CN101761237B - Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance - Google Patents
Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance Download PDFInfo
- Publication number
- CN101761237B CN101761237B CN2009102006980A CN200910200698A CN101761237B CN 101761237 B CN101761237 B CN 101761237B CN 2009102006980 A CN2009102006980 A CN 2009102006980A CN 200910200698 A CN200910200698 A CN 200910200698A CN 101761237 B CN101761237 B CN 101761237B
- Authority
- CN
- China
- Prior art keywords
- outer casing
- soil
- reinforcement cage
- pile
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本发明涉及一种隔离桩施工方法,尤指一种用于盾构近距离通过历史古建筑变形控制的盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法,其特征在于采用套管式的沉桩成孔步骤,以全回转套管机将外套管及位于外套管内的螺旋钻杆,分别以正转反转的钻设方式沉入,其中,外套管反向旋转、螺旋钻杆正向旋转取出外套管内的土,并外套管起护壁作用,以及辅助水泥浆与水玻璃双浆液桩间注浆,有效控制隔离桩施工过程中引起的沉降,并控制盾构近距离通过历史古建筑时的地表沉降,进而保护历史古建筑物的结构安全。
The invention relates to an isolation pile construction method, in particular to an isolation pile construction method used for shield tunnel passing through historical ancient building deformation control at short distance, which is characterized in that it adopts casing type In the pile sinking and hole-forming step, the outer casing and the auger drill pipe located in the outer casing are sunk in the forward and reverse drilling mode with the full-rotary casing machine, wherein the outer casing rotates in the opposite direction and the auger Rotate to take out the soil in the outer casing, and use the outer casing to protect the wall, and assist the cement slurry and water glass double grout grouting between the piles, effectively control the settlement caused by the isolation pile construction process, and control the shield passing through the historical ancient buildings at close range The surface subsidence of time, and then protect the structural safety of historical buildings.
Description
技术领域technical field
本发明涉及一种隔离桩施工方法,尤指一种用于盾构隧道近距离通过时,控制建筑物沉降的盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法。The invention relates to a construction method of an isolation pile, in particular to an isolation pile construction method for controlling the settlement of a building when the shield tunnel passes through the building at a short distance.
背景技术Background technique
由于盾构隧道施工技术的复杂性,目前还不能完全消除盾构上方土层的地表沉降。尤其对临近盾构隧道施工现场的历史价值较高、基础薄弱、结构极其脆弱的历史古建筑而言,盾构隧道施工造成的沉降影响是深深危害历史古建筑物的结构,即使使用了最先进的密闭盾构技术,仍无法完全消除地表沉降。Due to the complexity of shield tunneling construction technology, the surface settlement of the soil layer above the shield cannot be completely eliminated at present. Especially for historical buildings with high historical value, weak foundation and extremely fragile structure near the shield tunnel construction site, the settlement effect caused by shield tunnel construction will deeply damage the structure of historical ancient buildings. Advanced airtight shield technology still cannot completely eliminate surface subsidence.
目前,大多采用的施工简单、费用较低的搅拌隔离桩和普通灌注桩,利用隔离方式阻断盾构隧道近距离通过时对历史古建筑物基础的扰动,并减少地表沉降以保护古建筑物的结构。At present, most of the simple construction and low cost mixing isolation piles and ordinary cast-in-situ piles are used to block the disturbance of the foundation of historical ancient buildings when the shield tunnel passes through in a short distance by means of isolation, and reduce surface settlement to protect ancient buildings. Structure.
申请号为200610029159.1「用于重点建筑保护的隔离桩施工方法」的中国专利,公开一种可形成一堵围护墙的隔离排桩,并可提供隔水作用,有效保护重点建筑,并于通过重点保护建筑一侧的工程施工前,采用深层搅拌桩加固土体,作为隔离挡土墙体,以解决紧邻重点保护建筑一侧地下水的流失。The Chinese patent with the application number 200610029159.1 "Construction Method of Isolation Pile for Key Building Protection" discloses a kind of isolation row pile that can form a wall, and can provide water isolation, effectively protect key buildings, and passed Before the construction of the project on the side of the key protected building, the deep mixing pile is used to reinforce the soil as an isolated retaining wall to solve the loss of groundwater on the side adjacent to the key protected building.
