JPS6326211B2 - - Google Patents

Info

Publication number
JPS6326211B2
JPS6326211B2 JP56033817A JP3381781A JPS6326211B2 JP S6326211 B2 JPS6326211 B2 JP S6326211B2 JP 56033817 A JP56033817 A JP 56033817A JP 3381781 A JP3381781 A JP 3381781A JP S6326211 B2 JPS6326211 B2 JP S6326211B2
Authority
JP
Japan
Prior art keywords
steel
concrete
formwork
reactor building
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP56033817A
Other languages
Japanese (ja)
Other versions
JPS57148287A (en
Inventor
Shigeru Kyoda
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Tokyo Shibaura Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Shibaura Electric Co Ltd filed Critical Tokyo Shibaura Electric Co Ltd
Priority to JP56033817A priority Critical patent/JPS57148287A/en
Publication of JPS57148287A publication Critical patent/JPS57148287A/en
Publication of JPS6326211B2 publication Critical patent/JPS6326211B2/ja
Granted legal-status Critical Current

Links

Classifications

    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00—Energy generation of nuclear origin
    • Y02E30/30—Nuclear fission reactors

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 本発明は原子炉建屋の建築方法に係り、特に建
築工事のコンクリート躯体の型枠施工方法に関す
るものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing a nuclear reactor building, and particularly to a method of constructing formwork for a concrete frame for construction work.

原子炉建屋1は、第1図に示す如く、多くの壁
2、床3および梁4より構成されており、建築工
事は下層階より上層階へと順次進められていく。
As shown in FIG. 1, the reactor building 1 is composed of many walls 2, floors 3, and beams 4, and construction work is progressed sequentially from the lower floors to the upper floors.

最上層階では、第2図に示すように運転操作床
面5のコンクリート打設、鉄骨柱6の建築および
屋根鉄骨構造体7の設定が行なわれ、更に壁8お
よび天井梁9等の鉄筋・コンクリート打設工事が
行なわれる。
On the top floor, as shown in Fig. 2, concrete is poured for the operation floor 5, steel columns 6 are constructed, and the roof steel structure 7 is set, and the walls 8, ceiling beams 9, etc., are reinforced with concrete, etc. Concrete pouring work will be carried out.

これらの作業の後、原子力発電所建設において
最も重要な機器である天井走行クレーン10を走
行ガーダ11上に塔載し、据付を行なう。
After these operations, the overhead traveling crane 10, which is the most important equipment in nuclear power plant construction, is mounted on the traveling girder 11 and installed.

原子炉建屋の建築方法の概要は上述の如くであ
るが、特に最上層階について従来方法の詳細を説
明すると、運転操作床面5のコンクリート打設
後、第3図に示すように鉄骨柱6を構築し(第3
図では鉄骨柱の周囲をコンクリートで固めた状態
を示している。)、この鉄骨柱6に屋根鉄骨構造体
7を配置し、鋼板および特殊締付ボルトから成る
連結部材12にて設定・据付けを行なう。
The outline of the construction method for the reactor building is as described above, but to explain the details of the conventional method especially for the top floor, after pouring concrete for the operation floor 5, the steel columns 6 are constructed as shown in FIG. (3rd
The figure shows the steel columns surrounded by concrete. ), the roof steel frame structure 7 is arranged on the steel frame columns 6, and set and installed using connecting members 12 made of steel plates and special tightening bolts.

このようにして鉄骨構造体7が正規に据付られ
た後、鉄骨柱6周囲、壁8および天井梁9の鉄筋
組立を行ない更に運転操作床面5より仮設足場1
3を構築した上、この足場を利用してコンクリー
ト打設用の木製型枠14とそれを支持する仮設鋼
管15および支保工16の設定作業を行なつてい
く。
After the steel structure 7 is properly installed in this way, reinforcing bars are assembled around the steel columns 6, walls 8, and ceiling beams 9, and then temporary scaffolding 1 is installed from the operation floor 5.
3 is constructed, and this scaffolding is used to set up the wooden formwork 14 for concrete pouring, the temporary steel pipes 15 that support it, and the shoring 16.

