CN101761237A - Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance - Google Patents

Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance Download PDF

Info

Publication number
CN101761237A
CN101761237A CN200910200698A CN200910200698A CN101761237A CN 101761237 A CN101761237 A CN 101761237A CN 200910200698 A CN200910200698 A CN 200910200698A CN 200910200698 A CN200910200698 A CN 200910200698A CN 101761237 A CN101761237 A CN 101761237A
Authority
CN
China
Prior art keywords
outer casing
pile
soil
buildings
reinforcement cage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910200698A
Other languages
Chinese (zh)
Other versions
CN101761237B (en
Inventor
杨磊
丁志诚
黄德中
戴仕敏
周隽
马元
晁东辉
王金一
吴惠明
郑宜枫
顾沉颖
周永习
郝亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tunnel Engineering Co Ltd
Original Assignee
Shanghai Tunnel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Tunnel Engineering Co Ltd filed Critical Shanghai Tunnel Engineering Co Ltd
Priority to CN2009102006980A priority Critical patent/CN101761237B/en
Publication of CN101761237A publication Critical patent/CN101761237A/en
Application granted granted Critical
Publication of CN101761237B publication Critical patent/CN101761237B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明涉及一种隔离桩施工方法,尤指一种用于盾构近距离通过历史古建筑变形控制的盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法,其特征在于采用套管式的沉桩成孔步骤,以全回转套管机将外套管及位于外套管内的螺旋钻杆,分别以正转反转的钻设方式沉入,其中,外套管反向旋转、螺旋钻杆正向旋转取出外套管内的土,并外套管起护壁作用,以及辅助水泥浆与水玻璃双浆液桩间注浆,有效控制隔离桩施工过程中引起的沉降,并控制盾构近距离通过历史古建筑时的地表沉降,进而保护历史古建筑物的结构安全。

Figure 200910200698

The present invention relates to a construction method of isolation piles, especially to a construction method of isolation piles used for the deformation control of shield tunnels passing through buildings (structures) at short distances for the deformation control of shield tunnels passing through historical buildings at short distances. Using casing-type pile sinking to form holes, the outer casing and the auger drill pipe located in the outer casing are respectively sunk in the drilling method of forward and reverse rotation with a full-rotary casing machine, wherein the outer casing rotates in the opposite direction, The auger drill pipe rotates forward to take out the soil in the outer casing, and the outer casing acts as a wall protection, and assists the grouting between the cement slurry and the water glass double grout pile, effectively controlling the settlement caused by the construction of the isolation pile, and controlling the close distance of the shield. Through the surface settlement of historical ancient buildings, the structural safety of historical ancient buildings can be protected.

Figure 200910200698

Description

盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法 Construction method of isolated piles for deformation control of shield tunnel passing through buildings (structures) in short distance

技术领域technical field

本发明涉及一种隔离桩施工方法,尤指一种用于盾构隧道近距离通过时,控制建筑物沉降的盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法。The invention relates to an isolation pile construction method, in particular to an isolation pile construction method for controlling the settlement of buildings when the shield tunnel passes through the building (structure) at short distance.

背景技术Background technique

由于盾构隧道施工技术的复杂性,目前还不能完全消除盾构上方土层的地表沉降。尤其对临近盾构隧道施工现场的历史价值较高、基础薄弱、结构极其脆弱的历史古建筑而言,盾构隧道施工造成的沉降影响是深深危害历史古建筑物的结构,即使使用了最先进的密闭盾构技术,仍无法完全消除地表沉降。Due to the complexity of shield tunneling construction technology, the surface settlement of the soil layer above the shield cannot be completely eliminated at present. Especially for historical buildings with high historical value, weak foundation and extremely fragile structure near the shield tunnel construction site, the settlement effect caused by shield tunnel construction will deeply damage the structure of historical ancient buildings. Advanced airtight shield technology still cannot completely eliminate surface subsidence.

目前,大多采用的施工简单、费用较低的搅拌隔离桩和普通灌注桩,利用隔离方式阻断盾构隧道近距离通过时对历史古建筑物基础的扰动,并减少地表沉降以保护古建筑物的结构。At present, most of the simple construction and low cost mixing isolation piles and ordinary cast-in-situ piles are used to block the disturbance of the foundation of historical ancient buildings when the shield tunnel passes through in a short distance by means of isolation, and reduce surface settlement to protect ancient buildings. Structure.

申请号为200610029159.1「用于重点建筑保护的隔离桩施工方法」的中国专利,公开一种可形成一堵围护墙的隔离排桩,并可提供隔水作用,有效保护重点建筑,并于通过重点保护建筑一侧的工程施工前,采用深层搅拌桩加固土体,作为隔离挡土墙体,以解决紧邻重点保护建筑一侧地下水的流失。The Chinese patent with the application number 200610029159.1 "Construction Method of Isolation Pile for Key Building Protection" discloses a kind of isolation row pile that can form a wall, and can provide water isolation, effectively protect key buildings, and passed Before the construction of the project on the side of the key protected building, the deep mixing pile is used to reinforce the soil as an isolated retaining wall to solve the loss of groundwater on the side adjacent to the key protected building.

