JPS635529B2 - - Google Patents
Info
- Publication number
- JPS635529B2 JPS635529B2 JP57129025A JP12902582A JPS635529B2 JP S635529 B2 JPS635529 B2 JP S635529B2 JP 57129025 A JP57129025 A JP 57129025A JP 12902582 A JP12902582 A JP 12902582A JP S635529 B2 JPS635529 B2 JP S635529B2
- Authority
- JP
- Japan
- Prior art keywords
- jack
- pile body
- press
- foundation
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/20—Placing by pressure or pulling power
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Description
【発明の詳細な説明】
本発明は杭体圧入装置に関するものであり、更
に詳しく言えば構造物下部における狭隘な作業場
所で行われるアンダーピニング工事、つまり建設
基礎の増杭工事に使用するのに適した構築物の重
力を反力として利用する杭体圧入装置に関するも
のである。[Detailed Description of the Invention] The present invention relates to a pile press-in device, and more specifically, it is used for underpinning work performed in a narrow work area at the bottom of a structure, that is, for adding piles to a construction foundation. This invention relates to a pile press-in device that uses the gravity of a suitable structure as a reaction force.
周知のように、建設工事において、既設の基礎
杭が支持層に迄充分到達していない時、或いは建
設後杭体がネガチブフリクシヨンの影響を受ける
場合に建物の不同沈下が起ることがある。この場
合既設基礎を補強するためのアンダーピニング、
即ち増杭工事を行う必要がある。この増杭作業は
第3図に示すように構築物の下方を掘り下げ既設
の杭イの近くでフーチング下部に別個の杭ロを所
要の深さ迄圧入するのであつて、杭体としては長
さ約1m、径30〜50cmの単位鋼管を継ぎ足して形
成されるが、構築物基礎下面との間にジヤツキハ
を介挿し、構築物の動を反力としてこのジヤツキ
により単位鋼管を順次地中に圧入し、次いで各単
位鋼管を溶接により順次継ぎ足して所要の深さま
で到達させるものである。しかしながらこのよう
な従来の工法では、所要深さに達した杭圧入終了
毎にジヤツキハを取りはずして基礎下面との間に
再び次の単位鋼管を圧入すべき上部位置に再びジ
ヤツキを取りつける手間を要し、このことは作業
場所が狭隘なことと相まつて作業能率が悪くかつ
又かなりの重量(約100Kg)のあるジヤツキ取付
けを手作業で行うため事故を生じ易い欠点があつ
た。 As is well known, during construction work, uneven settlement of buildings can occur when the existing foundation piles do not reach the supporting layer sufficiently, or when the piles are affected by negative friction after construction. . In this case, underpinning to reinforce the existing foundation,
In other words, it is necessary to carry out pile increase work. As shown in Figure 3, this pile increase work involves digging beneath the structure and press-fitting separate piles to the required depth at the bottom of the footing near the existing piles A. It is formed by joining unit steel pipes of 1 m in diameter and 30 to 50 cm in diameter. A jack is inserted between the bottom surface of the structure's foundation, the movement of the structure is used as a reaction force, and the unit steel pipes are successively pressed into the ground using this jack. Each unit steel pipe is successively added by welding to reach the required depth. However, with such conventional construction methods, it is necessary to remove the jack every time the pile is press-fitted to the required depth, and to reinstall the jack at the upper position where the next unit steel pipe is to be press-fitted between the bottom surface of the foundation and the foundation. This, combined with the narrow working area, resulted in poor work efficiency and the disadvantage that the installation of the jacks, which weighed a considerable amount of weight (approximately 100 kg), was done manually, making accidents more likely.
本発明は上記の点を考慮してジヤツキを極めて
簡単に建物基礎下面にしかも機械的に所定の場所
に位置できるように構成したものである。 In consideration of the above points, the present invention is designed to allow the jack to be placed extremely easily on the underside of the building foundation and mechanically at a predetermined location.
