OA21411A - New technical-ecological process for building construction based on cement block or treated laterite. - Google Patents

New technical-ecological process for building construction based on cement block or treated laterite. Download PDF

Info

Publication number
OA21411A
OA21411A OA1202300396 OA21411A OA 21411 A OA21411 A OA 21411A OA 1202300396 OA1202300396 OA 1202300396 OA 21411 A OA21411 A OA 21411A
Authority
OA
OAPI
Prior art keywords
blocks
cement
concrete
building construction
laterite
Prior art date
Application number
OA1202300396
Other languages
French (fr)
Inventor
Mawuko BOLOUVI
Original Assignee
Mawuko BOLOUVI
Filing date
Publication date
Application filed by Mawuko BOLOUVI filed Critical Mawuko BOLOUVI
Publication of OA21411A publication Critical patent/OA21411A/en

Links

Abstract

La présente invention a pour objet un nouveau procédé technico-écologique de construction de bâtiment à base de bloc de ciment et ou en latérite traité. On sait que la construction de bâtiment moderne conformément aux règles de l'art relève beaucoup de défis qu'il convient de résoudre. Le nouveau procédé technico-écologique de construction de bâtiment à base de blocs en ciment ou latérite traité (Planche I) objet de l'invention est constitué de deux phases à savoir : - Composition et méthode de fabrication Les blocs sont fabriqués à base de béton de ciment composé de 70 % d'élément fin de granulométrie 0/3 et 30% de granulats de granulométrie 3/8. Le béton est dosé à 250 kg/m3 . Il est conseillé de mouler les blocs par presse à l'aide d'une pondeuse de brique industrielle. Le produit fini doit donner après séchage un parement très lisse. De géo béton composé de 90% de la latérite fin et de 10% de ciment pour la stabilisation. L'utilisation d'un moule introduit dans une presse manuelle ou électrique est recommandée pour la production des dits blocs. - Techniques d'assemblage La méthode d'assemblage est fonction de la nature des éléments qui composent le bâtiment à construire. <img file="OA21411A_A0001.tif"/> <img file="OA21411A_A0002.tif"/> <img file="OA21411A_A0003.tif"/> Planche I / XIThe present invention relates to a new technical-ecological process for building construction based on cement blocks and/or treated laterite. It is known that modern building construction in accordance with the rules of the art raises many challenges that need to be resolved. The new technical-ecological process for building construction based on cement blocks or treated laterite (Plate I) which is the subject of the invention consists of two phases, namely: - Composition and manufacturing method The blocks are made from cement concrete composed of 70% fine element with a grain size of 0/3 and 30% aggregates with a grain size of 3/8. The concrete is dosed at 250 kg/m3. It is advisable to mold the blocks by press using an industrial brick layer. The finished product must give a very smooth facing after drying. Geo-concrete composed of 90% fine laterite and 10% cement for stabilization. The use of a mold inserted into a manual or electric press is recommended for the production of said blocks. - Assembly techniques The assembly method depends on the nature of the elements that make up the building to be constructed. <img file="OA21411A_A0001.tif"/> <img file="OA21411A_A0002.tif"/> <img file="OA21411A_A0003.tif"/> Plate I / XI

Description

La présente invention a pour objet un nouveau procédé technico-écologique de construction de bâtiment à base de bloc de ciment et ou en latérite traité.The subject of the present invention is a new technical-ecological process for constructing buildings based on cement blocks and/or treated laterite.

On sait que la construction de bâtiment moderne conformément aux règles de l'art relève beaucoup de défis qu'il convient de résoudre :We know that the construction of modern buildings in accordance with the rules of the art raises many challenges that must be resolved:

I Problèmes que l'invention cherche à résoudreI Problems that the invention seeks to solve

Les problèmes techniques identifiés concernent :The technical problems identified concern:

- l'aspect structurel des constructions actuelles qui ne présentent pas une garantie technique due aux faibles enrobages en fer des bâtiments.- the structural aspect of current constructions which do not present a technical guarantee due to the weak iron coatings of the buildings.

- La finition de l'ouvrage qui laisse souvent à désirer et qu'on remarque au niveau du 10 crépissage, et des nombreuses reprises à faire pour des bavures du béton ou des mortiers.- The finish of the work which often leaves something to be desired and which is noted in the plastering, and the numerous repairs to be made for burrs in the concrete or mortars.

