JPS642728B2 - - Google Patents

Info

Publication number
JPS642728B2
JPS642728B2 JP15260984A JP15260984A JPS642728B2 JP S642728 B2 JPS642728 B2 JP S642728B2 JP 15260984 A JP15260984 A JP 15260984A JP 15260984 A JP15260984 A JP 15260984A JP S642728 B2 JPS642728 B2 JP S642728B2
Authority
JP
Japan
Prior art keywords
partition
space
plate
plates
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP15260984A
Other languages
Japanese (ja)
Other versions
JPS6131521A (en
Inventor
Takeo Morita
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tekken Corp
Original Assignee
Tekken Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tekken Corp filed Critical Tekken Corp
Priority to JP15260984A priority Critical patent/JPS6131521A/en
Publication of JPS6131521A publication Critical patent/JPS6131521A/en
Publication of JPS642728B2 publication Critical patent/JPS642728B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 この発明は地中連続壁接合工法に関する。[Detailed description of the invention] The present invention relates to an underground continuous wall joining method.

地中連続壁は種々の地盤条件、施工条件等によ
り壁体の長さが限定され、そのため壁体を複数の
単位壁体から構成しなければならず、互いに隣接
する各単位壁体間には接合部が生じる。
The length of an underground continuous wall is limited by various ground conditions, construction conditions, etc. Therefore, the wall must be composed of multiple unit walls, and there is no space between each adjacent unit wall. A joint occurs.

従来、単位壁体間の接合工法としては、接合部
に仕切板を設置し、この仕切板の両側に先行およ
び後行単位壁体を構築するのが一般的であり、そ
の特殊な例として仕切板に連続した凹凸部を形成
し、先行および後行単位壁体が接合部において噛
み合うようにした工法がある。この工法は前記の
ような噛み合いにより、単位壁体間の応力伝達の
向上を意図したものであるが、仕切板の凹所に溜
まつた泥水によるスライムを除去するのが困難で
あり、そのためスライムが残置し、結果として単
位壁体どうしの一体化が確実になされないという
欠点があつた。
Conventionally, the common method for joining unit walls is to install a partition plate at the joint and construct leading and trailing unit walls on both sides of this partition plate. There is a construction method in which continuous uneven parts are formed on the board so that the leading and trailing unit walls interlock at the joints. This construction method is intended to improve stress transmission between unit walls through the interlocking described above, but it is difficult to remove the slime caused by muddy water that has accumulated in the recesses of the partition plate, and as a result, the slime As a result, there was a drawback that the unit walls could not be reliably integrated with each other.