另申请号为200610116618.X「双圆盾构近距离穿越建筑物或构筑物的施工方法」的中国专利,公开一种盾构近距离穿越建筑物或构筑物时的施工保护技术,该技术主要采用预先设置普通隔离桩与控制盾构隧道施工技术参数的方式来减少对临近建筑物的影响,但未公开隔离桩的具体施工方法。Another Chinese patent application No. 200610116618.X "Construction method for double-circle shield passing through buildings or structures at short distances" discloses a construction protection technology when shields pass through buildings or structures at short distances. The method of setting ordinary isolation piles and controlling the construction technical parameters of the shield tunnel can reduce the impact on adjacent buildings, but the specific construction method of the isolation piles has not been disclosed.

上述两种工法均在控制工程施工时减少对临近建筑物的影响,但未充分考虑隔离桩本身施工时对临近建筑物带来的影响或风险。Both of the above two construction methods reduce the impact on adjacent buildings during the construction of the control project, but they do not fully consider the impact or risk on adjacent buildings during the construction of the isolation pile itself.

事实上,普通隔离桩的施工对沉降要求苛刻的历史古建筑物来说,存在有混凝土浇筑充盈率高(过程中有坍孔风险)、施工过程中对土体扰动大、强度低等因素会引起较大的地面沉降,并危害重要历史建筑物的结构安全。In fact, for the construction of ordinary isolated piles, for historical buildings with strict settlement requirements, there are factors such as high filling rate of concrete pouring (there is a risk of hole collapse in the process), large disturbance to the soil during construction, and low strength. It will cause large land subsidence and endanger the structural safety of important historical buildings.

发明内容Contents of the invention

本发明要解决的技术问题是:提供一种盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法,改善现有隔离桩施工方法造成的沉降问题,无法满足及保护沉降要求苛刻的历史古建筑物。The technical problem to be solved by the present invention is to provide a construction method of isolation piles for shield tunnels to pass through buildings (structures) in a short distance to control the deformation, improve the settlement problem caused by the existing isolation pile construction methods, which cannot meet and protect the settlement requirements Harsh historic buildings.

本发明的技术解决方案是:其是用于盾构施工近距离通过时,控制沉降以保护历史古建筑物,其特征在于,该盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法包含以下步骤:The technical solution of the present invention is: it is used to control the settlement to protect historical ancient buildings when the shield tunnel passes through in a short distance, and it is characterized in that the shield tunnel passes through the isolation of the deformation control of the building (structure) in a short distance. The pile construction method includes the following steps:

浇筑钢筋混凝土传力平台,依据施工作业面浇筑一层钢筋混凝土传力平台,并于欲钻孔的桩位处预留一孔径大于隔离桩直径的穿孔;Pour reinforced concrete force transmission platform, pour a layer of reinforced concrete force transmission platform according to the construction work surface, and reserve a perforation hole with a diameter larger than the diameter of the isolation pile at the pile position to be drilled;

沉桩成孔步骤,以一全回转套管机分别将一外套管及一位于该外套管内的螺旋钻杆沉入桩位,该外套管与螺旋钻杆的旋转方向相反,并依设计需求加接外套管与螺旋钻杆,直至设计标高再将螺旋钻杆提出,将外套管内的余土带出,并清除外套管内的虚土,确保隔离桩底端的土体为原始土层;In the pile drilling step, a full-rotary casing machine is used to respectively sink an outer casing and an auger drill rod inside the outer casing into the pile position. The rotation direction of the outer casing is opposite to that of the auger rod, and additional Connect the outer casing and the auger pipe until the design elevation is reached, then lift the auger pipe, take out the remaining soil in the outer casing, and remove the virtual soil in the outer casing to ensure that the soil at the bottom of the isolation pile is the original soil layer;

安装钢筋笼,将依照设计要求所制造的钢筋笼采用两点双钩缓慢起吊,逐步倒点下放并调整钢筋笼方位,并钢筋笼就位前均绑上测绳以监测钢筋笼是否上浮;To install the reinforcement cage, slowly lift the reinforcement cage manufactured according to the design requirements with two-point double hooks, gradually lower the point and adjust the orientation of the reinforcement cage, and tie a measuring rope before the reinforcement cage is in place to monitor whether the reinforcement cage is floating;

浇筑混凝土,将混凝土导管安置后进行首次混凝土灌注,首次混凝土下落完成后以拔管机进行拔管作业,并检查外套管起拔是否顺畅与钢筋笼是否上浮,钢筋笼上浮则进行反压处理,待外套管完全拔出后,便依需要进行补灌,灌完后再行拆除混凝土导管;以及辅助注浆措施,于盾构推进前完成隔离桩间的注浆孔成孔作业,根据盾构推进过程中的监测情形进行跟踪注浆。Concrete is poured, and the first concrete pouring is carried out after the concrete pipe is placed. After the first concrete drop is completed, the pipe pulling machine is used to pull the pipe, and check whether the outer pipe is pulled out smoothly and whether the steel cage is floating. After the outer casing is completely pulled out, supplementary irrigation shall be carried out as required, and the concrete conduit shall be removed after the filling is completed; and auxiliary grouting measures shall be taken to complete the grouting hole forming operation between the isolation piles before the shield tunneling. According to the shield tunneling The monitoring situation during the propulsion process is followed by grouting.

