WO2004067959A1 - Verfahren zur errichtung einer windenergieanlage sowie windenergieanlage - Google Patents
Verfahren zur errichtung einer windenergieanlage sowie windenergieanlage Download PDFInfo
- Publication number
- WO2004067959A1 WO2004067959A1 PCT/EP2004/000918 EP2004000918W WO2004067959A1 WO 2004067959 A1 WO2004067959 A1 WO 2004067959A1 EP 2004000918 W EP2004000918 W EP 2004000918W WO 2004067959 A1 WO2004067959 A1 WO 2004067959A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- power module
- tower
- wind
- foundation
- container
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/20—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
- F03D13/22—Foundations specially adapted for wind motors
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D80/00—Details, components or accessories not provided for in groups F03D1/00 - F03D17/00
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/10—Assembly of wind motors; Arrangements for erecting wind motors
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/20—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/20—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
- F03D13/25—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors specially adapted for offshore installation
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D80/00—Details, components or accessories not provided for in groups F03D1/00 - F03D17/00
- F03D80/60—Cooling or heating of wind motors
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D9/00—Adaptations of wind motors for special use; Combinations of wind motors with apparatus driven thereby; Wind motors specially adapted for installation in particular locations
- F03D9/20—Wind motors characterised by the driven apparatus
- F03D9/25—Wind motors characterised by the driven apparatus the apparatus being an electrical generator
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01F—MAGNETS; INDUCTANCES; TRANSFORMERS; SELECTION OF MATERIALS FOR THEIR MAGNETIC PROPERTIES
- H01F27/00—Details of transformers or inductances, in general
- H01F27/02—Casings
- H01F27/025—Constructional details relating to cooling
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2230/00—Manufacture
- F05B2230/60—Assembly methods
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2240/00—Components
- F05B2240/10—Stators
- F05B2240/14—Casings, housings, nacelles, gondels or the like, protecting or supporting assemblies there within
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2240/00—Components
- F05B2240/90—Mounting on supporting structures or systems
- F05B2240/95—Mounting on supporting structures or systems offshore
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2250/00—Geometry
- F05B2250/20—Geometry three-dimensional
- F05B2250/23—Geometry three-dimensional prismatic
- F05B2250/231—Geometry three-dimensional prismatic cylindrical
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2260/00—Function
- F05B2260/20—Heat transfer, e.g. cooling
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2260/00—Function
- F05B2260/60—Fluid transfer
- F05B2260/64—Aeration, ventilation, dehumidification or moisture removal of closed spaces
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01F—MAGNETS; INDUCTANCES; TRANSFORMERS; SELECTION OF MATERIALS FOR THEIR MAGNETIC PROPERTIES
- H01F27/00—Details of transformers or inductances, in general
- H01F27/08—Cooling; Ventilating
- H01F27/085—Cooling by ambient air
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/727—Offshore wind turbines
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P70/00—Climate change mitigation technologies in the production process for final industrial or consumer products
- Y02P70/50—Manufacturing or production processes characterised by the final manufactured product
Definitions
- the invention relates to a method for erecting a wind energy installation and the wind energy installation itself in its design.
- the object of the invention is now to develop a method by means of which the construction of wind energy plants can be carried out even more cheaply, but above all also faster.
- the power module is arranged in a container which has walls which lie between the wall of the tower and the power module.
- the power module therefore experiences its own encasement or is accommodated in a separate room within the tower of the wind turbine.
- the particular advantage of this solution is that it can be used in a special way to ensure that offshore wind turbines do not immediately affect the power module and the electrical equipment installed when water enters the tower.
- transformer and the other parts of the power module such as switchgear, inverters, etc.
- switchgear inverters
- inverters etc.
- these components are accommodated in a separate room within the wind turbine, it is also relatively easy to separate these components from the rest of the indoor air inside the tower of the wind turbine. Under certain circumstances, this can be very important in a wind energy installation if it is operated as an offshore wind energy installation and therefore a certain salt content in the air is not improbable. Due to the housing of the electrically sensitive parts, these can in principle be kept away from the salty internal air inside the tower of the wind energy plant, for example by the housing and the power module also being equipped with a walk-in lock.
- air can be introduced into the cooling channels (via a fan) through appropriate cooling channels that lead into the interior of the tower and, for example, also run along the wall of the tower, and then gets cooled in again the housing back so that the same air is always circulated within the housing and this may not be saline air is enriched in the rest of the tower interior.
- the power module in the container can deviate from the previous design of wind turbines after the foundation of the
- the power modules are already prefabricated and mounted on brackets, so that the power modules can be set up on the tower foundation or a platform and the entire operational production, in particular the laying of, using a crane, which is required anyway to set up a wind turbine Cables as well as the entire operational preparation of the wind turbine by setting individual control modules, fitting the switch cabinets etc. can take place in a protected room and these activities can be started after the tower has been erected.
- the supports of the power modules and / or the containers for the power module have support feet on their underside, which in turn rest on prepositioned plates on the tower foundation. These plates are already inserted at certain positions during the creation of the foundation and fixed in the foundation, so that a later installation of the line modules can be carried out very easily.
- empty pipes are provided for the cables that lead out of the wind energy installation, in particular the power transmission cables, control cables, etc.
- empty tube cross members are provided in the foundation of a wind energy installation or above the foundation, and these empty tube cross members fix the empty tubes in a defined position.
- the crossbeams are held in place by means of holding arms, which in turn are precisely predetermined in parts of the foundation or on the lower section of the cable feed that the cables that extend from the power module into the foundation have a standardized, shortest and optimal cable route.
- the measures according to the invention thus also facilitate the entire electrical installation of the wind energy installation by prefabricating individual modules or standardization such as empty tube cross members, power module supports, etc., even when the foundation is being set up.
- the entire installation time of the wind energy installation can be significantly reduced.
- the invention can also reduce the costs for the entire construction of the wind energy installation without having to accept any technical disadvantages.
- FIG. 1 shows a top view of a pre-set foundation (without concrete filling) with steel reinforcement 1 and 2, on an empty pipe 3, which is held by means of a strut with a lowermost tower section adjoining the reinforcement. Furthermore, support plates 5 can be seen, which are attached for holding arms in the lowermost tower section (which for the most part will no longer be visible after the wind energy installation has been erected).
- the empty pipe 3 is later used to hold cables, for example the power cables, via which the entire electrical energy of the wind power installation is discharged to the network via underground cables. Often, not only a single tube, but several tubes is provided for this.
- Figure 2 shows the foundation section after pouring the concrete. It can be seen here that the empty pipes remain in their pre-fixed position and the supporting plates are also concreted in. When concreting, it must be ensured that the supporting plates rest snugly on the construction concrete and thus ensure a flat load transfer. The concrete extends to the top edge of the base plates and is carefully worked into the edge of the plate. After the concrete has hardened, the holding arms for holding the supporting plates and the crossbeams for fixing the empty pipes can be removed and reused for the construction of further systems.
- the tower is not placed on the foundation section, as was customary until then, in order to further erect the wind turbine, but instead the power module according to the invention is placed on the support plates.
- Such a power module 7 is shown in FIG. 3 in a two-part design without a housing, the power module also being able to consist of further parts.
- the two parts of the power module 7 are placed one above the other and the entire power module consists of two superimposed carriers 8, which in turn hold essential parts of the power modules, for example the transformer, inverter, switch cabinets, medium-voltage system, etc.
- the stacked beams are built like a frame and fit exactly one above the other, so that a reliable attachment to each other is guaranteed.
- the individual beams have, among other things, four vertically aligned spars that span a rectangle and are connected to one another. These spars are screwed together on their top and bottom.
- the tower After installing the electrical power module on the foundation, the tower is erected and placed over the power module.
- the outer dimensions of the power module with regard to width and length are smaller than the inner diameter of the tower in the lower tower area / foundation area.
- the wind turbine After the tower has been erected, the wind turbine is equipped with the machine house as usual, the rotor is assembled and used for commissioning. Appropriate electrical connections are made between the generator and the power module and the power module (output of the transformer) is connected to the power supply network.
- the connection between the power module and the network can also be established extremely quickly and cheaply, the overall cable lengths being optimized because the empty pipes are positioned there and therefore the straps emerge from the foundation where they are required in a standardized, optimized design for connection to the corresponding parts of the power module.
- the wind power plant is no longer necessarily accessed in the fixed foundation area through a conventional door, but through a door (access) that is positioned in such a way that it is in the area above the tower or Medium-voltage parts of the power module open.
- a corresponding ladder or staircase can be provided on the outside of the tower.
- a corresponding intermediate platform is then provided in the area of the access door of the tower, which the personnel entering the tower can then climb to climb further inside the tower in the wind energy installation or to make settings at various control devices or to read measurement data.
- a wind power installation of the type according to the invention is one that regularly has a nominal output of more than 100 kW, preferably a nominal output in the range of 500 kW, 1 MW, 1.5 MW or significantly more.