この発明は上記のような従来工法の欠点を排除
し、仕切板に付着したスライムの除去を完全に行
うことができる地中連続壁接合工法を提供するこ
とを目的とする。すなわちこの発明は、同一垂直
面上に間隔を置いて配置され、かつ外側端縁間の
間隔が溝孔の巾とほぼ等しくなつている1対の外
方板と、両外方板の内側端縁に直交するように対
向して固着され、両側端部に係合部が形成された
1対の内方板とを有する仕切部材を具え、前記内
方板間に多数の支持杆を縦方向に亘つてじぐざぐ
に配列して固着し、これらの支持杆に骨材を通さ
ない程度の多数の網目を有する仕切網目板を順次
捲回して連続した凹凸部を形成し、前記仕切部材
に鉄筋籠と継手部材とをそれぞれ横向きに固着
し、前記鉄筋籠を前記外方板の1側面側に位置さ
せ、前記継手部材の継手部分を外方板の他側面側
に位置させてなる組立体をあらかじめ形成し、掘
削した先行溝孔に前記組立体を挿入設置し、それ
により先行溝孔を前記鉄筋籠が配置された第1空
間と、前記継手部分が配置された第2空間とに区
画し、次いで両側端部に係合部が形成された1対
の第1、第2仮仕切板をその係合部と前記内方板
の係合部とを係合させてこの内方板間に挿入設置
するとともに、前記第2空間に支持材を設置し、
次いで前記第1空間における第1仮仕切板と前記
仕切網目板との間に高圧水の噴出部材を挿入する
とともに、第2空間における第2仮仕切板と前記
仕切網目板との間に吸入部材を挿入し、前記噴出
部材から前記仕切網目板に向けて高圧水を噴射
し、それにより仕切網目板に付着したスライムを
前記吸入部材側に飛散させ、この吸入部材により
前記スライムを吸入除去しした後、前記噴出部材
を撤去し、次いで前記第1仮仕切板を撤去すると
ともに第1空間にコンクリートを打設硬化させて
先行単位壁体を構築し、次いで前記第2空間を含
む後行溝孔を掘削した後、この後行溝孔内に前記
と同様の組立体を挿入設置し、前記第2仮仕切板
を撤去するとともに、後行溝孔の第1空間にコン
クリートを打設硬化させて後行単位壁体を構築す
ることを特徴とする地中連続壁の接合工法にあ
る。
An object of the present invention is to provide an underground continuous wall joining method that eliminates the drawbacks of the conventional method as described above and can completely remove slime adhering to partition plates. That is, the present invention includes a pair of outer plates arranged at intervals on the same vertical plane and having a spacing between their outer edges approximately equal to the width of the slot, and inner edges of both outer plates. A partition member having a pair of inner plates fixed to face each other perpendicularly to the edge and having engaging portions formed at both ends thereof, and a plurality of support rods arranged longitudinally between the inner plates. A partition mesh board having a large number of meshes that does not allow the aggregate to pass through these supporting rods is sequentially wound to form a continuous uneven part, and reinforcing bars are attached to the partition member. A cage and a joint member are each fixed horizontally, the reinforcing bar cage is located on one side of the outer plate, and the joint part of the joint member is located on the other side of the outer plate. The assembly is inserted and installed in a pre-formed and excavated leading slot, thereby dividing the leading slot into a first space in which the reinforcing bar cage is arranged and a second space in which the joint portion is arranged. Next, a pair of first and second temporary partition plates each having an engaging portion formed at both end portions are engaged with the engaging portion of the inner plate to form a space between the inner plates. At the same time as inserting and installing, a support member is installed in the second space,
Next, a high-pressure water jetting member is inserted between the first temporary partition plate and the partition mesh plate in the first space, and a suction member is inserted between the second temporary partition plate and the partition mesh plate in the second space. was inserted, and high-pressure water was jetted from the jetting member toward the partition mesh plate, thereby scattering the slime adhering to the partition mesh plate to the suction member side, and the slime was sucked and removed by the suction member. After that, the ejection member is removed, the first temporary partition plate is removed, and concrete is cast and hardened in the first space to construct a leading unit wall, and then a trailing groove hole including the second space is constructed. After excavating, an assembly similar to the above is inserted into the trailing groove, the second temporary partition plate is removed, and concrete is poured into the first space of the trailing groove and allowed to harden. A method of joining an underground continuous wall characterized by constructing a trailing unit wall.

以下図面に示す一実施例について説明する。 An embodiment shown in the drawings will be described below.

第1、第2図に示すように、この発明工法に使
用する組立体1は仕切部材2を具え、この仕切部
材2は同一垂直面上に間隔を置いて配置された1
対の外方板3,3の内側端縁に、直交するように
1対の内方板4,4を対向して固着してなり、外
方板3の外側端縁間の間隔は溝孔の巾とほぼ等し
く、また内方板4,4はその内側端部が折曲さ
れ、それにより凸状の係合部5が形成されてい
る。
As shown in FIGS. 1 and 2, an assembly 1 used in the construction method of the present invention includes partition members 2, which are arranged at intervals on the same vertical plane.
A pair of inner plates 4, 4 are fixed to the inner edges of the pair of outer plates 3, 3 facing each other so as to be perpendicular to each other. The inner plates 4, 4 are bent at their inner ends, thereby forming a convex engaging portion 5.

内方板4,4間には多数の支持杆6が縦方向に
亘つて千鳥状に配列され、これらの支持杆6は両
端部に雄ねじ部を形成して、ナツト7により内方
板4,4に固着されている。支持杆6には骨材を
通さない程度の大きさの多数の網目を有する仕切
網目板8が順次捲回して固定され、それにより仕
切網目板8には連続した凹凸部9が形成されてい
る。図示の例では凹凸部9の先端は尖つている
が、支持杆6を階段状に配列し、凹凸部9の先端
を平坦としてもよい。
A large number of support rods 6 are arranged in a staggered manner in the vertical direction between the inner plates 4, 4, and these support rods 6 have male threads formed at both ends, and are connected to the inner plates 4, 4 by nuts 7. It is fixed to 4. A partition mesh plate 8 having a large number of meshes of a size that does not allow the aggregate to pass through is sequentially wound and fixed to the support rod 6, thereby forming continuous uneven portions 9 on the partition mesh plate 8. . In the illustrated example, the tips of the uneven portions 9 are sharp, but the support rods 6 may be arranged in a stepped manner, and the tips of the uneven portions 9 may be flat.

