PL218534B1 - Methane removal system for the caving area in longwalls with cavings - Google Patents

Methane removal system for the caving area in longwalls with cavings

Info

Publication number
PL218534B1
PL218534B1 PL395596A PL39559611A PL218534B1 PL 218534 B1 PL218534 B1 PL 218534B1 PL 395596 A PL395596 A PL 395596A PL 39559611 A PL39559611 A PL 39559611A PL 218534 B1 PL218534 B1 PL 218534B1
Authority
PL
Poland
Prior art keywords
methane
drainage
methane drainage
caving
valve
Prior art date
Application number
PL395596A
Other languages
Polish (pl)
Other versions
PL395596A1 (en
Inventor
Jan Drenda
Jan Kania
Stanisław Szweda
Józef Markowicz
Marek Jaszczuk
Zenon Różański
Lech Domagała
Grzegorz Pach
Dariusz Musioł
Krzysztof Słota
Original Assignee
Politechnika Śląska
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Politechnika Śląska filed Critical Politechnika Śląska
Priority to PL395596A priority Critical patent/PL218534B1/en
Publication of PL395596A1 publication Critical patent/PL395596A1/en
Publication of PL218534B1 publication Critical patent/PL218534B1/en

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Treatment Of Sludge (AREA)
  • Gas Separation By Absorption (AREA)

Abstract

Instalacja odmetanowania strefy zawału w ścianach zawałowych, charakteryzuje się tym, że ma wysięgniki zawałowe z wbudowanymi zawałowymi przewodami odmetanowania (2) połączonymi z króćcami (3) zbiorczego ścianowego przewodu odmetanowania (4), za pomocą złączy z zabezpieczeniem przed samoczynnym odłączeniem.The caving zone methane drainage installation in the caving walls is characterized by the fact that it has caving booms with built-in caving methane drainage conduits (2) connected to the stubs (3) of the collective longwall methane drainage conduit (4) by means of connectors with protection against automatic disconnection.

Description

Przedmiotem wynalazku jest instalacja odmetanowania strefy zawału w ścianach zawałowych stosowana celem odsysania mieszaniny metanowo - powietrznej ze strefy zawału przodka ścianowego prowadzonego z zawałem stropu. Odsysanie mieszaniny metanowo-powietrznej ze strefy zawału przodka ścianowego spowoduje zmniejszenie stężenia metanu za sekcjami zmechanizowanej obudowy ścianowej, zmniejszenie wydzielania się metanu ze strefy zawału do przedziału roboczego wyrobiska ścianowego oraz zmniejszenie liczby lub wyeliminowanie występujących lokalnie dużych stężeń metanu w przypadku pracy kombajnu na końcówce ściany.The subject of the invention is the installation for methane drainage of the fall zone in the caving walls, used to suck the methane-air mixture from the fall zone of the longwall face with the fall of the roof. Suction of the methane-air mixture from the fall zone of the longwall longwall will reduce the concentration of methane downstream of the mechanized longwall support sections, reduce the release of methane from the fall zone to the working compartment of the longwall excavation, and reduce the number or eliminate locally high methane concentrations in the case of the roadheader's operation at the end of the longwall.

Znane i stosowane dotychczas w praktyce górniczej różne sposoby zwalczania zagrożeń metanowych.Various methods of combating methane hazards known and used so far in mining practice.

Znany jest m.in. z polskiego opisu patentowego nr 114 988 sposób odmetanowania wyrobisk górniczych poprzez wprowadzanie powietrza rozrzedzającego niebezpieczne koncentracje metanu, który polega na tym, że wentylacyjne powietrze prowadzone wyrobiskiem ścianowym do nadścianowego chodnika rozdziela się na dwa strumienie. Jeden strumień jest kierowany przy czole chodnika usytuowanym w linii zawałowej, a drugi pod ciśnieniem dodatkowo zadanym jest kierowany lutniociągiem bezpośrednio pod strop tego chodnika, skąd po zmieszaniu z metanem łączy się z pierwszym strumieniem, aby razem wypłynąć z zagrożonego miejsca.He is known, among others from the Polish patent description No. 114 988, a method of methane drainage in mining excavations by introducing air diluting dangerous methane concentrations, which consists in the ventilation air led through the longwall heading to the over-the-wall tunnel, divided into two streams. One stream is directed at the head of the pavement situated in the caving line, and the other, under additional pressure, is directed via a duct directly under the roof of this pavement, from where, after mixing with methane, it joins the first stream to flow out of the endangered place together.

