 239000011810 insulating material Substances 0.000 claims description 6
- 238000003466 welding Methods 0.000 claims description 4
- 230000035515 penetration Effects 0.000 claims 1
- 238000007796 conventional method Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 230000001629 suppression Effects 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 210000005069 ears Anatomy 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 238000007689 inspection Methods 0.000 description 2
- 238000009413 insulation Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 239000000853 adhesive Substances 0.000 description 1
- 230000001070 adhesive effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Structure Of Emergency Protection For Nuclear Reactors (AREA)
Description
【発明の詳細な説明】
本発明は原子炉格納容器内ダイアフラムフロア
建設方法に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing a diaphragm floor in a nuclear reactor containment vessel.
まず従来の建設方法について添付図を参照しな
がら説明する。原子炉格納容器内ダイアフラムフ
ロア8は第1図に示すような構造をしている。す
なわち原子力発電所の原子炉建屋1の中に原子炉
2並びに原子炉一次系の機器配管を格納する原子
炉格納容器3が設けられている。原子炉格納容器
3はナツクル部4を境に上下2つの空間に分けら
れる。下部の空間はサプレツシヨンプール5、上
部のエリアはドライウエル6と称し、ドライウエ
ル内に事故時放出した原子炉主蒸気をベントパイ
プ7を通じてサプレツシヨンプールに導き凝縮さ
せる役割をもつている。このサプレツシヨンプー
ルとドライウエルの間切りの役割をもつているの
がダイアフラムフロア8である。 First, the conventional construction method will be explained with reference to the attached drawings. The diaphragm floor 8 in the reactor containment vessel has a structure as shown in FIG. That is, a reactor containment vessel 3 is provided in a reactor building 1 of a nuclear power plant to house a nuclear reactor 2 and equipment piping for a primary reactor system. The reactor containment vessel 3 is divided into two spaces, an upper and a lower space, with a nuticle section 4 as a boundary. The lower space is called the suppression pool 5, and the upper area is called the dry well 6, which has the role of guiding reactor main steam released during an accident into the dry well to the suppression pool through the vent pipe 7 and condensing it. . The diaphragm floor 8 has the role of separating the suppression pool and the dry well.
つぎにダイアフラムフロアの従来の建設方法に
ついて説明する。第2図、第3図はダイアフラム
フロアの構造を示す図である。ダイアフラムフロ
アの建設は、原子炉格納容器3と原子炉基礎台9
の組立建設と同時期に実施される。つまり、原子
炉格納容器3のナツクル部4とダイアフラムフロ
アサポート10が完成し、かつ、原子炉基礎台9
の下部9aと上部9bの一部が完成した状態の時
にダイアフラムフロアビーム11を取付る。次に
該ビーム上にシールプレート12を全面にわたつ
て溶接をする。この場合予め取付られているベン
トパイプ7があり、本パイプの部分は切欠いて溶
接される。一方原子炉格納容器3並びに原子炉基
礎台上部9bは更に上方に組立建設を進めて順次
完成をさせてゆく。 Next, a conventional method of constructing a diaphragm floor will be explained. FIGS. 2 and 3 are diagrams showing the structure of the diaphragm floor. Construction of the diaphragm floor consists of reactor containment vessel 3 and reactor foundation 9.
This will be carried out at the same time as the assembly and construction of. In other words, the knuckle portion 4 of the reactor containment vessel 3 and the diaphragm floor support 10 have been completed, and the reactor foundation 9 has been completed.
The diaphragm floor beam 11 is attached when the lower part 9a and part of the upper part 9b are completed. Next, the seal plate 12 is welded over the entire surface of the beam. In this case, there is a vent pipe 7 installed in advance, and a portion of this pipe is cut out and welded. On the other hand, the reactor containment vessel 3 and the reactor foundation upper part 9b will be assembled and constructed further upward and will be completed one by one.