内方板4には多数の縦向鉄筋10と横向鉄筋1
1とを固着してなる鉄筋籠12および継手鉄筋1
3がそれぞれ横向きに固着され、鉄筋籠12は外
方板3の一側面側に位置し、継手鉄筋13の継手
部分13aは他側面側に位置している。次に上記
のような組立体を使用して地中連続壁接合工法に
ついて説明する。
The inner plate 4 has a large number of vertical reinforcing bars 10 and horizontal reinforcing bars 1.
1 and the reinforcing bar cage 12 and the joint reinforcing bar 1
3 are fixed laterally, the reinforcing bar cage 12 is located on one side of the outer plate 3, and the joint portion 13a of the joint reinforcing bar 13 is located on the other side. Next, an explanation will be given of an underground continuous wall joining method using the above-mentioned assembly.

まず第1、第2図に示すように地盤Eに掘削機
により先行溝孔14を掘削し、その際溝孔14に
は従来と同様に泥水を満たしながら掘削を行い、
壁面の崩壊を防ぐ。
First, as shown in FIGS. 1 and 2, a preliminary trench hole 14 is excavated in the ground E using an excavator, and at this time, the trench hole 14 is filled with muddy water as in the conventional method.
Prevent wall collapse.

次に溝孔14に組立体1を挿入設置し、それに
より溝孔14を鉄筋籠12が配置された第1空間
S1と継手鉄筋13の継手部分13aが配置された
第2空間S2とに区画する。そして内方板4,4間
に1対の第1、第2仮仕切板18a,18bを挿
入設置し、内方板4,4および第1、第2仮仕切
板18a,18bによつて区画されたボツクス状
の空間を形成する。第1、第2仮仕切板18a,
18bの両側端部には凹状の係合部17が形成さ
れ、その挿入の際は係合部17と内方板4の係合
部5とを係合させる。また第2空間S2には防護柵
15を設置して継手部分13aを覆い、さらにロ
ツキングパイプ16を設置して組立体1を支持す
る。
Next, the assembly 1 is inserted into the slot 14, thereby converting the slot 14 into the first space where the reinforcing bar cage 12 is placed.
It is divided into S 1 and a second space S 2 in which the joint portion 13a of the joint reinforcing bar 13 is arranged. Then, a pair of first and second temporary partition plates 18a and 18b are inserted and installed between the inner plates 4 and 4, and partitioned by the inner plates 4 and 4 and the first and second temporary partition plates 18a and 18b. It forms a box-like space. First and second temporary partition plates 18a,
Concave engaging portions 17 are formed at both end portions of 18b, and upon insertion, the engaging portions 17 and the engaging portions 5 of the inner plate 4 are engaged. A protective fence 15 is installed in the second space S2 to cover the joint portion 13a, and a locking pipe 16 is installed to support the assembly 1.

次に第1仮仕切板18aと仕切網目板8との間
に高圧水の噴出管19、第2仮仕切板18bと仕
切網目板8との間に吸入管20をそれぞれ挿入
し、噴出管19を上下に移動させながらまた先端
を回転させながら該先端から仕切網目板8に向け
て高圧水を噴射し、それにより仕切網目板8に付
着した泥水によるスライムを吸入管20側に飛散
させ、この吸入管20によりスライムを吸入して
除去する。高圧水としては清水を使用し、吸入管
20から清水が出てくるのを確認したらその作業
を終了する。またこのような仕切網目板8の清掃
作業を併行して内外方板3,4等の清掃作業も行
う。
Next, a high-pressure water ejection pipe 19 is inserted between the first temporary partition plate 18a and the partition mesh plate 8, and a suction pipe 20 is inserted between the second temporary partition plate 18b and the partition mesh plate 8. While moving up and down, and rotating the tip, high-pressure water is injected from the tip toward the partition mesh plate 8, thereby scattering the slime due to muddy water adhering to the partition mesh plate 8 to the suction pipe 20 side. The slime is sucked in and removed through the suction pipe 20. Clean water is used as the high-pressure water, and once it is confirmed that clean water is coming out of the suction pipe 20, the work is finished. In addition to the cleaning work of the partition mesh plate 8, the cleaning work of the inner and outer plates 3, 4, etc. is also performed.