如上所述的盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法,外套管反向旋转,螺旋钻杆正向旋转并取出外套管内的土,使土从外套管上的排土孔排出,外套管形成护壁并辅助水泥浆与水玻璃注浆。In the isolation pile construction method for the shield tunnel passing through the deformation control of the building (structure) at a short distance as described above, the outer casing rotates in the opposite direction, the auger rod rotates forward and takes out the soil in the outer casing, so that the soil is removed from the outer casing. The soil discharge hole is discharged, and the outer casing forms a retaining wall and assists the grouting of cement slurry and water glass.

如上所述的盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法,于沉桩成孔步骤中,全回转套管机移机将外套管的中心与桩位中心对准,以全回转套管机的垂直仪调整外套管垂直度后,再次检查外套管的中心与桩为中心的重合度。In the isolation pile construction method for shield tunnel passing through buildings (structures) at short distances to control deformation as described above, in the step of sinking piles to form holes, the full-rotary casing machine is moved to align the center of the outer casing with the center of the pile position , after adjusting the verticality of the outer casing with the vertical instrument of the full-turn casing machine, check the coincidence degree between the center of the outer casing and the pile as the center again.

如上所述的盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法,于浇筑钢筋混凝土传力平台中,是浇筑厚度大于20公分的钢筋混凝土传力平台。The above-mentioned isolation pile construction method for shield tunnel passing through buildings (structures) at short distances for deformation control is to pour a reinforced concrete force transmission platform with a thickness greater than 20 centimeters in the pouring of the reinforced concrete force transmission platform.

如上所述的盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法,于安装钢筋笼步骤中,钢筋笼上设有定位滚轮,以及钢筋笼底部设有水平抗浮钢板。In the isolation pile construction method for the deformation control of the shield tunnel passing through the building (structure) at short distances as described above, in the step of installing the reinforcement cage, the reinforcement cage is provided with positioning rollers, and the bottom of the reinforcement cage is provided with a horizontal anti-floating steel plate.

如上所述的盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法,于浇筑混凝土步骤中,以贮料斗进行上料作业,贮料斗的堵头采用圆形钢板并以细钢丝绳悬吊,以及首次上料的量大于首次灌注混凝土的量。As mentioned above, the construction method of isolation piles for shield tunnel passing through buildings (structures) at short distances to control the deformation, in the step of pouring concrete, the loading operation is carried out with a storage hopper, and the plug of the storage hopper is made of a circular steel plate and thin Wire rope suspension, and the amount of the first feeding is greater than the amount of concrete poured for the first time.

如上所述的盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法,该隔离桩施工方法中,隔离桩的成孔顺序采用跳开成孔的方式。The isolation pile construction method for the shield tunnel passing through the building (structure) at a short distance to control the deformation as described above, in the isolation pile construction method, the hole forming sequence of the isolation pile adopts the method of jumping and opening holes.

本发明的优点是:于沉桩成孔步骤中采用特殊的套管法,即外套管与螺旋钻杆的旋转方向相反,且螺旋钻杆旋转取土的沉桩作法,使得外套管与螺旋钻杆同步钻至桩底标高,旋转取土的方式可以降低施工过程中的噪音,以及避免对土体的冲击,其中,外套管可以提供护壁作用并隔离施工过程中对周围土体的扰动,同时有明显的向外挤压作用,以减少土体损失,进一步辅助水泥浆与水玻璃注浆,有效控制隔离桩施工过程中的沉降,所以本发明盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法可以控制盾构施工近距离通过古建筑物时的沉降,同时保护古建筑物的安全,且针对上海特有土层,对环境要求苛刻条件下盾构隧道近距离穿越时,对历史建筑群的变形控制非常有效。The advantages of the present invention are: in the pile sinking hole forming step, a special casing method is adopted, that is, the rotation direction of the outer casing and the auger rod is opposite, and the pile sinking method in which the auger rod rotates to take soil, so that the outer casing and the auger The rods are drilled synchronously to the pile bottom elevation, and the method of rotating the soil can reduce the noise during the construction process and avoid the impact on the soil. Among them, the outer casing can provide the function of protecting the wall and isolate the disturbance of the surrounding soil during the construction process. It has an obvious outward extrusion effect to reduce soil loss, further assists cement slurry and water glass grouting, and effectively controls the settlement during the construction of the isolation pile. Therefore, the shield tunnel of the present invention passes through buildings (structures) at close distances. The construction method of isolation piles with deformation control can control the settlement of shield tunnels when they pass through ancient buildings at close range, and at the same time protect the safety of ancient buildings. , which is very effective for deformation control of historical buildings.

