Steel bracket for supporting a prefabricated element on another structure element

Info

Publication number
PL72015Y1
PL72015Y1 PL128390U PL12839019U PL72015Y1 PL 72015 Y1 PL72015 Y1 PL 72015Y1 PL 128390 U PL128390 U PL 128390U PL 12839019 U PL12839019 U PL 12839019U PL 72015 Y1 PL72015 Y1 PL 72015Y1
Authority
PL
Poland
Prior art keywords
prefabricated
steel bracket
steel
supporting
another structure
Prior art date
Application number
PL128390U
Other languages
Polish (pl)
Other versions
PL128390U1 (en
Inventor
Marcin Luber
Przemysław Borek
Original Assignee
Pekabex Bet Spolka Akcyjna
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pekabex Bet Spolka Akcyjna filed Critical Pekabex Bet Spolka Akcyjna
Priority to PL128390U priority Critical patent/PL72015Y1/en
Publication of PL128390U1 publication Critical patent/PL128390U1/en
Publication of PL72015Y1 publication Critical patent/PL72015Y1/en

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Reinforcement Elements For Buildings (AREA)

Description

PL 72 015 Y1 2 Opis wzoru Przedmiotem wzoru uzytkowego jest stalowy wspornik sluzacy do oparcia elementu prefabryko- wanego na innym elemencie konstrukcji. Znane sa rozwiazania umozliwiajace oparcie prefabrykowanych belek na slupie lub plyt stropo- wych na belkach za pomoca wsporników zelbetowych wykonstruowanych w elementach, które sa opar- ciem dla reszty konstrukcji. W kazdym wsporniku osadzone sa pionowo prety zbrojeniowe. Natomiast w prefabrykowanej belce osadzona jest rura na etapie jej produkcji. Po zamontowaniu belki na budowie pret zbrojeniowy zostaje umieszczony w rurze, a nastepnie jest zalany zaprawa niskoskurczowa wyso- kiej wytrzymalosci. Stalowy wspornik sluzacy do oparcia elementu prefabrykowanego na innym elemencie konstruk- cji wedlug wzoru uzytkowego, charakteryzuje sie tym, ze zawiera stalowa rure majaca w przekroju po- przecznym ksztalt prostokata i dwa prety zbrojeniowe o ksztalcie zblizonym do litery „L”, które polaczone sa nierozlacznie z przeciwleglymi sciankami tej rury. Z rura polaczony jest równiez nierozlacznie pret zbrojeniowy majacy ksztalt zblizony do litery „U”, którego konce ramion obejmuja rure. Dluzsze ramiona dwóch pretów zbrojeniowych o ksztalcie litery „L” usytuowane sa równolegle do scian rury. Wszystkie prety zbrojeniowe stalowego wspornika zabetonowane sa w dolnym elemencie kon- strukcyjnym na etapie jego produkcji w zakladzie. Po ustawieniu tego elementu prefabrykowanego w docelowym miejscu, zostaje wykonany górny element prefabrykowany opierajacy sie na tym dolnym elemencie. W górnym elemencie prefabrykowanym znajduje sie stalowa rura. Zarówno dolny element konstrukcji, jak i górny element prefabrykowany moga miec rózne ksztalty oraz spelniac rózne funkcje. Moga byc belka lub plyta. Stalowy wspornik wedlug wzoru uzytkowego charakteryzuje sie prosta budowa realizowana ko- rzystnie za pomoca polaczen spawanych. Wspornik sklada sie z prostych elementów, które z latwoscia moga byc przygotowane w zakladzie prefabrykacji, eliminujac tym samym koniecznosc korzystania z poddostawców. Stalowy wspornik powoduje zmniejszenie zuzycia materialów, zwlaszcza betonu po- trzebnego do wykonstruowania wspornika. Przedmiot wzoru uzytkowego uwidoczniony jest na rysunku, na którym fig. 1 przedstawia stalowy wspornik w widoku z boku, fig. 2 przedstawia stalowy wspornik w widoku z przodu, fig. 3 – stalowy wspornik, którego prety zbrojeniowe zabetonowane sa w dolnym elemencie konstrukcji, fig. 4, 5, 6 przedstawiaja schematycznie w widoku z przodu róznego ksztaltu elementy prefabrykowane oparte na stalowym wsporniku. Wspornik zawiera stalowa rure 1, majaca w przekroju poprzecznym ksztalt prostokata, z która polaczone sa nierozlacznie dwa prety zbrojeniowe 2 majace ksztalt zblizony do litery „L”. Prety te pola- czone sa z przeciwleglymi sciankami rury. Z rura polaczony jest równiez nierozlacznie pret zbroje- niowy 3 majacy ksztalt zblizony do litery „U”. Konce ramion tego preta obejmuja rure i usytuowane sa prostopadle do jej dolnej scianki. Natomiast dluzsze ramiona 4 pretów zbrojeniowych 2 usytuowane sa równolegle do scian stalowej rury. Stalowy wspornik jest czesciowo zabetonowany w zakladzie produ- kujacym elementy prefabrykowane w ten sposób, ze dluzsze ramiona 4 pretów zbrojeniowych oraz pret zbrojeniowy 3 sa zabetonowane w dolnym elemencie konstrukcji 5, 5’, 5’’. Stalowa rura jest usytuowana nieco powyzej tego elementu i równolegla do jego powierzchni. Po umieszczeniu tego elementu w do- celowym miejscu wbudowania, zostaje zabudowany górny element prefabrykowany 6, 6’, 6’’ opierajacy sie na dolnym elemencie konstrukcji. Stalowa rura 1 zostaje wypelniona betonem, co zapewnia odpo- wiednie zabezpieczenie polaczenia na dzialanie czynników zewnetrznych i spelnia wymóg odpornosci przeciwpozarowej. PL PL PL PL PL PL PL 72 015 Y1 2 Description of the model The subject of the utility model is a steel bracket used to support a prefabricated element on another element of the structure. There are known solutions that allow supporting prefabricated beams on a column or floor slabs on beams with the use of reinforced concrete supports constructed in the elements that support the rest of the structure. Reinforcing bars are mounted vertically in each bracket. On the other hand, a pipe is embedded in the prefabricated beam at the stage of its production. After the beam is installed at the construction site, the reinforcement rod is placed in the pipe, and then the high-strength low-shrinkage mortar is poured in. A steel bracket used to support a prefabricated element on another structure element according to a utility pattern, characterized by the fact that it comprises a steel pipe with a rectangular cross-section and two reinforcing bars with a shape close to the letter "L", which are inseparably connected with opposite sides of this pipe. The pipe is also inseparably connected with a reinforcement rod, which has a shape similar to the letter "U", the ends of which embrace the pipe. The longer legs of two L-shaped reinforcing bars are located parallel to the pipe walls. All the reinforcing bars of the steel bracket are concreted in the lower structural element at the stage of its production in the plant. After this prefabricated element is positioned in its final position, an upper prefabricated element is made resting on this lower element. There is a steel tube in the upper prefabricated element. Both the lower element of the structure and the upper prefabricated element can have different shapes and fulfill different functions. It can be a beam or a plate. The utility pattern steel bracket is characterized by a simple structure, preferably by means of welded joints. The bracket consists of simple elements that can easily be prepared in the prefabrication plant, thus eliminating the need for sub-suppliers. The steel bracket reduces the consumption of materials, especially the concrete needed for the construction of the bracket. The subject of the utility model is shown in the drawing, in which fig. 1 shows a steel bracket in a side view, fig. 2 shows a steel bracket in a front view, fig. 3 - a steel bracket, the reinforcement bars of which are concreted in the lower element of the structure, fig. 4, 5, 6 schematically show the front view of the various shapes of prefabricated elements based on a steel support. The support comprises a steel tube 1 having a rectangular cross-section to which two reinforcing bars 2 having a shape similar to the letter "L" are inseparably connected. These bars are connected to the opposite walls of the pipe. A reinforcement rod 3 having a shape similar to the letter "U" is also inseparably connected to the pipe. The ends of the arms of this bar embrace the tube and are perpendicular to its bottom wall. On the other hand, the longer arms 4 of the reinforcing bars 2 are situated parallel to the walls of the steel pipe. The steel bracket is partially concreted in the factory producing prefabricated elements in such a way that the longer arms 4 of the reinforcing bars and the rebar 3 are concreted in the lower element of the structure 5, 5 ', 5' '. The steel tube is positioned slightly above this element and parallel to its surface. After placing this element in the target place of installation, the upper prefabricated element 6, 6 ", 6" is built in, resting on the lower element of the structure. The steel pipe 1 is filled with concrete, which ensures adequate protection of the connection against external factors and meets the requirement of fire resistance. PL PL PL PL PL PL

Claims (1)

Zastrzezenia ochronneProtective reservations 1. Stalowy wspornik sluzacy do oparcia elementu prefabrykowanego na innym elemencie kon- strukcji, znamienny tym, ze zawiera stalowa rure (1) majaca w przekroju poprzecznym ksztalt prostokata i dwa prety zbrojeniowe (2) o ksztalcie zblizonym do litery „L”, które polaczone sa nierozlacznie z przeciwleglymi sciankami stalowej rury, oraz ze stalowa rura polaczony jest równiez nierozlacznie pret zbrojeniowy (3) majacy ksztalt zblizony do litery „U”, którego konce obejmuja ta rure. PL PL PL PL PL PL1. A steel bracket used to support a prefabricated element on another structural element, characterized in that it comprises a steel tube (1) with a rectangular cross-section and two reinforcing bars (2) with a shape similar to the letter "L", which are connected they are inseparable from the opposite walls of the steel tube, and that the steel tube is also inseparably connected with a reinforcement rod (3) having a shape similar to the letter "U", the ends of which are enclosed by this tube. PL PL PL PL PL PL
PL128390U 2019-07-02 2019-07-02 Steel bracket for supporting a prefabricated element on another structure element PL72015Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PL128390U PL72015Y1 (en) 2019-07-02 2019-07-02 Steel bracket for supporting a prefabricated element on another structure element

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PL128390U PL72015Y1 (en) 2019-07-02 2019-07-02 Steel bracket for supporting a prefabricated element on another structure element

Publications (2)

Publication Number Publication Date
PL128390U1 PL128390U1 (en) 2021-01-11
PL72015Y1 true PL72015Y1 (en) 2021-06-14

Family

ID=74121375

Family Applications (1)

Application Number Title Priority Date Filing Date
PL128390U PL72015Y1 (en) 2019-07-02 2019-07-02 Steel bracket for supporting a prefabricated element on another structure element

Country Status (1)

Country Link
PL (1) PL72015Y1 (en)

Also Published As

Publication number Publication date
PL128390U1 (en) 2021-01-11

Similar Documents

Publication Publication Date Title
CN108035554B (en) Construction method of section steel column support frame of super high-rise building frame column
KR101259156B1 (en) Method constructing precasting water-storage tank
CN210827825U (en) An assembled air-conditioning panel and its preparation mold
EP1925757A1 (en) Method for prefabricating the metal reinforcement of beams and columns for standard-length mixed steel/concrete structures and a telescopic beam
PL72015Y1 (en) Steel bracket for supporting a prefabricated element on another structure element
CN210767249U (en) A wall panel connection node suitable for the interior of the core tube of the outer steel plate concrete composite shear wall
TWM510942U (en) Precasted concrete foundation for upright shape steel post
RU2632592C1 (en) Reinforced formwork block and building structure
CN114232840B (en) Assembled type combined connecting wall frame structure and construction method
PL71271Y1 (en) Fastener of the precast column reinforcing bar with the foundation
RU2713826C2 (en) Method for manufacturing of prefabricated-monolithic reinforced-concrete resting on contour slabs of floors with round cavities using non-extractable cardboard-polyethylene cavities
KR100579586B1 (en) Composite reinforced concrete beam construction system using FRP structure used as permanent structure
KR20170118349A (en) deck for wall form
RU178522U1 (en) Precast monolithic overlap
JP2006316414A (en) Prop and its manufacturing method
PL173565B1 (en) Rigid cross-braced reinforcement combined with boarding
PL70800Y1 (en) Fastener of the precast column reinforcing bar with the push-in connection of the lower floor column or the foundation
KR101110744B1 (en) Vertical Post Tension Structure Of Sloping Structure And Its Construction Method
CN109826414B (en) Outer protective frame capable of turning over for assembled shear wall structure and construction method thereof
KR930003882Y1 (en) Reinforced truss plate
BE1022928B1 (en) Method for manufacturing a concrete column
RU144088U1 (en) PROFILED SHEET FOR FIXED FORMWORK
BE1019217A3 (en) METHOD FOR CONSTRUCTING A CONCRETE FLOOR FOR A BUILDING, A BUILDING CONSTRUCTED ACCORDING TO THIS METHOD, AND A CONCRETE FLOOR ELEMENT USE IN THIS METHOD.
RU150049U1 (en) ELEMENT OF MONOLITHIC CONCRETE COVERING
ES1291390U (en) Floor -forged system (Machine-translation by Google Translate, not legally binding)