以下に本発明の実施の一例を第1図および第2
図について説明する。油圧モータによる走行機構
(クローラ)1を有する台枠2上に油圧シリンダ
3ならびにプランジヤ4よりなる伸縮支柱5を立
設し、こ伸縮支柱5のプランジヤ4の上端に片持
支持して水平に旋回可能に設けたブロツク6に油
圧シリンダ7およびプランジヤ8よりなる伸縮腕
杆9を横架し、この伸縮腕杆9の先端環枠部にジ
ヤツキ10を左右吊バネ11,11により吊持取
付けされている。なお、12は伸縮腕杆9の伸縮
度調整用の回転ハンドル、13は伸縮支柱5のプ
ランジヤ4の回動を阻止するための締付輪、1
4,14はジヤツキ10の圧力油ホース取付口、
15は運転席であつて油圧ポンプと直結したエン
ジン16を備えている。 An example of the implementation of the present invention is shown below in Figures 1 and 2.
The diagram will be explained. A telescoping column 5 consisting of a hydraulic cylinder 3 and a plunger 4 is erected on an underframe 2 having a traveling mechanism (crawler) 1 by a hydraulic motor, and the telescoping column 5 is supported cantilevered on the upper end of the plunger 4 to rotate horizontally. A telescoping arm rod 9 consisting of a hydraulic cylinder 7 and a plunger 8 is horizontally mounted on a block 6 which is provided in a horizontal manner. There is. In addition, 12 is a rotary handle for adjusting the telescoping degree of the telescopic arm rod 9, 13 is a tightening ring for preventing the rotation of the plunger 4 of the telescoping column 5, and 1
4 and 14 are the pressure oil hose installation ports of Jatuki 10,
15 is a driver's seat and is equipped with an engine 16 directly connected to a hydraulic pump.
本発明による杭体圧入装置は上記のような構成
を有し、その使用に当り前記第3図に示した従来
のジヤツキによる場合と同じく、ジヤツキ10を
構築物基礎の下面と増杭すべき所要の杭体aの頂
部との間に位置させ、ジヤツキ10のプランジヤ
を圧下させることにより構築物の重量を反力とし
て杭体aを地中に圧入して行くものであつて、そ
の操作は次のような順序で行われる。 The pile body press-in device according to the present invention has the above-mentioned configuration, and when using it, the jack 10 is connected to the lower surface of the structure foundation and the required number of piles to be increased, as in the case of the conventional jack shown in FIG. The pile body a is positioned between the pile body a and the top of the pile body a, and by lowering the plunger of the jack 10, the pile body a is pressed into the ground using the weight of the structure as a reaction force.The operation is as follows. done in the same order.
(1) 走行機構1により装置全体を所要場所に移動
停止させる;
(2) 伸縮支柱5を予め降下させておき、伸縮腕杆
9の人手によりプランジヤ4を中心軸として水
平面内に旋回させ、かつ油圧シリンダ7により
伸縮させてジヤツキ10を構築物基礎下面の所
要の場所に位置せしめる;
(3) 回転ハンドル12により伸縮腕杆9の突出度
を加減してジヤツキ10の上面を構築物基礎下
面の所要場所に位置決めし、次いで伸縮支柱5
を油圧シリンダ3によりジヤツキ10の上面が
基礎部下面に接触する迄上昇させる。この場
合、ジヤツキ10はスプリング11,11によ
つて吊下げられているので多少上げすぎてもジ
ヤツキ10および上昇装置がこわれることはな
い。(1) The entire device is moved to a desired location by the traveling mechanism 1 and stopped; (2) The telescoping column 5 is lowered in advance, and the telescoping arm 9 is manually rotated around the plunger 4 in a horizontal plane, and Position the jack 10 at a desired location on the bottom surface of the building foundation by expanding and contracting it with the hydraulic cylinder 7; (3) Adjust the degree of protrusion of the telescopic arm rod 9 using the rotary handle 12 to position the top surface of the jack 10 at the desired location on the bottom surface of the building foundation. and then the telescopic column 5
is raised by the hydraulic cylinder 3 until the upper surface of the jack 10 contacts the lower surface of the foundation. In this case, since the jack 10 is suspended by the springs 11, 11, the jack 10 and the lifting device will not be damaged even if the jack is raised a little too high.