附图说明Description of drawings

图1为本发明盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法的一具体实施例的流程示意图。Fig. 1 is a schematic flow chart of a specific embodiment of the isolation pile construction method for shield tunnel passing through buildings (structures) for deformation control at short distances according to the present invention.

具体实施方式Detailed ways

如图1所示,揭示本发明所提供的盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法的流程示意图,该盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法是用于盾构施工近距离通过时,控制沉降以保护历史古建筑物,该盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法的实施步骤包含:浇筑钢筋混凝土传力平台,接续沉桩成孔步骤,并安装钢筋笼与浇筑混凝土,在执行辅助注浆措施。As shown in Figure 1, it discloses a schematic flow chart of the isolation pile construction method for the shield tunnel passing through the deformation control of the building (structure) at a short distance provided by the present invention. The isolation pile construction method is used to control the settlement to protect historical buildings when the shield tunnel passes through at a short distance. The implementation steps of the isolation pile construction method for the shield tunnel passing through the building (structure) deformation control at a short distance include: The reinforced concrete force transmission platform is poured, followed by the pile sinking to form the hole, and the reinforcement cage is installed and the concrete is poured, and the auxiliary grouting measures are carried out.

于浇筑钢筋混凝土传力平台的步骤中,根据实际施工作业面,浇筑一层厚度大于20公分的钢筋混凝土传力平台,并于欲钻孔的桩位处,在钢筋混凝土传力平台上预留一孔径大于隔离桩直径的穿孔,其中穿孔的直径比隔离桩直径大2公分,该钢筋混凝土传力平台形成导墙,并可确保后续成孔的垂直度。In the step of pouring the reinforced concrete force transmission platform, according to the actual construction work surface, pour a layer of reinforced concrete force transmission platform with a thickness greater than 20 cm, and reserve on the reinforced concrete force transmission platform at the pile position to be drilled. A perforation with a diameter larger than the diameter of the isolation pile, wherein the diameter of the perforation is 2 cm larger than the diameter of the isolation pile. The reinforced concrete force transmission platform forms a guide wall and can ensure the verticality of the subsequent hole formation.

于沉桩成孔的步骤中,将一全回转套管机移机,使全回转套管机上的外套管中心与桩位中心对准,并以该全回转套管机的垂直仪调整外套管垂直度后,再次检查外套管的中心与桩为中心的重合度,再以全回转套管机,分别将外套管及位于该外套管内的螺旋钻杆以旋转方式沉入,该外套管与螺旋钻杆的旋转方向相反,并依设计需求加接外套管与螺旋钻杆,直至设计标高再将螺旋钻杆提出,将外套管内的余土带出,并清除外套管内的虚土,确保隔离桩底端的土体为原始土层,其中,外套管反向旋转,螺旋钻杆正向旋转并取出外套管内的土,使土从外套管上的排土孔排出,外套管形成护壁并辅助水泥浆与水玻璃注浆,另外,外套管内的土面标高始终高于外套管的底标高3-5公尺,防止管涌,以及依据地质情况,外套管的深度可比实际桩长深1公尺,防止出现土体管涌现象,且施工中要实时监测,判断土层类别是否与地质数据相符。In the step of sinking piles to form holes, move a full-rotary casing machine so that the center of the outer casing on the full-rotary casing machine is aligned with the center of the pile position, and adjust the outer casing with the vertical instrument of the full-rotary casing machine After the verticality, check the coincidence degree of the center of the outer casing and the pile as the center again, and then use the full-rotary casing machine to respectively sink the outer casing and the auger pipe in the outer casing in a rotating manner, and the outer casing and the auger The rotation direction of the drill pipe is opposite, and the outer casing and the auger pipe are connected according to the design requirements, and the auger pipe is lifted up to the design elevation, and the remaining soil in the outer casing is brought out, and the virtual soil in the outer casing is removed to ensure that the isolation pile The soil at the bottom is the original soil layer, in which the outer casing rotates in reverse, the auger rod rotates forward and takes out the soil in the outer casing, so that the soil is discharged from the soil discharge hole on the outer casing, and the outer casing forms a retaining wall and assists the cement slurry Grouting with water glass, in addition, the soil level inside the outer casing is always 3-5 meters higher than the bottom elevation of the outer casing to prevent piping, and according to geological conditions, the depth of the outer casing can be 1 meter deeper than the actual pile to prevent Soil piping occurs, and real-time monitoring is required during construction to determine whether the type of soil layer is consistent with the geological data.

