OA21744A - Method for producing a gravity-based structure (GBS) at a specialized production site. - Google Patents

Method for producing a gravity-based structure (GBS) at a specialized production site. Download PDF

Info

Publication number
OA21744A
OA21744A OA1202400251 OA21744A OA 21744 A OA21744 A OA 21744A OA 1202400251 OA1202400251 OA 1202400251 OA 21744 A OA21744 A OA 21744A
Authority
OA
OAPI
Prior art keywords
concreted
slab
gbs
central part
outer walls
Prior art date
Application number
OA1202400251
Inventor
Valeriy Nikolaevich RETIVOV
Sergey Gennadyevich SOLOVYEV
Leonid Viktorovich MIKHELSN
Original Assignee
Publichnoe Aktsionernoe Obshchestvo ‘‘Novatek’’
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Publichnoe Aktsionernoe Obshchestvo ‘‘Novatek’’ filed Critical Publichnoe Aktsionernoe Obshchestvo ‘‘Novatek’’
Publication of OA21744A publication Critical patent/OA21744A/en

Links

Abstract

The invention pertains to fabrication of gravitybased structures (GBS) and can be used as part of development of various kinds of near-shore and offshore production (including natural gas liquefaction, ammonia, methanol, hydrogen production, and power generation), transportation, transshipment, and storage facilities. The GBS production method is as follows: a reinforcement cage is assembled for a rectangular base slab, formwork is installed and the base slab is then concreted. As separate sections of the base slab are concreted, reinforcement cages for inner and outer walls are assembled and concreted by slipforming. As separate wall sections are concreted, a reinforcement cage for a top slab is assembled, formwork is installed and then the top slab is concreted and the top slab and base slab, as well as inner and outer walls are posttensioned with reinforcement strands. The feature of the method is that GBS is fabricated, including a central part and protruding part that have a common base slab. The inner and outer walls as well as the top slab are concreted for the central part of GBS, that takes form of a rectangular prism. As separate sections of outer walls of the central part are concreted, a reinforcement cage is assembled, formwork is installed and concreting is performed for inner and outer walls of the GBS protruding part, the outer walls of which are made along the perimeter of the base slab, and at the same time the height of the outer walls of the protruding part is lower than the height of the outer walls of the central part. As separate wall sections of the protruding part are concreted, a reinforcement cage is assembled and formwork is installed for a top slab of the protruding part and then concreted. The base and top slabs of the central part, as well as the inner and outer walls of the central part and protruding part are posttensioned as the top slabs of the central part and protruding part are concreted and the concrete of the post-tensioned structures is cured. A protruding part adds to buoyancy of the GBS and the entire structure, as well as reduces its submersion during transportation to an installation site. <img file="OA21744A_A0001.tif"/> Fig. 5

