WO2021237402A1 - Assembled lining trolley allowing for rapid turnover - Google Patents

Assembled lining trolley allowing for rapid turnover Download PDF

Info

Publication number
WO2021237402A1
WO2021237402A1 PCT/CN2020/092069 CN2020092069W WO2021237402A1 WO 2021237402 A1 WO2021237402 A1 WO 2021237402A1 CN 2020092069 W CN2020092069 W CN 2020092069W WO 2021237402 A1 WO2021237402 A1 WO 2021237402A1
Authority
WO
WIPO (PCT)
Prior art keywords
assembly
template
template assembly
mast
heightening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/CN2020/092069
Other languages
French (fr)
Chinese (zh)
Inventor
卓文泽
许修亮
林波
李彦军
侯士祥
刘磊
张魏魏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Poly Changda Overseas Engineering Co Ltd
Original Assignee
Poly Changda Overseas Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Poly Changda Overseas Engineering Co Ltd filed Critical Poly Changda Overseas Engineering Co Ltd
Priority to PCT/CN2020/092069 priority Critical patent/WO2021237402A1/en
Publication of WO2021237402A1 publication Critical patent/WO2021237402A1/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Definitions

  • the invention relates to the field of tunnel construction equipment, and more specifically, it relates to an assembled lining trolley capable of realizing rapid turnover.
  • the technical problem to be solved by the present invention is to address the above-mentioned shortcomings of the prior art and provide a fabricated lining trolley that can realize rapid turnover.
  • the vehicle can take into account the lining construction of multiple caverns, shortening the construction period.
  • a prefabricated lining trolley capable of realizing rapid turnover includes a mast assembly, a template assembly, a hydraulic system, a traverse mechanism, and a walking mechanism;
  • the mast assembly includes a basic door
  • the assembled heightening door frame is superimposed and connected to the base door frame;
  • the template assembly includes a top template assembly and a side template assembly, the top template assembly
  • the finished and side formwork assemblies are connected by hinges;
  • the mast assembly and the formwork assembly are respectively connected by a mechanical screw, a top mold cylinder and a side mold cylinder;
  • the hydraulic system is arranged on the longitudinal beam Between the bottom surface and the top surface of the traverse machine;
  • the walking mechanism is arranged at the bottom of the traverse mechanism.
  • the basic door frame includes four pieces of uprights, two pieces of upper longitudinal beams, two pieces of lower longitudinal beams, and two pieces of crossbeams; High longitudinal beams, two raised beams and one supporting beam.
  • the top template assembly includes a foundation top template and a heightened top template;
  • the edge template assembly includes a foundation edge template and a heightened edge template;
  • the top template assembly consists of an upper supporting beam, a lifting beam, The top longitudinal beam and the translation jack are composed; the top template assembly and the door frame assembly are connected with the translation jack through the lug plates arranged on the cross beam and the top longitudinal beam.
  • the traverse mechanism is composed of an upper turntable, a lower turntable and a connecting bearing; the upper turntable and the lower turntable are connected by a connecting bearing; the upper turntable and the lower turntable are provided with the same number of reserved holes , The two ends of the matching bolts are respectively inserted into the reserved holes.
  • the bottom of the walking mechanism is also provided with a servo motor and a walking wheel; the bottom of the walking wheel is provided with a track.
  • the present invention has the following advantages:
  • the assembly type lining trolley of the present invention that can realize rapid turnover introduces the concept of assembly type, and can complete rapid disassembly and assembly in situ through the assembly type door frame assembly and template assembly, and its assembly and disassembly The process is simpler than traditional trolleys, saving a lot of time.
  • An assembled lining trolley capable of realizing rapid turnover of the present invention utilizes hydraulic system, traverse mechanism and walking mechanism to realize the rapid transfer of the same trolley between multiple caverns, thereby taking into account the requirements of multiple caverns. Lining construction ensures the smoothness and safety of construction.
  • Figure 1 is a cross-sectional view of the trolley of the present invention
  • Figure 2 is a longitudinal section view of the trolley of the present invention.
  • Figure 3 is a structural diagram of the traverse mechanism of the present invention.
  • Fig. 4 is a transfer diagram of the basic portal frame of the present invention.
  • an assembled lining trolley capable of realizing rapid turnover of the present invention includes a mast assembly 1, a template assembly 2, a hydraulic system 3, a traverse mechanism 4, and a traveling mechanism 5.
  • the gantry assembly includes a basic gantry 6 and an assembled heightening gantry 7, and the assembled heightening gantry 7 is superimposed and connected to the basic gantry 6.
  • the template assembly 2 includes a top template assembly 8 and an edge template assembly 9, and the top template assembly 8 and the edge template assembly 9 are connected by hinges.
  • the mast assembly 1 and the template assembly 2 are connected by a mechanical screw 10, a top mold cylinder 11, and a side mold cylinder 12, respectively.
  • the hydraulic system 3 is arranged between the bottom surface of the longitudinal beam 38 and the top surface of the traverse mechanism 4; the walking mechanism 5 is arranged at the bottom of the traverse mechanism 4.
  • the basic gantry 6 includes four uprights 13, two upper longitudinal beams 14, two lower longitudinal beams 15 and two transverse beams 16.
  • the heightening mast 7 includes two pieces of four heightening columns 17, two pieces of heightening longitudinal beams 18, two pieces of heightening cross beams 19, and a supporting beam 20.
  • the top template assembly 8 includes a base top template 21 and an elevated top template 22, and the side template assembly 9 includes a base edge template 23 and an elevated side template 24; the top template assembly 8 consists of an upper support beam 25 , Lifting beam 26, top longitudinal beam 27 and translation jack 28.
  • the top template assembly 8 and the door frame assembly 1 are connected to the translation jack 28 through the ear plates 29 arranged on the cross beam 16 and the top longitudinal beam 27.
  • the traverse mechanism 4 is composed of an upper turntable 30 and a lower turntable 31 and a connecting bearing 32.
  • the upper turntable 30 and the lower turntable 31 are connected by a connecting bearing 32.
  • the upper turntable 30 and the lower turntable 31 are provided with the same number of reserved holes 33, and both ends of the matching bolts 34 are inserted into the reserved holes 33 respectively.
  • the bottom of the traveling mechanism 5 is further provided with a servo motor 35 and a traveling wheel 36, and the bottom of the traveling wheel 36 is provided with a track 37.
  • the trolley of the invention can quickly complete assembly and disassembly between adjacent sections.
  • the assembly principle is divided into two stages: the first stage is the assembly installation of the heightened mast.
  • the heightening mast is assembled on the ground and superimposed on the base mast by hoisting to complete the assembly of the mast assembly.
  • the second stage is the prefabricated installation of the top template assembly.
  • the top template assembly is assembled on the ground synchronously, and then superimposed on the mast assembly by hoisting to complete the second assembly.
  • the top formwork assembly is split into several top formwork assembly units, and the parts are lifted to the door frame assembly before completion A simple assembly is enough.
  • the trolley of the present invention can complete rapid transfer between non-adjacent sections, which greatly saves the time that the trolley needs to be disassembled and then transferred to the next section for reassembly.
  • the disassembly process of the trolley of the present invention is opposite to the assembling process.
  • the top formwork assembly is hoisted and unloaded to the ground, and the whole is transferred to the next section to wait for hoisting again.
  • Use the same operation to unload the heightening mast assembly to the ground, and transfer it to the next section as a whole to wait for it to be hoisted again. It is necessary to judge whether the top template assembly needs to be widened according to the size of the next section, the side template assembly should be heightened, partial parts replacement or reinforcement of the heightened mast assembly, and the mechanical screw rod Make adjustments, etc.
  • cavern A and cavern C are non-adjacent caverns of a certain underground project, they have similar or identical cross-sectional dimensions, which conform to the scope of application of the trolley of the present invention.
  • the two caverns are connected by the main channel B, and the spatial relationship is shown in Figure 4. After using the trolley of the present invention to finish the lining of the cavern A, the trolley needs to be quickly transferred to the cavern C for lining construction.
  • cavern A and cavern C are the same, and the space of cavern B is enough for the trolley to be transported without disassembly and assembly, then only need to follow 3 steps to complete the transport:
  • Step 1 Evacuate the trolley in cavern A along the track to cavern B.
  • Step 2 Put temporary support structures such as piers on the bottom surfaces of the lower longitudinal beams of each trolley, start the hydraulic system of the trolley, and allow the hydraulic cylinder to contract to drive the traverse mechanism and the traveling system to separate from the track.
  • the weight of the trolley is borne by the temporary support structure.
  • Step 3 The operation of moving the trolley to cavern C only needs to repeat the operation of step 2, rotate the walking wheel 90 degrees again to restore it to its original position, and advance cavern C to start the lining construction.
  • cavern A and cavern C are similar, or the space of cavern B is not enough for the trolley to be transported without disassembly and assembly, then only the top template assembly and side of the trolley The template assembly or heightening mast assembly is unloaded and transferred to the vicinity of the hanging point of cave C to complete the necessary heightening mast adjustment or adding top and side templates and other preparations. Then, use the operations in steps 1-3 above to move the basic door frame assembly to the vicinity of the hanging point of the cavern C, and complete the assembly-type assembly of the trolley in the cavern C.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