- L'utilisation de beaucoup de bois pour le coffrage avec le problème de l'impact sur l'environnement forestier.- The use of a lot of wood for the formwork with the problem of the impact on the forest environment.

- La durée de construction trop longue liée aux travaux de coffrage et de finition.- The excessively long construction period linked to formwork and finishing work.

15 - Un autre problème non moins technique peut également être évoqué tel que le cout élevé de la construction finale. 15 - Another no less technical problem can also be mentioned such as the high cost of the final construction.

Il Etat de la techniqueState of the art

L'investigation des sources d'informations scientifiques et techniques dans le domaine de l'invention a permis d'identifier et de lister les supports ci-après.The investigation of sources of scientific and technical information in the field of the invention made it possible to identify and list the following supports.

20 A/ en matière de publication :2 0 A/ regarding publication:

- Livres- Books

- LA TECHNIQUE DU BATIMENT TOUT CORPS D'ETAT (AUTEURS : DANIEL MONTHARRY ET MICHEL PATZER)- THE TECHNIQUE OF BUILDING ALL STATES (AUTHORS: DANIEL MONTHARRY AND MICHEL PATZER)

- LA CONSTRUCTION COMMENT CA MARCHE ? (AUTEURS : ALAIN BOUTEVEILLE ET 25 URSULA BOUTEVEILLE- CONSTRUCTION, HOW DOES IT WORK ? (AUTHORS: ALAIN BOUTEVEILLE AND 25 URSULA BOUTEVEILLE

- Revues- Journals

- REVUES DU SECTEUR DU BATIMENT EN COTE D'IVOIRE, version finale 14 AVRIL 2017 (AUTEUR : SILVIO GIROUD, FELIX BOILEVE, JACQUES OTRO)- REVIEWS OF THE BUILDING SECTOR IN IVORY COAST, final version APRIL 14, 2017 (AUTHOR: SILVIO GIROUD, FELIX BOILEVE, JACQUES OTRO)

- DP135_GUIDE DE BONNES PRATIQUES MAÇONNERIE (CERIB Expertise concrète / FIB :- DP135_GUIDE OF GOOD MASONRY PRACTICES (CERIB Concrete expertise / FIB:

Fédération de l'industrie du béton)Concrete Industry Federation)

- Sites internet- Websites

- www.smart-systemes-beton.fr- www.smart-systemes-beton.fr

- https://www.abc-maconnerie.com/technologie/- https://www.abc-maconnerie.com/technologie/

- https://www.youtube.com/watch?v=uBF-n8oF8gU- https://www.youtube.com/watch?v=uBF-n8oF8gU

B/ Brevet d'inventionB/ Patent of invention

29791172979117

PROCEDE DE FABRICATION D'UN BLOC DE BETON MOULE ET BLOC AINSI OBTENUMETHOD FOR MANUFACTURING A MOLDED CONCRETE BLOCK AND BLOCK THUS OBTAINED

FR-22.02.2013FR-22.02.2013

CIB E04C %IPC E04C %

N° de demande 1157412Application No. 1157412

Déposant FABEMI GESTIONDepositor FABEMI GESTION

Inventeur DUMONT PIERREInventor DUMONT PIERRE

Procédé de fabrication d'un bloc de béton moulé de maçonnerie (1) consistant notamment à injecter du béton à l'intérieur d'un moule pour obtenir au moins un bloc en forme de parallélépipède creux comportant deux parois de parement (2) s'étendant parallèlement entre elles et reliées par au moins une entretoise (3), caractérisé en ce qu'il consiste à injecter dans le moule, au moins un premier type de béton (I) pour réaliser les parois de parement (2) et au moins un deuxième type de béton (II) pour réaliser les entretoises (3), le premier type de béton (I) possédant une conductivité thermique différente de la conductivité thermique du deuxième type de béton (II).Method for manufacturing a molded concrete masonry block (1) consisting in particular of injecting concrete inside a mold to obtain at least one block in the shape of a hollow parallelepiped comprising two facing walls (2) extending parallel to each other and connected by at least one spacer (3), characterized in that it consists of injecting into the mold, at least a first type of concrete (I) to produce the facing walls (2) and at least a second type of concrete (II) for making the spacers (3), the first type of concrete (I) having a thermal conductivity different from the thermal conductivity of the second type of concrete (II).