Description

Method for fabricating a gravity-based structure (GBS) at a specialized fabrication site
TECHNICAL FIELD
The invention pertains to fabrication (construction) of gravity-based structures (GBS) and can be used as part of development of various kinds of near-shore and offshore production (including natural gas liquéfaction, ammonia, methanol, hydrogen production, and power génération), transportation, transshipment, and storage facilities.
BACKGROUND ART
A gravity-based structure (GBS, a fixed gravity-based offshore platform) is a platform, which is fixed on a seabed with the help of its own weight. Gravity-based structures are used in Coastal and shelf waters where the water depths are sufficient to support a superstructure of the required height above the water level once the GBS is installed on the seabed. A GBS can feature internai compartments to enable its floatability during transportation to its installation site. GBS are designed to be floatable and hâve ballasting Systems to enable long-distance transportation and installation for operation at the intended offshore site without using expensive lifting and transportation equipment. GBS are mostly made of reinforced concrète and Steel.
GBS are produced at production sites and shipyards that hâve spécial equipment.
There exists a method for fabricating a gravity-based structure (GBS) made from reinforced concrète to support a floating power plant and store liquefied natural gas which has a form of a rectangular prism with a base slab, a top slab, and side walls. The method consists in placing reinforcement bars, concreting the GBS éléments, and performing pre-stressing and post21744 tensioning of the GBS éléments (KR20150136823A, publication date: 12/08/2015).
A method, which is the closest to the proposed one, features a gravitybased structure (GBS) fabrication for Adriatic LNG, an offshore liquified natural gas receiving and regasification terminal built at Algeciras' production site in Spain (Design and Construction on Gravity Based Structure and Modularized LNG Tanks for the Adriatic LNG Terminal. Lisa B. Waters et al. ExxonMobil Development Company. 2007.
http://www.ivt.ntnu.nO/ept/fag/tep4215/innhold/LNG%20Conferences/2007/f scommand/PS6 7 Waters s.pdf. )
This GBS is made in a form of a rectangular prism with a top slab, a base slab, an intermediate support slab for self-supported LNG tanks, external walls, internai longitudinal and transversal walls to separate the compartments.
The above production method features the following:
• a GBS construction site is prepared, including installation of concrète cavities for Steel skirts and installation of these Steel skirts, in this case the skirts hang loose in the concrète cavities in such a way that the GBS weight is shifted to the site backfilled with gravel and to the concrète foundations;
• a rectangular reinforcement cage is assembled for the base slab, formwork for the base slab is installed and the base slab is then concreted;
• once concreting of individual base slab areas is completed, reinforcement cages for the external and internai walls are assembled and the external and internai walls are slip-formed except the short-end walls on one of the GBS sides (on the side where the LNG tanks were installed);
• simultaneously with walls concreting, a reinforcement cage for the intermediate slab is assembled, formwork is erected and the intermediate slab is concreted;
• roof beams are fabricated and installed;
• as separate wall sections are concreted, a reinforcement cage for the top slab is assembled, the top slab formwork is installed and then the top slab is concreted, • insulation and a second barrier for LNG tank compartments are installed;
• sections for self-supporting LNG tanks are erected;
• the short-end walls on one of the GBS sides are concreted (on the side where the LNG tanks are installed);
• the top slab and base slab, as well as inner and outer walls are post-tensioned with the rereinforcement strands.
This method has the following drawbacks.
Installation of concrète cavities for Steel skirts and Steel skirts increases the scope and duration of works at a preparatory stage, presence of concrète cavities makes préparation of the foundation more complicated.
Use of roof beams complicates construction works and requires use of crânes with higher carrying capacity.
Concreting of the short-end walls on one side of the GBS (on which the LNG tanks are installed) is carried out the last after the tanks are installed in the GBS compartments, which increases the construction time and violâtes monolithic nature of the reinforced concrète structure due presence of cold joints in this section.
The rectangular prism-shaped GBS has large draft when transported to the installation site, which makes transportation through shallow water areas impossible.
The rectangular prism-shaped GBS is not protected from external influences such as ice drift and emergency ship impact.
SUMMARY OF THE INVENTION
The technical problem resolved with the invention is as follows. Taking into account the increasing share of production and infrastructure facilities located in underdeveloped areas, including Coastal and water area of Arctic seas, there is an urgent need to develop a new and efficient method for construction of gravity-based structures which could house production, transportation, transshipment and storage complexes for various purposes in the Coastal and water areas and adapted for use in water areas with ice conditions.
To résolve the above-said problem, there was proposed a method for producing a GBS representing a three-dimensional reinforced concrète structure with internai walls separating compartments and aimed for installation on a bottom of a water object and which may serve as a foundation to accommodate a topside for various purposes. Besides, the GBS may stay floating during its transportation though water routes from a production location to an installation location, and when installed on a seabed, it can resist ice loads from an iced basin. The topside can be erected either immediately after the GBS production or after the GBS placement onto a seabed or at one of the intérim locations during the GBS transportation from the production location to the installation location.
The technical issue is solved by a method of a gravity-based structure (GBS) production, meaning that a reinforcement cage is assembled for a rectangular base slab, a base slab formwork is installed and the base slab is then concreted, as separate sections of the base slab are concreted, reinforcement cages for inner and outer walls are assembled and concreted with slipforming, as separate wall sections are concreted, a reinforcement cage for top slab is assembled, a top slab formwork is installed and then the top slab is concreted, the top slab and base slab, as well as inner and outer walls are posttensioned with reinforcement strands, along with that, as per the invention, the GBS is fabricated, including a central part and a protruding part that hâve the common base slab, inner and outer walls as well as the top slab are concreted for the central part of GBS, that takes form of a rectangular prism, as separate sections of the outer walls of the central part are concreted, a reinforcement cage is assembled, a formwork is installed and concreting is performed for inner and outer walls of the GBS protruding part, the outer walls of which are made along a perimeter of the base slab, and at the same time height of the outer walls of the protruding part is lower than height of the outer walls of the central part, as separate wall sections of the protruding part are concreted, a reinforcement cage is assembled and a formwork is installed for the top slab of the protruding part and then concreted, and the base and top slabs of the central part, as well as the inner and outer walls of the central part and protruding part are post-tensioned as the top slabs of the central part and protruding part are concreted and the concrète of the post-tensioned structures gains required strength.