An assembled lining trolley allowing for rapid turnover comprises a mast assembly (1), a template assembly (2), a hydraulic system (3), a lateral movement mechanism (4), and a travelling mechanism (5). The mast assembly (1) comprises a base mast (6) and an assembled heightened mast (7). The assembled heightened mast (7) is stacked on the base mast (6) and connected thereto. The template assembly (2) comprises a top template assembly (8) and a side template assembly (9). The top template assembly (8) and the side template assembly (9) are hinge connected to each other. The mast assembly (1) and the template assembly (2) are connected to each other by means of a mechanical screw (10), a top template oil cylinder (11), and a side template oil cylinder (12). The hydraulic system (3) is provided between a bottom surface of a longitudinal beam (38) and a top surface of the lateral movement mechanism (4). The travelling mechanism (5) is provided at the bottom of the lateral movement mechanism (4). The lining trolley can be quickly disassembled and assembled on the spot, such that one trolley can be for to perform lining of multiple chambers, thereby ensuring smoothness and safety of construction, and greatly shortening a construction period.

Description

一种可实现快速周转的装配式衬砌台车Assembled lining trolley capable of realizing rapid turnover 技术领域Technical field

本发明涉及隧道施工设备领域,更具体地说,它涉及一种可实现快速周转的装配式衬砌台车。The invention relates to the field of tunnel construction equipment, and more specifically, it relates to an assembled lining trolley capable of realizing rapid turnover.

背景技术Background technique

随着国家建设的需要和区域发展的需求不断提高,地下工程的规模和种类已从传统的诸如铁路、公路、地铁、水渠等线状工程,扩展至诸如城市地下商场、地下厂房、地下洞库、人民防空工事等洞室尺寸众多的面状地下工程。在这些工程的建设中,需要开挖或者修建的隧道较多,利用衬砌台车完成混凝土的浇筑不仅能够保证混凝土结构的施工质量和美观度,而且能够减少人力成本投入、节约施工工期。As the needs of national construction and regional development continue to increase, the scale and types of underground projects have expanded from traditional linear projects such as railways, highways, subways, and canals to urban underground shopping malls, underground factories, and underground caverns. , Civil air defense fortifications and other underground projects with large cavern sizes. In the construction of these projects, there are many tunnels that need to be excavated or built. The use of lining trolleys to complete the concrete pouring can not only ensure the construction quality and aesthetics of the concrete structure, but also reduce labor costs and save construction time.