- the intermediate platform is preferably provided with a closable plate through which the personnel can enter the lower area of the power module. With the flap closed, the lower part of the power module is further secured against unauthorized access.
- the inner diameter of the tower in the foundation area can be several meters.
- B. is 100 m 2 or more and therefore a sufficiently large area for receiving the power modules is available.
- power module this means in particular the converter and network transfer area of the wind power plant.
- These are in particular the units such as transformers or inverters or emergency switches as well as the medium-voltage control cabinet or the distributors.
- the power module should be housed in a separate container or room within the wind turbine.
- This container can consist of a cylindrical tube, which is placed over the entire power module after the power module has been placed on the foundation, or the power module is already housed inside the cylindrical tube at the factory, so that the entire power module is transported for transporting the cylindrical tube ,
- the container can also be largely closed on all sides, but is provided with at least one access door and if the power module is designed on several levels within the tube, it is also possible for the different levels of the power module to be accessed via stairs or ladders inside of the module.
- An additional space can be provided within the container, which is available, for example, as a changing room and / or lounge for people such as service technicians, etc. This is particularly useful if the invention is implemented in offshore wind turbines and, in the event of bad weather, the technicians are forced to remain within the wind turbine for a certain time.
- This room should therefore also be provided with the most necessary utensils that enable a longer stay, such as fresh water, food, sleeping facilities, communication devices.
- this room can take on a lock function and can be hermetically sealed against the interior of the wind turbine.
- people can e.g. in the event of a fire in the wind turbine, rescue there and arrange for its recovery and wait.
- the housing consists of a cylindrical tube
- the upper and lower tube ends or any additional openings that may be present can be closed for transport to the body or the upper and lower tube ends are tightly closed from the start, so that transport is possible even in heavy weather to the construction site or an interruption in construction activity does not entail the risk that seawater or moisture can get into the container and thus into the electrically sensitive parts of the power module.
- the container is also equipped in such a way that air can be exchanged between the interior of the power module and the inside of the tower of the wind turbine.
- air can be exchanged between the interior of the power module and the inside of the tower of the wind turbine.
- a heat emission of the waste heat of the power module to the interior of the tower can take place outside the power module.
- a closed air circuit can be provided for the power module, which transfers the heat via a suitable heat exchanger, e.g. in the form of a cooling coil, to the interior of the tower.
- air shafts Air shafts
- these air shafts on the one hand lead into the housing, and these air shafts on another Place again in the chilled air to return to the enclosure.
- Fans at the entrance and / or exit of the individual air shafts must be used to set up forced convection of the air inside the housing. If these air ducts (air shafts) are guided in direct contact with the tower of the wind turbine, for example also in several layers one above the other, the air inside the air ducts is cooled because the tower wall itself forms a cooling element, which from the outside is always air or Water flows around.
- the above-mentioned variant has the particular advantage that the interior of the housing is then always separated from the interior of the tower and if the wind energy installation is an offshore wind energy installation, the interior of the housing is very securely protected from it, with possibly salty air entering the Inside the tower has come into contact. This protects all electrical parts of the power module inside the housing against the contact of very aggressive air, such as salty air, without measures being necessary to protect the entire interior of the tower from the ingress of salty air.
- a fire protection device within the housing, which is activated when a fire breaks out there.
- This fire protection device can also consist, for example, in that the entire device is flooded with an inert gas, for example C0 2 , so that the oxygen content within the housing is reduced and the necessary oxygen is thus removed from a possible fire.
- an inert gas for example C0 2
- a gas such as nitrogen or another inert gas can also be entered.
- This inert gas is stored in the tank and is opened via one or more sensors, which respond in the event of a fire (or at a very high temperature), via a valve that closes the tank with the inert gas, so that the inert gas is very quickly into the housing can flow in.
- safety devices are designed to prevent the inert gas from flowing into the housing when there are people.
- Such a safety device can, for example, also contain switching elements which are activated by the operating personnel when the housing is inspected, so that the inflow of the inert gases into the housing is then prevented.
- the housing is provided with a lock, which is preferably made of a glass fiber reinforced plastic (GRP).
- GFP glass fiber reinforced plastic
- the housing is also connected to a further tank within which largely salt-free air is stored and which is then pressed into the housing when operating personnel want to go into the housing via the lock.
- Such an agent can be, for example, a Peltier element.
- the means for desalination of the air as well as for reducing the moisture are activated if appropriate, if corresponding sensors which respond to the salt content in the air or the moisture determine that a certain salt value or moisture values have been exceeded.
- the means for desalting the air and for reducing the moisture are then activated until the salt content and / or moisture content has fallen below at least a predetermined value.
- the housing with the power module enclosed in it can be set up on the foundation of the wind energy installation or on a platform within the tower of the wind energy installation. This platform can preferably also be installed very high up just below the nacelle of the wind turbine in order to ensure the best possible way that as little salt as possible can get into the housing in a wind turbine that is set up as an offshore turbine ,
- the data that the sensors measure for the salt content and / or the moisture are forwarded to a control center in which the entire wind energy installation is controlled or monitored.
- the means for reducing the salinity or for reducing the moisture within the housing can be activated via the control center.
- the housing according to the invention can not only be accommodated within the wind energy installation, but can also be attached directly to the outside of the tower. This can be done, for example, by attaching the entire housing to the outside of the tower on a platform or is attached directly to the tower. If the housing is designed as a closed pipe and this pipe is arranged on the outside of the tower, the housing can be accessed via a door or lock to the housing and the interior of the tower. With this variant, too, it is easily possible for the interior of the housing to be cooled via air ducts which protrude into or surround the tower, without the outside air surrounding the wind power installation coming into contact with the air inside the housing.
- the housing is constructed in several parts, so that, for example when replacing a single part of the power module, it is not necessary to remove the entire housing, but only the module part of the housing which directly surrounds the part of the power module to be replaced.
- FIG. 5 shows a side view of a wind power installation 12 according to the invention with a tower 9.
- FIG. 6 shows a section along the line AA in FIG. 5. It can be seen in FIG. 6 that an enclosure 10 is located between the power module 7 and the tower wall lies, wherein this housing 10 can also be a tube.
- FIG. 7 shows a longitudinal section through the tower area. It can be seen here that the housing 10 in turn completely shields the power module 7 from the tower wall 9.
- the air inside the housing is flowed into an air cooling duct 12 via a fan 11 and this air duct 12 is partly mounted directly on the tower wall 9, so that in particular the heated air can be cooled there and then in turn into the housing 10 can flow back.
- the air cooling ducts can take any shape, in particular can also be guided spirally along the tower wall 9 in order to achieve optimal cooling of the air within the air duct 12.
- FIG. 8 shows an exploded view of a wind energy installation according to the invention, in which it can be seen that different parts of the wind energy installation lie on different levels within an enclosure.
- FIG. 9 shows a partial cutout in a top view of one of the planes shown in FIG. 8.
- FIG. 9 shows a top view (in outline) of the entrance level (third level), in which a control cabinet, control desk, DUV desk, etc. are accommodated.
- the floor slabs laid there can be removed in order to transport parts that are below this level to the third level and thus also to the entrance and exit level. This may be important if, for example, a part has to be moved from the first and second level by means of a crane to the third level in order to then be transported outside via the entrance of the wind turbine.
- FIG. 11 shows a partial tear-out on a power cabinet level.
- Such cabinet levels can also be in several levels, eg. B. in the 4th, 5th, 6th and 7th level, because larger systems regularly require several power cabinets and may not be able to accommodate all of them on one level.
- wall openings for exhaust air are provided on each level, so that exhaust air can be led out through collecting ducts and into the tower of the wind energy installation, where the air is then cooled by heat exchange with the tower wall.
- the air pressure inside the housing is different from the air pressure outside the housing, in particular also the air pressure outside the housing but inside the tower.
- a heating and / or cooling device is formed within the housing and / or in one of the air ducts, so that the temperature can be influenced within the housing.
- a heating device may make sense if the system - for whatever reason - is shut down for a longer period has stood and cools in winter to temperatures that are undesirable.
- the cooling of the air inside the housing can be carried out very effectively and quickly with a cooling device (e.g. heat exchanger).
- the entire housing is designed as a self-supporting device, so that the entire housing can be transported and in particular moved on a crane with the devices accommodated in the housing.
- the housing is a pipe (e.g. made of steel), such a solution is readily possible.
- the advantage of this solution is, in particular, that the entire housing, together with all the parts contained therein, can then be manufactured in the factory and thus in the highest quality and only has to be transported to the installation site.
- FIGS. 12 to 16 show further details of a wind energy installation according to the invention with the power module already described.
- it describes how a lock is formed between the outer entrance to the tower of the wind energy installation and the interior of the installation, i.e. where the electronic and electrical parts of the power module are located, which prevents the entire Wind energy plant is used as an offshore wind energy plant, salty air or salt water can get into the interior of the plant and thus damage or destroy electrical or electronic parts.
- FIG. 15 shows, in a partial longitudinal section of the lower tower, different levels on which the power module may be divided and in FIG. 15, top right, the outer entrance to the inside of the tower.