続いて、木製型枠14の中にコンクリートが打
設され、必要な養生期間を置いたのち、型枠14
と支保工16を徹去し、仮設足場13を解体す
る。
Next, concrete is poured into the wooden formwork 14, and after a necessary curing period, the formwork 14 is poured.
and shoring 16 will be removed, and temporary scaffolding 13 will be dismantled.

これらの解体は鉄骨柱6周囲、壁8および天井
梁9の順序で行なわれ、天井梁9の部分の建築工
事が終了し、仮設足場13が解体された後、第2
図に示すように天井走行クレーン10が所定の位
置に塔載され、組立試験が行なわれ、稼動するこ
とになる。
These demolition steps are carried out in the order of the surrounding steel columns 6, walls 8, and ceiling beams 9. After the construction work on the ceiling beams 9 is completed and the temporary scaffolding 13 is dismantled, the second
As shown in the figure, the overhead traveling crane 10 is mounted on a tower at a predetermined position, an assembly test is performed, and it is put into operation.

従来の原子炉建屋の建築方法は上述の通りであ
るが、これには次の様な欠点があつた。
The conventional method of constructing a nuclear reactor building is as described above, but this method has the following drawbacks.

即ち、従来方法では、木製型枠14の設定およ
び支持のため、仮設足場13をコンクリートの養
生が終るまで組立てておかねばならないので、そ
の解体後でなければ、天井走行クレーン10を塔
載出来ず、しかも、原子炉建屋の最上部であると
ころから最も遅い建築工事となり、必然的に、天
井走行クレーン10の稼動開始時期が遅くなる。
That is, in the conventional method, in order to set up and support the wooden formwork 14, the temporary scaffolding 13 must be erected until the concrete has finished curing, so the overhead traveling crane 10 cannot be mounted on the tower until it is dismantled. Moreover, the construction work starts from the top of the reactor building, which is the slowest, and the start of operation of the overhead traveling crane 10 is inevitably delayed.

このクレーン稼動開始時期が遅くなる結果原子
炉内構造物の据付工事が遅延し、原子力発電所の
建設工程に重大な支障をきたすおそれがある。
As a result of the delay in starting the crane operation, the installation work of the internal reactor structures may be delayed, which may seriously impede the construction process of the nuclear power plant.

また、運転操作床面上に壁に沿つて全周に仮設
足場を設定することにより、運転操作床面の有効
作業面積が狭くなりしかも長期にわたつて仮設足
場を設けておかなくてはならず、他の建設工程に
影響を及ぼすことになる。
In addition, by setting up temporary scaffolding all around the operating floor along the wall, the effective working area of the operating operating floor becomes narrower, and the temporary scaffolding must be kept in place for a long period of time. , which will affect other construction processes.

更には、壁、柱、天井梁および屋根鉄骨構造体
の構築は高所作業である上、運転操作床面上の他
作業とも上下平行作業で長期にわたつて建設を進
めねばならず、作業の出会い調整が複雑となり、
安全性の点からも問題がある。
Furthermore, the construction of walls, columns, ceiling beams, and roof steel structures requires work at heights, and construction must proceed over a long period of time in parallel vertically with other work on the operating floor. Coordinating encounters becomes complicated,
There are also problems from a safety point of view.

これらの理由から、天井走行クレーンの稼動時
期が原子力発電所の全体建設工程における大きな
クリテイカルパスとなり、全体の建設期間が長期
におよぶ最大の原因となつている。
For these reasons, the operating period of the overhead traveling crane is a critical path in the overall construction process of a nuclear power plant, and is the biggest reason for the long overall construction period.

本発明は以上の事情に鑑みてなされたもので、
その目的とするところは、工期の大巾短縮とコス
トの低減および作業上の安全性向上ならびに能率
向上を図つた原子炉建屋の建築方法を得ることを
目的としたものである。
The present invention was made in view of the above circumstances, and
The objective is to obtain a construction method for a nuclear reactor building that significantly shortens the construction period, reduces costs, and improves work safety and efficiency.

