KR20200029078A - 보강부재와 scw공법을 이용한 자립식 흙막이 공법 - Google Patents
보강부재와 scw공법을 이용한 자립식 흙막이 공법 Download PDFInfo
- Publication number
- KR20200029078A KR20200029078A KR1020180106893A KR20180106893A KR20200029078A KR 20200029078 A KR20200029078 A KR 20200029078A KR 1020180106893 A KR1020180106893 A KR 1020180106893A KR 20180106893 A KR20180106893 A KR 20180106893A KR 20200029078 A KR20200029078 A KR 20200029078A
- Authority
- KR
- South Korea
- Prior art keywords
- pile
- cast
- eye beam
- double
- place concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
- E02D17/083—Shoring struts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
- E02D29/055—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/40—Miscellaneous comprising stabilising elements
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
도 2는 본 발명에 따른 더블 아이 빔이 포함된 현장타설 타입 흙막이용 파일을 도시한 사시도.
도 3은 본 발명에 따른 현장타설콘크리트 파일 및 더블 아이 빔이 포함된 현장타설콘크리트 파일 제작단계를 도시한 상태도.
도 4는 본 발명에 따른 부분 굴착단계를 도시한 상태도.
도 5는 자립식 흙막이용 파일 제작단계를 도시한 상태도.
도 6은 도 5에서 경사보강부재를 결합한 상태를 도시한 상태도.
도 7은 도 6에서 수직 저항 보강말뚝을 결합한 상태를 도시한 상태도.
도 8은 도 7에서 수직 저항 보강말뚝을 결합하는 다른 실시 예를 도시한 상태도.
도 9는 본 발명에 따른 더블 아이 빔이 포함된 현장타설 타입 흙막이용 파일의 작용상태를 도시한 상태도.
G1 : 지면 G2 : 터파기 지면 O : 터파기 공간
100 : 더블 아이 빔이 포함된 현장타설 타입 흙막이용 파일
10 : 더블 아이 빔이 포함된 현장타설콘크리트 파일
11 : 더블 아이 빔
11a : 제1판 11b : 제2판 11c : 제3판 11d : 제4판
12 : 콘크리트 13 : 제1 절개면 14 : 제2 절개면
A1 : 노출구간 A2 : 비노출구간
20 : 수평보강부재
30 : 경사보강부재
40 : 수직 저항 보강말뚝
Claims (7)
- 천공부위가 서로 겹쳐서 천공된 다수의 천공홀을 형성함과 동시에 시멘트를 분사 및 교반시키고, 다수의 천공홀 중 어느 하나의 천공홀에 더블 아이 빔을 근입시킨 후 양생하여 현장타설콘크리트 파일과 더블 아이 빔의 외측으로 콘크리트가 형성된 더블 아이 빔이 포함된 현장타설콘크리트 파일이 연속적으로 형성되도록 제작하는 현장타설콘크리트 파일 및 더블 아이 빔이 포함된 현장타설콘크리트 파일 제작단계;
상기 현장타설콘크리트 파일 및 더블 아이 빔이 포함된 현장타설콘크리트 파일 제작단계에서 제작한 더블 아이 빔이 포함된 현장타설콘크리트 파일 위치만을 계획된 터파기 지면까지 부분 굴착하는 부분 굴착단계;
상기 부분 굴착단계를 통해 노출된 각각의 더블 아이 빔이 포함된 현장타설콘크리트 파일에서 내부의 더블 아이 빔이 외부에 노출되도록 제1 절개면을 형성한 후 노출된 더블 아이 빔에 주동토압에 의한 저항이 발생하도록 터파기 공간 방향으로 연장된 수평보강부재를 결합하여 더블 아이 빔이 포함된 현장타설 타입 흙막이용 파일을 제작하는 자립식 흙막이용 파일 제작단계;를 포함하여 이루어진 것에 특징이 있는 보강부재와 SCW공법을 이용한 자립식 흙막이 공법.
- 제1항에 있어서, 상기 현장타설콘크리트 파일 및 더블 아이 빔이 포함된 현장타설콘크리트 파일 제작단계에서의 더블 아이 빔은 서로 마주보는 제1, 2판 사이에 제3, 4판이 결합하여 ㅍ자 형상의 단면으로 이루어지되 수직방향으로 연장되어 구성된 것에 특징이 있는 보강부재와 SCW공법을 이용한 자립식 흙막이 공법.
- 제1항에 있어서, 상기 자립식 흙막이용 파일 제작단계에서 더블 아이 빔이 포함된 현장타설콘크리트 파일의 제1 절개면은 수평보강부재의 하측면이 터파기 지면과 맞닿을 수 있는 위치에 형성되는 것에 특징이 있는 보강부재와 SCW공법을 이용한 자립식 흙막이 공법.