シールプレート12の溶接が完了したならば所
定の検査を受ける。次にシールプレート上に第1
層目の断熱性を有するコンクリート13を打設す
る。コンクリートの養生完了の後、鉄筋組立1
4、ドレン配管15の取付、埋込金物16の取付
をおこなつて第2層目のコンクリート17を打設
する。コンクリートの養生完了後第2断熱材とし
て18を接着材にて貼付て、次に第3断熱材のコ
ンクリート19を打設する。第3断熱材のコンク
リート19の表面は、オイル、水の排水のため床
勾配が設けられているためコンクリート打設にあ
たつては、勾配定規を多数設定し、これに合わせ
てコテ等により勾配の設定をおこなつている。コ
ンクリートの打設は原子炉建屋外部からコンクリ
ート圧送管を介して、ポンプ車により圧送して原
子炉格納容器3に送り込みおこなう。ダイアフラ
ムフロア完成と同時に原子炉格納容器3の組立、
原子炉基礎台9の建設が完了し、原子炉格納容器
全体の耐圧力試験、気密漏洩試験を実施する。 Once welding of the seal plate 12 is completed, it undergoes a predetermined inspection. Next, place the first
Concrete 13 having layered heat insulation properties is poured. After concrete curing is completed, reinforcing steel assembly 1
4. Install the drain pipe 15 and the embedded hardware 16, and then pour the second layer of concrete 17. After curing of the concrete is completed, a second heat insulating material 18 is attached with an adhesive, and then a third heat insulating material 19 is poured. The surface of the concrete 19, which is the third heat insulating material, has a floor slope for drainage of oil and water, so when pouring concrete, set a number of slope rulers and use a trowel etc. to slope the surface according to the slope. The settings are being made. Concrete is poured from the outside of the reactor building through a concrete pressure pipe and pumped by a pump truck into the reactor containment vessel 3. At the same time as the diaphragm floor was completed, the reactor containment vessel 3 was assembled.
Construction of the reactor foundation 9 has been completed, and pressure tests and leakage tests of the entire reactor containment vessel will be conducted.
従来の原子炉格納容器内ダイアフラムフロアの
建設方法は、上述のようであつたが、このような
方法では次のような不具合があつた。 The conventional method of constructing a diaphragm floor in a reactor containment vessel was as described above, but such a method had the following problems.
すなわちこのような従来の方法では、原子炉格
納容器3の中での限定された極めて狭い場所で建
設を実施せねばならない事、加えて原子炉格納容
器の構造上頂部の開口が小さい事からダイアフラ
ムフロア上での作業に大型塔型クレーン等の機械
力が使用出来ないため人力に頼らねばならない事
から建設工期が非常に長くかかざるを得なかつ
た。 In other words, in this conventional method, construction must be carried out in a limited and extremely narrow space within the reactor containment vessel 3, and in addition, the opening at the top of the reactor containment vessel is small due to the structure, so the diaphragm Since mechanical power such as large tower cranes could not be used for the work on the floor, the construction period had to be extremely long because it had to rely on human power.
また長期間にわたつて原子炉格納容器組立と原
子炉基礎台の建設と上下同時作業となるため、安
全上好ましくない。加えて安全対策としての仮設
防護構造物の設置に多大の工数と費用が必要であ
る。 In addition, it is not desirable from a safety point of view, as it requires simultaneous assembly of the reactor containment vessel and construction of the reactor foundation, as well as up and down work over a long period of time. In addition, a large amount of man-hours and costs are required to install temporary protective structures as a safety measure.
本発明はこのような不具合を取り除き、工期の
大幅短縮と工数の大幅低減および作業上の安全性
向上、能率向上を図つた原子炉格納容器内ダイア
フラムフロア建設方法を得ることを目的としたも
のである。本発明の特徴は原子炉格納容器内ダイ
アフラムフロアビームとその上部に溶接するシー
ルプレートが完成したならば、工場もしくは現場
において製作した扇形もしくは半円形のブロツク
形ダイアフラムフロアを原子炉格納容器の組立の
合い間を利用し大型塔型クレーンでシールプレー
ト上に搬入し、ブロツク相互間を溶接し、接続部
並びにベントパイプ部の隙間のみをコンクリー
ト、充填、断熱材取付で済ませる事によりダイア
フラムフロアを建設する方法である。 The purpose of the present invention is to eliminate such defects and to provide a method for constructing a diaphragm floor in a reactor containment vessel that significantly shortens the construction period, significantly reduces the number of man-hours, and improves work safety and efficiency. be. The feature of the present invention is that once the diaphragm floor beam in the reactor containment vessel and the seal plate welded to its upper part are completed, the fan-shaped or semicircular block-shaped diaphragm floor manufactured in the factory or on-site can be used for assembly of the reactor containment vessel. A diaphragm floor is constructed by using the gap to transport the block onto the seal plate using a large tower crane, welding the blocks together, and filling only the gaps between the joints and vent pipes with concrete, filling, and installing insulation. It's a method.