In addition, it is advisable to concrète the top slab with upward bending of its central part so that the central part of the top slab lowers later on its own weight to a design position.
Moreover, in the preferred option of the invention, as separate sections of the top slab of the central part are concreted, a reinforcement cage is assembled, a formwork is installed, embedments are set and supports for equipment are concreted on the top slab.
Furthermore, as the outer and inner walls of the central part are concreted, it is advisable to leave openings for formwork removal and further installation of equipment inside the GBS compartments shaped by the walls and slabs.
Should it be required to accommodate at least one tank for storage of liquid in the GBS, then simultaneously with concreting of the walls of the central part, a reinforcement cage is assembled, a formwork is installed and an intermediate slab is concreted, post-tensioned, and inside at least one compartment shaped by the walls, intermediate slab and top slab, a tank for storage of liquid is assembled from panels, delivered through the wall openings.
The technical resuit is acheived by the GBS fabricated with the protruding part and it means the following. The protruding part adds to buoyancy of the GBS and the entire structure, as well as reduces its submersion during transportation to the installation site. Additional ballast compartments in the peripheral part of the GBS inside the protruding part make it easy to balance the GBS, i.e. to settle the GBS down evenly, without trim and list. Increased width of the GBS lower part adds to stability of the entire structure during its transportation, enabling to install the topside structure of greater height and weight onto the GBS.
Unlike platforms that are installed and towed in deepwater areas, the GBS that uses the protruding part instead of having the same volume across its height has a tangible advantage in terms of the draft and the overall weight-to-floatability ratio, which enables a much greater displacement for a relatively modest increase in the platform's own weight.
The protruding part of the GBS also protects the central part, which can accommodate main storage compartments, from drifting ice and emergency ship impact.
Erecting both side walls and short-end walls before the top slab is formed as well as having possibility to assemble the tanks from separate panels in a confined compartment helps to accelerate the GBS fabrication and to reduce the number of “cold welds” in the reinforced concrète construction.
To reduce the overall GBS production time, certain stages are carried out in parallel.
LIST OF DRAWINGS
Fig. 1 shows fabrication of the base slab and walls of the GBS central part between the base slab and the intermediate slab.
Fig. 2 - fabrication of the base slab and intermediate slab as well as inner walls of the GBS central part.
Fig. 3 - fabrication of the inner and outer walls of the GBS central part.
Fig. 4 - fabrication of the outer walls of the GBS central part, top slab, topside supports on the top slab, outer walls of the GBS protruding part and tanks for liquids storage inside the GBS.
Fig. 5 - fabrication of the top slab of the GBS central part, top slab of the GBS protruding part and top structure supports.
Fig. 6 - the fabricated GBS when towed out of a dock, front view.
Figure 7 - the fabricated GBS when towed out of the dock, side view.
EXAMPLES OF THE INVENTION IMPLEMENTATION
The production program implies mass production of GBSs as part of a staged process at a specialized fabrication site with dry docks. The location of the fabrication site facilities allows producing materials for every separate stage of fabrication within limits of a separate facility with subséquent transportation to dry docks for use in the GBS fabrication. The GBS fabrication sequence is designed to optimize the use of equipment and personnel and reduce construction time through parallel performance of part of the work stages.
The GBS is fabricated as follows.
The dry dock is isolated from the adjacent water area using a dock gâte, then the dock is drained with pumps. Then, at the bottom of the dock, an area with a cover of compacted crushed rock is prepared for fabrication of the GBS foundation slab.
Reinforcement is eut and bent and reinforcement cages are fabricated and labelled in a reinforcement shop. Reinforcement éléments are transported to the dry dock by road and fed at the GBS reinforcement cage assembly site with loaders or lifting crânes. The GBS reinforcement cage is assembled by welding, lashing, and sleeving.
Simultaneously with the reinforcement cage, duct tubes for bundles of post-tensioning reinforcement strands are installed in the tensioned structures, as well as the anchors and embedments for equipment to be installed.
Three types of formworks are used for the GBS concreting: traditional formwork, inventory formwork and permanent formwork. In a formwork shop, traditional and permanent formwork is produced, and inventory formwork assembly sections are assembled. Completed sections are stored in a formwork laydown area and, when needed, they are transported to the dry dock and installed for concreting of the GBS structure.
Traditional formwork panels are produced from eut wood and laminated plywood in the formwork shop. The traditional formwork is used to concrète objects of smaller height, mainly for slabs and supports.
Basic éléments of the inventory formwork are panels or blocks, frames, bearing structures, connectors and fastenings. Depending on the structure to be concreted, two types of inventory formwork are applied: panel-type formwork and slipforming.
Panel-type formwork is collapsible and consists of large-sized éléments, accelerating construction of large-scale objects. Slipforming consists of two identical rows of panels, 1.0- 1.2 m high, rigidly connected to one another by bolts and attached to a spécial frame, which is moved upwards by jacks along with the structure's concreting process. Slipforming is used for the GBS walls concreting. With slipforming applied, concreting is monolithic, that is, without the cold seams, thus improving the structure's performance parameters. Moreover, the use of slipforming enables the GBS walls to be concreted very fast - over 2.5 meters upwards per day.
Permanent formwork is used when formwork removal is impossible, e.g. during concreting of the intermediate ceiling slab when the equipment is installed inside the compartment. This type of formwork is also used for construction of pit structures in LNG tanks and other parts of the GBS, removal of which is labor-intensive after closure of outer structures.
Concrète, which is the main construction material for GBS production, is mixed at a concrète batching plant, located close to the dry docks. Location of the concrète batching plant ensures the least distance for concrète to be transported to the pouring point.
Bulk materials for concrète mixing may be delivered to the fabrication site via a quay, located in front of the concrète batching plant, and it secures the shortest way for the materials from the offloading point to the place where they are stored and consequently used.
The GBS production employs spécial concrète mix designs of high strength, having the pre-requisite density and durability features. The use of concrète of different densities in combination with weight control allows to achieve optimal targets for mass, buoyancy and stability of the structure. The concrète mix is delivered to the dry dock by truck mixers. The concrète is poured into the formwork with concrète pumps.
Concreting starts with sectionalized concrète casting of the base slab 1, which is common for the GBS central and protruding parts (Fig. 1). A reinforcement cage is assembled for the rectangular base slab 1, a formwork for the base slab 1 is installed and the base slab 1 is then concreted. As individual sections of the base slab 1 are completed, reinforcement cages are assembled in the central part of the GBS for internai walls 2 with the help of an inventory formwork. In parallel, reinforcement installation is performed for internai walls 3 and external walls 4 in the GBS central part (Fig. 2, 3), which are slipformed. During this process, the GBS central part is shaped as a rectangular prism. For the purposes of formwork removal and subséquent equipment installation in GBS compartments, relatively small service openings are left in the walls to be further thoroughly closed and sealed once the work inside the compartments is finished.