于安装钢筋笼的步骤中,钢筋笼的制造是依照设计要求,钢筋笼四周设有定位滚轮,以及钢筋笼底部设有水平抗浮钢板,将以两点双钩缓慢起吊制成后的钢筋笼,逐步倒点下放,不得使钢筋笼发生变形,于下放过程中,逐步调整钢筋笼方向,并钢筋笼就位前均绑上测绳,以确保钢筋笼定位准确及监测钢筋笼是否上浮。In the step of installing the reinforcement cage, the manufacture of the reinforcement cage is in accordance with the design requirements. There are positioning rollers around the reinforcement cage, and a horizontal anti-floating steel plate at the bottom of the reinforcement cage. The completed reinforcement cage will be hoisted slowly with two-point double hooks. Gradually lower the reinforcement cage to prevent deformation of the reinforcement cage. During the lowering process, gradually adjust the direction of the reinforcement cage, and tie the measuring rope before the reinforcement cage is in place, so as to ensure the accurate positioning of the reinforcement cage and monitor whether the reinforcement cage is floating.

于浇筑混凝土的步骤中,将混凝土导管安置后进行首次混凝土灌注,首次混凝土下落完成后以拔管机进行拔管作业,采用拔管机进行拔管,并检查外套管起拔是否顺畅与钢筋笼是否上浮,钢筋笼上浮则进行反压处理,起拔量控制在10-20公分,待外套管完全拔出后,便依需要进行补灌,灌完后再行拆除混凝土导管,其中,于浇筑混凝土的步骤中采用贮料斗进行上料作业,贮料斗的堵头采用圆形钢板并以细钢丝绳悬吊,以及首次上料的量大于首次灌注混凝土的量。In the step of pouring concrete, the first concrete pouring is carried out after the concrete pipe is placed, and the pipe pulling operation is carried out after the first concrete drop is completed. Whether it is floating or not, when the steel cage is floating, it will carry out back pressure treatment, and the lifting amount will be controlled at 10-20 cm. In the step of concrete, a storage hopper is used for feeding operations, the plug of the storage hopper is made of a circular steel plate and suspended by a thin steel wire rope, and the amount of the first feeding is greater than the amount of the first poured concrete.

于辅助注浆措施的步骤中,于盾构推进前完成隔离桩间的注浆孔成孔作业,根据盾构推进过程中的监测情形进行跟踪注浆。In the step of auxiliary grouting measures, the grouting holes between the isolation piles are completed before the shield tunneling, and the tracking grouting is carried out according to the monitoring situation during the shield tunneling.

于本发明盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法中,隔离桩的成孔顺序采用跳开成孔的方式,例如成孔顺序的施工桩号顺序为1-7-12...,待强度达到一定程度后再对相邻的施工桩号2-8-13...进行施工。In the isolation pile construction method of the shield tunnel passing through the deformation control of the building (structure) at a short distance of the present invention, the hole forming sequence of the isolation pile adopts the method of jumping out of the hole, for example, the construction pile number sequence of the hole forming sequence is 1- 7-12..., the adjacent construction pile number 2-8-13... will be constructed after the strength reaches a certain level.

综上所述,本发明盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法中采用外套管与螺旋钻杆的旋转方向相反的沉桩作法,以螺旋钻杆旋转取土并经由外套管上的排土孔排出,以及外套管与螺旋钻杆可同步钻至桩底标高,其中,旋转取土的方式可以降低施工过程中的噪音与避免对土体的冲击,此外,外套管于施工过程中可以提供护壁作用,并隔离施工过程中对周围土体的扰动,同时产生明显的向外挤压作用,使得土体损失减少,又可辅助水泥浆与水玻璃注浆,达到有效控制隔离桩施工过程中的沉降量,同时可以隔离盾构施工过程中的沉降影响,所以本发明盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法可以控制盾构施工近距离通过古建筑物时的沉降,保护古建筑物的结构安全,尤其适用于上海特有土层。In summary, in the isolation pile construction method of the shield tunnel passing through the deformation control of the building (structure) at a short distance, the pile sinking method in which the outer sleeve and the auger rod are rotated in the opposite direction is adopted, and the auger rod is rotated to take soil And it is discharged through the drainage hole on the outer casing, and the outer casing and the auger pipe can be drilled to the pile bottom level synchronously. Among them, the method of rotating soil can reduce the noise during construction and avoid the impact on the soil. In addition, During the construction process, the outer casing can provide wall protection, isolate the disturbance of the surrounding soil during the construction process, and at the same time produce an obvious outward extrusion effect, which reduces the loss of soil, and can also assist cement slurry and water glass grouting, To effectively control the settlement during the construction of the isolation pile, and at the same time isolate the influence of settlement during the construction of the shield tunnel, so the isolation pile construction method of the present invention can control the deformation of the shield tunnel passing through the building (structure) at a short distance. Settlement when passing through ancient buildings at close range during construction, to protect the structural safety of ancient buildings, especially suitable for Shanghai's unique soil layers.