另申请号为200610116618.X「双圆盾构近距离穿越建筑物或构筑物的施工方法」的中国专利,公开一种盾构近距离穿越建筑物或构筑物时的施工保护技术,该技术主要采用预先设置普通隔离桩与控制盾构隧道施工技术参数的方式来减少对临近建筑物的影响,但未公开隔离桩的具体施工方法。Another Chinese patent application No. 200610116618.X "Construction method for double-circle shield passing through buildings or structures at short distances" discloses a construction protection technology when shields pass through buildings or structures at short distances. The method of setting ordinary isolation piles and controlling the construction technical parameters of the shield tunnel can reduce the impact on adjacent buildings, but the specific construction method of the isolation piles has not been disclosed.
上述两种工法均在控制工程施工时减少对临近建筑物的影响,但未充分考虑隔离桩本身施工时对临近建筑物带来的影响或风险。Both of the above two construction methods reduce the impact on adjacent buildings during the construction of the control project, but they do not fully consider the impact or risk on adjacent buildings during the construction of the isolation pile itself.
事实上,普通隔离桩的施工对沉降要求苛刻的历史古建筑物来说,存在有混凝土浇筑充盈率高(过程中有坍孔风险)、施工过程中对土体扰动大、强度低等因素会引起较大的地面沉降,并危害重要历史建筑物的结构安全。In fact, for the construction of ordinary isolated piles, for historical buildings with strict settlement requirements, there are factors such as high filling rate of concrete pouring (there is a risk of hole collapse in the process), large disturbance to the soil during construction, and low strength. It will cause large land subsidence and endanger the structural safety of important historical buildings.
发明内容Contents of the invention
本发明要解决的技术问题是:提供一种盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法,改善现有隔离桩施工方法造成的沉降问题,无法满足及保护沉降要求苛刻的历史古建筑物。The technical problem to be solved by the present invention is to provide a construction method of isolation piles for shield tunnels to pass through buildings at short distances to control deformation, improve the settlement problems caused by existing isolation pile construction methods, and cannot meet and protect historical ancient buildings with strict settlement requirements. building.
本发明的技术解决方案是:其是用于盾构施工近距离通过时,控制沉降以保护历史古建筑物,其特征在于,该盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法包含以下步骤:The technical solution of the present invention is: it is used to control the settlement to protect historical ancient buildings when the shield tunnel passes through in a short distance, and it is characterized in that the construction method of the isolated pile for the deformation control of the shield tunnel passing through the building in a short distance includes The following steps:
浇筑钢筋混凝土传力平台,依据施工作业面浇筑一层钢筋混凝土传力平台,并于欲钻孔的桩位处预留一孔径大于隔离桩直径的穿孔;Pour reinforced concrete force transmission platform, pour a layer of reinforced concrete force transmission platform according to the construction work surface, and reserve a perforation hole with a diameter larger than the diameter of the isolation pile at the pile position to be drilled;
沉桩成孔步骤,以一全回转套管机分别将一外套管及一位于该外套管内的螺旋钻杆沉入桩位,该外套管与螺旋钻杆的旋转方向相反,并依设计需求加接外套管与螺旋钻杆,直至设计标高再将螺旋钻杆提出,将外套管内的余土带出,并清除外套管内的虚土,确保隔离桩底端的土体为原始土层;In the pile drilling step, a full-rotary casing machine is used to respectively sink an outer casing and an auger drill rod inside the outer casing into the pile position. The rotation direction of the outer casing is opposite to that of the auger rod, and additional Connect the outer casing and the auger pipe until the design elevation is reached, then lift the auger pipe, take out the remaining soil in the outer casing, and remove the virtual soil in the outer casing to ensure that the soil at the bottom of the isolation pile is the original soil layer;
安装钢筋笼,将依照设计要求所制造的钢筋笼采用两点双钩缓慢起吊,逐步倒点下放并调整钢筋笼方位,并钢筋笼就位前均绑上测绳以监测钢筋笼是否上浮;To install the reinforcement cage, slowly lift the reinforcement cage manufactured according to the design requirements with two-point double hooks, gradually lower the point and adjust the orientation of the reinforcement cage, and tie a measuring rope before the reinforcement cage is in place to monitor whether the reinforcement cage is floating;
