PL157272B1 - Method for rock anchoring - Google Patents
Method for rock anchoringInfo
- Publication number
- PL157272B1 PL157272B1 PL27009288A PL27009288A PL157272B1 PL 157272 B1 PL157272 B1 PL 157272B1 PL 27009288 A PL27009288 A PL 27009288A PL 27009288 A PL27009288 A PL 27009288A PL 157272 B1 PL157272 B1 PL 157272B1
- Authority
- PL
- Poland
- Prior art keywords
- anchor
- hole
- glue
- rock
- anchoring
- Prior art date
Links
- 238000000034 method Methods 0.000 title claims abstract description 11
- 239000011435 rock Substances 0.000 title claims description 23
- 238000004873 anchoring Methods 0.000 title claims description 9
- 239000003292 glue Substances 0.000 claims abstract description 7
- 239000000853 adhesive Substances 0.000 claims description 7
- 230000001070 adhesive effect Effects 0.000 claims description 7
- 239000010410 layer Substances 0.000 description 5
- 238000005065 mining Methods 0.000 description 3
- 210000002435 tendon Anatomy 0.000 description 3
- 238000009412 basement excavation Methods 0.000 description 2
- 239000011229 interlayer Substances 0.000 description 1
- 239000011513 prestressed concrete Substances 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
Przedmiotem wynalazku jest sposób kotwienia górotworu, poprzez spinanie warstw skalnych za pomocą cięgien kotwiowych wklejanych do otworów wiertniczych.The subject of the invention is a method of anchoring a rock mass by fastening rock layers with the use of tie rods glued to boreholes.
Znany jest sposób kotwienia górotworu poprzez wprowadzanie cięgien kotwiowych do otworów wiertniczych wypełnionych klejem na całej długości. Tak osadzone cięgna kotwiowe spinają cienkie warstwy w jedną grubą warstwę skalną oraz przejmują naprężenia rozciągające. Uzyskany tym sposobem wzrost wytrzymałości skał jest wystarczający tylko w tych przypadkach, gdy nie jest naruszona naturalna spójność warstw górotworu.There is a known method of anchoring the rock mass by introducing tie rods into boreholes filled with glue along the entire length. The so-mounted tie rods bind thin layers into one thick rock layer and absorb tensile stresses. The increase in rock strength obtained in this way is sufficient only in those cases where the natural cohesion of the rock layers is not affected.
Znany jest również sposób kotwienia górotworu polegający na wklejaniu do otworu wiertniczego tylko głowicy kotwi, a następnie naprężaniu cięgna kotwiowego na pozostałej długości. Sposób ten zapewnia sztuczne wytworzenie naprężeń ściskających w górotworze, a tym samym zwiększenie tarcia międzywarstwowego, jednak nie powoduje przywrócenia utraconej wcześniej spójności między warstwami. W przypadku zmniejszenia się naciągu wstępnego cięgna kotwiowego, które może wystąpić na skutek ruchów górotworu lub poluzowania się głowicy kotwi, cięgno nie zwiększa już wytrzymałości skały, lecz podtrzymuje jedynie pułap wyrobiska górniczego, zapobiegając opadaniu bloków skalnych do przestrzeni roboczej.There is also a known method of anchoring a rock mass, which consists in sticking only the head of the bolt into the borehole, and then tensioning the tie rod over the remaining length. This method provides artificial creation of compressive stresses in the rock mass, and thus increases the inter-layer friction, but does not restore the previously lost cohesion between the layers. In the event of a reduction in the initial tension of the anchor strand, which may occur as a result of movements of the rock mass or loosening of the anchor head, the tendon no longer increases the strength of the rock, but only supports the mine heading ceiling, preventing the rock blocks from falling into the working space.
Powyższe wady i niedogodności ograniczają możliwość stosowania kotwi wklejanych tylko do górotworu o dużej zwięzłości.The above disadvantages and inconveniences limit the possibility of using bolts glued only to the rock mass of high compactness.
Istotą wynalazku jest sposób kotwienia górotworu polegający na tym, że po utwierdzeniu za pomocą kleju szybkowiążącego głowicy kotwy w otworze wiertniczym napręża się jej cięgno wstępnie siłą mniejszą od obciążenia nominalnego a następnie utwierdza się cięgno kotwy w otworze na pozostałej części jego długości klejem późnowiążącym po czym napręża się kotwę równą obciążeniu nominalnemu kotwy.The essence of the invention is the method of anchoring the rock mass consisting in the fact that after fixing the anchor head in the borehole with quick-setting adhesive, its tendon is pre-tensioned with a force lower than the nominal load, and then the anchor tendon is fixed in the hole on the remaining part of its length with late-setting adhesive and then tensioned the anchor is equal to the nominal load of the anchor.
Przykład kotwienia górotworu sposobem według wynalazku opisany jest poniżej.An example of rock anchoring according to the invention is described below.