24205132420513

PROCEDE DE FABRICATION DE BLOCS DE BETON PRESENTANT UNE SURFACE 20 CORRESPONDANT A LA SURFACE NATURELLE DU GRESMETHOD FOR MANUFACTURING CONCRETE BLOCKS HAVING A SURFACE 20 CORRESPONDING TO THE NATURAL SURFACE OF SANDSTONE

FR-19.10.1979FR-19.10.1979

CIB B28B 1/16CIB B28B 1/16

N° de demande 7907723Application No. 7907723

Déposant KRONIMUS BETONSTEApplicant KRONIMUS BETONSTE

INWERKInventeurINWERKInventor

La présente invention concerne un procédé de fabrication de blocs de béton présentant une surface correspondant à la surface naturelle du grès.The present invention relates to a method of manufacturing concrete blocks having a surface corresponding to the natural surface of sandstone.

Procédé caractérisé en ce que dans un moule approprié, on introduit tout d'abord une couche d'un mélange de béton, de sable quartzeux et d'un colorant correspondant à la couleur de la 30 surface de grès désirée et qu'ensuite, on applique sur ce mélange un autre mélange de béton, de sable de moindre qualité, de gravillon ou de gravier, après quoi, on dame et on vibre le contenu du moule et qu'après le démoulage et la prise, on fait passer les pièces présentant la surface de grès à reproduire, à travers un appareil de grenaillage ou de sablage.Process characterized in that in a suitable mold, a layer of a mixture of concrete, quartz sand and a dye corresponding to the color of the desired sandstone surface is first introduced and then, applies to this mixture another mixture of concrete, sand of lesser quality, gravel or gravel, after which the contents of the mold are rammed and vibrated and after unmolding and setting, the pieces presenting the sandstone surface to be reproduced, through a shot blasting or sandblasting device.

L'invention est plus particulièrement adaptable à la fabrication de pierres artificielles. WO/2022/223845.The invention is more particularly adaptable to the manufacture of artificial stones. WO/2022/223845.

BLOC DE CONSTRUCTION POUR LA FABRICATION D'UN BATIMENT ET PROCÉDÉ DE FABRICATION D'UN BATIMENTWO - 27.10.2022BUILDING BLOCK FOR MANUFACTURING A BUILDING AND METHOD FOR MANUFACTURING A BUILDINGWO - 10/27/2022

Cl B E04B 1/14Cl B E04B 1/14

N° de demande PCT/EP2022/060936Application No. PCT/EP2022/060936

Déposant NOCA, LaurentNOCA Applicant, Laurent

Inventeur NOCA, LaurentInventor NOCA, Laurent

Un bloc de construction (1) pour la fabrication d'un bâtiment (2) comporte un plancher (3) et des murs (4). Un des murs (4) comporte une réservation traversant. Les murs (4) sont fixés au plancher (3) et entre eux. Le plancher (3) comporte un support réalisé en béton-bois et il définit des rainures. Une armature métallique formée par une pluralité de tiges métalliques est disposée dans les rainures. Au moins des premières tiges métalliques font saillies aux extrémités de premières rainures. Un béton remplit les rainures et recouvre complètement l'armature métallique et le support. Les murs (4) sont réalisés en béton-bois et définissent sur leur paroi externe une rainure verticale s'étendant sur la hauteur des murs (4) et débouchant sur les premières tiges métalliques en saillie du support.A building block (1) for manufacturing a building (2) has a floor (3) and walls (4). One of the walls (4) has a crossing reservation. The walls (4) are fixed to the floor (3) and to each other. The floor (3) has a support made of concrete-wood and it defines grooves. A metal frame formed by a plurality of metal rods is arranged in the grooves. At least first metal rods protrude from the ends of first grooves. Concrete fills the grooves and completely covers the metal frame and the support. The walls (4) are made of concrete-wood and define on their external wall a vertical groove extending over the height of the walls (4) and opening onto the first metal rods projecting from the support.

L'analyse des informations tirées des supports de l'état de la technique ci-dessus n'a pas permis de trouver des solutions aux problèmes techniques évoqués contrairement à l'objet de la présente invention un nouveau procédé technico-écologique de construction de bâtiment à base de bloc de ciment et ou en latérite traité.The analysis of the information taken from the state of the art media above did not make it possible to find solutions to the technical problems mentioned contrary to the object of the present invention a new technical-ecological process for building construction based on cement block and or treated laterite.