In case the GBS is fabricated with an intermediate slab 7 to accommodate at least one liquid storage tank 8 (Fig. 4), as concreting of individual sections of the walls 2 of the central part between the base slab 1 and intermediate slab 7 is completed, concreting of the GBS intermediate slab 7 begins, in parallel with concreting of the internai and external walls 3 and 4 in the GBS central part. For this purpose, a reinforcement cage is assembled, formwork is erected and the intermediate slab 7 is concreted.
As individual sections of the external walls 4 of the central part are concreted, a reinforcement cage is assembled, formwork is installed, and external and internai walls of the protruding part are concreted section by section, using slipforming. The external walls 5 of the GBS protruding part are erected ail along the base slab perimeter, with the external walls 5 of the protruding part being lower than the external walls 4 of the central part.
In parallel, in the sections where concreting of walls 3, 4 of the GBS central part is completed, concreting of the top slab 9 of the GBS central part begins. For this purpose, a reinforcement cage is assembled for the top slab 9, formwork is erected for the top slab 9 and the top slab 9 is concreted. In addition, to erect the formwork, the scaffolding and trestles are installed inside the GBS compartments allowing to avoid using roof beams. Using scaffolding in combination with the formwork provides their universal usage both for building the top slab 9 and for performing subséquent préparation and installation of structural éléments of tanks 8 at different heights, which ultimately results in overall construction accélération.
To offset the downward bending of the top slab 9 due to its weight, the central part of the slab is bent upwards before concreting to ensure camber in the opposite direction. Once the concreting is completed and the formwork is removed, the slab settles down due to its weight and takes design configuration enabling partial offset of downward bending. Using a beamless design for the top slab 9 with uneven thickness similar to an arc where the slab is thicker near its edges than in the span (not shown in the drawings) enables better target spécifications for weight and rigidity as well as accelerated formwork instalation through simplification of the slab bottom surface, which has no protruding parts.
At least in one of the compartments formed by internai reinforcedconcrete walls 3, intermediate slab 7 and top slab 9, the liquid storage tank 8 is locally erected from panels delivered through the openings in the walls.
In parallel, as the external walls 5 of the GBS protruding part are completed, concreting of top slabs 6 of the GBS protruding part begins (Fig. 4, 5). The top slabs 6 of the GBS protruding part are connected to the external walls 4 of the central part by extending and tying protruding reinforcements into sleeves and anchor rods that were earlier flush-mounted during slipforming of walls 4 in accordance with the design.
If the intended use of the GBS includes berthing of vessels, supports are built from reinforced concrète along the outer edge of the GBS protruding part above the top slab 6 for the purpose of installation of berthing structures and fenders for berthing and mooring of vessels enabling the use of GBS structures as a berth. These supports are erected with the help of an inventory formwork.
Should it be required to fabricate a GBS with supports 10 for a topside equipment to be installed on the top slab 9, then a reinforcement cage is assembled, formwork is installed, embedments are set in and the supports 10 are concreted to provide support for load-bearing structures of the topside cages which may house process equipment (Fig. 5).
The post-tensioning materials workshop accommodâtes storage of reinforcement strands, duct tubes and anchores, préparation of materials and equipment to perform post-tensioning. In the areas where sequence of works makes it possible to start this type of work, the equipment is installed in the dry dock. Once the equipment is ready, the post-tensioning materials are transported to the dry dock where strand bundles are installed and tensioned to the design values with anchoring and transmission of tensioning force to anchoring devices on reinforced concrète structures of the GBS.
Concrète structures are post-tensioned using “tension on concrète” with bonding restoration, which means that after the concrète of the tensioned reinforced concrète structures of the GBS is poured, the strands are forced/pulled through the pre-installed duct tubes made of corrugated Steel. After the concrète has reached the minimum required strength, the strand bundles are tensioned and fixed thus transmitting the tensioning force to Steel anchoring devices pre-installed onto the short ends of the structure body.
Reinforcement strands are tensioned with hydraulic jacks. After strand bundles are tensioned and pull-out testing is done, the duct tubes are filled with nonshrink cernent mortar and ail temporary openings and niches are filled up. The duct tubes will protect the reinforcement strands from external impact and partially transfer load from the strands to the concrète along the entire length of the structure.
With post-tensioning during GBS construction, the targeted performance can be achieved more efficiently, especially for limit States group II, such as crack résistance and impermeability. As a resuit, it reduces the amount of non-tensioned reinforcement required and contributes to reducing the structure weight, as well as increases the overall spatial stiffness of the load-bearing reinforced concrète cage of the GBS.
Closing of process openings in the GBS walls, concreting of posttension anchors, and cleaning of concrète surface take place in the end.
After the GBS fabrication is complété, equipment 11 is installed inside compartments and on the top slab 9 and a modular topside structure 12 is installed onto the supports 10 on the top slab 9 (see Fig. 6 and 7). Topside modules 12 may be fabricated in parallel and independently of the GBS construction schedule, and then installed on the supports 10 with the help of a specialized jacking and skidding System. The supports 10 are also the main load-carrying éléments supporting the bearing guardrails of the topsides skidding System.
Besides the skidding System, crânes are also used in the dry docks, allowing to install heavy equipment and Steel structures onto the GBS from the area near the dock.
After the GBS construction and equipment installation are complété, the dry dock 13 with the GBS inside is gradually filled with water 14 from the nearby water area with the help of pumps. At each stage of the dock flooding,
GBS compartments are checked for leak tightness by hydraulic and pneumatic tests. Along with the dock flooding, GBS ballast compartments are flooded as well, to increase the structure's weight and thus ensure its steadiness on the dock bottom.
Once tests are complété, GBS is fixed inside the dock with mooring hawsers and rétention and guiding dolphins located at the bottom of the dry dock. Once GBS testing and mooring is complété, water is pumped out of the compartments of the moored GBS to ensure its floating up during the high tide.
The GBS is towed out of the dock by tugboats. After being towed out of the dry dock, the GBS is towed to the installation site. By the onshore winches and by tugs, the GBS is installed in the point of destination at a quayside, where the GBS is connected to onshore communication lines in the deposit area. Once its position is confirmed as correct, the GBS is ballasted to be installed onto a foundation, previously arranged in the bottom of a water body.