- This entrance is regularly a gate or door that can be locked.
- a platform 101 extends from this door 100 inwards essentially perpendicular to the tower wall, which platform 101 is preferably directly connected to the tower, so that this platform is already accessible when the tower is erected.
- FIG. 16 shows the embodiment shown in FIG. 15 with a view from above, wherein the tubular module 7 can be seen as well as the gate 100 and the platform 101.
- platforms to the side of the platform preferably gratings, which are also fixed to the platform Tower walls are attached and which allow a person to go to the ladder 103 provided in the tower at a very early stage after the construction of the wind energy installation through the gate via the platforms 101, 102 described above.
- a space directly adjoins the platform 101 towards the inside of the tower (see also FIG. 10, lower right part of the figure), which, if necessary, together with the Space that forms above platform 101 forms a closed lock.
- the area of this lock space is shown in dashed lines in FIG. 16.
- This door 104 is preferably moisture-proof, so that if under certain circumstances Moisture enters the lock room, cannot get through the door 104 into the interior of the system.
- FIG. 12 shows a top view of the entrance door 100 of the wind power installation.
- FIG. 13 again shows an enlarged section into the lock entrance space from FIG. 16.
- FIG. 14 shows a further detailed view from FIG. 15.
- the floor of the lock entrance space is fastened to the inside of the tower itself and this floor is preferably permeable to moisture, so that when splashing water or the like when opening the entrance door 100. enters the lock entrance room, through which floor can flow.
- a water-impermeable plate which is inclined outward towards the tower wall is formed. If spray water or moisture drips from the clothing of the operating personnel into this room through the grating, this water can flow out again directly through an opening 105.
- the lock entrance space 101 can be closed by a further door 106.
- This door which is also preferably moisture-proof and watertight, separates the lock entrance room from the lock central room with the sanitary facilities already described.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Wind Motors (AREA)
Abstract
Description
Claims
Priority Applications (14)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| BRPI0406933-1A BRPI0406933B1 (pt) | 2003-02-01 | 2004-02-02 | Instalação de energia eólica, e, processo para a montagem da mesma |
| CA2513303A CA2513303C (en) | 2003-02-01 | 2004-02-02 | Method for the erection of a wind energy plant, and wind energy plant |
| AU2004207180A AU2004207180C1 (en) | 2003-02-01 | 2004-02-02 | Method for the erection of a wind energy plant and wind energy plant |
| NZ541284A NZ541284A (en) | 2003-02-01 | 2004-02-02 | A wind energy plant where in the electrical equipment resides inside a sealed housing, inside the pylon |
| DK04707228.5T DK1592886T3 (en) | 2003-02-01 | 2004-02-02 | Procedure for the construction of a wind power plant and wind power plant |
| EP04707228.5A EP1592886B1 (de) | 2003-02-01 | 2004-02-02 | Verfahren zur errichtung einer windenergieanlage sowie windenergieanlage |
| ES04707228.5T ES2557154T3 (es) | 2003-02-01 | 2004-02-02 | Procedimiento para erigir un aerogenerador y aerogenerador |
| US10/543,020 US7436084B2 (en) | 2003-02-01 | 2004-02-02 | Wind energy plant and method for use in erection of a wind energy plant |
| JP2005518656A JP4282667B2 (ja) | 2003-02-01 | 2004-02-02 | 風力発電設備の構築方法および風力発電設備 |
| SI200432285T SI1592886T1 (sl) | 2003-02-01 | 2004-02-02 | Postopek postavitve postrojenja na vetrno energijo kot tudi postrojenje na vetrno energijo |
| US11/713,151 US7504742B2 (en) | 2003-02-01 | 2007-03-02 | Method for the erection of a wind energy plant, and wind energy plant |
| US11/713,382 US7482707B2 (en) | 2003-02-01 | 2007-03-02 | Method for the erection of a wind energy plant, and wind energy plant |
| US12/072,143 US7610723B2 (en) | 2003-02-01 | 2008-02-25 | Wind energy plant with drainage |
| US12/564,141 US8291646B2 (en) | 2003-02-01 | 2009-09-22 | Wind power installation pylon interior |
Applications Claiming Priority (4)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE10304026.9 | 2003-02-01 | ||
| DE10304026 | 2003-02-01 | ||
| DE10310036.9 | 2003-03-06 | ||
| DE10310036A DE10310036A1 (de) | 2003-02-01 | 2003-03-06 | Verfahren zur Errichtung einer Windenergieanlage, Windenergieanlage |
Related Child Applications (4)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US10/543,020 A-371-Of-International US7436084B2 (en) | 2003-02-01 | 2004-02-02 | Wind energy plant and method for use in erection of a wind energy plant |
| US11/713,151 Division US7504742B2 (en) | 2003-02-01 | 2007-03-02 | Method for the erection of a wind energy plant, and wind energy plant |
| US11/713,382 Division US7482707B2 (en) | 2003-02-01 | 2007-03-02 | Method for the erection of a wind energy plant, and wind energy plant |
| US12/072,143 Division US7610723B2 (en) | 2003-02-01 | 2008-02-25 | Wind energy plant with drainage |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2004067959A1 true WO2004067959A1 (de) | 2004-08-12 |
Family
ID=32826190
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/EP2004/000918 Ceased WO2004067959A1 (de) | 2003-02-01 | 2004-02-02 | Verfahren zur errichtung einer windenergieanlage sowie windenergieanlage |
Country Status (10)
| Country | Link |
|---|---|
| US (5) | US7436084B2 (de) |
| EP (1) | EP1592886B1 (de) |
| JP (1) | JP4282667B2 (de) |
| KR (1) | KR100707111B1 (de) |
| AU (1) | AU2004207180C1 (de) |
| BR (1) | BRPI0406933B1 (de) |
| CA (1) | CA2513303C (de) |
| DK (1) | DK2278160T3 (de) |
| PL (1) | PL214873B1 (de) |
| WO (1) | WO2004067959A1 (de) |
Cited By (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2006056196A1 (en) * | 2004-11-23 | 2006-06-01 | Vestas Wind Systems A/S | A wind turbine, a method for assembling and handling the wind turbine and uses hereof |
| WO2006077084A1 (de) | 2005-01-19 | 2006-07-27 | Aloys Wobben | Stableuchte zur befeuerung eines turmes |
| US7365446B2 (en) * | 2001-09-14 | 2008-04-29 | Aloys Wobben | Wind power plant having power module mounted on tower foundation and method for use in constructing same |
| JP2008519930A (ja) * | 2004-11-10 | 2008-06-12 | ヴェスタス,ウィンド,システムズ エー/エス | 風力タービンの塔の部分、開口部のカバー装置、及び、風力タービンの塔の部分の製造方法及びその使用 |
| JP2010116925A (ja) * | 2004-09-24 | 2010-05-27 | Aloys Wobben | 発電機冷却システムを備えた風力タービン |
| WO2010010442A3 (en) * | 2008-07-23 | 2010-07-15 | Clipper Windpower, Inc. | Wind turbine tower heat exchanger |
| US7805893B2 (en) * | 2008-02-21 | 2010-10-05 | General Electric Company | Preassembled tower section of a wind power plant |
| US7806660B2 (en) | 2004-02-02 | 2010-10-05 | Aloys Wobben | Wind power plant |
| CN102269128A (zh) * | 2010-06-07 | 2011-12-07 | 上海电气风电设备有限公司 | 一种海上风力发电机组塔底内置变压系统设备的配置和布置方案 |
| WO2012072063A3 (de) * | 2010-12-03 | 2012-08-23 | Bard Holding Gmbh | Offshore-windenergieanlagen-turmfusssegment, offshore-windenergieanlage mit demselben und verfahren zur errichtung einer derartigen offshore-windenergieanlage |
| DE102012003572A1 (de) * | 2012-02-27 | 2013-08-29 | Rwe Innogy Gmbh | Offshore-Plattform-Konstruktion sowie Verfahren zur Errichtung einer Offshore-Windturbinenstation |