浇筑混凝土,将混凝土导管安置后进行首次混凝土灌注,首次混凝土下落完成后以拔管机进行拔管作业,并检查外套管起拔是否顺畅与钢筋笼是否上浮,钢筋笼上浮则进行反压处理,待外套管完全拔出后,便依需要进行补灌,灌完后再行拆除混凝土导管;以及辅助注浆措施,于盾构推进前完成隔离桩间的注浆孔成孔作业,根据盾构推进过程中的监测情形进行跟踪注浆。Concrete is poured, and the first concrete pouring is carried out after the concrete pipe is placed. After the first concrete drop is completed, the pipe pulling machine is used to pull the pipe, and check whether the outer pipe is pulled out smoothly and whether the steel cage is floating. After the outer casing is completely pulled out, supplementary irrigation shall be carried out as required, and the concrete conduit shall be removed after the filling is completed; and auxiliary grouting measures shall be taken to complete the grouting hole forming operation between the isolation piles before the shield tunneling. According to the shield tunneling The monitoring situation during the propulsion process is followed by grouting.
如上所述的盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法,外套管反向旋转,螺旋钻杆正向旋转并取出外套管内的土,使土从外套管上的排土孔排出,外套管形成护壁并辅助水泥浆与水玻璃注浆。In the isolation pile construction method for shield tunnel passing through building deformation control at short distances as described above, the outer casing rotates in reverse, the auger rod rotates forward and takes out the soil in the outer casing, so that the soil is discharged from the soil discharge hole on the outer casing , the outer casing forms the retaining wall and assists the grouting of cement slurry and water glass.
如上所述的盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法,于沉桩成孔步骤中,全回转套管机移机将外套管的中心与桩位中心对准,以全回转套管机的垂直仪调整外套管垂直度后,再次检查外套管的中心与桩位中心的重合度。In the isolation pile construction method for the shield tunnel passing through the deformation control of the building at a short distance as described above, in the step of sinking the pile and forming the hole, the full-rotation casing machine moves the center of the outer casing to the center of the pile to align the center of the outer casing with the full-turn After the verticality gauge of the casing machine adjusts the verticality of the outer casing, check the coincidence degree between the center of the outer casing and the center of the pile position again.
如上所述的盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法,于浇筑钢筋混凝土传力平台中,是浇筑厚度大于20公分的钢筋混凝土传力平台。The above-mentioned isolation pile construction method for the shield tunnel passing through the building deformation control at a short distance is to pour a reinforced concrete force transmission platform with a thickness greater than 20 cm in the pouring of the reinforced concrete force transmission platform.
如上所述的盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法,于安装钢筋笼步骤中,钢筋笼上设有定位滚轮,以及钢筋笼底部设有水平抗浮钢板。In the isolation pile construction method for the deformation control of the shield tunnel passing through the building at close range as described above, in the step of installing the reinforcement cage, positioning rollers are provided on the reinforcement cage, and a horizontal anti-floating steel plate is provided at the bottom of the reinforcement cage.
如上所述的盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法,于浇筑混凝土步骤中,以贮料斗进行上料作业,贮料斗的堵头采用圆形钢板并以细钢丝绳悬吊,以及首次上料的量大于首次灌注混凝土的量。In the construction method of isolation piles for the shield tunnel passing through the building deformation control at short distances as described above, in the step of pouring concrete, a storage hopper is used for loading operations, and the plug of the storage hopper is made of a circular steel plate and suspended by a thin steel wire rope. And the amount of the first feeding is greater than the amount of concrete poured for the first time.