以下図面により本発明の一実施例について説明
する。 An embodiment of the present invention will be described below with reference to the drawings.
第4図は本発明で使用されるブロツク化したダ
イアフラムフロア21の一実施例を示す斜視図で
ある。 FIG. 4 is a perspective view of one embodiment of a blocked diaphragm floor 21 used in the present invention.
例えば、建設現場の別の場所で扇形の型枠(図
示せず)を組立、分解して何度も使用出来る構造
で製作し、この型枠にまず第1層断熱コンクリー
ト13Aを施工する。次に鉄筋14A、埋込金物
16A及び吊り耳24、接続部材23を組み込み
第2層コンクリート17Aを打設する。次に第2
層コンクリート17A上に第2断熱材18A、第
3断熱コンクリート19Aの順に施工する。 For example, a fan-shaped formwork (not shown) is assembled and disassembled at another location on the construction site to produce a structure that can be used many times, and the first layer of insulating concrete 13A is first applied to this formwork. Next, reinforcing bars 14A, embedded hardware 16A, hanging ears 24, and connecting members 23 are incorporated, and second layer concrete 17A is poured. Then the second
A second heat insulating material 18A and a third heat insulating concrete 19A are constructed in this order on the layered concrete 17A.
次に前記ブロツク化したダイアフラムフロア2
1を使つての建設工法の一例を説明する。第5図
は本発明による原子炉格納容器内ダイアフラムフ
ロア建設方法を示す説明図である。 Next, the block-shaped diaphragm floor 2
An example of a construction method using 1 will be explained. FIG. 5 is an explanatory diagram showing a method for constructing a diaphragm floor in a reactor containment vessel according to the present invention.
() まず前述したように建設現場内でのプレハ
ブ工場、あるいは現場外の製造工場で、ブロツ
ク化したダイアフラムフロアの製作をしてお
き、工程手順に合わせて据付場所に運搬してお
く。() First, as mentioned above, a block diaphragm floor is manufactured at a prefabricated factory on the construction site or at an off-site manufacturing factory, and then transported to the installation site according to the process procedure.
() 前記()に対し建設現場では、原子炉格
納容器の組立をすすめ、ダイアフラムフロアサ
ポート10、原子炉基礎台上部9bの一部が完
成するのを待つてダイアフラムフロアビーム1
1を大型塔型クレーンで吊込み、続いてシール
プレート12をダイアフラムフロアビーム上に
溶接する。シールプレートの完成検査を受け
る。() In contrast to () above, at the construction site, the reactor containment vessel was assembled, and the diaphragm floor beam 1 was assembled after the diaphragm floor support 10 and part of the reactor foundation upper part 9b were completed.
1 is lifted by a large tower crane, and then the seal plate 12 is welded onto the diaphragm floor beam. The seal plate undergoes a final inspection.
() 次に前記()で完成したダイアフラムフ
ロアシールプレート上に()で完成している
ブロツク化ダイアフラムフロア21を吊り耳2
4を利用して、吊り卸し順次並べてゆく。全ブ
ロツクの搭載が完了したならば、ブロツク相互
の接続部材23を溶接にて固着させ、全体を一
枚のダイアフラムフロアとして完成させる。ブ
ロツク相互間の接続部の隙間25並びにベント
パイプ7とブロツク化したダイアフラムフロア
21との隙間にドレン配管15、コンクリート
26、断熱材18B、断熱コンクリート19B
を組込み、充填してダイアフラムフロアの組立
は完了する。() Next, place the block diaphragm floor 21 completed in () on the diaphragm floor seal plate completed in () above with hanging ears 2.