针对洞室多、且呈面状分布的地下工程而言,如果采用常规的台车进行衬砌结构的施工,会带来两个方面的负面影响:其一是所需的台车数量陡增,施工成本势必加倍;其二是台车数量增加,加大了台车在洞内周转的难度,增加了台车的拼装、拆卸时间,无疑也会影响到材料和渣土运输,从而大大增加了施工工期延误的风险。采用传统的支模脚手架方法完成此类工程的衬砌结构施工,更是不可避免需要进行反复多次的脚手架和模板拆卸及拼装,不但耗时费力致使施工成本增加,而且极易发生跑模、漏浆、错台等施工质量问题。For underground projects with many caverns and distributed in a planar shape, if conventional trolleys are used to construct the lining structure, it will bring about two negative effects: one is the sharp increase in the number of trolleys required. The construction cost is bound to double; the second is the increase in the number of trolleys, which increases the difficulty of the trolley’s turnover in the cave, increases the assembly and disassembly time of the trolley, and undoubtedly also affects the transportation of materials and muck, which greatly increases The risk of construction delays. The use of traditional formwork and scaffolding methods to complete the construction of the lining structure of this type of project requires repeated disassembly and assembly of scaffolding and formwork. Construction quality problems such as slurry and misalignment.

发明内容Summary of the invention

本发明要解决的技术问题是针对现有技术的上述不足,提供一种可实现快速周转的装配式衬砌台车,该衬砌台车能够在原地完成快速的拆卸和拼装,且能够实现一套台车可兼顾多个洞室的衬砌施工,缩短施工工期。The technical problem to be solved by the present invention is to address the above-mentioned shortcomings of the prior art and provide a fabricated lining trolley that can realize rapid turnover. The vehicle can take into account the lining construction of multiple caverns, shortening the construction period.

本发明的技术方案是这样的:一种可实现快速周转的装配式衬砌台车包括门架总成、模板总成、液压系统、横移机构以及行走机构;所述门架总成包括基础门架和装配式加高门架;所述的装配式加高门架叠加连接于基础门架上;所述的模板总成包括顶部模板总成和边部模板总成,所述的顶部模板总成和边部模板总成通过铰接方式相连;所述的门架总成与模板总成之间分别通过机械丝杆、顶模油缸和边模油缸相连;所述的液压系统设置于中纵梁底面与横移机顶面之间;所述的行走机构设置于横移机构底部。The technical scheme of the present invention is as follows: a prefabricated lining trolley capable of realizing rapid turnover includes a mast assembly, a template assembly, a hydraulic system, a traverse mechanism, and a walking mechanism; the mast assembly includes a basic door The assembled heightening door frame is superimposed and connected to the base door frame; the template assembly includes a top template assembly and a side template assembly, the top template assembly The finished and side formwork assemblies are connected by hinges; the mast assembly and the formwork assembly are respectively connected by a mechanical screw, a top mold cylinder and a side mold cylinder; the hydraulic system is arranged on the longitudinal beam Between the bottom surface and the top surface of the traverse machine; the walking mechanism is arranged at the bottom of the traverse mechanism.

进一步地,所述基础门架包括四件立柱、两件上纵梁、两件下纵梁和两件横梁;所述的装配置加高门架包括两件四件加高立柱、两件加高纵梁、两件加高横梁和一件支撑梁。Further, the basic door frame includes four pieces of uprights, two pieces of upper longitudinal beams, two pieces of lower longitudinal beams, and two pieces of crossbeams; High longitudinal beams, two raised beams and one supporting beam.

进一步地,所述顶部模板总成包括基础顶部模板和加高顶部模板;边部模板总成包括基础边部模板和加高边部模板;所述顶部模板总成由上支撑梁、抬梁、顶纵梁以及平移千斤顶组成;所述顶部模板总成和门架总成通过设置在横梁和顶纵梁上的耳板与平移千斤顶连接。Further, the top template assembly includes a foundation top template and a heightened top template; the edge template assembly includes a foundation edge template and a heightened edge template; the top template assembly consists of an upper supporting beam, a lifting beam, The top longitudinal beam and the translation jack are composed; the top template assembly and the door frame assembly are connected with the translation jack through the lug plates arranged on the cross beam and the top longitudinal beam.

进一步地,所述的横移机构由上转盘和下转盘以及连接轴承组成;所述的上转盘和下转盘通过连接轴承连接;所述的上转盘和下转盘上设置有相同数量的预留孔,配套螺栓两端分别插接于预留孔内。Further, the traverse mechanism is composed of an upper turntable, a lower turntable and a connecting bearing; the upper turntable and the lower turntable are connected by a connecting bearing; the upper turntable and the lower turntable are provided with the same number of reserved holes , The two ends of the matching bolts are respectively inserted into the reserved holes.

进一步地,所述行走机构底部还设有伺服电机和行走轮;所述的行走轮底部设有轨道。Further, the bottom of the walking mechanism is also provided with a servo motor and a walking wheel; the bottom of the walking wheel is provided with a track.

本发明与现有技术相比,具有以下优点:Compared with the prior art, the present invention has the following advantages:

1、本发明的一种可实现快速周转的装配式衬砌台车,引入装配式的理念,通过装配式的门架总成和模板总成能够在原地完成快速的拆卸和拼装,其拼装和拆卸过程比传统台车更为简单,节省大量时间。1. The assembly type lining trolley of the present invention that can realize rapid turnover introduces the concept of assembly type, and can complete rapid disassembly and assembly in situ through the assembly type door frame assembly and template assembly, and its assembly and disassembly The process is simpler than traditional trolleys, saving a lot of time.

2、本发明的一种可实现快速周转的装配式衬砌台车,利用液压系统、横移 机构以及行走机构实现同一台台车在多处洞室之间快速转移,从而兼顾多个洞室的衬砌施工,保证施工的流畅程度和安全性。2. An assembled lining trolley capable of realizing rapid turnover of the present invention utilizes hydraulic system, traverse mechanism and walking mechanism to realize the rapid transfer of the same trolley between multiple caverns, thereby taking into account the requirements of multiple caverns. Lining construction ensures the smoothness and safety of construction.