本発明の特徴は、コンクリート打設に必要な型
枠を鉄板化し、この鉄板型枠を吊り支持部材を介
して建屋躯体の天井梁部の型鋼に固着し、この鉄
板型枠付きの型鋼を鉄骨柱の間に設定・固定した
後、そのままコンクリート躯体の中に埋め込むこ
とにより、型枠を支える支保工、仮設足場を不要
にしようとするものである。
A feature of the present invention is that the formwork necessary for concrete pouring is made of steel plates, the steel plate formwork is fixed to the form steel of the ceiling beam of the building frame via suspension support members, and the form steel with the steel plate formwork is attached to the steel frame. By setting and fixing the formwork between the pillars and then embedding it directly into the concrete structure, it is possible to eliminate the need for shoring and temporary scaffolding to support the formwork.

以下、図面に示す一実施例を参照して本発明の
詳細を説明する。
Hereinafter, the present invention will be explained in detail with reference to an embodiment shown in the drawings.

本発明においては、従来通り運転操作床のコン
クリート打設後、第4図および第5図に示す様に
鉄骨柱6のH型鋼17を構築する。
In the present invention, after pouring concrete for the operation floor as in the past, the H-shaped steel 17 of the steel column 6 is constructed as shown in FIGS. 4 and 5.

天井梁9のH型鋼18には鉄板型枠19を鋼材
等を利用した吊り支持部材20にて予じめ取付け
ておく。
An iron plate form 19 is attached to the H-beam 18 of the ceiling beam 9 in advance with a hanging support member 20 made of steel or the like.

この様にして組み立てた鉄板型枠19付H型鋼
18を鉄骨柱6のH型鋼17の間に設定・固定す
るとともに、屋根鉄骨構造体7を連結部材12を
用いて据付けておく。
The H-shaped steel 18 with the steel plate formwork 19 assembled in this way is set and fixed between the H-shaped steel 17 of the steel column 6, and the roof steel structure 7 is installed using the connecting member 12.

これらの鉄構物が設定・固定されたならば従来
通り、鉄骨柱6および壁8内の鉄筋組みを運転操
作床面より構築した仮設足場を使用して行なう。
Once these steel structures have been set and fixed, reinforcing bars within the steel columns 6 and walls 8 are constructed using temporary scaffolding constructed from the operation floor as usual.

また、これと平行して、天井梁9の鉄筋組を上
部鋼より行う。続いてコンクリート打設を行なう
が、本発明の方法では従来の様な支保工なしで、
鉄板型枠内にコンクリート打設が出来ることか
ら、仮設足場は鉄骨柱や壁のコンクリートが天井
梁の下端位置まで打設された後、直ちに解体・徹
去する。
In addition, in parallel with this, reinforcing bars for the ceiling beam 9 are constructed from the upper steel. Next, concrete is poured, but with the method of the present invention, there is no need for shoring as in the conventional method.
Since concrete can be poured within the steel plate formwork, the temporary scaffolding will be dismantled and removed immediately after the concrete for the steel columns and walls has been poured to the bottom of the ceiling beams.

以上のように本発明による原子炉建屋の建築方
法では、原子炉建屋最上部の最も遅く施工される
天井梁部分の型枠を仮設足場や支保工なしで施工
出来ることから、鉄骨柱と壁のコンクリート工事
が終わつた後、直ちに仮設足場を解体・徹去する
ことが可能となり、更には天井梁用の支保工と型
枠の組立・解体が不要になるので、天井走行クレ
ーンの塔載及び稼動開始を早めることができる。
As described above, in the reactor building construction method according to the present invention, the formwork for the ceiling beam section at the top of the reactor building, which is the latest to be constructed, can be constructed without temporary scaffolding or shoring. After the concrete work is completed, the temporary scaffolding can be dismantled and removed immediately, and furthermore, there is no need to assemble and dismantle the support and formwork for the ceiling beams, making it easier to mount and operate the overhead crane. You can start earlier.