Using 4, hang and line up in order. Once all the blocks have been mounted, the connecting members 23 between the blocks are fixed by welding to complete the whole as one diaphragm floor. Drain piping 15, concrete 26, heat insulating material 18B, and heat insulating concrete 19B are installed in the gap 25 between the connections between the blocks and the gap between the vent pipe 7 and the blocked diaphragm floor 21.
The diaphragm floor assembly is completed by incorporating and filling the diaphragm floor.
() この間に原子炉格納容器と原子炉基礎台は
同時に組立、建設を進める事になるが、極めて
短時間のため、一時的にエリア調整を実施しな
がら作業が進められるので問題は殆ど皆無にな
る。() During this time, the reactor containment vessel and the reactor foundation will be assembled and constructed at the same time, but since it is an extremely short period of time, the work can be done while temporarily adjusting the area, so there will be almost no problems. Become.
以上説明したようにブロツク化ダイアフラムフ
ロアを用いた原子炉格納容器内のダイアフラムフ
ロアの建設方法によつて、ダイアフラムフロアの
建設工期は極めて大幅に短縮出来る。 As explained above, the construction period of the diaphragm floor can be significantly shortened by the method of constructing the diaphragm floor in the reactor containment vessel using the blocked diaphragm floor.
これにより、従来原子炉格納容器の組立、原子
炉基礎台の組立とダイアフラムフロアの建設が上
下並行作業となつていたものが、工期が大幅に短
縮されることから一時的なエリア調整をおこなう
のみで安全に、能率良く作業が遂行出来ること。
又、原子炉格納容器の頂部の開口が小さいために
底部にあるダイアフラムフロア上での作業には大
型揚重設備が使用出来なかつたが、本発明により
原子炉格納容器の組立がナツクル部組立の低いレ
ベルで大開口のある時期に大型揚重設備が使用し
て高能率で短期間に作業が出来ること。 As a result, whereas previously the assembly of the reactor containment vessel, the assembly of the reactor foundation, and the construction of the diaphragm floor had to be done in parallel up and down, the construction period has been significantly shortened, so only temporary area adjustments are needed. Be able to perform work safely and efficiently.
In addition, because the opening at the top of the reactor containment vessel was small, large-scale lifting equipment could not be used for work on the diaphragm floor at the bottom. Large lifting equipment can be used to perform work with high efficiency in a short period of time when there is a large opening at a low level.
以上扇形をしたブロツク化ダイアフラムフロア
を用いた建設方法を説明したが、ブロツク化した
ダイアフラムフロアは半円形でも良く、又ブロツ
ク化したダイアフラムフロアを接続する方法は部
分的な接続でなく、ブロツク化したダイアフラム
フロアの周囲を鋼材で囲み、これを隣接するブロ
ツクの鋼材を全周にしても良い。 The construction method using fan-shaped blocked diaphragm floors has been explained above, but the blocked diaphragm floors may also be semicircular, and the method of connecting the blocked diaphragm floors is not partial connection but block diaphragm floors. The periphery of the diaphragm floor may be surrounded by steel material, and the steel material of adjacent blocks may be used all around the diaphragm floor.
第1図は従来の原子炉建屋と原子炉格納容器と
の位置関係を示す縦断面図、第2図、第3図は従
来工法により建設中のダイアフラムフロアを示す
説明図、第4図は本発明にかかるブロツク化した
ダイアフラムフロアを示す斜視図、第5図は本発
明による建設工法を示す説明図である。
1……原子炉建屋、3……原子炉格納容器、8
……ダイアフラムフロア、10……ダイアフラム
フロアサポート、12……シールプレート、21
……ブロツク化したダイアフラムフロア。
Figure 1 is a vertical cross-sectional view showing the positional relationship between the conventional reactor building and the reactor containment vessel, Figures 2 and 3 are explanatory diagrams showing the diaphragm floor being constructed using the conventional construction method, and Figure 4 is the main FIG. 5 is a perspective view showing a block-shaped diaphragm floor according to the invention, and FIG. 5 is an explanatory view showing the construction method according to the invention. 1... Reactor building, 3... Reactor containment vessel, 8
...Diaphragm floor, 10...Diaphragm floor support, 12...Seal plate, 21
...Blocked diaphragm floor.