| EP2148089A4 (de) * | 2007-05-18 | 2013-11-13 | Mitsubishi Heavy Ind Ltd | Windgetriebener generator |
| EP2801988A3 (de) * | 2013-05-07 | 2014-12-24 | Elektro-Bauelemente GmbH | Einspeisevorrichtung |
Families Citing this family (72)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| BRPI0406933B1 (pt) * | 2003-02-01 | 2014-04-08 | Aloys Wobben | Instalação de energia eólica, e, processo para a montagem da mesma |
| DE102004063508B4 (de) * | 2004-12-27 | 2008-10-16 | Siemens Ag | Elektrisches Bauteil mit Kühlkreislauf für den Unterwasserbetrieb |
| WO2007034305A1 (en) | 2005-09-21 | 2007-03-29 | High Techonology Investments, B.V. | Combined labyrinth seal and screw-type gasket bearing sealing arrangement |
| ITBZ20050062A1 (it) | 2005-11-29 | 2007-05-30 | High Technology Invest Bv | Rotore a magneti permanenti per generatori e motori elettrici |
| ITBZ20050063A1 (it) | 2005-11-29 | 2007-05-30 | High Technology Invest Bv | Pacco di lamierini per generatori e motori elettrici e procedimento per la sua attuazione |
| PT2002120E (pt) * | 2006-03-25 | 2010-01-07 | Clipper Windpower Technology | Sistema de gestão térmica para turbina eólica |
| ES2312280B1 (es) * | 2007-07-10 | 2009-12-17 | Acciona Windpower, S.A. | Configuracion y metodo de m0ntaje de los equipos electricos de un aerogenerador. |
| US8763313B2 (en) * | 2007-11-15 | 2014-07-01 | General Electric Company | Methods and systems for assembling a tower |
| FI121052B (fi) * | 2007-12-27 | 2010-06-15 | Abb Oy | Ilmankuivain taajuusmuuttajajärjestelyä varten sekä menetelmä ilman kuivaamiseksi taajuusmuuttajajärjestelyssä |
| DE102008012664A1 (de) * | 2008-01-30 | 2009-08-06 | Repower Systems Ag | Windenergieanlage und ein Turm oder Turmsegment und eine Türzarge dafür |
| US20090223139A1 (en) * | 2008-03-05 | 2009-09-10 | Karl-Heinz Meiners | Method and system for assembling components in a tower of a wind energy turbine |
| US8646219B2 (en) * | 2008-05-30 | 2014-02-11 | General Electric Company | Fixture for locating wind turbine equipment on foundation prior to tower installation |
| ITMI20081122A1 (it) | 2008-06-19 | 2009-12-20 | Rolic Invest Sarl | Generatore eolico provvisto di un impianto di raffreddamento |
| IT1390758B1 (it) | 2008-07-23 | 2011-09-23 | Rolic Invest Sarl | Generatore eolico |
| PT2151833E (pt) * | 2008-08-07 | 2013-04-30 | Starkstrom Geraetebau Gmbh | Sistema transformador |
| US20100095617A1 (en) * | 2008-10-16 | 2010-04-22 | General Electric Wind Energy Gmbh | Wind turbine tower foundation containing power and control equipment |
| IT1391939B1 (it) | 2008-11-12 | 2012-02-02 | Rolic Invest Sarl | Generatore eolico |
| IT1391770B1 (it) | 2008-11-13 | 2012-01-27 | Rolic Invest Sarl | Generatore eolico per la generazione di energia elettrica |
| US8555600B2 (en) * | 2008-12-10 | 2013-10-15 | Cortina Innovations, S.A. De C.V. | Method for mounting in sections an annular tower for wind power generator, heliostatic power generator or chimney composed from three concrete segments or more |
| EP2376778B1 (de) * | 2008-12-17 | 2017-02-08 | XEMC Darwind BV | Einen kühlkreislauf umfassende windturbine |
| IT1392804B1 (it) | 2009-01-30 | 2012-03-23 | Rolic Invest Sarl | Imballo e metodo di imballo per pale di generatori eolici |
| WO2010103114A1 (en) | 2009-03-13 | 2010-09-16 | Xemc Darwind B.V. | Method of constructing a wind turbine and bottom tower section of wind turbine |
| IT1393937B1 (it) * | 2009-04-09 | 2012-05-17 | Rolic Invest Sarl | Aerogeneratore |
| IT1393707B1 (it) | 2009-04-29 | 2012-05-08 | Rolic Invest Sarl | Impianto eolico per la generazione di energia elettrica |
| IT1394723B1 (it) | 2009-06-10 | 2012-07-13 | Rolic Invest Sarl | Impianto eolico per la generazione di energia elettrica e relativo metodo di controllo |
| WO2011011515A1 (en) * | 2009-07-21 | 2011-01-27 | Ener2 Llc | Wind turbine |
| US8201378B2 (en) * | 2009-07-29 | 2012-06-19 | General Electric Company | Guide system for power modules |
| US20110027100A1 (en) * | 2009-07-30 | 2011-02-03 | Daniel Francis Cummane | Mobile wind power station |
| IT1395148B1 (it) | 2009-08-07 | 2012-09-05 | Rolic Invest Sarl | Metodo e apparecchiatura di attivazione di una macchina elettrica e macchina elettrica |
| IT1397081B1 (it) | 2009-11-23 | 2012-12-28 | Rolic Invest Sarl | Impianto eolico per la generazione di energia elettrica |
| IT1398060B1 (it) | 2010-02-04 | 2013-02-07 | Wilic Sarl | Impianto e metodo di raffreddamento di un generatore elettrico di un aerogeneratore, e aerogeneratore comprendente tale impianto di raffreddamento |
| BRPI1000005A2 (pt) * | 2010-02-08 | 2018-02-14 | Mitsubishi Heavy Industries, Ltd. | gerador eólico |
| DE102010011549A1 (de) | 2010-03-15 | 2011-09-15 | Repower Systems Ag | Wartungsazimutwinkel |
| IT1399201B1 (it) | 2010-03-30 | 2013-04-11 | Wilic Sarl | Aerogeneratore e metodo di rimozione di un cuscinetto da un aerogeneratore |
| IT1399511B1 (it) | 2010-04-22 | 2013-04-19 | Wilic Sarl | Generatore elettrico per un aerogeneratore e aerogeneratore equipaggiato con tale generatore elettrico |
| US20110138699A1 (en) * | 2010-06-29 | 2011-06-16 | Thomas Niehues | Rescue kit for a wind turbine, a wall for a wind turbine, and a portion of a compartment of a wind turbine |
| DE102011109215A1 (de) * | 2010-09-21 | 2012-03-22 | Dennis Patrick Steel | Zwillingsturbinensystem, das dem Wind/Wasser folgt (Windtracker), für Wind- und/oder Wasserkraft, mit optimierter Flügelform |
| JP5667822B2 (ja) * | 2010-09-21 | 2015-02-12 | 株式会社日立製作所 | 風車タワー内の部品搭載構造 |
| JP5550508B2 (ja) | 2010-09-28 | 2014-07-16 | 株式会社日立製作所 | 風力発電装置 |
| US8896144B2 (en) * | 2010-10-27 | 2014-11-25 | Carlos Wong | Wind turbine energy storage system and method |
| US8421264B2 (en) * | 2010-11-14 | 2013-04-16 | Asia Vital Components Co., Ltd. | Wind power generation device for electronic equipment |
| JP5717410B2 (ja) * | 2010-11-19 | 2015-05-13 | 三菱重工業株式会社 | ナセルカバーおよびこれを備えた風力発電装置 |
| ITMI20110378A1 (it) | 2011-03-10 | 2012-09-11 | Wilic Sarl | Macchina elettrica rotante per aerogeneratore |
| ITMI20110377A1 (it) | 2011-03-10 | 2012-09-11 | Wilic Sarl | Macchina elettrica rotante per aerogeneratore |
| ITMI20110375A1 (it) | 2011-03-10 | 2012-09-11 | Wilic Sarl | Turbina eolica |
| JP5912518B2 (ja) * | 2011-06-22 | 2016-04-27 | 株式会社日立産機システム | 静止機器 |
| US20120139256A1 (en) * | 2011-10-06 | 2012-06-07 | General Electric Company | Wind turbine installation with a self-contained power production component enclosure |
| DE102012202979A1 (de) * | 2012-02-28 | 2013-08-29 | Wobben Properties Gmbh | Windenergieanlage |
| US8677700B2 (en) | 2012-03-01 | 2014-03-25 | Thomas & Betts International, Inc. | Foundation system for electrical utility structures |
| EP2653715B1 (de) | 2012-04-19 | 2016-04-13 | Nordex Energy GmbH | Turm für eine Windenergieanlage sowie Verfahren zur Errichtung eines solchen |
| ES2639954T3 (es) | 2012-06-08 | 2017-10-30 | Vestas Wind Systems A/S | Disposición de una aparamenta en una torre de una turbina eólica |
| US20140152631A1 (en) | 2012-12-05 | 2014-06-05 | Braeburn Systems Llc | Climate control panel with non-planar display |
| US20150027068A1 (en) * | 2013-07-24 | 2015-01-29 | General Electric Company | Tower base assembly for a wind turbine |