Znane sposoby często okazują się mało skuteczne.The known methods often turn out to be ineffective.

Instalacja odmetanowania według wynalazku charakteryzuje się tym, że ma wysięgniki zawałowe z wbudowanymi zawałowymi przewodami odmetanowania połączonymi z króćcami zbiorczego ścianowego przewodu odmetanowania, za pomocą złączy z zabezpieczeniem przed samoczynnym odłączeniem. Na króćcach odmetanowania wychodzących ze zbiorczego ścianowego przewodu odmetanowania zainstalowane są zawory do zamknięcia zawałowych przewodów odmetanowania, jeżeli stężenie metanu w zawałowych przewodach odmetanowania jest mniejsze od 30%. Przed każdym zaworem zamykającym w króćcach odmetanowania, znajduje się wentyl lub zaślepiony króciec, pozwalający na pomiar stężenia metanu metanomierzem przenośnym w każdym zawałowym przewodzie odmetanowania.The methane drainage installation according to the invention is characterized in that it has caving booms with built-in cave methane drainage pipes connected to the stub pipes of the collective methane drainage pipe by means of couplings with protection against automatic disconnection. Valves are installed on the methane drainage pipes coming out of the bulk methane drainage pipes to close the goblet methane drainage pipes, if the concentration of methane in the gank methane drainage pipes is lower than 30%. In front of each shut-off valve in the methane drainage nozzles, there is a valve or a blanked spigot, which allows the measurement of methane concentration with a portable methane meter in each cavage methane drainage pipe.

Na końcu zbiorczego ścianowego przewodu odmetanowania zainstalowany jest zawór automatyczny z metanomierzem rejestrująco - blokującym 6, który w przypadku zmniejszenia się stężenia metanu poniżej 30% w zasysanej z zawału mieszaninie metanowo - powietrznej, powoduje zamknięcie zaworu automatycznego i blokadę przepływu tej mieszaniny.An automatic valve with a recording and blocking methane meter 6 is installed at the end of the bulk methane drainage pipe, which, in the event of a decrease in methane concentration below 30% in the methane-air mixture sucked in from the bank, closes the automatic valve and blocks the flow of this mixture.

Instalacja odmetanowania strefy zawału w ścianach zawałowych powoduje efektywne i skuteczne ujęcie metanu ze stref odprężonych zawału, w trakcie eksploatacji, co w konsekwencji powoduje obniżenie poziomu zagrożenia metanowego podczas eksploatacji ścian w pokładach metanowych oraz zabezpiecza strefę zawału ścian przed zwiększonym wypływem mieszaniny metanowo - powietrznej z zawału do przestrzeni roboczej ściany.The installation of methane drainage of the collapse zone in the collapsing walls results in an effective and efficient collection of methane from the relaxation zones of the collapse, during operation, which in turn reduces the level of methane hazard during the exploitation of walls in methane seams and protects the collapse zone of walls against increased outflow of methane-air mixture from the collapse to the working space of the wall.

Przedmiot wynalazku objaśniono w przykładzie wykonania na rysunku, który przedstawia schemat wyrobiska ścianowego z kombajnem i sekcjami zmechanizowanej obudowy ścianowej. W wyrobisku ścianowym z sekcjami obudowy ścianowej zabudowano instalację odmetanowania strefy zawału w ścianach zawałowych wyposażoną w zawałowe wysięgniki odmetanowania 1 z wymiennymi segmentami rurowymi, ciągniętymi przez te sekcje w cyklu ich technologicznego przesuwania, z za wałowymi przewodami odmetanowania 2, króćce odmetanowania 3, zbiorczy ścianowy przewód odmetanowania 4, zawory z wentylami usytuowanymi na króćcach odmetanowania 5, zawór automatyczny z metanomierzem rejestrująco - blokującym 6, rurociąg odmetanowania 7. Z sekcji zmechanizowanej obudowy ścianowej do strefy zawału przodka ścianowego wprowadzone są wytrzymałe na ciśnienie skał zawałowych zawałowe wysięgniki odmetanowania i z wymiennymi segmentami osłaniające, znajdujące się w ich środku, zawałowe przewody odmetanowania 2, połączone ze zbiorczym ścianowym przewodem odmetanowania 4 rozciągniętym w przestrzeni roboczej ściany od strony zawału. Zawałowe wysięgniki odmetanowania 1 z wymiennymi segmentami mogą być przedłużane i przyjmować długości od kilku do kilkudziesięciu metrów.The subject of the invention is explained in the embodiment in the drawing, which shows a diagram of a longwall working with a shearer and sections of a mechanized longwall lining. In the longwall excavation with sections of the longwall lining, there is a methane drainage system for the collapse zone in the caving walls equipped with caving booms for methane drainage 1 with replaceable pipe segments, pulled by these sections in the process of their technological shifting, with after the shaft methane drainage pipes 2, methane drainage connectors 3, collective longwall pipe methane drainage 4, valves with valves located on the methane drainage nozzles 5, automatic valve with a recording and blocking methane meter 6, methane drainage pipeline 7. From the mechanized longwall support section to the cave zone of the longwall face, cave-down methane drainage booms with replaceable shielding segments are introduced, in their center, caving methane drainage pipes 2, connected with a collective wall methane drainage pipe 4 stretched in the working space of the wall from the side of the bank. Cave methane drainage booms 1 with replaceable segments can be extended and take lengths from several to several dozen meters.