如上所述的盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法,该隔离桩施工方法中,隔离桩的成孔顺序采用跳开成孔的方式。In the isolation pile construction method for the deformation control of the shield tunnel passing through the building at a short distance as described above, in the isolation pile construction method, the hole forming sequence of the isolation pile adopts the method of jumping and opening holes.
本发明的优点是:于沉桩成孔步骤中采用特殊的套管法,即外套管与螺旋钻杆的旋转方向相反,且螺旋钻杆旋转取土的沉桩作法,使得外套管与螺旋钻杆同步钻至桩底标高,旋转取土的方式可以降低施工过程中的噪音,以及避免对土体的冲击,其中,外套管可以提供护壁作用并隔离施工过程中对周围土体的扰动,同时有明显的向外挤压作用,以减少土体损失,进一步辅助水泥浆与水玻璃注浆,有效控制隔离桩施工过程中的沉降,所以本发明盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法可以控制盾构施工近距离通过古建筑物时的沉降,同时保护古建筑物的安全,且针对上海特有土层,对环境要求苛刻条件下盾构隧道近距离穿越时,对历史建筑群的变形控制非常有效。The advantages of the present invention are: in the pile sinking hole forming step, a special casing method is adopted, that is, the rotation direction of the outer casing and the auger rod is opposite, and the pile sinking method in which the auger rod rotates to take soil, so that the outer casing and the auger The rods are drilled synchronously to the pile bottom elevation, and the method of rotating the soil can reduce the noise during the construction process and avoid the impact on the soil. Among them, the outer casing can provide the function of protecting the wall and isolate the disturbance of the surrounding soil during the construction process. It has an obvious outward extrusion effect to reduce soil loss, further assists cement slurry and water glass grouting, and effectively controls the settlement during the construction of the isolation pile. Therefore, the shield tunnel of the present invention passes through the isolation of the deformation control of the building at a short distance The pile construction method can control the settlement when the shield tunnel passes through the ancient buildings at close range, and at the same time protect the safety of the ancient buildings, and for the unique soil layer of Shanghai, the shield tunnel passes through the historical buildings under harsh environmental conditions. The deformation control of the group is very effective.
附图说明Description of drawings
图1为本发明盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法的一具体实施例的流程示意图。Fig. 1 is a flow diagram of a specific embodiment of the isolation pile construction method of the shield tunnel passing through the building deformation control at a short distance according to the present invention.
具体实施方式Detailed ways
如图1所示,揭示本发明所提供的盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法的流程示意图,该盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法是用于盾构施工近距离通过时,控制沉降以保护历史古建筑物,该盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法的实施步骤包含:浇筑钢筋混凝土传力平台,接续沉桩成孔步骤,并安装钢筋笼与浇筑混凝土,在执行辅助注浆措施。As shown in Figure 1, it discloses a schematic flow chart of the isolation pile construction method for the deformation control of the shield tunnel passing through the building at a short distance provided by the present invention. The isolation pile construction method for the deformation control of the shield tunnel passing through the building at a short distance is used When the shield tunnel passes through at a short distance, the settlement is controlled to protect the historical buildings. The implementation steps of the isolation pile construction method of the shield tunnel passing through the building deformation control at a short distance include: pouring a reinforced concrete force transmission platform, and continuing to sink the pile to form a hole steps, and install reinforcement cages and pour concrete, performing auxiliary grouting measures.