次いで第3図に示すように、噴出管19を撤去
し、第1空間S1にコンクリートを打設して硬化さ
せ、先行単位壁体21を構築する。コンクリート
打設の際は第1仮仕切板18aの下端が、上昇す
るコンクリートヘツドよりも常時下方に位置する
ようにしながら、仮仕切板18aを徐々に上昇さ
せて撤去し、それによりコンクリート打設による
スライムの巻込みを防止する。
Next, as shown in FIG. 3, the ejection pipe 19 is removed, and concrete is poured into the first space S1 and hardened to construct the preceding unit wall 21. When placing concrete, the lower end of the first temporary partition plate 18a is always positioned below the rising concrete head, and the temporary partition plate 18a is gradually raised and removed. Prevents slime from getting caught.

上記のようにして先行単位壁体21を構築した
ら、ロツキングパイプ16を撤去し、第2空間S2
を含む後行溝孔22を掘削し、掘削終了後防護柵
15を撤去してこの後行溝孔22に前記と同様の
組立体(その鉄筋籠12のみ示す)を挿入設置す
る。そして第2仮仕切板18bと仕切網目板8と
の間に噴出管19および吸入管20の双方を挿入
し、噴出管19からの高圧水により仕切網目板8
に付着したスライムを飛散させ、このスライムお
よび先行単位壁体21のコンクリート打設の際に
仕切網目板8を通過したセメントペーストを吸入
管20により吸入して除去する。この時のスライ
ム量およびセメントペースト量は極く微少であ
り、このような清掃作業は必ずしも行わなくとも
よい。
After constructing the preceding unit wall 21 as described above, the locking pipe 16 is removed and the second space S 2
A trailing groove hole 22 including the following groove is excavated, and after the excavation is completed, the protective fence 15 is removed and an assembly similar to that described above (only the reinforcing bar cage 12 is shown) is inserted and installed into the trailing groove hole 22. Then, both the ejection pipe 19 and the suction pipe 20 are inserted between the second temporary partition plate 18b and the partition mesh plate 8, and the high pressure water from the ejection pipe 19 is applied to the partition mesh plate 8.
The slime adhering to the wall is scattered, and the slime and the cement paste that passed through the partition mesh plate 8 during the concrete placement of the preceding unit wall body 21 are sucked into the suction pipe 20 and removed. The amount of slime and cement paste at this time is extremely small, so such cleaning work does not necessarily have to be performed.

次いで第4、5図に示すように噴出管19およ
び吸入管20を撤去し、後行溝孔22の第1空間
S1にコンクリートを打設して硬化させ、後行単位
壁体23を構築する。コンクリート打設の際は、
第2仮仕切板18bを第1仮仕切板18のときと
同様に徐々に上昇させて撤去する。
Next, as shown in FIGS. 4 and 5, the ejection pipe 19 and the suction pipe 20 are removed, and the first space of the trailing slot 22 is opened.
Concrete is placed in S 1 and hardened, and the trailing unit wall 23 is constructed. When pouring concrete,
The second temporary partition plate 18b is gradually raised and removed in the same way as the first temporary partition plate 18.

以上のように単位壁体を順次構築して接合し、
接合部において単位壁体どうしが噛み合つた地中
連続壁を形成するものである。
As described above, unit walls are constructed and joined in sequence,
Unit walls interlock with each other at joints to form underground continuous walls.

この発明は上記のようであつて、仕切部材の内
方板間に連続した凹凸部を形成した仕切網目板を
設け、コンクリートの打設前に前記仕切網目板に
高圧水を噴射して付着したスライムを反対側に飛
散させ、このスライムを吸入管により吸入して除
去するので、仕切網目板の清掃が完全になされ、
とくにその凹部にスライムが残置することがな
く、単位壁体が互いに噛み合つて確実に一体化さ
れ、したがつて止水性に優れ、また応力伝達性に
優れた地中連続壁を構築できる。
This invention is as described above, in which a partition mesh plate with continuous uneven parts formed between the inner plates of the partition member is provided, and high-pressure water is sprayed onto the partition mesh plate to adhere to the partition mesh plate before concrete is poured. The slime is scattered to the other side, and the slime is sucked in and removed by the suction pipe, so the partition mesh plate is completely cleaned.
In particular, no slime remains in the recess, and the unit walls mesh with each other and are reliably integrated, making it possible to construct an underground continuous wall with excellent water-stopping properties and stress transmission properties.