附图说明Description of the drawings

图1为本发明的台车横截面图;Figure 1 is a cross-sectional view of the trolley of the present invention;

图2为本发明的台车纵截面图;Figure 2 is a longitudinal section view of the trolley of the present invention;

图3为本发明的横移机构结构图;Figure 3 is a structural diagram of the traverse mechanism of the present invention;

图4为本发明的基础门架转运图。Fig. 4 is a transfer diagram of the basic portal frame of the present invention.

其中:1-门架总成、2-模板总成、3-液压系统、4-横移机构、5-行走机构、6-基础门架、7-装配式加高门架、8-顶部模板总成、9-边部模板总成、10-机械丝杆、11-顶模油缸、12-边模油缸、13-立柱、14-上纵梁、15-下纵梁、16-横梁、17-加高立柱、18-加高纵梁、19-加高横梁、20-支撑梁、21-基础顶部模板、22-加高顶部模板、23-基础边部模板、24-加高边部模板、25-上支撑梁、26-抬梁、27-顶纵梁、28-平移千斤顶、29-耳板、30-上转盘、31-下转盘、32-连接轴承、33-预留孔、34-配套螺栓、35-伺服电机、36-行走轮、37-轨道、38-中纵梁、A-洞室A、B-洞室B、C-洞室C。Among them: 1-door frame assembly, 2-template assembly, 3-hydraulic system, 4-horizontal movement mechanism, 5-walking mechanism, 6-basic door frame, 7-prefabricated heightened door frame, 8-top template Assembly, 9-side template assembly, 10-mechanical screw, 11-top mold cylinder, 12-side mold cylinder, 13-column, 14-upper longitudinal beam, 15-lower longitudinal beam, 16-cross beam, 17 -Heightened column, 18-elevated stringer, 19-elevated beam, 20-support beam, 21-foundation top formwork, 22-elevated top formwork, 23-foundation edge formwork, 24-elevated edge formwork , 25-upper support beam, 26-lift beam, 27-top longitudinal beam, 28-translation jack, 29-ear plate, 30-upper turntable, 31-lower turntable, 32-connection bearing, 33-prepared hole, 34 -Matching bolts, 35-servo motor, 36-walking wheel, 37-track, 38-longitudinal beam, A-cavity A, B-cavity B, C-cavity C.

具体实施方式Detailed ways

下面结合附图中的具体实施例对本发明做进一步的说明。The present invention will be further described below in conjunction with the specific embodiments in the drawings.

参阅附图,本发明的一种可实现快速周转的装配式衬砌台车,包括门架总成1、模板总成2、液压系统3、横移机构4以及行走机构5。门架总成包括基础门架6和装配式加高门架7,装配式加高门架7叠加连接于基础门架6上。模板总成2包括顶部模板总成8和边部模板总成9,顶部模板总成8和边部模板总成9通过铰接方式相连。门架总成1与模板总成2之间分别通过机械丝杆10、顶模油缸11和边模油缸12相连。液压系统3设置于中纵梁38底面与横移机构4顶面之间;行走机构5设置于横移机构4底部。通过装配式的门架总成和模板 总成能够在原地完成快速的拆卸和拼装,拼装和拆卸过程比传统台车更为简单,能够节省大量时间。Referring to the accompanying drawings, an assembled lining trolley capable of realizing rapid turnover of the present invention includes a mast assembly 1, a template assembly 2, a hydraulic system 3, a traverse mechanism 4, and a traveling mechanism 5. The gantry assembly includes a basic gantry 6 and an assembled heightening gantry 7, and the assembled heightening gantry 7 is superimposed and connected to the basic gantry 6. The template assembly 2 includes a top template assembly 8 and an edge template assembly 9, and the top template assembly 8 and the edge template assembly 9 are connected by hinges. The mast assembly 1 and the template assembly 2 are connected by a mechanical screw 10, a top mold cylinder 11, and a side mold cylinder 12, respectively. The hydraulic system 3 is arranged between the bottom surface of the longitudinal beam 38 and the top surface of the traverse mechanism 4; the walking mechanism 5 is arranged at the bottom of the traverse mechanism 4. Through the assembled gantry assembly and template assembly, quick disassembly and assembly can be completed in situ. The assembly and disassembly process is simpler than traditional trolleys, which can save a lot of time.

优选的,基础门架6包括四件立柱13、两件上纵梁14、两件下纵梁15和两件横梁16。装配置加高门架7包括两件四件加高立柱17、两件加高纵梁18、两件加高横梁19和一件支撑梁20。Preferably, the basic gantry 6 includes four uprights 13, two upper longitudinal beams 14, two lower longitudinal beams 15 and two transverse beams 16. The heightening mast 7 includes two pieces of four heightening columns 17, two pieces of heightening longitudinal beams 18, two pieces of heightening cross beams 19, and a supporting beam 20.

优选的,顶部模板总成8包括基础顶部模板21和加高顶部模板22,边部模板总成9包括基础边部模板23和加高边部模板24;顶部模板总成8由上支撑梁25、抬梁26、顶纵梁27以及平移千斤顶28组成。顶部模板总成8和门架总成1通过设置在横梁16和顶纵梁27上的耳板29与平移千斤顶28连接。Preferably, the top template assembly 8 includes a base top template 21 and an elevated top template 22, and the side template assembly 9 includes a base edge template 23 and an elevated side template 24; the top template assembly 8 consists of an upper support beam 25 , Lifting beam 26, top longitudinal beam 27 and translation jack 28. The top template assembly 8 and the door frame assembly 1 are connected to the translation jack 28 through the ear plates 29 arranged on the cross beam 16 and the top longitudinal beam 27.

优选的,横移机构4由上转盘30和下转盘31以及连接轴承32组成。上转盘30和下转盘31通过连接轴承32连接,上转盘30和下转盘31上设置有相同数量的预留孔33,配套螺栓34两端分别插接于预留孔33内。Preferably, the traverse mechanism 4 is composed of an upper turntable 30 and a lower turntable 31 and a connecting bearing 32. The upper turntable 30 and the lower turntable 31 are connected by a connecting bearing 32. The upper turntable 30 and the lower turntable 31 are provided with the same number of reserved holes 33, and both ends of the matching bolts 34 are inserted into the reserved holes 33 respectively.