于浇筑钢筋混凝土传力平台的步骤中,根据实际施工作业面,浇筑一层厚度大于20公分的钢筋混凝土传力平台,并于欲钻孔的桩位处,在钢筋混凝土传力平台上预留一孔径大于隔离桩直径的穿孔,其中穿孔的直径比隔离桩直径大2公分,该钢筋混凝土传力平台形成导墙,并可确保后续成孔的垂直度。In the step of pouring the reinforced concrete force transmission platform, according to the actual construction work surface, pour a layer of reinforced concrete force transmission platform with a thickness greater than 20 cm, and reserve on the reinforced concrete force transmission platform at the pile position to be drilled. A perforation with a diameter larger than the diameter of the isolation pile, wherein the diameter of the perforation is 2 cm larger than the diameter of the isolation pile. The reinforced concrete force transmission platform forms a guide wall and can ensure the verticality of the subsequent hole formation.
于沉桩成孔的步骤中,将一全回转套管机移机,使全回转套管机上的外套管中心与桩位中心对准,并以该全回转套管机的垂直仪调整外套管垂直度后,再次检查外套管的中心与桩位中心的重合度,再以全回转套管机,分别将外套管及位于该外套管内的螺旋钻杆以旋转方式沉入,该外套管与螺旋钻杆的旋转方向相反,并依设计需求加接外套管与螺旋钻杆,直至设计标高再将螺旋钻杆提出,将外套管内的余土带出,并清除外套管内的虚土,确保隔离桩底端的土体为原始土层,其中,外套管反向旋转,螺旋钻杆正向旋转并取出外套管内的土,使土从外套管上的排土孔排出,外套管形成护壁并辅助水泥浆与水玻璃注浆,另外,外套管内的土面标高始终高于外套管的底标高3-5公尺,防止管涌,以及依据地质情况,外套管的深度可比实际桩长深1公尺,防止出现土体管涌现象,且施工中要实时监测,判断土层类别是否与地质数据相符。In the step of sinking piles to form holes, move a full-rotary casing machine so that the center of the outer casing on the full-rotary casing machine is aligned with the center of the pile position, and adjust the outer casing with the vertical instrument of the full-rotary casing machine After the verticality, check the coincidence degree of the center of the outer casing and the center of the pile again, and then use the full-rotary casing machine to respectively sink the outer casing and the auger pipe in the outer casing in a rotating manner, and the outer casing and the auger The rotation direction of the drill pipe is opposite, and the outer casing and the auger pipe are connected according to the design requirements, and the auger pipe is lifted up to the design elevation, and the remaining soil in the outer casing is brought out, and the virtual soil in the outer casing is removed to ensure that the isolation pile The soil at the bottom is the original soil layer, in which the outer casing rotates in reverse, the auger rod rotates forward and takes out the soil in the outer casing, so that the soil is discharged from the soil discharge hole on the outer casing, and the outer casing forms a retaining wall and assists the cement slurry Grouting with water glass, in addition, the soil level inside the outer casing is always 3-5 meters higher than the bottom elevation of the outer casing to prevent piping, and according to geological conditions, the depth of the outer casing can be 1 meter deeper than the actual pile to prevent Soil piping occurs, and real-time monitoring is required during construction to determine whether the type of soil layer is consistent with the geological data.
于安装钢筋笼的步骤中,钢筋笼的制造是依照设计要求,钢筋笼四周设有定位滚轮,以及钢筋笼底部设有水平抗浮钢板,将以两点双钩缓慢起吊制成后的钢筋笼,逐步倒点下放,不得使钢筋笼发生变形,于下放过程中,逐步调整钢筋笼方向,并钢筋笼就位前均绑上测绳,以确保钢筋笼定位准确及监测钢筋笼是否上浮。In the step of installing the reinforcement cage, the manufacture of the reinforcement cage is in accordance with the design requirements. There are positioning rollers around the reinforcement cage, and a horizontal anti-floating steel plate at the bottom of the reinforcement cage. The completed reinforcement cage will be hoisted slowly with two-point double hooks. Gradually lower the reinforcement cage to prevent deformation of the reinforcement cage. During the lowering process, gradually adjust the direction of the reinforcement cage, and tie the measuring rope before the reinforcement cage is in place, so as to ensure the accurate positioning of the reinforcement cage and monitor whether the reinforcement cage is floating.