Do wykonanego otworu kotwiowego 0 42 o długości 1,6 t 3, lm wprowadza się najpierw pojemniki dwuskładnikowego kleju o czasie wiązania 0,5 t 1 min. wypełniając nimi 1/3 długości otworu a resztę otworu wypełnia się pojemnikami z klejem o czasie wiązania równym 20 + 30 min. Następnie wprowadza się do tak wypełnionego otworu kotwę nadając jej ruch posuwisty i obrotowy za pomocą wiertarki górniczej, dzięki czemu następuje wymieszanie składników kleju zawartych w pojemnikach. Po upływie czasu 1+2 min. niezbędnego na utwardzenie kleju szybkowiążącego napręża się żerdź kotwy siłą rzędu 50 kN a następnie po upływie czasu ok. 30 min. zwiększa się naciąg kotwy do wartości normalnej równej 150 kN.The containers of two-component adhesive with a setting time of 0.5 t 1 min are first introduced into the prepared anchor hole 0 42 with a length of 1.6 t 3.1 m. filling 1/3 of the opening length with them, and the rest of the opening is filled with containers with glue with a setting time of 20 + 30 minutes. Then, the anchor is introduced into the so filled hole, making it sliding and rotating with the help of a mining drill, thanks to which the adhesive components contained in the containers are mixed. After 1 + 2 min. The quick-setting adhesive necessary for hardening is tensioned in the anchor rod with a force of 50 kN, and then after approx. 30 minutes. the tension of the anchor is increased to a normal value of 150 kN.
Zaletą kotwienia górotworu sposobem w/g wynalazku jest trwałe wzmocnienie skał otaczających wyrobisko górnicze gwarantując tym samym poprawę bezpieczeństwa pracy pracownikom w podziemiach kopalni. Uzyskany tym sposobem wzrost wytrzymałości skały jest wystarczający dla zachowania i/lub przywrócenia jej struktury oraz przyjęcia przez nią naprężeń występu157 272 jących dookoła wyrobiska. Wielkość naciągu jest stale utrzymywana na takim poziomie, że skały, przez które kotew przechoddi, są ściskane i nie mają moOliwości rozprężenia się. Seria skał spięta kotwiami, posiadająca strukturę i własności zbliżone do strunobetonu, przenosi obciążeniawgłąi górotworu.The advantage of anchoring the rock mass using the method according to the invention is the permanent strengthening of the rocks surrounding the mining excavation, thus ensuring improvement of work safety for workers in the mine underground. The increase in rock strength thus obtained is sufficient to maintain and / or restore its structure and to absorb the stresses of the projection157 272 around the excavation. The amount of tension is constantly kept at a level such that the rocks through which the bolt passes are compressed and cannot expand. A series of rocks, fastened with bolts, with a structure and properties similar to pre-stressed concrete, transfers the loads into the rock and rock mass.
Sposób kotwienia według wynalazku umożliwia znacznie rozszerzenie zakresu stosowania kotwi wklejanych w górnictwie.The anchoring method according to the invention makes it possible to considerably expand the range of use of bonded bolts in mining.
157 272157 272
Zakład Wydawnictw UP RP. Nakład 90 egz.Department of Publishing of the UP RP. Circulation of 90 copies
Cena 5000 zł.Price PLN 5,000.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| PL27009288A PL157272B1 (en) | 1988-01-11 | 1988-01-11 | Method for rock anchoring |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| PL27009288A PL157272B1 (en) | 1988-01-11 | 1988-01-11 | Method for rock anchoring |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| PL270092A1 PL270092A1 (en) | 1989-07-24 |
| PL157272B1 true PL157272B1 (en) | 1992-05-29 |
Family
ID=20040122
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PL27009288A PL157272B1 (en) | 1988-01-11 | 1988-01-11 | Method for rock anchoring |
Country Status (1)
| Country | Link |
|---|---|
| PL (1) | PL157272B1 (en) |
-
1988
- 1988-01-11 PL PL27009288A patent/PL157272B1/en unknown
Also Published As
| Publication number | Publication date |
|---|---|
| PL270092A1 (en) | 1989-07-24 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| Peng et al. | Roof bolting in underground mining: a state-of-the-art review | |
| Villaescusa et al. | Ground support technology for highly stressed excavations: integrated theoretical, laboratory, and field research | |
| Martin et al. | A new experimental and analytical study of fully grouted rockbolts | |
| Al-Shayea | Displacement of rods during pullout failure of rock anchors: a case study | |
| RU2320875C1 (en) | Mine support method and device | |
| Guntumadugu | Methodology for the design of dynamic rock supports in burst prone ground | |
| Aldrian et al. | Bolting with pumpable reactive resins–More than fixation of steel dowels in rock | |
| Scott | Interior rock reinforcement fixtures | |
| Farah et al. | An investigation of the dynamic characteristics of cable bolts | |
| Choquet et al. | Rock bolting practical guide | |
| Brady et al. | Rock support and reinforcement | |
| Rataj et al. | Development of roofbolting in Australian coal mining | |
| SU1513146A1 (en) | Method of supporting development working | |
| Lu | Geomechanical behaviour of laminated, weak roof strata and development of an appropriate reinforcement strategy | |
| SU968439A1 (en) | Roof bolting | |
| EP0758419B1 (en) | Ground support | |
| Seegmiller et al. | Bolts and anchors | |
| Seedsman | Further Considerations on the Application of De-Bonded Cables | |
| Gerdeen et al. | Design Criteria for Roof Bolting Plans Using Fully Resin-Grouted Nontensioned Bolts to Reinforce Bedded Mine Roof. 5 Volume Set, Volume 1–Executive Summary and Literature Review | |
| Hasmukh et al. | Recent Trends on Rock Bolting in Tunnel Construction | |
| Kendorski | Caving operations drift support design | |
| Villaescusa et al. | Excavation reinforcement using cement grouted split set bolts | |
| Singh et al. | Central Mining Research Institute, Dhanbad, India | |
| Ortlepp et al. | Reinforcement support of concrete shaft lining in Westonaria formation lava in the Ezulwini vertical shaft system | |
| Singh et al. | The Status of Art of Cable Bolting |