- 제1항에 있어서, 상기 자립식 흙막이용 파일 제작단계에서 더블 아이 빔이 포함된 현장타설콘크리트 파일에 형성된 제1 절개면의 상측으로 더블 아이 빔이 노출되도록 제2 절개면을 더 형성한 후, 제2 절개면에 의해 노출된 더블 아이 빔과 수평보강부재에 경사지게 결합하는 경사보강부재를 더 결합하는 것에 특징이 있는 보강부재와 SCW공법을 이용한 자립식 흙막이 공법.
- 제1항에 있어서, 상기 자립식 흙막이용 파일 제작단계에서 수평보강부재에는 터파기 지면에 근입되는 수직 저항 보강말뚝이 더 결합되는 것에 특징이 있는 보강부재와 SCW공법을 이용한 자립식 흙막이 공법.
- 제5항에 있어서, 상기 자립식 흙막이용 파일 제작단계에서 수직 저항 보강말뚝은 수평보강부재를 더블 아이 빔이 포함된 현장타설콘크리트에 결합하기 전에 터파기 지면에 근입한 후 수평보강부재를 더블 아이 빔이 포함된 현장타설콘크리트 파일과 수직 저항 보강말뚝에 결합하는 것에 특징이 있는 보강부재와 SCW공법을 이용한 자립식 흙막이 공법.
- 제5항에 있어서, 상기 자립식 흙막이용 파일 제작단계에서 수직 저항 보강말뚝은 더블 아이 빔이 포함된 현장타설콘크리트 파일에 수평보강부재를 결합한 후 수직 저항 보강말뚝을 수평보강부재의 단부에 결합할 수 있는 위치의 터파기 지면에 근입한 후 수직 저항 보강말뚝을 결합하는 것에 특징이 있는 보강부재와 SCW공법을 이용한 자립식 흙막이 공법.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020180106893A KR102194394B1 (ko) | 2018-09-07 | 2018-09-07 | 보강부재와 scw공법을 이용한 자립식 흙막이 공법 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020180106893A KR102194394B1 (ko) | 2018-09-07 | 2018-09-07 | 보강부재와 scw공법을 이용한 자립식 흙막이 공법 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| KR20200029078A true KR20200029078A (ko) | 2020-03-18 |
| KR102194394B1 KR102194394B1 (ko) | 2020-12-24 |
Family
ID=69999247
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| KR1020180106893A Active KR102194394B1 (ko) | 2018-09-07 | 2018-09-07 | 보강부재와 scw공법을 이용한 자립식 흙막이 공법 |
Country Status (1)
| Country | Link |
|---|---|
| KR (1) | KR102194394B1 (ko) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111455990A (zh) * | 2020-05-14 | 2020-07-28 | 中建四局华南建设有限公司 | 一种三轴水泥搅拌桩机施工桩位精准定位装置及定位方法 |
| CN116770810A (zh) * | 2023-05-04 | 2023-09-19 | 中交第二航务工程局有限公司 | 地连墙用钢筋笼匹配制造及高精度安装施工方法 |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0460022A (ja) * | 1990-06-28 | 1992-02-26 | Okumura Corp | 土留方法とその土留杭 |
| JPH06116942A (ja) * | 1992-08-20 | 1994-04-26 | Kajima Corp | 自立山留壁の構築法 |
| JP2000045282A (ja) * | 1998-07-27 | 2000-02-15 | Takenaka Komuten Co Ltd | 斜杭からなる組杭による山留め工法 |
| KR20140055639A (ko) * | 2012-11-01 | 2014-05-09 | 이전우 | 흙막이 겸용 건축빔 구조체의 시공방법 및 그 방법에 의하여 시공된 건축빔 구조체 |
| JP3209590U (ja) * | 2017-01-13 | 2017-03-30 | ジェコス株式会社 | 箱形断面溶接切梁 |
-
2018
- 2018-09-07 KR KR1020180106893A patent/KR102194394B1/ko active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0460022A (ja) * | 1990-06-28 | 1992-02-26 | Okumura Corp | 土留方法とその土留杭 |
| JPH06116942A (ja) * | 1992-08-20 | 1994-04-26 | Kajima Corp | 自立山留壁の構築法 |
| JP2000045282A (ja) * | 1998-07-27 | 2000-02-15 | Takenaka Komuten Co Ltd | 斜杭からなる組杭による山留め工法 |
| KR20140055639A (ko) * | 2012-11-01 | 2014-05-09 | 이전우 | 흙막이 겸용 건축빔 구조체의 시공방법 및 그 방법에 의하여 시공된 건축빔 구조체 |
| JP3209590U (ja) * | 2017-01-13 | 2017-03-30 | ジェコス株式会社 | 箱形断面溶接切梁 |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111455990A (zh) * | 2020-05-14 | 2020-07-28 | 中建四局华南建设有限公司 | 一种三轴水泥搅拌桩机施工桩位精准定位装置及定位方法 |
| CN116770810A (zh) * | 2023-05-04 | 2023-09-19 | 中交第二航务工程局有限公司 | 地连墙用钢筋笼匹配制造及高精度安装施工方法 |
Also Published As
| Publication number | Publication date |
|---|---|
| KR102194394B1 (ko) | 2020-12-24 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101014796B1 (ko) | 기성 콘크리트 기둥부재를 이용한 탑다운 시공방법 | |
| KR102195504B1 (ko) | 보강부재와 cip공법을 이용한 자립식 흙막이 공법 | |