III DescriptionIII Description

Le nouveau procédé technico-écologique de construction de bâtiment à base de blocs en ciment ou latérite (Planche I) traité objet de l'invention est constitué de deux phases à savoir : 1) Composition et méthode de fabricationThe new technical-ecological process for building construction based on cement or laterite blocks (Plate I) treated as the subject of the invention consists of two phases, namely: 1) Composition and manufacturing method

Les blocs sont fabriqués à base :The blocks are made based on:

❖ De béton de ciment composé de 70 % d'élément fin de granulométrie 0/3 et 30% de granulats de granulométrie 3/8. Le béton est dosé à 250 kg /m3. Il est conseillé de mouler les blocs par presse à l'aide d'une pondeuse de brique industrielle. Le produit fini doit donner après séchage un parement très lisse.❖ Cement concrete composed of 70% fine element with a grain size of 0/3 and 30% aggregates with a grain size of 3/8. The concrete is dosed at 250 kg/m3. It is recommended to mold the blocks by press using an industrial brick laying machine. The finished product should give a very smooth surface after drying.

❖ De géo béton composé de 90% de la latérite fin et de 10% de ciment pour la stabilisation.❖ Geo concrete composed of 90% fine laterite and 10% cement for stabilization.

L'utilisation d'un moule introduit dans une presse manuelle ou électrique est recommandée pour la production des dits blocs.The use of a mold introduced into a manual or electric press is recommended for the production of said blocks.

2) TECHNIQUES D'ASSEMBLAGE2) ASSEMBLY TECHNIQUES

La méthode d'assemblage est fonction de la nature des éléments qui composent le bâtiment à construire.The assembly method depends on the nature of the elements that make up the building to be constructed.

2.1 ASSEMBLAGE DES BLOCS POUR UN MUR CONTINU (planche II)2.1 ASSEMBLY OF BLOCKS FOR A CONTINUOUS WALL (Plate II)

Les blocs BRS (bloc de remplissage standard) sont utilisés pour l'assemblage des murs continus Ils sont disposés dans le sens de la longueur en quinconce.BRS blocks (standard infill block) are used for assembling continuous walls. They are arranged lengthwise in a staggered pattern.

Les abouts formant les demis cercle sont collés Γ u n contre l'autre formant une éprouvette cylindrique qui sera rempli e du béton ou du mortier légèrement fluide afin d'assurer la stabilité du mur.The ends forming the semi-circles are glued against each other forming a cylindrical test piece which will be filled with concrete or slightly fluid mortar to ensure the stability of the wall.

2.2 ASSEMBLAGE DES BLOCS POUR UN MUR D'ANGLE (Planche III)2.2 ASSEMBLY OF BLOCKS FOR A CORNER WALL (Plate III)

Le montage des murs d'angle est composé d'un bloc tableau (BT) et d'un bloc BRS.The corner wall assembly is made up of a panel block (BT) and a BRS block.

La partie pleine du bloc BT est disposée dans le premier sens et la partie creuse du bloc BRS est disposée dansle sens inverse buter contre le BT formant un angle de 90 degrés. La partie creuse buté contre le BT sera remplie par le béton ou le mortier fluide en qualité du liant.The solid part of the BT block is arranged in the first direction and the hollow part of the BRS block is arranged in the opposite direction abutting against the BT forming an angle of 90 degrees. The hollow part abutting against the BT will be filled with concrete or fluid mortar as a binder.

2.3 ASSEMBLAGE DES BLOCKS POUR UN MUR CROISE (Planche IV)2.3 ASSEMBLY OF BLOCKS FOR A CROSS WALL (Plate IV)

Il existe deux catégories de murs croisésThere are two categories of cross walls

2.3.1 Mur croisé en T2.3.1 T-shaped cross wall

2.3.2 Mur croisé en croie2.3.2 Cross wall

Les murs croisés en T sont réalisés par les blocs BT et les blocs BRS.The T-shaped cross walls are made by BT blocks and BRS blocks.

Dans ce premier cas, les parties pleines des blocs BT sont apparentes et les parties creuses des blocs BRS sont butées contre une partie du bloc BT dans le sens contraire formant un angle de 90 degrés.In this first case, the solid parts of the BT blocks are visible and the hollow parts of the BRS blocks abut against a part of the BT block in the opposite direction forming an angle of 90 degrees.

La partie creuse butée contre le BT sera remplie du béton ou de mortier fluide.Dans le second cas (mur croisé en croix), seuls les blocs BRS sont utilisés.The hollow part abutting against the BT will be filled with concrete or fluid mortar. In the second case (cross wall), only BRS blocks are used.