于浇筑混凝土的步骤中,将混凝土导管安置后进行首次混凝土灌注,首次混凝土下落完成后以拔管机进行拔管作业,采用拔管机进行拔管,并检查外套管起拔是否顺畅与钢筋笼是否上浮,钢筋笼上浮则进行反压处理,起拔量控制在10-20公分,待外套管完全拔出后,便依需要进行补灌,灌完后再行拆除混凝土导管,其中,于浇筑混凝土的步骤中采用贮料斗进行上料作业,贮料斗的堵头采用圆形钢板并以细钢丝绳悬吊,以及首次上料的量大于首次灌注混凝土的量。In the step of pouring concrete, the first concrete pouring is carried out after the concrete pipe is placed, and the pipe pulling operation is carried out after the first concrete drop is completed. Whether it is floating or not, when the steel cage is floating, it will carry out back pressure treatment, and the lifting amount will be controlled at 10-20 cm. In the step of concrete, a storage hopper is used for feeding operations, the plug of the storage hopper is made of a circular steel plate and suspended by a thin steel wire rope, and the amount of the first feeding is greater than the amount of the first poured concrete.
于辅助注浆措施的步骤中,于盾构推进前完成隔离桩间的注浆孔成孔作业,根据盾构推进过程中的监测情形进行跟踪注浆。In the step of auxiliary grouting measures, the grouting holes between the isolation piles are completed before the shield tunneling, and the tracking grouting is carried out according to the monitoring situation during the shield tunneling.
于本发明盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法中,隔离桩的成孔顺序采用跳开成孔的方式,例如成孔顺序的施工桩号顺序为1-7-12...,待强度达到一定程度后再对相邻的施工桩号2-8-13...进行施工。In the isolation pile construction method for the shield tunnel passing through the deformation control of the building at a short distance in the present invention, the hole forming sequence of the isolation pile adopts the method of jumping and opening the hole, for example, the construction pile number sequence of the hole forming sequence is 1-7-12. .., after the strength reaches a certain level, the adjacent construction pile number 2-8-13... will be constructed.
综上所述,本发明盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法中采用外套管与螺旋钻杆的旋转方向相反的沉桩作法,以螺旋钻杆旋转取土并经由外套管上的排土孔排出,以及外套管与螺旋钻杆可同步钻至桩底标高,其中,旋转取土的方式可以降低施工过程中的噪音与避免对土体的冲击,此外,外套管于施工过程中可以提供护壁作用,并隔离施工过程中对周围土体的扰动,同时产生明显的向外挤压作用,使得土体损失减少,又可辅助水泥浆与水玻璃注浆,达到有效控制隔离桩施工过程中的沉降量,同时可以隔离盾构施工过程中的沉降影响,所以本发明盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法可以控制盾构施工近距离通过古建筑物时的沉降,保护古建筑物的结构安全,尤其适用于上海特有土层。In summary, in the isolation pile construction method for the shield tunnel passing through the deformation control of the building at a short distance in the present invention, the pile sinking method in which the outer sleeve and the auger rod rotate in the opposite direction is adopted, and the auger rod is used to rotate the soil and pass through the outer sleeve. The soil discharge hole on the top is discharged, and the outer casing and the auger pipe can be drilled to the pile bottom level synchronously. Among them, the way of rotating the soil can reduce the noise during the construction process and avoid the impact on the soil. In addition, the outer casing is used in the construction During the process, it can provide wall protection and isolate the disturbance of the surrounding soil during the construction process. At the same time, it can produce obvious outward extrusion, which reduces the loss of soil. It can also assist cement slurry and water glass grouting to achieve effective control and isolation. The settlement during the pile construction process can be isolated at the same time, and the settlement influence during the shield construction process can be isolated, so the isolation pile construction method of the present invention can control the deformation of the shield tunnel passing through the building at a short distance. Settlement, to protect the structural safety of ancient buildings, especially for Shanghai's unique soil.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2009102006980A CN101761237B (en) | 2009-12-24 | 2009-12-24 | Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2009102006980A CN101761237B (en) | 2009-12-24 | 2009-12-24 | Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101761237A CN101761237A (en) | 2010-06-30 |