従つて、この天井走行クレーンを利用すること
によつて、原子炉内構造物の据付けが効率的に行
われ、原子力発電所建設の全体工期を大巾に短縮
することが可能となる。
Therefore, by using this overhead traveling crane, the internal reactor structures can be installed efficiently, and the overall construction period for nuclear power plant construction can be significantly shortened.

また、仮設足場を早期に徹去することができる
ことから運転操作床面の作業有効面積が確保でき
る上、作業の出合い調整や上下作業が減少し、高
所作業の減少等による安全性の向上も著しい。
In addition, since the temporary scaffolding can be removed quickly, the effective working area of the operation floor can be secured, and safety is improved by reducing work encounter coordination and up-and-down work, and reducing the need for work at heights. Significant.

しかも梁部の支保工や型枠の組立・解体が不要
となることから、コスト低減に大巾に寄与し得
る。
Moreover, since there is no need to assemble or disassemble the shoring of the beam or the formwork, it can significantly contribute to cost reduction.

このように本発明によれば、上述の種々の効果
の総合により、原子力発電所建設工期の大巾短縮
と費用の節約を図ることができる。
As described above, according to the present invention, by combining the various effects described above, it is possible to significantly shorten the construction period of a nuclear power plant and save costs.

なお、以上の説明では本発明をその実施例につ
き述べたが、本発明はこの特定の実施例に限定さ
れるものではなく、本発明の精神を逸脱しない範
囲で幾多の変化、変形をなし得ることは勿論であ
る。
In the above description, the present invention has been described with reference to its embodiments, but the present invention is not limited to these specific embodiments, and can be modified and modified in many ways without departing from the spirit of the present invention. Of course.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は原子炉建屋全体の一構造例を示す縦断
面図、第2図は第1図の枠に示す原子炉建屋最
上階部分の縦断面図、第3図は従来方法を説明す
るもので、第2図の枠に示す天井部分梁部を下
から見上げた斜視図、第4図は本発明の実施例を
説明するもので原子炉建屋を天井梁部内で横断し
た断面図、第5図は第4図の−線に沿う縦断
面図である。 1……原子炉建屋、2……壁、3……床、4…
…梁、5……運転操作床面、6……鉄骨柱、7…
…屋根鉄骨構造体、8……壁(最上階)、9……
天井梁、10……天井走行クレーン、11……走
行ガーダ、12……連結部材、13……仮設足
場、14……木製型枠、15……仮設鋼管(型枠
支持用)、16……支保工(型枠支持用)、17…
…H型鋼(鉄骨柱)、18……H型鋼(天井梁)、
19……鉄板型枠、20……鉄板型枠吊り支持部
材。
Figure 1 is a vertical cross-sectional view showing an example of the overall structure of the reactor building, Figure 2 is a vertical cross-sectional view of the top floor of the reactor building shown in the frame of Figure 1, and Figure 3 is a diagram explaining the conventional method. FIG. 4 is a perspective view of the ceiling beam shown in the frame of FIG. 2, looking up from below; FIG. The figure is a longitudinal sectional view taken along the - line in FIG. 4. 1... Reactor building, 2... Wall, 3... Floor, 4...
...Beam, 5...Operation floor, 6...Steel column, 7...
...Roof steel structure, 8...Wall (top floor), 9...
Ceiling beam, 10... Overhead traveling crane, 11... Traveling girder, 12... Connecting member, 13... Temporary scaffolding, 14... Wooden formwork, 15... Temporary steel pipe (for formwork support), 16... Shoring (for formwork support), 17...
...H type steel (steel column), 18...H type steel (ceiling beam),
19... Steel plate formwork, 20... Steel plate formwork suspension support member.