(4) ジヤツキ10のプランジヤを上昇状態として
ジヤツキと地面との間に所要の杭体a(単位鋼
管)を位置させ、次でジヤツキのプランジヤを
少し下降させて杭体aの頂面に位置させたの
ち、ジヤツキ10を作動せしめ、構造物の重量
を反力として杭体aを地中に圧入する;
(5) 杭体aを頂部が少し地表に残る程度に迄圧入
したのち、ジヤツキ10のプランジヤを上昇
し、上記杭体の上に次の杭体(単位鋼管)を載
架し、載架部分周縁を溶接して圧入された鋼管
杭と一体になる如く接続したのち、ジヤツキ1
0のプランジヤを作動せしめ次の杭体を圧入さ
せる;
(6) 上記(4)と(5)の作業を順次繰返して多数接続さ
れた杭体を所要の深度に圧入させたのち、走行
機構1により装置全体を退去せしめ、構築物基
礎下面と杭体頂面との間にに鉄板・コンクリー
トブロツク等の固定材を挾着し掘削部分の埋め
戻しを行つて工事を完了する。(4) With the plunger of the jack 10 in the raised position, position the required pile body a (unit steel pipe) between the jack and the ground, then lower the plunger of the jack a little and position it on the top surface of the pile body a. After that, activate the jack 10 and press the pile body a into the ground using the weight of the structure as a reaction force; (5) Press the pile body a until the top remains slightly on the ground surface, and then press the jack 10. Raise the plunger, place the next pile body (unit steel pipe) on top of the above pile body, weld the periphery of the mounted part and connect it to the press-fitted steel pipe pile, and then
Activate the plunger 0 and press-fit the next pile body; (6) After repeating the steps (4) and (5) above in order to press-fit a large number of connected pile bodies to the required depth, move the traveling mechanism 1. The entire equipment is removed, fixed materials such as steel plates and concrete blocks are placed between the bottom of the structure's foundation and the top of the pile, and the excavated area is backfilled to complete the construction work.
本発明の杭体圧入装置は、以上説明したよう
に、走行機構1、伸縮支柱5、旋回自在の伸縮腕
杆9によりジヤツキ10の移動ならびに位置決め
が極めて容易であり、かつジヤツキ10は左右吊
バネ11,11により垂直方向に自由にかつ傾動
可能に吊設されているので、構築物基礎下面の傾
斜に倣つて位置させることができ、かつ作動時は
ジヤツキ10上面を構築物基礎下面に平均して圧
接保持させることができる。さらにジヤツキ10
を構築物基礎下面に送り込む操作が伸縮腕杆9の
伸縮および水平廻転により機械的に行われるため
作業上安全である等多くの利点がある。 As explained above, in the pile body press-fitting device of the present invention, the movement and positioning of the jack 10 is extremely easy due to the traveling mechanism 1, the telescoping column 5, and the rotatable telescoping arm 9, and the jack 10 is mounted on the left and right suspension springs. 11, 11 so that it can be freely and tilted in the vertical direction, it can be positioned to follow the slope of the lower surface of the structure's foundation, and when activated, the upper surface of the jack 10 is evenly pressed against the lower surface of the structure's foundation. can be retained. Furthermore, Jyatsuki 10
Since the operation of feeding the material to the lower surface of the construction foundation is performed mechanically by the extension and contraction and horizontal rotation of the telescopic arm rod 9, there are many advantages such as operational safety.
第1図は本発明による杭体圧入装置の側面図、
第2図は正面図、第3図は従来の工法における増
杭工事の説明図である。
図中符号:1は走行機構、2は台枠、5は伸縮
支柱、9は伸縮腕杆、10はジヤツキ、11は吊
バネ、aは杭体を示す。
FIG. 1 is a side view of a pile body press-in device according to the present invention;
Fig. 2 is a front view, and Fig. 3 is an explanatory diagram of pile increase work using the conventional construction method. Codes in the figure: 1 is a traveling mechanism, 2 is an underframe, 5 is a telescopic support, 9 is a telescopic arm, 10 is a jack, 11 is a suspension spring, and a is a pile body.