| WO2015078476A1 (en) | 2013-11-27 | 2015-06-04 | Vestas Wind Systems A/S | An internal tower structure for a wind turbine generator |
| US10761704B2 (en) | 2014-06-16 | 2020-09-01 | Braeburn Systems Llc | Graphical highlight for programming a control |
| US9487960B2 (en) * | 2014-06-17 | 2016-11-08 | One Energy Enterprises Llc | Suspended deck systems, kits, and methods of installing, inspecting, and repairing a suspended deck system |
| MX2015014860A (es) | 2014-10-22 | 2017-03-13 | Braeburn Systems Llc | Sistema de entrada del codigo de termostato y metodo para el mismo que utiliza el identificador del conjunto de servicios. |
| CA2910895C (en) | 2014-10-30 | 2023-01-10 | Braeburn Systems Llc | System and method for monitoring building environmental data |
| MX360294B (es) | 2014-10-30 | 2018-10-29 | Braeburn Systems Llc | Sistema de edicion rapida. |
| DK178587B1 (en) * | 2015-02-02 | 2016-07-25 | Vestas Wind Sys As | Access panel for a wind turbine tower and method for securing same |
| DK178586B1 (en) | 2015-02-02 | 2016-07-25 | Vestas Wind Sys As | Wind turbine access panel and method for securing same |
| CA2920281C (en) | 2015-02-10 | 2021-08-03 | Daniel S. Poplawski | Thermostat configuration duplication system |
| US10317867B2 (en) | 2016-02-26 | 2019-06-11 | Braeburn Systems Llc | Thermostat update and copy methods and systems |
| US10319395B2 (en) * | 2016-03-11 | 2019-06-11 | Limbic Media Corporation | System and method for predictive generation of visual sequences |
| US10317919B2 (en) | 2016-06-15 | 2019-06-11 | Braeburn Systems Llc | Tamper resistant thermostat having hidden limit adjustment capabilities |
| CN106150929B (zh) * | 2016-08-05 | 2020-12-01 | 江苏金风科技有限公司 | 风力发电机组塔底冷却装置及控制方法 |
| MX2017011987A (es) | 2016-09-19 | 2018-09-26 | Braeburn Systems Llc | Sistema de gestion de control que tiene calendario perpetuo con excepciones. |
| FR3067179B1 (fr) * | 2017-06-06 | 2020-10-09 | Stx France Sa | Sous-station electrique, installation et procede de mise en place |
| US10921008B1 (en) | 2018-06-11 | 2021-02-16 | Braeburn Systems Llc | Indoor comfort control system and method with multi-party access |
| US10802513B1 (en) | 2019-05-09 | 2020-10-13 | Braeburn Systems Llc | Comfort control system with hierarchical switching mechanisms |
| US11925260B1 (en) | 2021-10-19 | 2024-03-12 | Braeburn Systems Llc | Thermostat housing assembly and methods |
| CN116906288B (zh) * | 2023-08-30 | 2025-04-04 | 华锐风电科技(集团)股份有限公司 | 风电机组塔筒的散热系统 |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3732670A1 (de) * | 1987-09-28 | 1989-04-13 | Siemens Ag | Anordnung eines transformators und eines mastes in einem freileitungsnetz zur elektrizitaetsuebertragung |
| DE9417738U1 (de) * | 1994-10-27 | 1994-12-22 | Rudersdorf, Friedemann, Dipl.-Ing., 50968 Köln | Windkraftmast mit Trafostation |
| DE20102051U1 (de) * | 2001-01-31 | 2001-05-03 | Sulz, Adolf, 16775 Gransee | Windkraftanlage mit frontal angeströmten Vertikalrotoren |
Family Cites Families (150)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US702324A (en) * | 1902-04-14 | 1902-06-10 | William Mcilvrid | Air-lock for caissons. |
| US1415645A (en) | 1921-08-01 | 1922-05-09 | Holterud Samuel | Wind wheel |
| US1523977A (en) * | 1923-08-02 | 1925-01-20 | Seeley L Pillar | Pole foundation |
| US1544863A (en) * | 1924-04-28 | 1925-07-07 | Ross Alfred | Reenforced-concrete pole base |
| US1578829A (en) * | 1924-05-03 | 1926-03-30 | John E Jennings | Mast for high-tension electric transmission |
| US1633460A (en) | 1926-07-26 | 1927-06-21 | Giuseppe Nobile | Wind-power-generating device |
| GB457231A (en) | 1934-11-10 | 1936-11-24 | Henry Kapferer | Shelter for protection against gas warfare |
| US2106557A (en) | 1935-06-22 | 1938-01-25 | Palmer C Putnam | Aero-electric generation system |
| US2417022A (en) | 1945-05-23 | 1947-03-04 | Stagg Allen | Windmill |
| AT191530B (de) | 1954-06-15 | 1957-08-26 | Western Electric Co | Gekapselte elektrische Einrichtung |
| US3095994A (en) * | 1960-06-23 | 1963-07-02 | Gen Motors Corp | Dynamoelectric machine closure means |
| US3289369A (en) * | 1964-08-11 | 1966-12-06 | Spring City Foundry Company | Light standard base hold down |
| DE1509511C3 (de) | 1965-07-30 | 1979-08-09 | Interatom Internationale Atomreaktorbau Gmbh, 5060 Bensberg | Personenschleuse für Druck- oder Sicherheitsräume |
| AT309483B (de) * | 1969-07-02 | 1973-08-27 | Manfred Dipl Ing Kuegler | Ventilator-Kühlturm in Rundbauweise zum Kühlen von Flüssigkeiten und Gasen unter Anwendung des Gegenstromprinzips |
| US3672103A (en) * | 1969-12-31 | 1972-06-27 | City Of Fort Collins | Modular utility vault |
| US3891899A (en) | 1971-07-19 | 1975-06-24 | Donald F Sparling | Concrete utility post with meter, gas line and water line |
| FR2225591B1 (de) | 1973-04-12 | 1980-04-18 | Pennecot Jean | |
| US3912937A (en) * | 1973-07-20 | 1975-10-14 | Jerome M Lesser | Submarine electrical energy generating apparatus |
| US3942026A (en) | 1974-06-11 | 1976-03-02 | Carter Frank H | Wind turbine with governor |
| US3944839A (en) | 1974-07-18 | 1976-03-16 | Carter Frank H | Multi-windmill wheel power generator |
| US4017698A (en) * | 1975-04-02 | 1977-04-12 | Westinghouse Electric Corporation | Draw-out type circuit interrupter with modular construction |
| US4012163A (en) | 1975-09-08 | 1977-03-15 | Franklin W. Baumgartner | Wind driven power generator |
| US4068131A (en) | 1975-10-20 | 1978-01-10 | Jacobs Marcellus L | Wind electric plant |
| US4066911A (en) | 1976-10-04 | 1978-01-03 | Sarchet Douglas P | Wind-driven prime mover |
| US4228363A (en) | 1979-04-03 | 1980-10-14 | Jacobs Marcellus L | Modular wind electric power plant |
| US4272929A (en) | 1979-08-23 | 1981-06-16 | Hanson Bror H | Tower and method of construction |
| US4291233A (en) | 1980-01-29 | 1981-09-22 | Westinghouse Electric Corp. | Wind turbine-generator |
| DE3007442C2 (de) | 1980-02-28 | 1983-02-10 | Messerschmitt-Bölkow-Blohm GmbH, 8000 München | Vorrichtung zum Verankern von freitragenden hohen, dynamisch beanspruchten Strukturen |
| US4340822A (en) | 1980-08-18 | 1982-07-20 | Gregg Hendrick J | Wind power generating system |
| US4335319A (en) * | 1980-08-27 | 1982-06-15 | Charles B. Cannon | Hydro-electric power apparatus utilizing ocean currents |
| US4449053A (en) | 1981-07-27 | 1984-05-15 | Aluminum Company Of America | Vertical axis wind turbine |
| DE3132711C1 (de) * | 1981-08-19 | 1982-12-16 | M.A.N. Maschinenfabrik Augsburg-Nürnberg AG, 4200 Oberhausen | Fussgelenk zur Verbindung eines beweglichen Versorgungsturmes einer Off-Shore-Anlage mit einem Fundament |
| DE3144141C2 (de) * | 1981-11-06 | 1986-01-09 | Manfred 4053 Jüchen Janitzky | Unterirdische Schutzbunkeranlage mit mehreren Schutzzellen |
| US4565929A (en) | 1983-09-29 | 1986-01-21 | The Boeing Company | Wind powered system for generating electricity |
| JPS60195382A (ja) | 1984-03-19 | 1985-10-03 | Hitachi Ltd | 海水用水力機械 |
| US4551631A (en) * | 1984-07-06 | 1985-11-05 | Trigilio Gaetano T | Wind and solar electric generating plant |
| AU572675B2 (en) * | 1984-07-23 | 1988-05-12 | Hitchins, W.G. | Foundation with bolting means |
| US4609827A (en) | 1984-10-09 | 1986-09-02 | Nepple Richard E | Synchro-vane vertical axis wind powered generator |
| JPS61112780A (ja) | 1984-10-25 | 1986-05-30 | Naomi Kikuchi | 風力発電機 |
| JPS61105768A (ja) | 1984-10-27 | 1986-05-23 | Mitsubishi Electric Corp | ビデオカセツトレコ−ダ |