Claims (1)

【特許請求の範囲】 1 原子炉建屋のコンクリート打設に使用する鉄
板型枠を吊り支持部材を介して建屋躯体の天井梁
部の型鋼に固着し、この鉄板型枠付きの型鋼を鉄
骨柱の間に設定・固定した後、前記鉄板型枠を用
いてコンクリート打設を行ない、この鉄板型枠を
コンクリート打設後もそのままコンクリート躯体
に埋め込むことを特徴とする原子炉建屋の建築方
法。 2 天井梁部が原子炉建屋の最上階天井梁部であ
ることを特徴とする特許請求の範囲第1項記載の
原子炉建屋の建築方法。
[Scope of Claims] 1. A steel plate form used for pouring concrete in a reactor building is fixed to a form steel of a ceiling beam of a building frame via a suspension support member, and the form steel with the steel plate form is attached to a steel column. A method for constructing a nuclear reactor building, characterized in that after setting and fixing the steel plate formwork in between, concrete is poured using the steel plate formwork, and the steel plate formwork is embedded in the concrete frame as it is even after the concrete is poured. 2. The method for constructing a nuclear reactor building as set forth in claim 1, wherein the ceiling beam portion is a ceiling beam portion on the top floor of the reactor building.
JP56033817A 1981-03-11 1981-03-11 Method of building nuclear reactor building Granted JPS57148287A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP56033817A JPS57148287A (en) 1981-03-11 1981-03-11 Method of building nuclear reactor building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP56033817A JPS57148287A (en) 1981-03-11 1981-03-11 Method of building nuclear reactor building

Publications (2)

Publication Number Publication Date
JPS57148287A JPS57148287A (en) 1982-09-13
JPS6326211B2 true JPS6326211B2 (en) 1988-05-28

Family

ID=12397025

Family Applications (1)

Application Number Title Priority Date Filing Date
JP56033817A Granted JPS57148287A (en) 1981-03-11 1981-03-11 Method of building nuclear reactor building

Country Status (1)

Country Link
JP (1) JPS57148287A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2616604B2 (en) * 1991-05-29 1997-06-04 住友電装株式会社 Waterproof connector

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5415282Y2 (en) * 1974-07-03 1979-06-21
JPS5520942Y2 (en) * 1974-07-09 1980-05-20
JPS5127926A (en) * 1974-09-02 1976-03-09 Canon Kk Kogakusosasochi

Also Published As

Publication number Publication date
JPS57148287A (en) 1982-09-13

Similar Documents

Publication Publication Date Title
CN207739437U (en) A kind of prefabricated steel reinforced concrete shear wall structure
KR102296982B1 (en) Transfer Structure Construction Method Using U-shaped Steel Girder
JPH0699959B2 (en) Nuclear power plant building construction method
JPH0657710A (en) Construction of concrete main tower
KR102910984B1 (en) Construction method of doorway type cast-in-place beam support of civil building frame structure
JPH0953277A (en) Nuclear power plant construction method
JPH0784762B2 (en) Steel column base fixing method
JP7674919B2 (en) How to install safety equipment
JP3207276B2 (en) How to build a unit building
KR960011364B1 (en) Fixing method of steel-frame/steel concrete beam
JPH06136821A (en) Construction method for steel reinforced concrete structures
JP2518568Y2 (en) Connection structure of steel beams to concrete columns
SU1214874A1 (en) Three-dimensional ferroconcrete skeleton of multistorey building
SU977644A1 (en) Method for erecting cast-in-place buildings
JPH0791876B2 (en) Radiation shielding slab and its construction method
JPS6156474B2 (en)
JPS58118987A (en) Reactor building construction method
SU1190046A1 (en) Method of constructing the ceiling of column-type underground railway station
JPH0522777B2 (en)
JPS6349773B2 (en)
JPH03161657A (en) Temporarily set support for erecting slab semi-pca plate
JP2001032376A (en) Floor slab frame and construction method for skeleton
JPH04149365A (en) Construction method of beam
JPH04360964A (en) Constructing method for steel-frame and reinforced-concrete section
JPH0692669B2 (en) Frame method using shaped steel for beam with rebar concrete structure