| CN101761237B true CN101761237B (en) | 2011-06-01 |
Family
ID=42492607
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2009102006980A Expired - Fee Related CN101761237B (en) | 2009-12-24 | 2009-12-24 | Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101761237B (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102733821A (en) * | 2012-06-19 | 2012-10-17 | 浙江大学 | Secondary double-liquid slurry re-grouting method capable of effectively controlling surface deformation |
Families Citing this family (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102704937B (en) * | 2011-03-28 | 2014-06-25 | 同济大学 | Method for identifying settlement pattern during shield tunnel construction |
| CN102817378B (en) * | 2011-06-09 | 2014-06-25 | 同济大学 | Construction method of extra-large diameter shield tunnel penetrating through urban overhead pile foundations in close range |
| CN102995666A (en) * | 2011-09-13 | 2013-03-27 | 上海市基础工程有限公司 | Construction method for reducing effect of vibration on peripheral buildings (structures) |
| CN102888839A (en) * | 2012-10-16 | 2013-01-23 | 深圳市金泰建设工程有限公司 | Construction method of static-pressure sleeve rotary digging filling pile |
| CN104863183B (en) * | 2015-03-04 | 2019-03-05 | 中铁第六勘察设计院集团有限公司 | Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction |
| CN105804761B (en) * | 2016-03-14 | 2018-08-31 | 上海隧道工程有限公司 | Construction method suitable for liquefied sand stratum shield near-distance passing through building |
| CN108533277B (en) * | 2018-04-12 | 2020-07-24 | 中启胶建集团有限公司 | Sedimentation control construction method for long-distance penetration of large-diameter slurry shield through shed area under non-reinforced condition |
| CN109488209A (en) * | 2018-12-26 | 2019-03-19 | 腾达建设集团股份有限公司 | A kind of steel sleeve, full-sleeve full-rotation drill and drilling machine drilling method |
| CN110939450B (en) * | 2019-11-27 | 2021-04-13 | 中建五局土木工程有限公司 | Shield excavation grouting structure for water-rich disturbance sensitive stratum and construction method |
| CN111396063B (en) * | 2020-03-25 | 2021-05-28 | 中铁三局集团有限公司 | A construction method for a water-rich sand layer shield to cross an existing line and penetrate a sewage jacking pipe at a short distance |
| CN111997522B (en) * | 2020-08-31 | 2022-05-31 | 中启胶建集团有限公司 | A drilling device and a construction method for a cast-in-place pile running through a deep buried abandoned pipeline underground |
| CN114086545A (en) * | 2021-11-29 | 2022-02-25 | 上海隧道工程有限公司 | Ultra-deep MJS construction method |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP1457602A2 (en) * | 2003-02-27 | 2004-09-15 | BAUER Maschinen GmbH | Method of forming a foundation structure and device therefore |
| CN1900466A (en) * | 2006-07-20 | 2007-01-24 | 上海市第一建筑有限公司 | Isolation pile construction method for important building protection |
| CN1932244A (en) * | 2006-09-28 | 2007-03-21 | 上海隧道工程股份有限公司 | Construction method for double-circular shield near-distance passing through building or structure |
| CN1944939A (en) * | 2006-11-09 | 2007-04-11 | 北京东方泰晟基础机械技术有限公司 | Separable driving type sleeve screw drilling rig and its construction method |
-
2009
- 2009-12-24 CN CN2009102006980A patent/CN101761237B/en not_active Expired - Fee Related
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP1457602A2 (en) * | 2003-02-27 | 2004-09-15 | BAUER Maschinen GmbH | Method of forming a foundation structure and device therefore |
| CN1900466A (en) * | 2006-07-20 | 2007-01-24 | 上海市第一建筑有限公司 | Isolation pile construction method for important building protection |
| CN1932244A (en) * | 2006-09-28 | 2007-03-21 | 上海隧道工程股份有限公司 | Construction method for double-circular shield near-distance passing through building or structure |
| CN1944939A (en) * | 2006-11-09 | 2007-04-11 | 北京东方泰晟基础机械技术有限公司 | Separable driving type sleeve screw drilling rig and its construction method |