【図面の簡単な説明】[Brief explanation of drawings]

図面はその発明工法の施工手順を示し、第1図
は組立体を先行溝孔に建込んだ状態を示す横断面
図、第2図は同上の縦断面図、第3図は先行単位
壁体を構築した状態を示す横断面図、第4図は後
行単位壁体を構築した状態を示す横断面図。第5
図は同上の縦断面図。 1…組立体、2…仕切部材、3…外方板、4…
内方板、5…係合部、6…支持杆、8…仕切網目
板、9…凹凸部、12…鉄筋籠、13…継手鉄
筋、13a…継手部分、14…先行溝孔、15…
防護柵、16…ロツキングパイプ、17…係合
部、18a…第1仮仕切板、18b…第2仮仕切
板、19…噴出管、20…吸入管、21…先行単
位壁体、22…後行溝孔、23…後行単位壁体。
The drawings show the construction procedure of the invented construction method; Fig. 1 is a cross-sectional view showing the assembly installed in the preceding groove, Fig. 2 is a longitudinal sectional view of the same, and Fig. 3 is the preceding unit wall. FIG. 4 is a cross-sectional view showing the state in which the trailing unit wall is constructed. Fifth
The figure is a longitudinal cross-sectional view of the same as above. 1... Assembly, 2... Partition member, 3... Outer plate, 4...
Inner plate, 5... Engagement part, 6... Support rod, 8... Partition mesh plate, 9... Uneven part, 12... Rebar cage, 13... Joint reinforcing bar, 13a... Joint part, 14... Leading slot, 15...
Protective fence, 16... Locking pipe, 17... Engaging portion, 18a... First temporary partition plate, 18b... Second temporary partition plate, 19... Ejection pipe, 20... Suction pipe, 21... Leading unit wall, 22... Trailing groove, 23... trailing unit wall.

Claims (1)

【特許請求の範囲】[Claims] 1 同一垂直面上に間隔を置いて配置され、かつ
外側端縁間の間隔が溝孔の巾とほぼ等しくなつて
いる1対の外方板と、両外方板の内側端縁に直交
するように対向して固着され、両側端部に係合部
が形成された1対の内方板とを有する仕切部材を
具え、前記内方板間に多数の支持杆を縦方向に亘
つてじぐざぐに配列して固着し、これらの支持杆
に骨材を通さない程度の多数の網目を有する仕切
網目板を順次捲回して連続した凹凸部を形成し、
前記仕切部材に鉄筋籠と継手部材とをそれぞれ横
向きに固着し、前記鉄筋籠を前記外方板の1側面
側に位置させ、前記継手部材の継手部分を外方板
の他側面側に位置させてなる組立体をあらかじめ
形成し、掘削した先行溝孔に前記組立体を挿入設
置し、それにより先行溝孔を前記鉄筋籠が配置さ
れた第1空間と、前記継手部分が配置された第2
空間とに区画し、次いで両側端部に係合部が形成
された1対の第1、第2仮仕切板をその係合部と
前記内方板の係合部とを係合させてこの内方板間
に挿入設置するとともに、前記第2空間に支持材
を設置し、次いで前記第1空間における第1仮仕
切板と前記仕切網目板との間に高圧水の噴出部材
を挿入するとともに、第2空間における第2仮仕
切板と前記仕切網目板との間に吸入部材を挿入
し、前記噴出部材から前記仕切網目板に向けて高
圧水を噴射し、それにより仕切網目板に付着した
スライムを前記吸入部材側に飛散させ、この吸入
部材により前記スライムを吸入除去しした後、前
記噴出部材を撤去し、次いで前記第1仮仕切板を
撤去するとともに第1空間にコンクリートを打設
硬化させて先行単位壁体を構築し、次いで前記第
2空間を含む後行溝孔を掘削した後、この後行溝
孔内に前記と同様の組立体を挿入設置し、前記第
2仮仕切板を撤去するとともに、後行溝孔の第1
空間にコンクリートを打設硬化させて後行単位壁
体を構築することを特徴とする地中連続壁の接合
工法。
1. A pair of outer plates spaced apart on the same vertical plane and with the spacing between their outer edges approximately equal to the width of the slot, and a pair of outer plates that are perpendicular to the inner edges of both outer plates. A partition member is provided with a pair of inner plates that are fixed to face each other and have engaging portions formed at both ends thereof, and a large number of support rods are vertically connected between the inner plates. Partition mesh plates are fixed in a jagged arrangement and have a large number of meshes that do not allow aggregate to pass through these support rods, and are sequentially wound to form a continuous uneven portion.
A reinforcing bar cage and a joint member are each fixed horizontally to the partition member, the reinforcing bar cage is located on one side of the outer plate, and the joint part of the joint member is located on the other side of the outer plate. An assembly is formed in advance, and the assembly is inserted and installed in a pre-excavated slot, thereby dividing the pre-slot into a first space where the rebar cage is placed and a second space where the joint portion is placed.
space, and then a pair of first and second temporary partition plates each having an engaging portion formed at both end portions are engaged with the engaging portion of the inner plate. At the same time, a support member is installed in the second space, and a high-pressure water jetting member is inserted between the first temporary partition plate and the partition mesh plate in the first space. , a suction member is inserted between the second temporary partition plate and the partition mesh plate in the second space, and high-pressure water is injected from the jetting member toward the partition mesh plate, thereby causing water to adhere to the partition mesh plate. After scattering the slime to the suction member side and sucking and removing the slime with the suction member, the spouting member is removed, and then the first temporary partition plate is removed and concrete is poured into the first space and hardened. Then, after excavating a trailing groove containing the second space, an assembly similar to that described above is inserted and installed in the trailing groove, and the second temporary partition plate is installed. At the same time, the first trailing groove
A method of joining underground continuous walls characterized by constructing a trailing unit wall by pouring concrete into a space and allowing it to harden.
JP15260984A 1984-07-23 1984-07-23 Joining method for underground continuous wall Granted JPS6131521A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15260984A JPS6131521A (en) 1984-07-23 1984-07-23 Joining method for underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15260984A JPS6131521A (en) 1984-07-23 1984-07-23 Joining method for underground continuous wall