| US4722999A (en) * | 1985-05-03 | 1988-02-02 | Yale University | Cyclophilin |
| JPS6220678A (ja) | 1985-07-19 | 1987-01-29 | Matsushita Seiko Co Ltd | 風力暖房装置 |
| US4772999A (en) | 1986-12-16 | 1988-09-20 | Merlin Gerin | Static converter, especially for an uninterruptible electrical power supply system |
| US4842224A (en) * | 1987-10-20 | 1989-06-27 | The United States Of American As Represented By The Administrator, National Aeronautics And Space Administration | Suitport extra-vehicular access facility |
| US4976087A (en) * | 1987-12-07 | 1990-12-11 | Edward Pizzino | Method of forming footing and laying first course of block |
| US4873028A (en) | 1988-02-22 | 1989-10-10 | Baltimore Aircoil Company, Inc. | Low silhouette cooling tower with trapezoidal fill and method of air flow therethrough |
| US5050356A (en) * | 1988-07-19 | 1991-09-24 | Houston Industries Incorporated | Immured foundation |
| US4999966A (en) * | 1988-07-19 | 1991-03-19 | Houston Industries Incorporated | Method of forming an-before "immured" |
| US4987719A (en) * | 1988-12-29 | 1991-01-29 | Goodson Jr Albert A | Reinforced concrete building construction and method of forming same |
| US5075564A (en) | 1989-12-19 | 1991-12-24 | Hickey John J | Combined solar and wind powered generator with spiral surface pattern |
| US5140855A (en) * | 1990-11-13 | 1992-08-25 | Biological Monitoring, Inc. | Monitoring tank modules and array for use with biological sensors |
| US5140856A (en) | 1990-12-03 | 1992-08-25 | Dynamic Rotor Balancing, Inc. | In situ balancing of wind turbines |
| JP2575960B2 (ja) | 1991-03-01 | 1997-01-29 | 株式会社トプコン | 自動レンズ研削装置 |
| DE4143243A1 (de) | 1991-12-31 | 1993-07-01 | Emmerich Tetkov | Kuehlzelle zur einlagerung und bevorratung von lebensmitteln u. dgl. |
| US5254876A (en) * | 1992-05-28 | 1993-10-19 | Hickey John J | Combined solar and wind powered generator with spiral blades |
| US5437519A (en) * | 1992-08-26 | 1995-08-01 | Roger Bullivant Of Texas, Inc. | Piles and pile forming methods |
| US5285112A (en) * | 1992-09-21 | 1994-02-08 | Star Energy Company, L.L.C. | Fluid energy collection system |
| DE4241952C2 (de) | 1992-12-12 | 1996-03-07 | Licentia Gmbh | Schaltanlagen-Container |
| US5499482A (en) | 1993-08-06 | 1996-03-19 | Ptmw, Incorporated | Structure and method for encapsulating an existing building |
| JPH07122438A (ja) | 1993-10-22 | 1995-05-12 | Tohoku Denki Seizo Kk | 電柱一体形変圧器 |
| US5487849A (en) | 1993-12-03 | 1996-01-30 | Tower Tech, Inc. | Pultruded cooling tower construction |
| SE503948C2 (sv) | 1993-12-15 | 1996-10-07 | Mafi Ab | Mast |
| NL9400506A (nl) | 1994-03-30 | 1995-11-01 | Samenwerkingen Energiebedrijf | Betonnen transformatorhuis. |
| DE9411575U1 (de) | 1994-07-16 | 1994-09-15 | Winter, Reinhard, 18528 Bergen | Längsachsenwindturbine |
| US5586417A (en) * | 1994-11-23 | 1996-12-24 | Henderson; Allan P. | Tensionless pier foundation |
| JP3002107B2 (ja) * | 1994-12-19 | 2000-01-24 | 勤伍 内藤 | 柱脚構造及び柱脚工法 |
| JPH0993729A (ja) | 1995-09-25 | 1997-04-04 | Tokyo Electric Power Co Inc:The | 電気機器収容箱の扉錠 |
| DE29518899U1 (de) | 1995-12-01 | 1997-01-09 | G. Mokinski & Sohn KG, 33442 Herzebrock-Clarholz | Sohlenelement für ein Transformatoren-Häuschen o.dgl. |
| US5806262A (en) * | 1995-12-05 | 1998-09-15 | Schuylkill Products, Inc. | Post and method of emplacing a post |
| US5845230A (en) | 1996-01-30 | 1998-12-01 | Skf Condition Monitoring | Apparatus and method for the remote monitoring of machine condition |
| DE59811213D1 (de) | 1997-05-14 | 2004-05-27 | Betonbau Gmbh | Elektrische Umspannstation |
| US5969693A (en) * | 1997-11-10 | 1999-10-19 | Edwards And Keley Wireless, L.L.C. | Multi-user antenna telecommunication tower |
| DK9700453U3 (da) | 1997-12-01 | 1998-03-13 | Ove Mejlholm | Transformatormodul til placering i vindmølle |
| JP2001526357A (ja) | 1997-12-08 | 2001-12-18 | シーメンス アクチエンゲゼルシヤフト | 風力発電設備及び風力発電設備の発電機の冷却方法 |
| US6097104A (en) * | 1999-01-19 | 2000-08-01 | Russell; Thomas H. | Hybrid energy recovery system |
| DE19816483C2 (de) | 1998-04-14 | 2003-12-11 | Aloys Wobben | Windenergieanlage |
| DE19853790A1 (de) | 1998-11-21 | 2000-05-31 | Wilhelm Groppel | Windkraftanlage |
| US6191496B1 (en) | 1998-12-01 | 2001-02-20 | Dillyn M. Elder | Wind turbine system |
| US6448669B1 (en) | 1998-12-01 | 2002-09-10 | Dillyn M. Elder | Water power generation system |
| WO2000036724A2 (en) | 1998-12-17 | 2000-06-22 | Dan-Control Engineering A/S | Wind mill with a suspension for cables and the like, such suspension for cables and the like and a holder for such suspension |
| DE19859628C1 (de) | 1998-12-23 | 2000-03-23 | Aerodyn Eng Gmbh | Vorrichtung zur Vermeidung des Eindringens von korrosiv wirkenden Salzpartikeln |
| DE19860211C1 (de) | 1998-12-24 | 2000-11-23 | Aerodyn Energiesysteme Gmbh | Verfahren zum Verlegen von elektrischen Kabeln von einer ersten Offshore-Windenergieanlage zu einer zweiten Offshore-Windenergieanlage |
| JP2000213451A (ja) | 1999-01-22 | 2000-08-02 | Hitachi Zosen Corp | 風力発電装置 |
| JP2000265938A (ja) | 1999-03-17 | 2000-09-26 | Hitachi Ltd | 風力発電の雷保護システム |
| US6272810B1 (en) * | 1999-05-24 | 2001-08-14 | Jack L. Ingram | Method and system for providing foundation and perimeter stem walls for mobile homes |
| WO2001006121A1 (de) | 1999-07-14 | 2001-01-25 | Aloys Wobben | Windenergieanlage mit einem geschlossenen kühlkreislauf |
| DE19941306C1 (de) * | 1999-08-31 | 2001-01-18 | Monforts Textilmaschinen Gmbh | Rollenkette |
| US6530553B1 (en) * | 1999-09-20 | 2003-03-11 | Philip A. Diorio | Method and apparatus for making concrete buildings |
| DE19948194C2 (de) | 1999-10-06 | 2001-11-08 | Aloys Wobben | Verfahren zur Überwachung von Windenergieanlagen |
| DE19950620C1 (de) * | 1999-10-20 | 2001-04-12 | Aloys Wobben | Rotorblatt |
| ES2160078B1 (es) | 1999-11-23 | 2002-05-01 | Marrero O Shanahan Pedro M | Torre eolica con aceleracion de flujo. |
| DE19962453C1 (de) | 1999-12-22 | 2001-07-12 | Aerodyn Eng Gmbh | Offshore-Windenergieanlage mit Subsysteme aufnehmenden austauschbaren Containern |
| IL134724A0 (en) | 2000-02-24 | 2001-04-30 | Giltek Telecomm Ltd | Foundation for a tower and a method for its deployment on site |
| US6665990B1 (en) | 2000-03-06 | 2003-12-23 | Barr Engineering Co. | High-tension high-compression foundation for tower structures |
| DK200000086U3 (da) | 2000-03-09 | 2000-05-12 | Villy Bruun A S Elautomatik | Fleksibel og justerbar indbygningsmodul til vindmøller |
| ATE284487T1 (de) | 2000-03-17 | 2004-12-15 | Gen Electric | Offshore-windkraftanlage |
| DE10013442C1 (de) | 2000-03-17 | 2001-10-31 | Tacke Windenergie Gmbh | Windkraftanlage |
| DK174156B1 (da) | 2000-04-03 | 2002-07-29 | Henrik Frans Christensen | Vind- og bølgeenergianlæg |
| US20010038207A1 (en) * | 2000-05-02 | 2001-11-08 | Willis Jeffrey O. | Method and means for mounting a wind turbine on a tower |
| US6278198B1 (en) * | 2000-05-02 | 2001-08-21 | Valmont Industries, Inc. | Method and means for mounting a wind turbine on a tower |
| PE20020090A1 (es) * | 2000-07-11 | 2002-02-10 | Pacheco Pedro Saavedra | Generador electrico eolico marino |
| CA2424334C (en) | 2000-09-27 | 2008-07-22 | Allan P. Henderson | Perimeter weighted foundation for wind turbines and the like |
| US6470645B1 (en) | 2000-11-09 | 2002-10-29 | Beaird Industries, Inc. | Method for making and erecting a wind tower |
| GB0029498D0 (en) * | 2000-12-02 | 2001-01-17 | Oceans Engineering Ltd | A method of making a foundation |
| US6782667B2 (en) | 2000-12-05 | 2004-08-31 | Z-Tek, Llc | Tilt-up and telescopic support tower for large structures |
| DE10119429A1 (de) | 2001-04-20 | 2002-10-24 | Enron Wind Gmbh | Windkraftanlage mit verschiebbarem Behälter |
| TW522764B (en) * | 2001-08-28 | 2003-03-01 | Via Tech Inc | Power layout structure on host bridge chip substrate and motherboard |
| US6661113B1 (en) | 2001-08-31 | 2003-12-09 | Walter E. Bonin | Power generator |
| DE10145414B4 (de) | 2001-09-14 | 2013-09-12 | Aloys Wobben | Verfahren zur Errichtung einer Windenergieanlage, Windenergieanlage |
| DE10226996B4 (de) | 2001-10-09 | 2014-07-03 | Aloys Wobben | Verfahren zur Erstellung eines Fundaments, insbesondere für einen Turm einer Windenergieanlage |
| DE10160306B4 (de) * | 2001-12-07 | 2004-01-15 | Wobben, Aloys, Dipl.-Ing. | Turm einer Windenergieanlage |
| DE10205988B4 (de) | 2002-02-14 | 2006-02-09 | Aloys Wobben | Windenergieanlage |
| EP1336704B1 (de) * | 2002-02-15 | 2013-02-13 | NTT Infrastructure Network Corporation | Elektrischer Betonmast und Bewehrungsmethode des Mastes |
| US6688842B2 (en) | 2002-06-24 | 2004-02-10 | Bruce E. Boatner | Vertical axis wind engine |
| US7137225B2 (en) | 2002-06-25 | 2006-11-21 | David Zuppan | Foundation wall system |
| US6666021B1 (en) * | 2002-07-12 | 2003-12-23 | Ford Global Technologies, Llc | Adaptive engine control for low emission vehicle starting |
| DE10233947A1 (de) | 2002-07-25 | 2004-02-12 | Siemens Ag | Windkraftanlage |
| DE10237908A1 (de) | 2002-08-14 | 2004-05-13 | Abb Patent Gmbh | Verfahren und Vorrichtung zum Versorgen und Warten von baulichen Einrichtungen auf dem Meer |
| DE20212512U1 (de) | 2002-08-14 | 2003-12-24 | Dautel Gmbh | Verschiebe- und Sperrvorrichtung für zwei Baueinheiten und Transportfahrzeug mit einer Vorrichtung |
| DE10245078B4 (de) | 2002-09-27 | 2005-08-11 | Aloys Wobben | Windenergieanlage |
| JP4355949B2 (ja) * | 2002-10-01 | 2009-11-04 | ゼネラル・エレクトリック・カンパニイ | 風力タービンタワー用のモジュラーキット |
| US6841894B2 (en) | 2003-01-02 | 2005-01-11 | Josep Lluis Gomez Gomar | Wind power generator having wind channeling body with progressively reduced section |
| BRPI0406933B1 (pt) * | 2003-02-01 | 2014-04-08 | Aloys Wobben | Instalação de energia eólica, e, processo para a montagem da mesma |
| JP4102278B2 (ja) | 2003-03-19 | 2008-06-18 | 三菱電機株式会社 | 風力発電システム |
| US7171787B2 (en) | 2003-06-24 | 2007-02-06 | Ch2M Hill Inc. | Rectangular tilt-up concrete tank construction |
| US6798082B1 (en) * | 2003-09-29 | 2004-09-28 | Chen Chin-Yih | Turbine wind energy generator structure for the same |
| US7185467B2 (en) | 2003-10-06 | 2007-03-06 | Oscar Marty | Modular system of permanent forms for casting reinforced concrete buildings on site |
| US7618217B2 (en) | 2003-12-15 | 2009-11-17 | Henderson Allan P | Post-tension pile anchor foundation and method therefor |
| DE602004005414D1 (de) | 2004-02-10 | 2007-05-03 | Gamesa Eolica S A Soc Uniperso | Prüfstand für Windkraftanlagen |
| KR20050088522A (ko) | 2004-03-02 | 2005-09-07 | 김영민 | 싱글 로터 방식의 수평-수직축 통합형 풍력 발전기 시스템 |
| CA2591536A1 (en) * | 2004-11-23 | 2006-06-01 | Vestas Wind Systems A/S | A wind turbine, a method for assembling and handling the wind turbine and uses hereof |
| US20060169868A1 (en) * | 2005-01-31 | 2006-08-03 | Precast Concepts, Llc | Precast concrete meter pit and method and apparatus for making same |
| US8282869B2 (en) * | 2005-01-31 | 2012-10-09 | Precast Concepts, Llc | Method for making precast concrete meter pit |
| JP4700980B2 (ja) | 2005-03-01 | 2011-06-15 | 株式会社リバーコーポレーション | ギャングウエイタワーのリプレース方法 |
| EP2390421A3 (de) * | 2005-03-16 | 2012-07-25 | Illinois Tool Works Inc. | Turmfundamentsystem und Verfahren zur Bereitstellung solch eines Systems |
| DE102005044989B3 (de) * | 2005-09-21 | 2006-12-14 | Nordex Energy Gmbh | Verfahren zur Gründung eines Fundamentkörpers für eine Windenenergieanlage |
| US7230347B2 (en) | 2005-10-14 | 2007-06-12 | General Electric Company | Corrosion protection for wind turbine units in a marine environment |
| US7762037B2 (en) * | 2005-11-18 | 2010-07-27 | General Electric Company | Segment for a tower of a wind energy turbine and method for arranging operating components of a wind energy turbine in a tower thereof |
| KR100747661B1 (ko) * | 2005-12-07 | 2007-08-08 | (주)엠씨에스공법 | 거푸집-콘크리트 복합보 및 이를 이용한 건축물 시공 방법 |
| US7178298B1 (en) | 2006-04-17 | 2007-02-20 | Ebeling Sr Albert | Building construction system and method |
| US7530780B2 (en) * | 2006-05-22 | 2009-05-12 | General Electric Company | Method and apparatus for wind power foundation |
| US7841143B2 (en) | 2006-07-05 | 2010-11-30 | Vestas Wind Systems A/S | Tower construction |
| EP2064393B1 (de) * | 2006-09-21 | 2012-07-04 | Ahmed Phuly Engineering & Consulting, Inc. | Teilweise vorgefertigtes modulares fundamentsystem |
| US8056299B2 (en) * | 2007-03-12 | 2011-11-15 | Mack Industries, Inc. | Foundation construction for superstructures |
| US7921616B2 (en) * | 2008-01-16 | 2011-04-12 | Willy Reyneveld | Method and apparatus for setting support columns within a foundation |
| US7805893B2 (en) * | 2008-02-21 | 2010-10-05 | General Electric Company | Preassembled tower section of a wind power plant |
| US20090223139A1 (en) * | 2008-03-05 | 2009-09-10 | Karl-Heinz Meiners | Method and system for assembling components in a tower of a wind energy turbine |
| ES2347742A1 (es) * | 2008-03-18 | 2010-11-03 | GAMESA INNOVATION & TECHNOLOGY S.L. | Cimentacion de aerogenerador. |
| DE102008022654A1 (de) * | 2008-05-07 | 2009-11-12 | Berg, Mario, Dr. | Verfahren und Vorrichtung zur Montage eines modulartigen Bauwerks, wie einer Windenergieanlage |
| US8646219B2 (en) * | 2008-05-30 | 2014-02-11 | General Electric Company | Fixture for locating wind turbine equipment on foundation prior to tower installation |
-
2004
- 2004-02-02 BR BRPI0406933-1A patent/BRPI0406933B1/pt not_active IP Right Cessation
- 2004-02-02 US US10/543,020 patent/US7436084B2/en not_active Expired - Lifetime
- 2004-02-02 PL PL376599A patent/PL214873B1/pl unknown
- 2004-02-02 CA CA2513303A patent/CA2513303C/en not_active Expired - Fee Related
- 2004-02-02 WO PCT/EP2004/000918 patent/WO2004067959A1/de not_active Ceased
- 2004-02-02 AU AU2004207180A patent/AU2004207180C1/en not_active Ceased
- 2004-02-02 KR KR1020057013672A patent/KR100707111B1/ko not_active Expired - Fee Related
- 2004-02-02 DK DK10180856.6T patent/DK2278160T3/en active
- 2004-02-02 EP EP04707228.5A patent/EP1592886B1/de not_active Expired - Lifetime
- 2004-02-02 JP JP2005518656A patent/JP4282667B2/ja not_active Expired - Lifetime
-
2007
- 2007-03-02 US US11/713,151 patent/US7504742B2/en not_active Expired - Lifetime
- 2007-03-02 US US11/713,382 patent/US7482707B2/en not_active Expired - Lifetime
-
2008
- 2008-02-25 US US12/072,143 patent/US7610723B2/en not_active Expired - Lifetime
-
2009
- 2009-09-22 US US12/564,141 patent/US8291646B2/en not_active Expired - Fee Related
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3732670A1 (de) * | 1987-09-28 | 1989-04-13 | Siemens Ag | Anordnung eines transformators und eines mastes in einem freileitungsnetz zur elektrizitaetsuebertragung |