优选的,行走机构5底部还设有伺服电机35和行走轮36,行走轮36底部设有轨道37。Preferably, the bottom of the traveling mechanism 5 is further provided with a servo motor 35 and a traveling wheel 36, and the bottom of the traveling wheel 36 is provided with a track 37.

以下是一种可实现快速周转的装配式衬砌台车的装配原理:The following is the assembly principle of a prefabricated lining trolley that can realize rapid turnover:

本发明台车可在相邻断面之间快速完成拼装和拆卸。装配原理分为两个阶段:第一个阶段是加高门架的装配式安装。加高门架是在地面完成组装,通过吊装叠加于基础门架之上,完成门架总成的装配。第二个阶段是顶部模板总成的装配式安装。顶部模板总成是同步在地面完成组装,再通过吊装叠加于门架总成之上,完成第二次装配。采用挖机或者在洞顶设置预埋吊点的方式进行吊装作业,根据吊装的能力将顶部模板总成拆分成若干个顶部模板总成单体,分部吊装至门架总成之后再完成一次简易的拼装即可。The trolley of the invention can quickly complete assembly and disassembly between adjacent sections. The assembly principle is divided into two stages: the first stage is the assembly installation of the heightened mast. The heightening mast is assembled on the ground and superimposed on the base mast by hoisting to complete the assembly of the mast assembly. The second stage is the prefabricated installation of the top template assembly. The top template assembly is assembled on the ground synchronously, and then superimposed on the mast assembly by hoisting to complete the second assembly. Use an excavator or set a pre-embedded lifting point on the roof of the cave to carry out the lifting operation. According to the lifting capacity, the top formwork assembly is split into several top formwork assembly units, and the parts are lifted to the door frame assembly before completion A simple assembly is enough.

本发明台车可在非相邻的断面之间完成快速转运,大量节省了台车需要先拆卸再转移至下一断面重新拼装的时间。本发明台车的拆卸过程与其拼装的过 程相反,首先将顶部模板总成吊起并卸载至地面,整体转运至下一个断面等待再次吊装。利用同样的操作将加高门架总成卸载至地面,整体转运至下一个断面等待再次吊装。需要根据下一个断面的尺寸情况来判断是否需要对顶部模板总成进行加宽,对边部模板总成进行加高,对加高门架总成进行局部零配件替换或者加固,对机械丝杆进行调整等。The trolley of the present invention can complete rapid transfer between non-adjacent sections, which greatly saves the time that the trolley needs to be disassembled and then transferred to the next section for reassembly. The disassembly process of the trolley of the present invention is opposite to the assembling process. First, the top formwork assembly is hoisted and unloaded to the ground, and the whole is transferred to the next section to wait for hoisting again. Use the same operation to unload the heightening mast assembly to the ground, and transfer it to the next section as a whole to wait for it to be hoisted again. It is necessary to judge whether the top template assembly needs to be widened according to the size of the next section, the side template assembly should be heightened, partial parts replacement or reinforcement of the heightened mast assembly, and the mechanical screw rod Make adjustments, etc.

以下是一种可实现快速周转的装配式衬砌台车的周转原理:The following is the turnover principle of a prefabricated lining trolley that can realize rapid turnover:

如果洞室A和洞室C为某地下工程的非相邻洞室,二者具有相似或者相同的断面尺寸,符合本发明台车的适用范围。两个洞室通过主干通道B连接,其空间关系如图4所示。当使用本发明台车做完洞室A的衬砌之后,需要将台车快速转移至洞室C进行衬砌施工。If cavern A and cavern C are non-adjacent caverns of a certain underground project, they have similar or identical cross-sectional dimensions, which conform to the scope of application of the trolley of the present invention. The two caverns are connected by the main channel B, and the spatial relationship is shown in Figure 4. After using the trolley of the present invention to finish the lining of the cavern A, the trolley needs to be quickly transferred to the cavern C for lining construction.

a.如果洞室A和洞室C的断面尺寸相同,而洞室B的空间又足够让台车在不进行拆装的情况下进行转运,那只需按照3个步骤完成转运:a. If the cross-sectional dimensions of cavern A and cavern C are the same, and the space of cavern B is enough for the trolley to be transported without disassembly and assembly, then only need to follow 3 steps to complete the transport:

步骤1:将洞室A中的台车沿着轨道撤离至洞室B内。Step 1: Evacuate the trolley in cavern A along the track to cavern B.

步骤2:分别在每根台车下纵梁两端的底面放入墩柱等临时支撑结构,启动台车液压系统,让液压油缸收缩从而带动横移机构和行走系统脱离与轨道发生分离,此时台车的重量由临时支撑结构承担。拆掉横移机构中的配套螺栓,在横移机构中轴承的辅助下,90度转动下转盘及其连接的行走系统,再利用配套螺栓将横移机构固定。将轨道抽出并移至洞室B中重新摆放,以迎接行走轮的再次下放。再次启动台车液压系统,让液压油缸伸缩从而带动横移机构和行走系统脱离与钢轨再次接触,抽离临时支撑机构,此时台车的重量重新通过液压系统和行走系统施加给轨道。启动台车行走系统,让台车行走至洞室C的出口。此步骤的目的是让台车的上部结构保持方位不变的情况下,让其行走轮在洞室B中发生90度旋转,然后继续行走至与洞室C的交叉口。Step 2: Put temporary support structures such as piers on the bottom surfaces of the lower longitudinal beams of each trolley, start the hydraulic system of the trolley, and allow the hydraulic cylinder to contract to drive the traverse mechanism and the traveling system to separate from the track. The weight of the trolley is borne by the temporary support structure. Remove the matching bolts in the traverse mechanism, and with the assistance of the bearings in the traverse mechanism, rotate the lower turntable and its connected walking system by 90 degrees, and then use the matching bolts to fix the traverse mechanism. Pull out the track and move it to cave B to reposition it to welcome the lowering of the walking wheels again. Start the hydraulic system of the trolley again to allow the hydraulic cylinder to expand and contract to drive the traverse mechanism and the traveling system out of contact with the steel rail again, and remove the temporary support mechanism. At this time, the weight of the trolley is again applied to the track through the hydraulic system and the traveling system. Start the trolley traveling system and let the trolley travel to the exit of cave C. The purpose of this step is to keep the upper structure of the trolley in the same position, let its traveling wheels rotate 90 degrees in cave B, and then continue to walk to the intersection with cave C.