Claims (7)

1.一种盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法,其是用于盾构施工近距离通过时,控制沉降以保护历史古建筑物,其特征在于,该方法包含以下步骤:1. A shield tunnel passes through an isolation pile construction method for the deformation control of buildings (structures) at short distances, it is used for shield tunneling when passing at short distances, and controls settlement to protect historic buildings. It is characterized in that the The method includes the following steps: 浇筑钢筋混凝土传力平台,依据施工作业面浇筑一层钢筋混凝土传力平台,并于欲钻孔的桩位处预留一孔径大于隔离桩直径的穿孔;Pour reinforced concrete force transmission platform, pour a layer of reinforced concrete force transmission platform according to the construction work surface, and reserve a perforation hole with a diameter larger than the diameter of the isolation pile at the pile position to be drilled; 沉桩成孔步骤,以一全回转套管机分别将一外套管及一位于该外套管内的螺旋钻杆沉入桩位,该外套管与螺旋钻杆的旋转方向相反,并依设计需求加接外套管与螺旋钻杆,直至设计标高再将螺旋钻杆提出,将外套管内的余土带出,并清除外套管内的虚土,确保隔离桩底端的土体为原始土层;In the pile drilling step, a full-rotary casing machine is used to respectively sink an outer casing and an auger drill rod inside the outer casing into the pile position. The rotation direction of the outer casing is opposite to that of the auger rod, and additional Connect the outer casing and the auger pipe until the design elevation is reached, then lift the auger pipe, take out the remaining soil in the outer casing, and remove the virtual soil in the outer casing to ensure that the soil at the bottom of the isolation pile is the original soil layer; 安装钢筋笼,将依照设计要求所制造的钢筋笼采用两点双钩缓慢起吊,逐步倒点下放并调整钢筋笼方位,并钢筋笼就位前均绑上测绳以监测钢筋笼是否上浮;To install the reinforcement cage, slowly lift the reinforcement cage manufactured according to the design requirements with two-point double hooks, gradually lower the point and adjust the orientation of the reinforcement cage, and tie a measuring rope before the reinforcement cage is in place to monitor whether the reinforcement cage is floating; 浇筑混凝土,将混凝土导管安置后进行首次混凝土灌注,首次混凝土下落完成后以拔管机进行拔管作业,并检查外套管起拔是否顺畅与钢筋笼是否上浮,钢筋笼上浮则进行反压处理,待外套管完全拔出后,便依需要进行补灌,灌完后再行拆除混凝土导管;以及Concrete is poured, and the first concrete pouring is carried out after the concrete pipe is placed. After the first concrete drop is completed, the pipe pulling machine is used to pull the pipe, and check whether the outer pipe is pulled out smoothly and whether the steel cage is floating. After the outer casing is completely pulled out, supplementary irrigation will be carried out as required, and the concrete conduit will be removed after the irrigation is completed; and 辅助注浆措施,于盾构推进前完成隔离桩间的注浆孔成孔作业,根据盾构推进过程中的监测情形进行跟踪注浆。Auxiliary grouting measures, complete the grouting hole forming operation between the isolated piles before the shield tunneling, and track the grouting according to the monitoring situation during the shield tunneling. 2.根据权利要求1所述的方法,其特征在于:外套管反向旋转,螺旋钻杆正向旋转并取出外套管内的土,使土从外套管上的排土孔排出,外套管形成护壁并辅助水泥浆与水玻璃注浆。2. The method according to claim 1, characterized in that: the outer casing rotates in reverse, the auger rod rotates forward and takes out the soil in the outer casing, so that the soil is discharged from the soil discharge hole on the outer casing, and the outer casing forms a retaining wall And auxiliary cement slurry and water glass grouting. 3.根据权利要求1或2所述的方法,其特征在于:于沉桩成孔步骤中,全回转套管机移机将外套管的中心与桩位中心对准,以全回转套管机的垂直仪调整外套管垂直度后,再次检查外套管的中心与桩为中心的重合度。3. The method according to claim 1 or 2, characterized in that: in the step of sinking piles and forming holes, the full-rotary casing machine moves the center of the outer casing to align with the center of the pile position, and the full-rotary casing machine After adjusting the verticality of the outer casing with the vertical instrument, check the coincidence degree between the center of the outer casing and the pile as the center again. 4.根据权利要求3所述的方法,其特征在于:于浇筑钢筋混凝土传力平台中,是浇筑厚度大于20公分的钢筋混凝土传力平台。4. The method according to claim 3, characterized in that: in pouring the reinforced concrete force transmission platform, the reinforced concrete force transmission platform with a thickness greater than 20 cm is poured. 5.根据权利要求4所述的方法,其特征在于:于安装钢筋笼步骤中,钢筋笼上设有定位滚轮,以及钢筋笼底部设有水平抗浮钢板。5. The method according to claim 4, characterized in that: in the step of installing the reinforcement cage, positioning rollers are provided on the reinforcement cage, and a horizontal anti-floating steel plate is provided at the bottom of the reinforcement cage. 6.根据权利要求5所述的方法,其特征在于:于浇筑混凝土步骤中,以贮料斗进行上料作业,贮料斗的堵头采用圆形钢板并以细钢丝绳悬吊,以及首次上料的量大于首次灌注混凝土的量。6. The method according to claim 5, characterized in that: in the step of pouring concrete, the loading operation is carried out with a storage hopper, the plug of the storage hopper adopts a circular steel plate and is suspended with a thin steel wire rope, and the first loading The amount is greater than the amount of concrete poured for the first time. 7.根据权利要求6所述的方法,其特征在于:在所述施工方法中,隔离桩的成孔顺序采用跳开成孔的方式。7. The method according to claim 6, characterized in that: in the construction method, the hole forming sequence of the isolation piles adopts the method of jumping and opening holes.
CN2009102006980A 2009-12-24 2009-12-24 Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance Expired - Fee Related CN101761237B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009102006980A CN101761237B (en) 2009-12-24 2009-12-24 Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009102006980A CN101761237B (en) 2009-12-24 2009-12-24 Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance

Publications (2)

Publication Number Publication Date
CN101761237A true CN101761237A (en) 2010-06-30
CN101761237B CN101761237B (en) 2011-06-01

Family

ID=42492607

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009102006980A Expired - Fee Related CN101761237B (en) 2009-12-24 2009-12-24 Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance

Country Status (1)

Country Link
CN (1) CN101761237B (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704937A (en) * 2011-03-28 2012-10-03 同济大学 Method for identifying settlement pattern during shield tunnel construction
CN102817378A (en) * 2011-06-09 2012-12-12 同济大学 Construction method of extra-large diameter shield tunnel penetrating through urban overhead pile foundations in close range
CN102888839A (en) * 2012-10-16 2013-01-23 深圳市金泰建设工程有限公司 Construction method of static-pressure sleeve rotary digging filling pile
CN102995666A (en) * 2011-09-13 2013-03-27 上海市基础工程有限公司 Construction method for reducing effect of vibration on peripheral buildings (structures)
CN104863183A (en) * 2015-03-04 2015-08-26 中铁隧道勘测设计院有限公司 Isolation damping pile structure used for construction of large cross-section tunnel closed-spaced building and construction method of isolation damping pile structure
CN105804761A (en) * 2016-03-14 2016-07-27 上海隧道工程有限公司 Construction method suitable for making shield penetrate through building in close range on liquefied sandy soil stratum
CN108533277A (en) * 2018-04-12 2018-09-14 中启胶建集团有限公司 Major diameter slurry shield passes through shanty town settlement Control construction over long distances under the conditions of non-reinforced
CN109488209A (en) * 2018-12-26 2019-03-19 腾达建设集团股份有限公司 A kind of steel sleeve, full-sleeve full-rotation drill and drilling machine drilling method
CN110939450A (en) * 2019-11-27 2020-03-31 中建五局土木工程有限公司 Grouting structure and construction method of shield excavation in water-rich disturbance sensitive stratum
CN111396063A (en) * 2020-03-25 2020-07-10 中铁三局集团有限公司 A construction method for a water-rich sand layer shield to cross an existing line and penetrate a sewage jacking pipe at a short distance
CN111997522A (en) * 2020-08-31 2020-11-27 中启胶建集团有限公司 Drilling device penetrating through underground deep-buried waste pipeline and cast-in-place pile construction method
CN114086545A (en) * 2021-11-29 2022-02-25 上海隧道工程有限公司 Ultra-deep MJS construction method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102733821A (en) * 2012-06-19 2012-10-17 浙江大学 Secondary double-liquid slurry re-grouting method capable of effectively controlling surface deformation

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10308540B4 (en) * 2003-02-27 2005-02-17 Bauer Maschinen Gmbh Method and device for producing a foundation element
CN1900466A (en) * 2006-07-20 2007-01-24 上海市第一建筑有限公司 Isolation pile construction method for important building protection
CN1932244A (en) * 2006-09-28 2007-03-21 上海隧道工程股份有限公司 Construction method for double-circular shield near-distance passing through building or structure
CN1944939B (en) * 2006-11-09 2012-09-05 山河智能装备股份有限公司 Separable driving type sleeve screw drilling rig and its construction method