Claims (1)
ムフロア建設において、原子炉下部基礎台と原子
炉格納容器のダイアフラムフロアサポート上にダ
イアフラムフロアビーム並びにシールプレートを
組立溶接した後、その上部に2個以上にブロツク
化したダイアフラムフロアを吊卸し、これらを接
続し、しかる後に接続部分並びに他の貫通部分の
隙間とにコンクリート充填と断熱材の取付をおこ
なつて、ダイアフラムフロアを施工することを特
徴とする原子炉格納容器内ダイアフラムフロア建
設方法。1. In the construction of a diaphragm floor in the reactor containment vessel of a nuclear power plant, after assembling and welding the diaphragm floor beam and seal plate on the reactor lower foundation and the diaphragm floor support of the reactor containment vessel, two or more The diaphragm floor is constructed by suspending the block-formed diaphragm floor, connecting them, and then filling the connecting parts and gaps in other penetration parts with concrete and installing heat insulating material. Method of constructing a diaphragm floor in a reactor containment vessel.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP389079A JPS5596493A (en) | 1979-01-19 | 1979-01-19 | Method of building diaphragm floor in nuclear reactor containment vessel * block type diaphragm floor therefor |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP389079A JPS5596493A (en) | 1979-01-19 | 1979-01-19 | Method of building diaphragm floor in nuclear reactor containment vessel * block type diaphragm floor therefor |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5596493A JPS5596493A (en) | 1980-07-22 |
| JPS6318155B2 true JPS6318155B2 (en) | 1988-04-16 |
Family
ID=11569770
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP389079A Granted JPS5596493A (en) | 1979-01-19 | 1979-01-19 | Method of building diaphragm floor in nuclear reactor containment vessel * block type diaphragm floor therefor |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5596493A (en) |
-
1979
- 1979-01-19 JP JP389079A patent/JPS5596493A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5596493A (en) | 1980-07-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108590005A (en) | A kind of hollow two-way superstructure of assembled integral concealed beam and assembly method | |
| CN104975614B (en) | Shaped steel combination formula single side formwork strengthening construction engineering method | |
| CN106677340A (en) | Flange plate type precast assembly type concrete hidden bracket dry type connecting system | |
| JP3283735B2 (en) | Method for constructing upper dry well of reactor containment vessel and module used for the method | |
| CN118564101B (en) | A method for renovating the layout of old buildings without temporary support and improving earthquake resistance | |
| JPS6318155B2 (en) | ||
| CN118639681A (en) | A construction method for underwater structures in complex environments | |
| CN216840692U (en) | Construction device for super high-rise building | |
| CN113089777B (en) | Modular annular concrete stainless steel water tank and construction method thereof | |
| CN212001725U (en) | Full bolted connection multilayer prefabricated section steel concrete shear wall structure | |
| CN214364034U (en) | A prefabricated reinforced concrete building main structure | |
| CN211949045U (en) | A steel-concrete composite connection multi-layer prefabricated steel-concrete shear wall structure | |
| CN109469332B (en) | Method for installing multilayer steel structure | |
| CN109736589B (en) | A kind of construction method of lattice column force transmission member | |
| KR100379740B1 (en) | Framework | |
| JP2945707B2 (en) | Installation method of pedestal supporting reactor pressure vessel | |
| CN110805063A (en) | Building bottom plate construction method | |
| CN112761245A (en) | Assembled reinforced concrete building main body structure and installation construction method thereof | |
| CN111576478A (en) | Elevator well foundation structure | |
| CN219219027U (en) | A pump containment device | |
| CN217267621U (en) | An underground building structure that bans the post-settling pouring zone | |
| CN223410107U (en) | An assembled flood wall | |
| CN114622589B (en) | Construction method of building structure using high ductility concrete belt instead of settlement post-cast belt | |
| KR102892985B1 (en) | The method for repairing the underwater construction | |
| CN223317445U (en) | A kind of anti-leakage structure for steel-concrete structure connection |