步骤3:将台车移至洞室C的操作只需要重复步骤2的操作,将行走轮再次 旋转90度将其恢复原位,推进洞室C开始衬砌施工。Step 3: The operation of moving the trolley to cavern C only needs to repeat the operation of step 2, rotate the walking wheel 90 degrees again to restore it to its original position, and advance cavern C to start the lining construction.

b.如果洞室A和洞室C的断面尺寸相似,或洞室B的空间不足以让台车在不进行拆装的情况下进行转运,那只需要将台车顶部模板总成、边部模板总成或者加高门架总成卸载下来,并转运至洞室C的吊点附近,完成必要的加高门架调整或者增加顶部和边部模板等准备工作。之后利用上述步骤1-3的操作将基础门架总成移动至洞室C的吊点附近,在洞室C内完成台车的装配式拼装。b. If the cross-sectional dimensions of cavern A and cavern C are similar, or the space of cavern B is not enough for the trolley to be transported without disassembly and assembly, then only the top template assembly and side of the trolley The template assembly or heightening mast assembly is unloaded and transferred to the vicinity of the hanging point of cave C to complete the necessary heightening mast adjustment or adding top and side templates and other preparations. Then, use the operations in steps 1-3 above to move the basic door frame assembly to the vicinity of the hanging point of the cavern C, and complete the assembly-type assembly of the trolley in the cavern C.

以上的仅是本实用新型的优选实施方式,应当指出对于本领域的技术人员来说,在不脱离本实用新型结构的前提下,还可以作出若干变形和改进,这些都不会影响本实用新型实施的效果和专利的实用性。The above are only the preferred embodiments of the present utility model. It should be pointed out that for those skilled in the art, without departing from the structure of the present utility model, several modifications and improvements can be made, and these will not affect the present utility model. The effect of implementation and the practicability of the patent.

Claims (5)

一种可实现快速周转的装配式衬砌台车,其特征在于,包括门架总成(1)、模板总成(2)、液压系统(3)、横移机构(4)以及行走机构(5);所述的门架总成包括基础门架(6)和装配式加高门架(7);所述的装配式加高门架(7)叠加连接于基础门架(6)上;所述的模板总成(2)包括顶部模板总成(8)和边部模板总成(9),所述的顶部模板总成(8)和边部模板总成(9)通过铰接方式相连;所述的门架总成(1)与模板总成(2)之间分别通过机械丝杆(10)、顶模油缸(11)和边模油缸(12)相连;所述的液压系统(3)设置于中纵梁(38)底面与横移机构(4)顶面之间;所述的行走机构(5)设置于横移机构(4)底部。A fabricated lining trolley capable of realizing rapid turnover, which is characterized in that it includes a mast assembly (1), a template assembly (2), a hydraulic system (3), a transverse movement mechanism (4) and a walking mechanism (5). ); The door frame assembly includes a basic door frame (6) and an assembled heightening door frame (7); The assembled heightening door frame (7) is superimposed and connected to the basic door frame (6); The template assembly (2) includes a top template assembly (8) and an edge template assembly (9), and the top template assembly (8) and the edge template assembly (9) are connected by hinges The mast assembly (1) and the template assembly (2) are respectively connected by a mechanical screw (10), a top mold cylinder (11) and a side mold cylinder (12); the hydraulic system ( 3) It is arranged between the bottom surface of the longitudinal beam (38) and the top surface of the transverse movement mechanism (4); the walking mechanism (5) is arranged at the bottom of the transverse movement mechanism (4). 根据权利要求1所述的一种可实现快速周转的装配式衬砌台车,其特征在于,所述基础门架(6)包括四件立柱(13)、两件上纵梁(14)、两件下纵梁(15)和两件横梁(16);所述的装配置加高门架(7)包括两件四件加高立柱(17)、两件加高纵梁(18)、两件加高横梁(19)和一件支撑梁(20)。The fabricated lining trolley capable of realizing rapid turnover according to claim 1, characterized in that the basic mast (6) includes four uprights (13), two upper longitudinal beams (14), and two A lower longitudinal beam (15) and two transverse beams (16); the heightening mast (7) includes two four heightening columns (17), two heightening longitudinal beams (18), two One piece of heightening beam (19) and one piece of supporting beam (20). 根据权利要求1所述的一种可实现快速周转的装配式衬砌台车,其特征在于,所述顶部模板总成(8)包括基础顶部模板(21)和加高顶部模板(22);边部模板总成(9)包括基础边部模板(23)和加高边部模板(24);所述顶部模板总成(8)由上支撑梁(25)、抬梁(26)、顶纵梁(27)以及平移千斤顶(28)组成;所述顶部模板总成(8)和门架总成(1)通过设置在横梁(16)和顶纵梁(27)上的耳板(29)与平移千斤顶(28)连接。The fabricated lining trolley capable of realizing rapid turnover according to claim 1, characterized in that, the top template assembly (8) includes a foundation top template (21) and a heightened top template (22); The part template assembly (9) includes a foundation side template (23) and a heightened side template (24); the top template assembly (8) consists of an upper support beam (25), a lifting beam (26), and a top longitudinal The beam (27) and the translation jack (28) are composed; the top template assembly (8) and the door frame assembly (1) pass through the ear plates (29) provided on the cross beam (16) and the top longitudinal beam (27) Connect with the translation jack (28). 根据权利要求1所述的一种可实现快速周转的装配式衬砌台车,其特征在于,所述的横移机构(4)由上转盘(30)和下转盘(31)以及连接轴承(32)组成;所述的上转盘(30)和下转盘(31)通过连接轴承(32)连接;所述的上转盘(30)和下转盘(31)上设置有相同数量的预留孔(33),配套螺栓(34)两端分别插接于预留孔(33)内。The fabricated lining trolley capable of realizing rapid turnover according to claim 1, characterized in that, the transverse movement mechanism (4) consists of an upper turntable (30), a lower turntable (31) and a connecting bearing (32). The upper turntable (30) and the lower turntable (31) are connected by a connecting bearing (32); the upper turntable (30) and the lower turntable (31) are provided with the same number of reserved holes (33) ), the two ends of the matching bolt (34) are respectively inserted into the reserved holes (33). 根据权利要求1所述的一种可实现快速周转的装配式衬砌台车,其特征 在于,所述行走机构(5)底部还设有伺服电机(35)和行走轮(36);所述的行走轮(36)底部设有轨道(37)。The fabricated lining trolley capable of realizing rapid turnover according to claim 1, characterized in that, the bottom of the traveling mechanism (5) is also provided with a servo motor (35) and a traveling wheel (36); the The bottom of the walking wheel (36) is provided with a track (37).
PCT/CN2020/092069 2020-05-25 2020-05-25 Assembled lining trolley allowing for rapid turnover Ceased WO2021237402A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/CN2020/092069 WO2021237402A1 (en) 2020-05-25 2020-05-25 Assembled lining trolley allowing for rapid turnover