Długość zawałowego wysięgnika odmetanowania według wynalazku, w strefie zawału, limitowana jest dopuszczalnym 30% stężeniem metanu w zawałowym przewodzie odmetanowania. Wytworzone podciśnienie w strefie zawału wokół końcówki zawałowego wysięgnika odmetanowania powoduje odsysanie mieszaniny metanowo-powietrznej ze szczelin w półkulistej przestrzeni strefy zawałuThe length of the cave-over methane drainage boom according to the invention, in the caving zone, is limited by the permissible 30% methane concentration in the cave-over methane drainage pipe. The created negative pressure in the collapse zone around the tip of the collapse of the methane drainage boom causes suction of the methane-air mixture from the gaps in the hemispherical space of the collapse zone

PL 218 534 B1 o promieniu zależnym od wartości podciśnienia, które można zmieniać w zawałowych przewodach odmetanowania 2 poprzez zawory.With a radius which depends on the value of the negative pressure, which can be changed in the gully methane drainage lines 2 via valves.

Grubość ścianek wymiennych segmentów zawałowego wysięgnika odmetanowania 1 powinna mieć co najmniej 5 mm, aby nie nastąpiło ich odkształcenie (zgniecenie) przez skały zawałowe.The thickness of the removable sections of the methane drainage boom 1 should be at least 5 mm thick to prevent their deformation (crushing) by caving rocks.

Claims (4)

1. Instalacja odmetanowania strefy zawału w ścianach zawałowych, znamienna tym, że ma wysięgniki zawałowe z wbudowanymi zawałowymi przewodami odmetanowania 2 połączonymi z króćcami 3 zbiorczego ścianowego przewodu odmetanowania 4 za pomocą złączy z zabezpieczeniem przed samoczynnym odłączeniem.1. System for methane drainage of the collapse zone in caving walls, characterized in that it has caving booms with built-in collapsed methane drainage pipes 2 connected with stub pipes 3 of the collective wall methane drainage pipe 4 by means of couplings with protection against automatic disconnection. 2. Instalacja odmetanowania według zastrz. 1, znamienna tym, że na króćcach odmetanowania 3 wychodzących ze zbiorczego ścianowego przewodu odmetanowania 4 zainstalowane są zawory 5 do zamknięcia zawałowych przewodów odmetanowania 2, jeżeli stężenie metanu w zawałowych przewodach odmetanowania 2 jest mniejsze od 30%.2. Methane drainage installation according to claim A method as claimed in claim 1, characterized in that valves 5 are installed on the methane drainage pipes 3 leading from the methane drainage manifold 4 to close the methane drainage gaps 2 if the concentration of methane in the methane drainage gaps 2 is less than 30%. 3. Instalacja odmetanowania według zastrz. 1, znamienna tym, że przed każdym zaworem zamykającym 5 w króćcach odmetanowania 3, znajduje się wentyl lub zaślepiony króciec, pozwalający na pomiar stężenia metanu metanomierzem przenośnym w każdym zawałowym przewodzie odmetanowania 2.3. Methane drainage installation according to claim A valve according to claim 1, characterized in that upstream of each shut-off valve 5 in the methane drainage pipes 3, there is a valve or a blanked pipe, allowing the measurement of methane concentration with a portable methane meter in each gobble methane drainage line 2. 4. Instalacja odmetanowania według zastrz. 1, znamienna tym, że na końcu zbiorczego ścianowego przewodu odmetanowania 4 zainstalowany jest zawór automatyczny z metanomierzem rejestrująco - blokującym 6, który w przypadku zmniejszenia się stężenia metanu poniżej 30% w zasysanej z zawału mieszaninie metanowo - powietrznej, spowoduje zamknięcie zaworu automatycznego i blokadę przepływu tej mieszaniny.4. Methane drainage installation according to claim 1, characterized in that an automatic valve with a recording and blocking methane meter 6 is installed at the end of the bulk methane drainage pipe 4, which, in the event of a decrease in the methane concentration below 30% in the methane-air mixture sucked in from the bank, will close the automatic valve and block the flow this mixture.
PL395596A 2011-07-11 2011-07-11 Methane removal system for the caving area in longwalls with cavings PL218534B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PL395596A PL218534B1 (en) 2011-07-11 2011-07-11 Methane removal system for the caving area in longwalls with cavings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PL395596A PL218534B1 (en) 2011-07-11 2011-07-11 Methane removal system for the caving area in longwalls with cavings