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704937B (en) * 2011-03-28 2014-06-25 同济大学 Method for identifying settlement pattern during shield tunnel construction
CN102704937A (en) * 2011-03-28 2012-10-03 同济大学 Method for identifying settlement pattern during shield tunnel construction
CN102817378A (en) * 2011-06-09 2012-12-12 同济大学 Construction method of extra-large diameter shield tunnel penetrating through urban overhead pile foundations in close range
CN102817378B (en) * 2011-06-09 2014-06-25 同济大学 Construction method of extra-large diameter shield tunnel penetrating through urban overhead pile foundations in close range
CN102995666A (en) * 2011-09-13 2013-03-27 上海市基础工程有限公司 Construction method for reducing effect of vibration on peripheral buildings (structures)
CN102888839A (en) * 2012-10-16 2013-01-23 深圳市金泰建设工程有限公司 Construction method of static-pressure sleeve rotary digging filling pile
CN104863183B (en) * 2015-03-04 2019-03-05 中铁第六勘察设计院集团有限公司 Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction
CN104863183A (en) * 2015-03-04 2015-08-26 中铁隧道勘测设计院有限公司 Isolation damping pile structure used for construction of large cross-section tunnel closed-spaced building and construction method of isolation damping pile structure
CN105804761A (en) * 2016-03-14 2016-07-27 上海隧道工程有限公司 Construction method suitable for making shield penetrate through building in close range on liquefied sandy soil stratum
CN108533277A (en) * 2018-04-12 2018-09-14 中启胶建集团有限公司 Major diameter slurry shield passes through shanty town settlement Control construction over long distances under the conditions of non-reinforced
CN108533277B (en) * 2018-04-12 2020-07-24 中启胶建集团有限公司 Sedimentation control construction method for long-distance penetration of large-diameter slurry shield through shed area under non-reinforced condition
CN109488209A (en) * 2018-12-26 2019-03-19 腾达建设集团股份有限公司 A kind of steel sleeve, full-sleeve full-rotation drill and drilling machine drilling method
CN110939450A (en) * 2019-11-27 2020-03-31 中建五局土木工程有限公司 Grouting structure and construction method of shield excavation in water-rich disturbance sensitive stratum
CN111396063A (en) * 2020-03-25 2020-07-10 中铁三局集团有限公司 A construction method for a water-rich sand layer shield to cross an existing line and penetrate a sewage jacking pipe at a short distance
CN111396063B (en) * 2020-03-25 2021-05-28 中铁三局集团有限公司 A construction method for a water-rich sand layer shield to cross an existing line and penetrate a sewage jacking pipe at a short distance
CN111997522A (en) * 2020-08-31 2020-11-27 中启胶建集团有限公司 Drilling device penetrating through underground deep-buried waste pipeline and cast-in-place pile construction method
CN111997522B (en) * 2020-08-31 2022-05-31 中启胶建集团有限公司 A drilling device and a construction method for a cast-in-place pile running through a deep buried abandoned pipeline underground
CN114086545A (en) * 2021-11-29 2022-02-25 上海隧道工程有限公司 Ultra-deep MJS construction method

Also Published As

Publication number Publication date
CN101761237B (en) 2011-06-01

Similar Documents

Publication Publication Date Title
CN101761237B (en) Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN106284313B (en) Long spire based on circulating mud retaining wall is squeezed into rock filling pile construction method
CN101638891B (en) Construction method of all casing precessing isolation pile
CN105275381B (en) Impact drill drilling construction method in rich water pebble layer
CN110735432B (en) Pile foundation removal and parameter control method within the tunneling range of shield tunneling
CN108894214B (en) Karst cave geological environment cast-in-place pile and pile-forming construction method thereof
CN104612179B (en) Through the construction method of the diaphram wall of super thick silty sand ground
CN102286984A (en) Water-stop curtain and construction method thereof
CN104631438B (en) Long auger guncreting uplift pile construction method
CN108166483A (en) Bored pile construction method
CN106013078B (en) A construction method for strengthening curtain structure in highly permeable ground
CN102286981A (en) Waterproof curtain and construction method thereof
CN110593254A (en) Construction method of cast-in-situ bored pile in stratum with karst cave in joint zone
CN106988302A (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN110093927B (en) A method for controlling the deformation of the tunnel outside the foundation pit
CN115977102B (en) Combined construction structure and construction method of upper foundation pit and lower tunnel in saturated soft loess stratum
CN110284885A (en) Shield inspection-pit construction method
CN114108649A (en) Foundation pit reinforcing construction method for mucky soil layer
CN217028947U (en) Construction structure of shield tunnel lower-passing water pipeline
CN202194149U (en) Waterproof curtain
CN115596453A (en) "Micro brush slope" entry method for long-distance side of tunnel passing through accumulation
CN201762702U (en) Drilling secant pile
CN204401612U (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction equipment
CN110777775A (en) Foundation pit structure and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANGHAI TUNNEL ENGINEERING CO., LTD.

Free format text: FORMER OWNER: SHANGHAI TUNNEL ENGINEERING CO LTD

Effective date: 20150130

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 200082 HONGKOU, SHANGHAI TO: 200232 XUHUI, SHANGHAI

TR01 Transfer of patent right

Effective date of registration: 20150130

Address after: 200232 Shanghai Wanping Road No. 1099

Patentee after: SHANGHAI TUNNEL ENGINEERING Co.,Ltd.

Address before: 200082 No. 118, Dalian Road, Shanghai

Patentee before: SHANGHAI TUNNEL ENGINEERING Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110601

CF01 Termination of patent right due to non-payment of annual fee