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/CN2020/092069 WO2021237402A1 (en) 2020-05-25 2020-05-25 Assembled lining trolley allowing for rapid turnover

Publications (1)

Publication Number Publication Date
WO2021237402A1 true WO2021237402A1 (en) 2021-12-02

Family

ID=78745116

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/092069 Ceased WO2021237402A1 (en) 2020-05-25 2020-05-25 Assembled lining trolley allowing for rapid turnover

Country Status (1)

Country Link
WO (1) WO2021237402A1 (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114233332A (en) * 2022-01-10 2022-03-25 杭州市水库管理服务中心 Tunnel secondary lining trolley
CN114320424A (en) * 2021-12-21 2022-04-12 中铁十九局集团第六工程有限公司 Double-layer walking trolley, ventilator parallel walking system and use method of ventilator parallel walking system
CN114438900A (en) * 2022-03-07 2022-05-06 山东高速路桥国际工程有限公司 Adjustable movable support portal system for bridge construction
CN114941426A (en) * 2022-04-08 2022-08-26 福建建工基础设施建设集团有限公司 Construction method of single-side wall formwork trolley with mechanical demolding device
CN115162406A (en) * 2022-08-04 2022-10-11 广东省水利水电第三工程局有限公司 Whole template portal suitable for box culvert structure
CN115288746A (en) * 2022-09-06 2022-11-04 甘肃路桥建设集团有限公司 Construction Method of Assembling in Trolley Hole of Secondary Lining Formwork of Highway Tunnel
CN115419438A (en) * 2022-09-23 2022-12-02 湖北工业大学 Lining trolley for pouring low-temperature concrete into high-ground-temperature tunnel and working method
CN115450656A (en) * 2020-05-25 2022-12-09 保利长大海外工程有限公司 Lining trolley turnover method for underground space engineering
CN115467258A (en) * 2022-09-28 2022-12-13 河南省沿太行高速公路有限公司 High efficiency culvert construction bearing structure
CN115748524A (en) * 2022-12-09 2023-03-07 四川港航建设工程有限公司 Cast-in-place concrete drainage box culvert and construction method thereof
CN116677226A (en) * 2022-02-23 2023-09-01 中铁十四局集团大盾构工程有限公司 A partition wall installation device and installation method in a large-diameter tunnel
CN116892404A (en) * 2023-08-14 2023-10-17 长安大学 A secondary lining trolley with adjustable pouring size
CN117027843A (en) * 2023-09-18 2023-11-10 上海隧道工程有限公司 Hydraulic combination lifting type tunnel excavation stand trolley
CN117027869A (en) * 2023-08-31 2023-11-10 河南赢创矿山工程有限公司 Construction technology of trestle type formwork trolley and double-layer shaft wall pouring of frozen inclined shaft
CN117108309A (en) * 2023-07-19 2023-11-24 中国水利水电第十四工程局有限公司 An integrated trolley for small-span high-side wall tunnels
WO2024139250A1 (en) * 2022-12-26 2024-07-04 中铁七局集团有限公司 Inner and outer formwork trolley for buried culvert of concrete structure, and construction method using same
CN118601038A (en) * 2024-07-02 2024-09-06 上海建工集团股份有限公司 Adjustable trolley formwork system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1096105A2 (en) * 1999-10-28 2001-05-02 Ed. Züblin Ag Method for shuttering the walls of a tunnel and shutter for use in the method
CN202071835U (en) * 2011-05-24 2011-12-14 四川芙蓉集团实业有限责任公司 Rotary flat cart
KR20130102977A (en) * 2012-03-09 2013-09-23 우신기계(주) Bogie for Tunnel Construction
CN106593472A (en) * 2016-12-23 2017-04-26 湖南五新隧道智能装备股份有限公司 Section-variable tunnel-crossing lining trolley
CN107130978A (en) * 2017-05-31 2017-09-05 中铁隧道集团四处有限公司 Combined type working jumbo for tunnel lining
CN110056374A (en) * 2019-04-12 2019-07-26 中铁三局集团有限公司 A kind of constructing device and construction method in variable cross-section tunnel
CN110284904A (en) * 2019-07-01 2019-09-27 湖南五新隧道智能装备股份有限公司 A kind of lining trolley and its construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1096105A2 (en) * 1999-10-28 2001-05-02 Ed. Züblin Ag Method for shuttering the walls of a tunnel and shutter for use in the method
CN202071835U (en) * 2011-05-24 2011-12-14 四川芙蓉集团实业有限责任公司 Rotary flat cart
KR20130102977A (en) * 2012-03-09 2013-09-23 우신기계(주) Bogie for Tunnel Construction
CN106593472A (en) * 2016-12-23 2017-04-26 湖南五新隧道智能装备股份有限公司 Section-variable tunnel-crossing lining trolley
CN107130978A (en) * 2017-05-31 2017-09-05 中铁隧道集团四处有限公司 Combined type working jumbo for tunnel lining
CN110056374A (en) * 2019-04-12 2019-07-26 中铁三局集团有限公司 A kind of constructing device and construction method in variable cross-section tunnel
CN110284904A (en) * 2019-07-01 2019-09-27 湖南五新隧道智能装备股份有限公司 A kind of lining trolley and its construction method