Publications (2)

Publication Number Publication Date
JPS6131521A JPS6131521A (en) 1986-02-14
JPS642728B2 true JPS642728B2 (en) 1989-01-18

Family

ID=15544137

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15260984A Granted JPS6131521A (en) 1984-07-23 1984-07-23 Joining method for underground continuous wall

Country Status (1)

Country Link
JP (1) JPS6131521A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02108827U (en) * 1989-02-18 1990-08-29
JPH02141331U (en) * 1989-05-01 1990-11-28

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7250627B2 (en) * 2019-06-19 2023-04-03 ケミカルグラウト株式会社 Retaining wall construction method
JP7390909B2 (en) * 2020-01-30 2023-12-04 清水建設株式会社 Continuous underground walls and construction methods for continuous underground walls

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02108827U (en) * 1989-02-18 1990-08-29
JPH02141331U (en) * 1989-05-01 1990-11-28

Also Published As

Publication number Publication date
JPS6131521A (en) 1986-02-14

Similar Documents

Publication Publication Date Title
JPS642728B2 (en)
JP2942807B2 (en) Seismic retrofitting method for existing RC structures
JP3681314B2 (en) Water stop device used for small-scale continuous wall construction
KR100812845B1 (en) Device to facilitate removal of formwork
JP3620323B2 (en) How to renovate underground structures
JPH09228365A (en) Method and apparatus for cleaning steel material for underground wall
JPH11158865A (en) Underground structure having a wall made of steel sheet pile as core material and construction method thereof
JPH0551727B2 (en)
DE3632703A1 (en) Joint-shuttering element
JPH041811B2 (en)
JPS6358976B2 (en)
JP7499694B2 (en) Steel element installation equipment
JPH0517326B2 (en)
DE2616970B2 (en) Process and devices for the production of a diaphragm wall in a prefabricated composite construction
AT367130B (en) METHOD FOR PRODUCING A SLOT WALL IN THE GROUND FLOOR, FIRST POST-LIKE PRECAST CONCRETE PART, MOLDING BOX AND SECOND PLATE-SHAPED PRECAST CONCRETE PART FOR IMPLEMENTING THE METHOD
JPS61257530A (en) Underground continuous wall construction wall
JPH05179804A (en) Concrete placing joint method in reverse depositing
JP2987662B2 (en) How to build a continuous underground wall
JPS63125721A (en) Construction method of underground continuous wall and joints for connecting elements
JPH0430491B2 (en)
DE202026100926U1 (en) Flushing head for slurry wall grabber
DE29513952U1 (en) Brick with knobs on at least one outside
JPH07173830A (en) Partition member for continuous underground wall
JPS6138987Y2 (en)
JP2002081056A (en) Steel pipe sheet pile wall construction method