Un rangé de bloc BRS est disposée dans le premier sens et une seconde rangé dans l'a utre sens formant une croix. Les parties creuse des BRS sont butés contre les parties pleines conformément à la planche ci jointe.A row of BRS blocks is arranged in the first direction and a second row in the other direction forming a cross. The hollow parts of the BRS are butted against the solid parts in accordance with the attached board.

2.4 ASSEMBLAGE DES BLOCS POUR UN POTEAU D'ANGLE (Planche V)2.4 ASSEMBLY OF BLOCKS FOR A CORNER POST (Plate V)

Le montage des poteaux d'angle nécessite l'utilisation des blocs embouts, les blocs de poteau x standard(BPS) et les blocs de remplissage standards (BRS) conformément aux images ci-dessous.Mounting the corner posts requires the use of End Blocks, Standard x Post Blocks (BPS) and Standard Filler Blocks (BRS) as per the images below.

Le bloc BPS est posé premièrement pour encadrer les armatures du poteau, la partie ouverte de ' PBS est dirigé vers l'extérieur et la partie fermée est dirigé dans l'alignement du mu continu.The BPS block is placed first to frame the post reinforcements, the open part of the PBS is directed outwards and the closed part is directed in alignment with the continuous wall.

La partie ouverte du BPS est fermée par la grande longueur du bloc about (BA) et la petite longueur du BA est dirigée dans l'autie alignement du mur et l'ensemble forme un mur d'angle droit.The open part of the BPS is closed by the long length of the about block (BA) and the short length of the BA is directed in the other alignment of the wall and the whole forms a right corner wall.

Les parties creuses sont toujours fermée par les du béton ou du mortier fluide.The hollow parts are always closed with concrete or fluid mortar.

Les mêmes opérations se reproduisent en ver le haut en disposant les blocs en quinconce.The same operations are repeated upwards by arranging the blocks in a staggered pattern.

2.5 MONTAGE DES BLOCS POUR UN POTEAUX DANS L'ALLIGNEMENT DU MUR (Planche VI)2.5 ASSEMBLY OF BLOCKS FOR A POSTS IN LINE WITH THE WALL (Plate VI)

Le montage des blocs pour les poteaux dans l'alignement des murs nécessite l'utilisation des blocs BRS et les blocs BPS.Mounting the blocks for the posts in alignment with the walls requires the use of BRS blocks and BPS blocks.

Dans l'alignement du mur, on positionne premièrement le BPS pour encadrer les armatures des poteaux Ensuite on pose les blocs BR S de part et d'autre formant une ligne droite.In alignment with the wall, we first position the BPS to frame the post reinforcements. Then we place the BR S blocks on either side forming a straight line.

Les partie creuses sont toujours fermée par les du béton ou du mortier fluide.The hollow parts are always closed with concrete or fluid mortar.

Les mêmes opérations se reproduisent en ver le haut en disposant les blocs en quinconceThe same operations are repeated upwards by arranging the blocks in a staggered pattern.

2.6 MONTAGE DES BLOCS POUR UN POTEAUX DANS LE CROISEMENT DES MURS (Planche VII)2.6 ASSEMBLY OF BLOCKS FOR A POSTS IN THE CROSSING OF WALLS (Plate VII)

La technique de montage est idem à la technique de montage du paragraphe 2.4The assembly technique is the same as the assembly technique in paragraph 2.4

2.7 MONTAGE DES BLOCS POUR UN POTEAUX ISOLE (Planche VIII)2.7 ASSEMBLY OF BLOCKS FOR AN INSULATED POST (Plate VIII)

Les poteaux isolés sont montés à partir des blocs BPI (BLOC DE POTEAU ISOLE)Insulated posts are mounted from BPI blocks (INSULATED POST BLOCK)

2o Les blocs BPI sont composés de deux parties (une partie fermée et une partie ouverte e) Pour monter un poteau isolé ; on joint les deux partie s ouvertes pour couvrir les armatures et on les superpose de la même manière jusqu'à la hauteur du poteau.2o BPI blocks are made up of two parts (a closed part and an open part e) To mount an insulated post; we join the two open parts to cover the reinforcements and we overlap them in the same way up to the height of the post.

Au fur et à mesure que les deux blocs opposés se dispose les uns sur les autres, on prend le soin de boucher les trous de scellement (situés à la partie fermé des blocs) avec du béton.As the two opposing blocks are placed on top of each other, we take care to fill the sealing holes (located in the closed part of the blocks) with concrete.