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115450656A (en) * 2020-05-25 2022-12-09 保利长大海外工程有限公司 Lining trolley turnover method for underground space engineering
CN114320424A (en) * 2021-12-21 2022-04-12 中铁十九局集团第六工程有限公司 Double-layer walking trolley, ventilator parallel walking system and use method of ventilator parallel walking system
CN114233332A (en) * 2022-01-10 2022-03-25 杭州市水库管理服务中心 Tunnel secondary lining trolley
CN116677226A (en) * 2022-02-23 2023-09-01 中铁十四局集团大盾构工程有限公司 A partition wall installation device and installation method in a large-diameter tunnel
CN114438900A (en) * 2022-03-07 2022-05-06 山东高速路桥国际工程有限公司 Adjustable movable support portal system for bridge construction
CN114438900B (en) * 2022-03-07 2022-08-26 山东高速路桥国际工程有限公司 Adjustable movable support portal system for bridge construction
CN114941426A (en) * 2022-04-08 2022-08-26 福建建工基础设施建设集团有限公司 Construction method of single-side wall formwork trolley with mechanical demolding device
CN114941426B (en) * 2022-04-08 2023-11-10 福建建工基础设施建设集团有限公司 Single-side wall template trolley construction method with mechanical demoulding device
CN115162406A (en) * 2022-08-04 2022-10-11 广东省水利水电第三工程局有限公司 Whole template portal suitable for box culvert structure
CN115162406B (en) * 2022-08-04 2023-11-28 广东省水利水电第三工程局有限公司 Integral template portal suitable for box culvert structure
CN115288746A (en) * 2022-09-06 2022-11-04 甘肃路桥建设集团有限公司 Construction Method of Assembling in Trolley Hole of Secondary Lining Formwork of Highway Tunnel
CN115419438A (en) * 2022-09-23 2022-12-02 湖北工业大学 Lining trolley for pouring low-temperature concrete into high-ground-temperature tunnel and working method
CN115467258A (en) * 2022-09-28 2022-12-13 河南省沿太行高速公路有限公司 High efficiency culvert construction bearing structure
CN115467258B (en) * 2022-09-28 2024-01-26 河南省沿太行高速公路有限公司 High efficiency culvert construction bearing structure
CN115748524A (en) * 2022-12-09 2023-03-07 四川港航建设工程有限公司 Cast-in-place concrete drainage box culvert and construction method thereof
WO2024139250A1 (en) * 2022-12-26 2024-07-04 中铁七局集团有限公司 Inner and outer formwork trolley for buried culvert of concrete structure, and construction method using same
CN117108309A (en) * 2023-07-19 2023-11-24 中国水利水电第十四工程局有限公司 An integrated trolley for small-span high-side wall tunnels
CN116892404A (en) * 2023-08-14 2023-10-17 长安大学 A secondary lining trolley with adjustable pouring size
CN117027869A (en) * 2023-08-31 2023-11-10 河南赢创矿山工程有限公司 Construction technology of trestle type formwork trolley and double-layer shaft wall pouring of frozen inclined shaft
CN117027843A (en) * 2023-09-18 2023-11-10 上海隧道工程有限公司 Hydraulic combination lifting type tunnel excavation stand trolley
CN118601038A (en) * 2024-07-02 2024-09-06 上海建工集团股份有限公司 Adjustable trolley formwork system

Similar Documents

Publication Publication Date Title
WO2021237402A1 (en) Assembled lining trolley allowing for rapid turnover
CN109538238B (en) Tunnel arch prefabricated segment construction device and control method
CN102296971B (en) A lining method for a tunnel emergency avoidance zone and a tunnel lining trolley
KR20210054303A (en) Concrete lining formwork for tunnels with sloped construction
CN104727229B (en) Movable bottom formwork trolley system suitable for large concrete prefabricated component and method for prefabricating base plate of large concrete component
CN107060823B (en) Non-dismantling trolley for tunnel anchor section secondary lining concrete construction
CN209444345U (en) Tunnel arch prefabricated segment construction device
CN208203298U (en) A kind of big punching block of rail type side wall
CN111809660A (en) Rectangular trolley for integrated pipe gallery and construction method
CN100497833C (en) High-altitude framework type simple plate supporting machine
CN114933233A (en) Reverse disassembling method for non-enlarged cavern in TBM (tunnel boring machine)
US11480054B2 (en) Rapid construction method for secondary lining of small-section tunnel
CN108868829A (en) Movable door type combined die carrier for variable cross-section tunnel secondary lining
CN111561328A (en) Can realize assembled lining cutting platform truck of quick turnover
CN115405326B (en) A tunnel lining piece assembly trolley
CN115492603B (en) A construction technology of a tunnel lining segment assembly trolley
CN210975880U (en) Adjustable open cut tunnel is hydraulic pressure platform truck by oneself
CN112853998B (en) An assembly-integrated bridge erecting machine suitable for small and medium spans and a construction method thereof
CN201908665U (en) Movable variable-cross section lining trolley
CN114277688A (en) Bridge erecting machine
CN116557002B (en) Standardized and rapid assembly construction method for tunnel secondary lining reinforcement
CN103615262A (en) Steel form jumbo with main structure capable of passing conventional sections, and implementation method thereof
CN118933885A (en) A single-track railway tunnel secondary lining construction trolley and construction method thereof
CN116623570B (en) A construction method for dismantling frame beams
CN208252130U (en) Tunnel lining can turn to reinforcement trolley

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20937616

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20937616

Country of ref document: EP

Kind code of ref document: A1