Non-Patent Citations (3)
| Title |
|---|
| JP特开2008-223391A 2008.09.25 |
| 白廷辉等.盾构超近距离穿越地铁运营隧道的保护技术.《地下工程与隧道》.2000,(第3期),2-6. * |
| 路明鉴.盾构穿越临近建(构)筑物施工控制技术.《铁道标准设计》.2007,54-57. * |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102733821A (en) * | 2012-06-19 | 2012-10-17 | 浙江大学 | Secondary double-liquid slurry re-grouting method capable of effectively controlling surface deformation |
Also Published As
| Publication number | Publication date |
|---|---|
| CN101761237A (en) | 2010-06-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101761237B (en) | Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance | |
| CN106284313B (en) | Long spire based on circulating mud retaining wall is squeezed into rock filling pile construction method | |
| CN108442382B (en) | In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method | |
| CN105275381B (en) | Impact drill drilling construction method in rich water pebble layer | |
| CN101638891B (en) | Construction method of all casing precessing isolation pile | |
| CN110735432B (en) | Pile foundation removal and parameter control method within the tunneling range of shield tunneling | |
| CN108894214B (en) | Karst cave geological environment cast-in-place pile and pile-forming construction method thereof | |
| CN104612179B (en) | Through the construction method of the diaphram wall of super thick silty sand ground | |
| CN102286984A (en) | Water-stop curtain and construction method thereof | |
| CN104631438B (en) | Long auger guncreting uplift pile construction method | |
| CN108166483A (en) | Bored pile construction method | |
| CN102286981A (en) | Waterproof curtain and construction method thereof | |
| CN106988302A (en) | A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method | |
| CN110593254A (en) | Construction method of cast-in-situ bored pile in stratum with karst cave in joint zone | |
| CN103255764A (en) | Construction method for vibrating sunken tube construction secant pile wall | |
| CN106013078B (en) | A construction method for strengthening curtain structure in highly permeable ground | |
| CN103541352A (en) | Underground and overground continuous construction method for major-diameter high flat bed pile in sandy soil stratum | |
| CN110093927B (en) | A method for controlling the deformation of the tunnel outside the foundation pit | |
| CN113323584A (en) | Drilling method of large vibrating long spiral drilling machine | |
| CN108265720A (en) | A kind of single-point bellows grouting device and its method for controlling soil deformation | |
| CN115584722A (en) | A construction method of occlusal piles in soft soil areas with rich water and rock-filled layers | |
| CN114108649A (en) | Foundation pit reinforcing construction method for mucky soil layer | |
| CN202194149U (en) | Waterproof curtain | |
| CN115596453A (en) | "Micro brush slope" entry method for long-distance side of tunnel passing through accumulation | |
| CN201762702U (en) | Drilling secant pile |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| ASS | Succession or assignment of patent right |
Owner name: SHANGHAI TUNNEL ENGINEERING CO., LTD. Free format text: FORMER OWNER: SHANGHAI TUNNEL ENGINEERING CO LTD Effective date: 20150130 |
|
| C41 | Transfer of patent application or patent right or utility model | ||
| COR | Change of bibliographic data |
Free format text: CORRECT: ADDRESS; FROM: 200082 HONGKOU, SHANGHAI TO: 200232 XUHUI, SHANGHAI |
|
| TR01 | Transfer of patent right |
Effective date of registration: 20150130 Address after: 200232 Shanghai Wanping Road No. 1099 Patentee after: SHANGHAI TUNNEL ENGINEERING Co.,Ltd. Address before: 200082 No. 118, Dalian Road, Shanghai Patentee before: SHANGHAI TUNNEL ENGINEERING Co.,Ltd. |
|
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110601 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |