WO2009118634A1 - Grue portuaire pour le levage et la manutention de charges, en particulier les conteneurs - Google Patents
Grue portuaire pour le levage et la manutention de charges, en particulier les conteneurs Download PDFInfo
- Publication number
- WO2009118634A1 WO2009118634A1 PCT/IB2009/005098 IB2009005098W WO2009118634A1 WO 2009118634 A1 WO2009118634 A1 WO 2009118634A1 IB 2009005098 W IB2009005098 W IB 2009005098W WO 2009118634 A1 WO2009118634 A1 WO 2009118634A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- crane according
- trolleys
- jib
- crane
- loads
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C19/00—Cranes comprising trolleys or crabs running on fixed or movable bridges or gantries
- B66C19/002—Container cranes
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/101—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means for containers
- B66C1/104—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means for containers for two or more containers side by side
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C9/00—Travelling gear incorporated in or fitted to trolleys or cranes
- B66C9/10—Undercarriages or bogies, e.g. end carriages, end bogies
- B66C9/12—Undercarriages or bogies, e.g. end carriages, end bogies with load-distributing means for equalising wheel pressure
Definitions
- the present invention relates to a port dock crane for lifting and handling loads, in particular containers.
- the dock cranes are moved into position in order to prepare for the actual loading or unloading. These cranes are positioned on the dock in front of the ship with their jibs up.
- the cranes are each equipped with their own spreaders. For some years now these so-called “twin-lift” spreader models have been utilized. These are able to handle one forty-foot container or two twenty- foot ones per cycle, and unload up to 35/40 forty-foot containers or about 60/70 twenty-foot containers per hour.
- the port is activated for all the successive sorting and distribution activities of the containers from the inbound dock to the yard or vice versa.
- the unloading of containers is done:
- the port is equipped with self-loading and self- unloading equipment such as fork-lift trucks, reach-stackers or straddle carriers that can transfer the unloaded containers to the yard where they are then stacked.
- self-loading and self- unloading equipment such as fork-lift trucks, reach-stackers or straddle carriers that can transfer the unloaded containers to the yard where they are then stacked.
- the dock cranes are able to increase their productivity. The reason for this is because by placing the container directly on the ground rather than having to place it on a trailer they can work more quickly and securely.
- the high daily layover costs of a ship in a port, in particular for large ships also have to be taken into account.
- ports that are able to release ships in a shorter time are the ones which will be able to acquire more and more traffic and attract new shipping companies. Therefore it is of great importance for ports to increase their productivity during all phases of the container handling, so that port operators can release ships as soon as possible.
- the main object of the present invention is to speed up activities of loading and unloading off and on ships, starting from the system of unloading containers on the ground in order to avoid any downtime in the area under the cranes.
- Another object of the present invention is to reduce containers loading and unloading time, on equal number of cranes used.
- the present port dock crane for lifting and handling loads, in particular containers, which comprises at least a first and a second vertical structure sliding on the ground, at least a scaffold frame mounted substantially horizontally on said vertical structures, and at least a substantially horizontal jib which extends overhanging from said scaffold frame, characterized in that at least two sliding trolleys along said jib are mounted, and each one connected to respective loads lifting units suitable for operate contemporarily with each other in order to lift and/or lower different loads to each other.
- figure 1 is a side view of the crane according to the invention
- figure 2 is a front view of the crane according to the invention
- figure 3 is a plan view of the crane according to the invention
- figure 4 is a partial and front view, on an enlarged scale, of the crane wheel boxes according to the invention
- figure 5 is a front view, on an enlarged scale, of a container hooked up and lifted by the crane according to the invention
- figure 6 is a side view of the two independent trolleys of the crane according to the invention, each trolley has two spreaders with two hooked containers
- figure 7 is a side view of one trolley of figure 6 in an alternative operating modality, wherein there is only one spreader to handle only one container
- figure 8 is a side and schematic view of another possible operating modality of one trolley of figure 6;
- a port dock crane for lifting and handling loads, in particular containers has been globally indicated by 1.
- Crane 1 comprises a first vertical bearing structure 2a, 2b and a second vertical bearing structure 3a, 3b to support a scaffold frame 4a, 4b, substantially horizontal and connected to each other.
- a substantially horizontal jib 5 extends overhanging from the scaffold frame 4a, 4b.
- Two sliding trolleys 6 along the jib 5 are mounted and provided with a pulleys series 7 which create the funicular movement of these trolleys and the relative load lifting and lowering, with respective lifting units 8 suitable for working contemporarily to lift and/or lower a plurality of containers 9 different to each other.
- the first vertical structure 2a, 2b is composed of a plurality of vertical legs 2a mounted on a carrier beam 2b which connects them and which lays on an orthogonal direction respect to jib 5.
- the first vertical structure 2a, 2b is positioned at the median portion of jib 5.
- the second vertical structure 3a, 3b is composed of two vertical legs 3a mounted on a carrier beam 3b which connects them and which lays on an orthogonal direction respect to the jib 5.
- the second vertical structure 3a, 3b is approximately positioned at the median portion of the space defined between the first vertical structure 2a, 2b and one end of jib 5.
- the first vertical structure 2a, 2b is located near the edge of the dock 10 for loading/unloading the containers 9 on/off the ship 1 1 with jib 5 which extends itself to completely cover the hold of the ship 1 1 in order to carry out the lifting and the placing of the containers 9 off and on said hold.
- To the carrier beams 2b, 3b are associated two series of wheels 12, 13 sliding on respective rails (tracks) 14 and having handling means suitable for making the entire crane 1 mobile along an orthogonal direction respect to jib 5 and parallel to the edge of the dock 10.
- These handling means aren't shown in the figures and are composed of motorized gearboxes mounted in a number to meet the necessary power requirement for handling the crane 1 on tracks 14.
- the wheels 12, 13 are made of steel and are mounted in double pairs on appropriate supports or wheel boxes 15, associated to respective motorized gearboxes suitable for allowing their movement.
- the wheel boxes 15 are anchored along the whole length of the carrier beams 2b, 3b and are associated with them through an equalizer 16 hinged on a side to the beams 2b, 3b.
- the cylinders (hydraulic jacks) 17 are connected together by a hydraulic circuit 15 that allows the transfer of the same level of oil and pressure between one cylinder and another and which hydraulic circuit is controlled by a central unit that constantly maintains the preset pressure depending on the load in any movement.
- the entire scaffold frame 4a, 4b is mounted on the top of legs 2a, 3a and consists in a perimeter structure formed by cross beams 4a, which are parallel to the carrier beams 2b, 3b, and by longitudinal beams 4b, which connect the cross beams 4a and which are parallel to jib 5.
- the cross beams 4a are associated with jib 5.
- Jib 5 is formed by a moving front section oriented towards the sea which can be raised, and if lowered, is stretched out on the whole of the hold of the ship 1 1 , and by a rear section oriented towards the land, which is fixed and integral with the cross beams 4a, which in turn are connected to the vertical legs 2a, 3a.
- the length of the rear section is almost equal to that of the front section of jib 5 to allow containers 9 to be unloaded also in the rear part of the crane 1 as well as from the part between the vertical bearing structures 2a, 2b and track 14 in order to distribute containers 9 rationally and efficiently in an optimized space in order to distribute them to the yard.
- the lifted configuration of front section of jib 5 is shown in figure 1 with dotted line.
- Jib 5 has normally two sliding trolleys 6 along the same jib and a machine room which has two lifting units (lifting winches) 8, one for each trolley 6.
- Each trolley 6 supports at least two spreaders 19 and since the crane 1 is equipped with two trolleys 6, there is a preferably total number of four spreaders 19 that can be handled simultaneously and independentlyof each other, in order to load or unload four forty-foot containers or eight twenty-foot container.
- Each trolley 6 has an equipped crosspiece 20 for holding the spreaders 19 in order to handle containers 9.
- a spacer element 21 is mounted which connect two spreaders 19, which contemporarily handle two containers 9 keeping these containers distanced to each other up to two meters (figure 8) or adjacent (figure
- Figure 5 shows a crosspiece 20 on which top portion pulleys 7 are mounted, on which there are sliding ropes 22, which in turn are connected to lifting winches
- Control cabin 23 at the end of each trolley 6 for the operator who has to execute all the necessary operations to handling containers 9 and to handling the lifting unit 8 and, in particular, the lifting, the lowering and all handling operations of trolleys 6 and containers 9 hanged up, each one, to its spreader 19 either on loading phase or on unloading phase of containers 9 from a ship.
- Control cabins 23 are mounted in the portion below the trolleys 6 and are associated to an end of them.
- figure 6 In the configuration of figure 6 is shown, for example, the solution of trolleys 6 with their control cabins 23 for contemporarily handling four containers 9 connected together two by two, in the configuration of figure 7 is shown one of the trolleys 6 with the lifting solution for only a container 9, whereas figure 8 shows the possibility to handle two containers 9 and to separate them by the spacer element 21.
- a ottimale work cycle could be: beginning from the load or unload phase of ship 1 1 the first trolley 6 of jib 5 will start to unload the last container
- rear trolley will start which will take containers 9 of row group 25, reaching for first on dock 10 and it will unload in the farthest place from ship 1 1 (covering B route of figure 1 up to D unloading zone) in order to cover almost the same distance covered by the front trolley and synchronizing themselves up to the complete end of loading and unloading operations of containers 9 on the ground or on the ship 1 1. Since distances to cover are essentially equals for both trolleys 6, work cycles are practically the same, up to the end of bay portions covered by jib 5 and by their four spreaders 19.
- Crane according to the invention, has the peculiarity to have a control cabin for each bringing spreader trolley which allows every operator to operate and control all the operations in a simply and securely way.
- Another peculiarity of the invention is given by wheel boxes which are mounted on a hydraulic suspensions unit which allow lowering and distributing weight equally either on the wheels or on the rails and, also, on the deck.
- the invention thus conceived is susceptible to numerous modifications and variations, all of which falling within the scope of the inventive concept. Furthermore all the details can be replaced with others that are technically equivalent.
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Control And Safety Of Cranes (AREA)
- Ship Loading And Unloading (AREA)
- Load-Engaging Elements For Cranes (AREA)
Abstract
L'invention concerne une grue portuaire (1) pour le levage et la manutention de charges, en particulier les conteneurs (9), qui comprend des première et seconde structures verticales (2, 3) coulissant au sol, un bâti d'échafaudage (4) monté sensiblement à l'horizontale sur les structures, et une flèche sensiblement horizontale (5) qui s'étend en surplomb depuis le bâti, le long de laquelle sont montés deux chariots coulissants (6), chacun relié à des unités de levage (19) de charge respectives capables de fonctionner de façon synchronisée, de manière à assurer le levage et/ou l'abaissement de différentes charges l'un par rapport à l'autre. Chaque chariot soutient deux écarteurs (19) pouvant être connectés par un élément espaceur (21).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| EP09726316A EP2265534A1 (fr) | 2008-03-27 | 2009-03-27 | Grue portuaire pour le levage et la manutention de charges, en particulier les conteneurs |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| ITMO2008A000089 | 2008-03-27 | ||
| ITMO20080089 ITMO20080089A1 (it) | 2008-03-27 | 2008-03-27 | Gru da banchina portuale per il sollevamento e la movimentazione di carichi, particolarmente container |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2009118634A1 true WO2009118634A1 (fr) | 2009-10-01 |
Family
ID=40293043
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/IB2009/005098 Ceased WO2009118634A1 (fr) | 2008-03-27 | 2009-03-27 | Grue portuaire pour le levage et la manutention de charges, en particulier les conteneurs |
Country Status (3)
| Country | Link |
|---|---|
| EP (1) | EP2265534A1 (fr) |
| IT (1) | ITMO20080089A1 (fr) |
| WO (1) | WO2009118634A1 (fr) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102442606A (zh) * | 2010-10-12 | 2012-05-09 | 宁波港股份有限公司北仑第二集装箱码头分公司 | 一种用于集装箱的空箱起吊装置及其安装方法 |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US3877391A (en) * | 1972-09-14 | 1975-04-15 | Krupp Gmbh | Gantry loading bridge truck |
| DE19703286A1 (de) * | 1997-01-30 | 1998-08-06 | Estebanez Eva Garcia | Verladekran |
| DE19909466A1 (de) * | 1998-03-11 | 1999-10-07 | Mannesmann Rexroth Ag | Schienengebundenes Transport- oder Fördergerät |
| WO2005090223A1 (fr) * | 2004-03-24 | 2005-09-29 | Nsl Engineering Pte Ltd | Systeme de manipulation de conteneurs |
| EP1650156A1 (fr) * | 2003-07-30 | 2006-04-26 | Shanghai Zhenhua Port Machinery Co. Ltd. | Portiques a conteneurs capables d'elinguer de doubles conteneurs de 40 pieds |
-
2008
- 2008-03-27 IT ITMO20080089 patent/ITMO20080089A1/it unknown
-
2009
- 2009-03-27 EP EP09726316A patent/EP2265534A1/fr not_active Withdrawn
- 2009-03-27 WO PCT/IB2009/005098 patent/WO2009118634A1/fr not_active Ceased
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US3877391A (en) * | 1972-09-14 | 1975-04-15 | Krupp Gmbh | Gantry loading bridge truck |
| DE19703286A1 (de) * | 1997-01-30 | 1998-08-06 | Estebanez Eva Garcia | Verladekran |
| DE19909466A1 (de) * | 1998-03-11 | 1999-10-07 | Mannesmann Rexroth Ag | Schienengebundenes Transport- oder Fördergerät |
| EP1650156A1 (fr) * | 2003-07-30 | 2006-04-26 | Shanghai Zhenhua Port Machinery Co. Ltd. | Portiques a conteneurs capables d'elinguer de doubles conteneurs de 40 pieds |
| WO2005090223A1 (fr) * | 2004-03-24 | 2005-09-29 | Nsl Engineering Pte Ltd | Systeme de manipulation de conteneurs |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102442606A (zh) * | 2010-10-12 | 2012-05-09 | 宁波港股份有限公司北仑第二集装箱码头分公司 | 一种用于集装箱的空箱起吊装置及其安装方法 |
Also Published As
| Publication number | Publication date |
|---|---|
| EP2265534A1 (fr) | 2010-12-29 |
| ITMO20080089A1 (it) | 2009-09-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO2009118638A1 (fr) | Grue de quai de port pour soulever et manipuler des charges, en particulier des conteneurs | |
| KR101107745B1 (ko) | 두 개의 병립형 스프레더를 갖는 갠트리형 적재기 | |
| US8118534B2 (en) | Container cargo transfer system | |
| US6715977B2 (en) | Loading device for ISO containers | |
| EP0318264A1 (fr) | Grue à portique pour conteneurs | |
| EP2128074A1 (fr) | Chariot cavalier | |
| NO332033B1 (no) | System for handtering av last | |
| CN103318771B (zh) | 具有三套小车的岸边起重机 | |
| KR20170033259A (ko) | 컨테이너를 위한 중간 보관 영역을 구비한 스태커 크레인 | |
| EP2743217B1 (fr) | Système de chargement et de déchargement pour contenants de bord de quai | |
| EP2265537A1 (fr) | Machine pour le levage et la manutention de charges, en particulier des conteneurs | |
| EP2377801B1 (fr) | Procédé desservant un complexe incluant deux ou plusieurs grues à flèche de quai mobiles | |
| KR20070050417A (ko) | 컨테이너 화물의 하역 및 선적시스템 | |
| CN104114470A (zh) | 具有成双的空中吊运车的船到岸起重机 | |
| JP2002068078A (ja) | 浮体構造物 | |
| WO2009118634A1 (fr) | Grue portuaire pour le levage et la manutention de charges, en particulier les conteneurs | |
| KR101037262B1 (ko) | 키이 크레인과 협력하여 부둣가의 버퍼 지브 크레인에 의해 화물 컨테이너를 처리하기 위한 방법 | |
| US20190241379A1 (en) | Method for transferring standardised containers between a container ship and a quay | |
| JPH09175781A (ja) | コンテナクレーン | |
| EP2128073B1 (fr) | Chariot cavalier | |
| JPH09315758A (ja) | コンテナクレーン | |
| WO2024228189A1 (fr) | Systèmes de transfert de conteneur horizontal du navire à la terre | |
| KR20110041775A (ko) | 레일을 이용한 컨테이너 이송 장치 | |
| KR20260024747A (ko) | 적층 컨테이너의 붕괴방지장치 | |
| Branch | Container-handling equipment |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 09726316 Country of ref document: EP Kind code of ref document: A1 |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2009726316 Country of ref document: EP |