Claims (5)

1. A method for fabricating a gravity-based structure (GBS), consisting in that a reinforcement cage is assembled for a rectangular base slab, base slab formwork is installed and the base slab is then concreted, as separate sections of the base slab are concreted, reinforcement cages for inner and outer walls are assembled and the inner and outer walls are concreted by slipforming, as separate wall sections are concreted, a reinforcement cage for a top slab is assembled, a top slab formwork is installed and then the top slab is concreted, the top slab and base slab, as well as inner and outer walls are post-tensioned with reinforcement strands, characterized in that the GBS is fabricated including a central part and protruding part that hâve the common base slab, besides the inner and outer walls as well as the top slab are concreted for the central part of GBS, that takes form of a rectangular prism, as separate sections of the outer walls of the central part are concreted, a reinforcement cage is assembled, formwork is installed and concreting is performed for inner and outer walls of the GBS protruding part, the outer walls of which are made along the perimeter of the base slab, and at the same time the height of the outer walls of the protruding part is lower than the height of the outer walls of the central part, as separate wall sections of the protruding part are concreted, a reinforcement cage is assembled and formwork is installed for a top slab of the protruding part and then concreted, and the base and top slabs of the central part, as well as the inner and outer walls of the central part and protruding part are post-tensioned as the top slabs of the central part and protruding part are concreted and the concrète of the post-tensioned structures is cured.
2. The method according to claim 1, where the top slab is concreted with upward bending of its central part so that the central part of the slab lowers on its own weight to a design position.
3. The method according to claim 1, where, as soon as separate sections of the top slab of the central part are concreted, a reinforcement cage is assembled, a formwork is installed, embedments are set and supports for equipment are concreted on the top slab.
5
4. The method according to claim 1, where, in the course of the outer and inner walls of the central part being concreted, openings are left for formwork removal and further installation of equipment inside the GBS compartments shaped by the walls and slabs.
5. The method according to claim 3, where, simultaneously with 10 concreting of the walls of the central part, a reinforcement cage is assembled, aformwork is installed and an intermediate slab is concreted, post-tensioned, and inside at least one compartment shaped by the walls, intermediate slab and top slab, a tank for storage of liquids is arranged with panels, delivered through temporary wall openings.
OA1202400251 2022-02-15 2022-10-14 Method for producing a gravity-based structure (GBS) at a specialized production site. OA21744A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2022103801 2022-02-15