Apres après ces opérations, on introduit le béton dans la colonne formée. Pour des raisons de stabilité de la l'ensemble, il est recommandé de couler les poteaux en deux phase avec un intervalle de 3 heures de temps afin d'éviter les phénomènes de reprise de bétonnage. Une tige de stabilité peut être aussi utilisée pour stabiliser les blocs.After these operations, the concrete is introduced into the formed column. For reasons of stability of the whole, it is recommended to pour the posts in two phases with an interval of 3 hours in order to avoid the phenomena of resumption of concreting. A stability rod can also be used to stabilize the blocks.

2.8 RESERVATION DES PORTES ET FENETRES (Planche IX)2.8 RESERVATION OF DOORS AND WINDOWS (Plate IX)

Les blocs tableaux sont utilisé s spécialement pour la construction des tableaux des ouvertures (fenêtre, portes etc...) afin d'éviter toute travails ultérieurs de finition. Ils sont composés de deux parties (une partie circulaire et une partie plate)The painting blocks are used especially for the construction of opening paintings (windows, doors, etc.) in order to avoid any subsequent finishing work. They are composed of two parts (a circular part and a flat part)

Pendant le montage des murs dans un alignement où se trouvera une baie, il est recommandé de poser premièrement les blocs BT de part et d'autre, la partie plate est posée à la limite des baies et la partie creuse est posé dans le sens de l'alignement du mur continu.During the assembly of the walls in an alignment where there will be a bay, it is recommended to first lay the LV blocks on either side, the flat part is placed at the edge of the bays and the hollow part is placed in the direction of the alignment of the continuous wall.

2.9 MONTAGE DES BLOCS POUR UNE POUTRE PERIPHERIQUE, POUTRE CROISEE ET LINTEAU (Planche X)2.9 ASSEMBLY OF BLOCKS FOR A PERIPHERAL BEAM, CROSSED BEAM AND LINTEL (Plate X)

Les poutres périphériques, les poutres croisées et les linteaux sont monté s par les blocs de 5 coffrage horizontal I (BCH). Les BCH sont posés directement sur les derniers rangés de blocs BRS.The peripheral beams, cross beams and lintels are mounted by the 5 horizontal formwork blocks I (BCH). The BCHs are placed directly on the last rows of BRS blocks.

Ils sont disposés les uns contre les autres dans le sens longitudinal sans prévoir de joint entre eux.They are arranged against each other in the longitudinal direction without providing a joint between them.

Apres la pose longitudinale la partie basse interne des BCH présente des ouvertures qui seront par le béton pour assurer la stabilité desdits blocs. Apres le scellement interne on pose les 10 armatures à l'intérieur et on coule le béton. Ce qui donnera un double enrobage au ferraillageAfter longitudinal installation, the lower internal part of the BCH has openings which will be through the concrete to ensure the stability of said blocks. After the internal sealing, the 10 reinforcements are placed inside and the concrete is poured. Which will give a double coating to the reinforcement

NB : la hauteur des BCH des poutres périphériques sera complétée par un coffrage métallique (réutilisableplusieurs fois) pour le coffrage de l'épaisseur de la dalle.NB: the height of the BCH of the peripheral beams will be supplemented by a metal formwork (reusable several times) for the formwork of the thickness of the slab.

MONTAGE DES BLOCS POUR LES ANGLES DES POUTRES (Planche XI)ASSEMBLY OF BLOCKS FOR THE CORNERS OF THE BEAMS (Plate XI)

Dans les angles droit des poutres se généralement des poteaux et les blocs BCH sont utilisé s pour 15 habiller lesarmatures desdits poteaux.In the right angles of the beams there are generally posts and the BCH blocks are used to cover the reinforcements of said posts.

Vue la modélisation des BCH. Il faut couper une aille (selon l'orientation de l'angle) de deux blocs et disposer l'un dans le sens du mur courant et l'autre dans le sen s de l'autre murformant un angle de 90 degré.View the modeling of BCH. You must cut a side (according to the orientation of the angle) of two blocks and place one in the direction of the current wall and the other in the direction of the other forming an angle of 90 degrees.

Les parties où les ailles sont coupées doivent de rejoindre en 90 degrés en angle intérieur et les 20 ailles non coupées vont aussi se rejoindre formant 90 degré extérieur.The parts where the wings are cut must join at 90 degrees at an interior angle and the 20 uncut wings will also join at an exterior 90 degree.