Publications (2)

Publication Number Publication Date
PL395596A1 PL395596A1 (en) 2013-01-21
PL218534B1 true PL218534B1 (en) 2014-12-31

Family

ID=47624780

Family Applications (1)

Application Number Title Priority Date Filing Date
PL395596A PL218534B1 (en) 2011-07-11 2011-07-11 Methane removal system for the caving area in longwalls with cavings

Country Status (1)

Country Link
PL (1) PL218534B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106223995A (en) * 2016-08-25 2016-12-14 中煤科工集团重庆研究院有限公司 Method for analyzing gas extraction effect of underground coal seam area based on monitoring historical data

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106223995A (en) * 2016-08-25 2016-12-14 中煤科工集团重庆研究院有限公司 Method for analyzing gas extraction effect of underground coal seam area based on monitoring historical data
CN106223995B (en) * 2016-08-25 2019-01-29 中煤科工集团重庆研究院有限公司 Method for analyzing gas extraction effect of underground coal seam area based on monitoring historical data

Also Published As

Publication number Publication date
PL395596A1 (en) 2013-01-21

Similar Documents

Publication Publication Date Title
CN105041374B (en) High methane Goaf of Close Distance Coal Seams gas cooperates with control method with coal fire
US6851757B2 (en) Mining method
CN106979031B (en) Gas drainage system and tunnel structure in tunnel
CN102865099B (en) Under-building, under-railway and under-water mining filling process
CN110894794B (en) Comprehensive treatment method for gas on fully mechanized caving face of three-soft extra-thick coal seam
CN102094669A (en) Three-dimensional source separated pressure-releasing gas treatment method
RU2013129695A (en) BOTTOM EQUIPMENT WITH A HOSE WELDER LAYED ON IT FOR DETERMINING THE ALTITUDE OF THE INDIVIDUAL ELEMENTS OF THE BOTTOM EQUIPMENT
US9752207B2 (en) Systems and methods for recovery of metals and components
CN102518873A (en) Method for paving large-diameter pipeline in soft soil in jacking and pulling combined manner
CN104018844B (en) Shield machine hydraulic pressure air pressure balance control system in water rich strata and control method thereof
CN108386199A (en) The safe and efficient driving method of the projecting coal bed shield of high methane and device
PL218534B1 (en) Methane removal system for the caving area in longwalls with cavings
CN108678804B (en) Hydraulic perforation unmanned gas extraction method
CN107288655A (en) A method for strengthening the surrounding rock by grouting in the existing tunnel with two lines of the shield tunnel
CN106437742A (en) Earth pressure balance shield construction uprush control device and method in water-rich surrounding rock
PL219797B1 (en) Method for direct methane removal and inerting infarct zone in the longwall face
CN202381844U (en) Tool pipe applicable to laying large-diameter pipelines in soft soil in jacking and pulling combination mode
CN102777183B (en) Hydraulic coal mining process for bottom plate roadway
PL218821B1 (en) Direct methane removal and inertization method for the caving area of the heading
CN104863630A (en) Heading machine used for emergency rescue channel of well mine roadway roof
CN210217823U (en) Dust removal device for opencast coal mine
CN203717026U (en) Inert gas protection system for coalmine gob area
RU2415266C1 (en) Method of coal extraction from chambers with pre-production mining of methane
RU2462599C1 (en) Method of hydraulic flushing
Li A technology to extract coal mine gas using thin sub-layer mining with hydraulic jet