Publications (1)

Publication Number Publication Date
OA21744A true OA21744A (en) 2024-12-24

Family

ID=

Similar Documents

Publication Publication Date Title
CN211849244U (en) Novel assembled high-pile beam-slab wharf structure
US20160340855A1 (en) Modular construction mold apparatus and method for constructing concrete buildings and structures
CN114457668B (en) Large-span space special-shaped arch rib delphinium type basket steel box arch bridge and rapid construction method
EP3584373A1 (en) Maritime structure for laying the foundations of buildings, installations and wind turbines by means of gravity in a marine environment
CN217536681U (en) Assembling support of large-tonnage steel-concrete combined cross beam of cable-stayed bridge cable tower
CN115198645A (en) Two-point floating transportation and integral lifting installation construction method for arch rib
EP4480803A1 (en) Method for producing a gravity-based structure (gbs) at a specialized production site
CN111827239A (en) Construction method of assembled berthing pier
CN109823970B (en) Steel structure transportation method for bridge construction
WO2020200856A1 (en) Floatable structure and method of making same
CN113802461B (en) A steel box girder erection method
CN114775432A (en) Assembling support of large-tonnage reinforced concrete combined cross beam of cable-stayed bridge cable tower
CN110735394B (en) Cable tower structure and construction method thereof
KR101703441B1 (en) Cassion manufacturing method of bottom-up, pre-cast and a base plate type using floating dock, system, floating dock and cassion using thereof
CN217325062U (en) Assembling sliding support of large-tonnage steel cross beam of cable-stayed bridge cable tower
CN110656576A (en) Pier structure and construction method thereof
CN114991073A (en) Method for cooperatively installing precast high-pile wharf component by multiple devices
CN114703757A (en) Multifunctional support for steel cross beam of cable-stayed bridge and assembling method of steel cross beam
CN217536723U (en) Multifunctional support for steel cross beam of cable-stayed bridge
CN217322533U (en) Intelligent weight shifting device
CN217325063U (en) Embankment staggered track arrangement structure
Jansson Construction of the∅ resund Bridge
CN118911067A (en) High-pile pier assembled pier structure and construction method thereof
JP2024057389A (en) Substructure for floating offshore wind power generation and construction method for the substructure for floating offshore wind power generation
JPS5936041B2 (en) Road widening using the overhang method