| DE9417738U1 (de) * | 1994-10-27 | 1994-12-22 | Rudersdorf, Friedemann, Dipl.-Ing., 50968 Köln | Windkraftmast mit Trafostation |
| DE20102051U1 (de) * | 2001-01-31 | 2001-05-03 | Sulz, Adolf, 16775 Gransee | Windkraftanlage mit frontal angeströmten Vertikalrotoren |
Cited By (19)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US7365446B2 (en) * | 2001-09-14 | 2008-04-29 | Aloys Wobben | Wind power plant having power module mounted on tower foundation and method for use in constructing same |
| US7806660B2 (en) | 2004-02-02 | 2010-10-05 | Aloys Wobben | Wind power plant |
| JP2010116925A (ja) * | 2004-09-24 | 2010-05-27 | Aloys Wobben | 発電機冷却システムを備えた風力タービン |
| JP2008519930A (ja) * | 2004-11-10 | 2008-06-12 | ヴェスタス,ウィンド,システムズ エー/エス | 風力タービンの塔の部分、開口部のカバー装置、及び、風力タービンの塔の部分の製造方法及びその使用 |
| EP1856410B1 (de) * | 2004-11-10 | 2010-06-16 | Vestas Wind Systems A/S | Turmteil für eine windturbine, verfahren zur herstellung eines turmteils und verwendungen davon |
| US9541059B2 (en) | 2004-11-10 | 2017-01-10 | Vestas Wind Systems A/S | Tower part for a wind turbine, an aperture cover system, a method for manufacturing a tower part and uses hereof |
| US8752337B2 (en) | 2004-11-10 | 2014-06-17 | Vestas Wind Systems A/S | Tower part for a wind turbine, an aperture cover system, a method for manufacturing a tower part and uses hereof |
| US8109061B2 (en) | 2004-11-10 | 2012-02-07 | Vestas Wind Systems A/S | Tower part for a wind turbine, an aperture cover system, a method for manufacturing a tower part and uses hereof |
| JP2008520861A (ja) * | 2004-11-23 | 2008-06-19 | ヴェスタス,ウィンド,システムズ エー/エス | 風力タービン、風力タービンの組み立て及び取り扱い方法、並びにその使用 |
| WO2006056196A1 (en) * | 2004-11-23 | 2006-06-01 | Vestas Wind Systems A/S | A wind turbine, a method for assembling and handling the wind turbine and uses hereof |
| WO2006077084A1 (de) | 2005-01-19 | 2006-07-27 | Aloys Wobben | Stableuchte zur befeuerung eines turmes |
| EP2148089A4 (de) * | 2007-05-18 | 2013-11-13 | Mitsubishi Heavy Ind Ltd | Windgetriebener generator |
| US7805893B2 (en) * | 2008-02-21 | 2010-10-05 | General Electric Company | Preassembled tower section of a wind power plant |
| WO2010010442A3 (en) * | 2008-07-23 | 2010-07-15 | Clipper Windpower, Inc. | Wind turbine tower heat exchanger |
| CN102269128A (zh) * | 2010-06-07 | 2011-12-07 | 上海电气风电设备有限公司 | 一种海上风力发电机组塔底内置变压系统设备的配置和布置方案 |
| WO2012072063A3 (de) * | 2010-12-03 | 2012-08-23 | Bard Holding Gmbh | Offshore-windenergieanlagen-turmfusssegment, offshore-windenergieanlage mit demselben und verfahren zur errichtung einer derartigen offshore-windenergieanlage |
| DE102012003572A1 (de) * | 2012-02-27 | 2013-08-29 | Rwe Innogy Gmbh | Offshore-Plattform-Konstruktion sowie Verfahren zur Errichtung einer Offshore-Windturbinenstation |
| EP2631479A3 (de) * | 2012-02-27 | 2015-01-28 | RWE Innogy GmbH | Offshore-Plattform-Konstruktion sowie Verfahren zur Errichtung einer Offshore-Windturbinenstation |
| EP2801988A3 (de) * | 2013-05-07 | 2014-12-24 | Elektro-Bauelemente GmbH | Einspeisevorrichtung |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2006515400A (ja) | 2006-05-25 |
| US20100007153A1 (en) | 2010-01-14 |
| CA2513303A1 (en) | 2004-08-12 |
| US20060220386A1 (en) | 2006-10-05 |
| DK2278160T3 (en) | 2018-07-16 |
| AU2004207180B2 (en) | 2008-01-17 |
| AU2004207180A1 (en) | 2004-08-12 |
| BRPI0406933B1 (pt) | 2014-04-08 |
| JP4282667B2 (ja) | 2009-06-24 |
| US7610723B2 (en) | 2009-11-03 |
| US20070187956A1 (en) | 2007-08-16 |
| PL376599A1 (pl) | 2006-01-09 |
| US7436084B2 (en) | 2008-10-14 |
| US7504742B2 (en) | 2009-03-17 |
| EP1592886B1 (de) | 2015-10-14 |
| CA2513303C (en) | 2010-04-20 |
| AU2004207180C1 (en) | 2010-03-25 |
| US20080143118A1 (en) | 2008-06-19 |
| EP1592886A1 (de) | 2005-11-09 |
| US8291646B2 (en) | 2012-10-23 |
| US7482707B2 (en) | 2009-01-27 |
| PL214873B1 (pl) | 2013-09-30 |
| BRPI0406933A (pt) | 2006-01-03 |
| US20070152449A1 (en) | 2007-07-05 |
| KR100707111B1 (ko) | 2007-04-16 |
| KR20050096157A (ko) | 2005-10-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP1592886A1 (de) | Verfahren zur errichtung einer windenergieanlage sowie windenergieanlage | |
| EP2278160B1 (de) | Windenergieanlage | |
| EP1381775B2 (de) | Windturbineleistungsmodul auf dem turmfundament gelagert | |
| EP1478851B1 (de) | Offshore windpark | |
| EP1419350A1 (de) | Windenergieanlage | |
| DE10051513A1 (de) | Windpark | |
| EP2820294B1 (de) | Windenergieanlage mit brandschutzmodul für transformator im turm | |
| DE2209938C3 (de) | ||
| DE102006043936B4 (de) | Belüftung einer Windenergieanlage | |
| DE102004005179B4 (de) | Windenergieanlage | |
| AU2008201590B2 (en) | Method for the erection of a wind energy plant and wind energy plant | |
| DE202020101018U1 (de) | Straßentransportfähige Containereinhausung für eine elektrische Schaltanlage | |
| DE102025121897A1 (de) | Feuerfester lager- und löschbehälter für brennbare elektrische anlagen und insbesondere brennbare stromspeicher sowie verfahren zum löschen einer brennenden elektrischen anlage |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| AK | Designated states |
Kind code of ref document: A1 Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BW BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE EG ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NA NI NO NZ OM PG PH PL PT RO RU SC SD SE SG SK SL SY TJ TM TN TR TT TZ UA UG US UZ VC VN YU ZA ZM ZW |
|
| AL | Designated countries for regional patents |
Kind code of ref document: A1 Designated state(s): BW GH GM KE LS MW MZ SD SL SZ TZ UG ZM ZW AM AZ BY KG KZ MD RU TJ TM AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LU MC NL PT RO SE SI SK TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG |
|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application | ||
| WWE | Wipo information: entry into national phase |
Ref document number: 01346/KOLNP/2005 Country of ref document: IN Ref document number: 2004207180 Country of ref document: AU |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2513303 Country of ref document: CA |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 541284 Country of ref document: NZ |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2005518656 Country of ref document: JP Ref document number: 1020057013672 Country of ref document: KR |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 20048031273 Country of ref document: CN |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 376599 Country of ref document: PL |
|
| WWP | Wipo information: published in national office |
Ref document number: 2004207180 Country of ref document: AU |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2004707228 Country of ref document: EP |
|
| WWP | Wipo information: published in national office |
Ref document number: 1020057013672 Country of ref document: KR |
|
| WWP | Wipo information: published in national office |
Ref document number: 2004707228 Country of ref document: EP |
|
| ENP | Entry into the national phase |
Ref document number: PI0406933 Country of ref document: BR |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2006220386 Country of ref document: US Ref document number: 10543020 Country of ref document: US |
|
| DPEN | Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed from 20040101) | ||
| WWP | Wipo information: published in national office |
Ref document number: 10543020 Country of ref document: US |