Claims (1)
該伸縮支柱の頂部に伸縮かつ旋回可能な伸縮腕杆
を設け、かつ該伸縮腕杆の先端に、その一端を構
造物基礎下面に接触させ他端を杭体の頂面に圧接
させるジヤツキを傾斜可能に取り付けたことを特
徴とする杭体圧入装置。1 A telescopic support is provided on the underframe with a traveling mechanism,
A telescoping arm that can be extended and rotated is provided at the top of the telescoping column, and a jack is provided at the tip of the telescoping arm to bring one end into contact with the lower surface of the structure foundation and the other end into pressure contact with the top surface of the pile body. A pile body press-in device characterized in that it can be installed.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12902582A JPS5921819A (en) | 1982-07-26 | 1982-07-26 | Pile penetrator |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12902582A JPS5921819A (en) | 1982-07-26 | 1982-07-26 | Pile penetrator |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5921819A JPS5921819A (en) | 1984-02-03 |
| JPS635529B2 true JPS635529B2 (en) | 1988-02-04 |
Family
ID=14999276
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP12902582A Granted JPS5921819A (en) | 1982-07-26 | 1982-07-26 | Pile penetrator |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5921819A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO1992004291A1 (en) * | 1990-09-05 | 1992-03-19 | Luxtron Corporation | Method of endpoint detection and structure therefor |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS59109450A (en) * | 1983-11-28 | 1984-06-25 | Honda Motor Co Ltd | Prevention of skid for car |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS4331640Y1 (en) * | 1965-02-17 | 1968-12-23 | ||
| JPS5925049B2 (en) * | 1980-07-31 | 1984-06-14 | 大晃工業株式会社 | Static load type pile driver |
-
1982
- 1982-07-26 JP JP12902582A patent/JPS5921819A/en active Granted
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO1992004291A1 (en) * | 1990-09-05 | 1992-03-19 | Luxtron Corporation | Method of endpoint detection and structure therefor |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5921819A (en) | 1984-02-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4278368A (en) | Apparatus and method for compacting material | |
| GB1582269A (en) | Pile handling tool and methods | |
| CN114991149A (en) | Municipal construction piling device with auxiliary supporting structure and method thereof | |
| CN111101500B (en) | A construction site rammer | |
| CN210975790U (en) | High-pressure rotary jet grouting drilling machine suitable for windy sand high slope | |
| CN115217122B (en) | Municipal pipeline protection structure and construction method thereof | |
| JPS635529B2 (en) | ||
| EP1963580B1 (en) | Foundation pile driver | |
| JP2003213686A (en) | How to build a retaining wall | |
| JP3177196B2 (en) | Method and apparatus for moving tubing mechanism | |
| CN214832554U (en) | Hydraulic rammer compactor for construction site | |
| CN214497521U (en) | High-pressure rotary jet pile machine | |
| JP2004003291A (en) | Self-propelled tubing device | |
| CN210341940U (en) | Steel sheet pile sinking construction device for foundation pit support | |
| JP3536033B2 (en) | Steel pipe pile press-in and pull-out machine | |
| US4502390A (en) | Self-elevating acute turn guide hose hauler vehicle | |
| JP2023089499A (en) | Mobile installation device for full-circumferential excavator | |
| KR102773014B1 (en) | Beam extractor | |
| JP2945595B2 (en) | Press fitting device for shaft shaft casing | |
| JP2619792B2 (en) | Pipe laying method | |
| CN220948124U (en) | Labor-saving moving device for steel pipe pile | |
| CN116290156B (en) | Miniature mining excavator | |
| JP2971813B2 (en) | Embedding member embedding device and embedded member clamping tool used in the device | |
| JP2657679B2 (en) | Self-propelled all casing construction machine | |
| JP3145627B2 (en) | Excavator for all casing method |