Claims (2)

1. Nouveau procédé technico-écologique de construction de bâtiment à base de bloc de ciment et ou en latérite traité, caractérisé en ce que le procédé est basé sur une méthode de fabrication et d'assemblage de blocs en ciment ou 5 en latérite travaillé.1. New technical-ecological process for building construction based on cement blocks and or treated laterite, characterized in that the process is based on a method of manufacturing and assembling blocks made of cement or worked laterite. 2. Nouveau procédé technico-écologique de construction de bâtiment selon la revendication 1, caractérisé en ce que les blocs sont fabriqués à base de : - béton de ciment composé de 70% d'élément fin de granulométrie 0/3 et 30% degranulats de granulométrie 3/8, le béton est dosé à 250 kg/m3, lesdits blocs 10 sont moulés par presse à l'aide d'une pondeuse de brique industrielle, le produit fini possède un parement très lisse après séchage,2. New technical-ecological process for building construction according to claim 1, characterized in that the blocks are manufactured based on: - cement concrete composed of 70% of fine element of particle size 0/3 and 30% of granulates of particle size 3/8, the concrete is dosed at 250 kg/m 3 , said blocks 10 are molded by press using an industrial brick layer, the finished product has a very smooth facing after drying, - de géo béton composé de 90% de la latérite fin et de 10% de ciment pour la stabilisation, l'utilisation d'un moule introduit dans une presse manuelle ou électrique est recommandée pour la production des dits blocs.- geo concrete composed of 90% fine laterite and 10% cement for stabilization, the use of a mold introduced into a manual or electric press is recommended for the production of said blocks. 15 3. Nouveau procédé technico-écologique de construction de bâtiment selon la revendication 2, caractérisé en ce que les blocs sont assemblés de manière spécifique en fonction des éléments du bâtiment en construction.15 3. New technical-ecological process for building construction according to claim 2, characterized in that the blocks are assembled in a specific manner depending on the elements of the building under construction.
OA1202300396 2023-08-11 New technical-ecological process for building construction based on cement block or treated laterite. OA21411A (en)

Publications (1)

Publication Number Publication Date
OA21411A true OA21411A (en) 2024-06-05

Family

ID=

Similar Documents

Publication Publication Date Title
EP1454020A1 (en) Building component
FR3017889A1 (en) COMPOSITE BUILDING PANEL
US1911626A (en) larzelere
OA21411A (en) New technical-ecological process for building construction based on cement block or treated laterite.
US10669715B2 (en) Components for masonry construction
US20030218265A1 (en) Mold and process for casting and manufacturing of concrete structural columns
US1234244A (en) Concrete building-block.
US9630340B2 (en) System of forming walls with exterior applied finish panels
BE479632A (en) MOLDED CONSTRUCTION PART
FR2912163A1 (en) Construction block for e.g. wall, has vertical cavities and horizontal cavities permitting binder material to cross and to connect block, where block is fabricated with natural or synthetic rubber
RU2270302C1 (en) Retained form set and building wall erection method
US843956A (en) Method of making composite walls.
SK9132Y1 (en) Building block, in particular formwork building block, method of its production
US947492A (en) Concrete construction.
NL2017719B1 (en) Prefab building element and method for manufacturing such prefab building element
US699587A (en) Artificial building-stone.
AU2018236782B2 (en) Components for Masonry Construction
FR2566445A1 (en) Reinforced-concrete load-bearing beam and process for manufacturing it
US720747A (en) Manufacture of concrete beams, girders, &amp;c., with iron bars inlaid, for building purposes.
WO2017126996A2 (en) Method and tools for constructing a structural framework such as a structural wall used to build conventional houses
BE470493A (en)
FR2996571A1 (en) Prefabricated construction element for erecting e.g. outer wall of apartment building, has bricks or stones and lintels including plates, which form outer and inner walls and are connected by insulating material
WO2015128786A1 (en) A cast structural element
ITPN20130075A1 (en) CONSTRUCTION PROCESS OF PREFABRICATED LIVING STRUCTURES OF VARIOUS GENRE AND PREFABRICATED LIVING STRUCTURES SO SO IT HAS OBTAINED
NL2006456C2 (en) METHOD FOR BUILDING A BUILDING, PREFAB SANDWICH PANEL AND FORMWORK.