| KR100866162B1 (ko) | 의자형 자립식 흙막이벽의 시공방법 | |
| KR20100068597A (ko) | 아치형 강판파일과 H-Pile을 이용한 흙막이공법 | |
| JP2012107479A (ja) | 地下・地上構造物の施工方法 | |
| JP2013256793A (ja) | 地下構造の施工方法及び地下構造 | |
| KR20100065521A (ko) | 아치형 강판파일과 H-Pile을 이용한 흙막이공법 | |
| KR102195510B1 (ko) | 보강부재와 phc파일을 이용한 자립식 흙막이 공법 | |
| JP2007051541A (ja) | 擁壁及びその施工方法 | |
| JP2000352296A (ja) | 地下構造物直下の通路の形成方法 | |
| KR102396786B1 (ko) | 기존 지하 외벽의 보강을 통한 신설 건물의 지하 증축 및 역타 공법 | |
| KR101843023B1 (ko) | 흙막이벽체파일과 건축물외부벽체 연결전단키 및 이를 이용한 지하구조물 시공방법 | |
| JP6860895B2 (ja) | 擁壁及びその施工方法 | |
| KR102194394B1 (ko) | 보강부재와 scw공법을 이용한 자립식 흙막이 공법 | |
| KR102195496B1 (ko) | 더블 아이 빔이 포함된 현장타설콘크리트 파일을 이용한 자립식 흙막이용 파일 | |
| KR102194381B1 (ko) | 더블 아이 빔을 이용한 자립식 흙막이용 파일 | |
| KR102277470B1 (ko) | 흙막이 지하 합성벽 및 그 시공 방법 | |
| KR100831332B1 (ko) | 토목공사용 지하 흙막이벽 및 그의 시공방법 | |
| JP2868651B2 (ja) | 地下既設構造物上方における山留工法 | |
| KR20050113450A (ko) | 가설보조기둥을 이용한 철근콘크리트 역타설 지하구조물축조 공법 | |
| JP2003268770A (ja) | 土留工法並びにこの工法に使用する矢板の補強構造体 | |
| KR100429283B1 (ko) | Pc부재를 이용한 지하연속벽 시공방법 | |
| KR102194388B1 (ko) | 보강부재와 토류판공법 이용한 자립식 흙막이 공법 | |
| KR100327547B1 (ko) | 가설흙막이벽을영구구조물로활용하는지하옹벽구축방법 | |
| JP7275844B2 (ja) | 壁状構造物及び壁状構造物の構築方法 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PA0109 | Patent application |
St.27 status event code: A-0-1-A10-A12-nap-PA0109 |
|
| PA0201 | Request for examination |
St.27 status event code: A-1-2-D10-D11-exm-PA0201 |
|
| R17-X000 | Change to representative recorded |
St.27 status event code: A-3-3-R10-R17-oth-X000 |
|
| D13-X000 | Search requested |
St.27 status event code: A-1-2-D10-D13-srh-X000 |
|
| D14-X000 | Search report completed |
St.27 status event code: A-1-2-D10-D14-srh-X000 |
|
| E902 | Notification of reason for refusal | ||
| PE0902 | Notice of grounds for rejection |
St.27 status event code: A-1-2-D10-D21-exm-PE0902 |
|
| PG1501 | Laying open of application |
St.27 status event code: A-1-1-Q10-Q12-nap-PG1501 |
|
| T11-X000 | Administrative time limit extension requested |
St.27 status event code: U-3-3-T10-T11-oth-X000 |
|
| E13-X000 | Pre-grant limitation requested |
St.27 status event code: A-2-3-E10-E13-lim-X000 |
|
| P11-X000 | Amendment of application requested |
St.27 status event code: A-2-2-P10-P11-nap-X000 |
|
| P13-X000 | Application amended |
St.27 status event code: A-2-2-P10-P13-nap-X000 |
|
| E701 | Decision to grant or registration of patent right | ||
| PE0701 | Decision of registration |
St.27 status event code: A-1-2-D10-D22-exm-PE0701 |
|
| GRNT | Written decision to grant | ||
| PR0701 | Registration of establishment |
St.27 status event code: A-2-4-F10-F11-exm-PR0701 |
|
| PR1002 | Payment of registration fee |
St.27 status event code: A-2-2-U10-U11-oth-PR1002 Fee payment year number: 1 |
|
| PG1601 | Publication of registration |
St.27 status event code: A-4-4-Q10-Q13-nap-PG1601 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 4 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 5 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 6 |
|
| U11 | Full renewal or maintenance fee paid |
Free format text: ST27 STATUS EVENT CODE: A-4-4-U10-U11-OTH-PR1001 (AS PROVIDED BY THE NATIONAL OFFICE) Year of fee payment: 6 |