Excavation construction method is assisted at a kind of vertical shaft main tunnel crossings on different level
Technical field
The present invention relates to urban track traffic bored tunnel technical field of construction, in particular to a kind of vertical shaft main tunnel solid is handed over
Excavation construction method is assisted at fork.
Background technique
When urban track traffic bored tunnel need to pass through water-enriched layer, especially there is thicker rich water above tunnel vault
Layer, often will appear the geological disasters such as gushing water way mud, especially in rich water argillaceous siltstoue stratum vertical shaft and main tunnel crossings on different level
Locate boring construction, working procedure is complicated at this, once there is above-mentioned geological disaster, underground water carries a large amount of silts and gushs,
It will seriously affect Tunnel Construction Schedule and safety.
Therefore, how to prevent boring construction at water rich strata vertical shaft main tunnel crossings on different level and geological disaster occur, guarantee main tunnel
Safe construction becomes a problem urgently to be resolved.
Summary of the invention
The purpose of the present invention is to provide excavation construction method is assisted at a kind of vertical shaft main tunnel crossings on different level, effectively to prevent
The gushing water way mud caused by water rich strata boring construction.
In order to achieve the above object, the present invention, which uses, assists excavation construction method at a kind of vertical shaft main tunnel crossings on different level, including
Following construction procedure:
When below vertical shaft being constructed downwards to transverse passage-way, pipe canopy is applied to transverse passage-way top and carries out pre-reinforcement;
When transverse passage-way excavates, injected hole is bored in transverse passage-way arch, grouting pipe is applied in injected hole and injects slurries forms the
One fixing collar;
Before transverse passage-way enters main tunnel, pipe canopy is applied in main tunnel arch;
When main tunnel is excavated, using front pre-grouting reinforcing mode in the second fixing collar of tunnel arch construction.
Preferably, described when vertical shaft is constructed downwards to lower section at the top of transverse passage-way, to transverse passage-way at the top of apply pipe canopy and carry out
Pre-reinforcement, comprising:
Below the vertical shaft is constructed downwards to transverse passage-way when the position 2m, pipe canopy is applied to transverse passage-way top and carries out pre-add
Gu the outer limb of pipe canopy is 1 ° ~ 3 °, the circumferential spacing of pipe canopy is 0.4m.
Preferably, when the transverse passage-way excavates, injected hole is bored in transverse passage-way arch, grouting pipe is applied in injected hole simultaneously
It injects slurries and forms the first fixing collar, comprising:
When carrying out transverse passage-way top bar excavation, along 150 ° of transverse passage-way arch brill injected hole;
It is inserted into Grouting Pipe in injected hole, cement-water-clay system is injected into Grouting Pipe;
First fixing collar is formed after the completion of slip casting.
Preferably, the injected hole includes centre bore and annular distance, and centre bore is arranged in tunnel center position, with centre bore
For the center of circle concentric round edge as concentric ring, annular distance is arranged on concentric ring.
Preferably, described before transverse passage-way enters main tunnel, pipe canopy is applied in main tunnel arch, comprising:
Before transverse passage-way enters main tunnel, using main tunnel center as the center of circle, main tunnel arch is as circular arc, in circular arc both ends and circle center line connecting
The central angle of formation is that the main tunnel arch within the scope of 150 ° applies pipe canopy, and wherein the outer limb of pipe canopy is 1 ° ~ 3 °, the circumferential direction of pipe canopy
Spacing is 0.4m
Preferably, the line in main tunnel arch center position and the center of circle is the angular bisector of the central angle.
Preferably, when to the injected hole slip casting, comprising:
Injected hole interval slip casting from injected hole of the injected hole on outer ring in inner ring successively slip casting, same ring.
Preferably, retrusive slip casting is used when the injected hole slip casting.
Preferably, the cement grout ratio of mud of the slurries is 1:1.07, and cement slurry and waterglass volume ratio are 1:0.65.
Compared with prior art, there are following technical effects by the present invention: the present invention assists excavation method grouting and reinforcing range
(the above 5m in arch) greatly, the stratum according to locating for tunnel are rich water completely decomposed argillaceous siltstoue, increase water in terms of slip casting proportion
The dosage of mud suitably reduces waterglass ratio, can be shortened slurries setting time, effectively improves grouting consolidation effect.The method
Apply the generation that can effectively prevent unfavorable geology disaster in water rich strata boring construction.
Detailed description of the invention
With reference to the accompanying drawing, specific embodiments of the present invention will be described in detail:
Fig. 1 is auxiliary excavation construction method flow diagram at vertical shaft main tunnel crossings on different level;
Fig. 2 is slip casting schematic cross-sectional view;
Fig. 3 is slip casting schematic longitudinal section;
Fig. 4 is Grouting Pipe schematic diagram.
In figure: 1: vertical shaft;2: transverse passage-way;3: pipe canopy;4: Grouting Pipe;5: injected hole;6: main tunnel;7: the first fixing collars;9:
Second fixing collar.
Specific embodiment
In order to further explain feature of the invention, reference should be made to the following detailed description and accompanying drawings of the present invention.Institute
Attached drawing is only for reference and purposes of discussion, is not used to limit protection scope of the present invention.
As shown in Figure 1, present embodiment discloses excavation construction method is assisted at a kind of vertical shaft main tunnel crossings on different level, including such as
Lower construction procedure S1 to S4:
S1, when vertical shaft is constructed downwards to lower section at the top of transverse passage-way, to transverse passage-way at the top of apply pipe canopy and carry out pre-reinforcement;
When S2, transverse passage-way excavate, injected hole is bored in transverse passage-way arch, grouting pipe is applied in injected hole and injects slurries is formed
First fixing collar;
S3, before transverse passage-way enters main tunnel, apply pipe canopy in main tunnel arch;
S4, main tunnel excavate when, using front pre-grouting reinforcing mode tunnel arch construct the second fixing collar.
It should be noted that being finished in slip casting, excavated after forming the second fixing collar, erects grid steel frame, and spray
C25 gunite concrete.When construction needs, face can be closed using 50mm thickness C25 gunite concrete.The note of the present embodiment
It is larger to starch reinforcing scope, can effectively prevent the generation of unfavorable geology disaster in water rich strata boring construction in the above 5m in arch.
Specifically, as shown in Figure 2 to Figure 3, in above-mentioned steps S1, in the lower section of the construction downwards of vertical shaft 1 to 2 top of transverse passage-way
When the position 2m, to transverse passage-way 2 at the top of perform 108 pipe canopy 3 of φ, pipe canopy length L=10m, 1 ° ~ 3 ° of outer limb, circumferential spacing 0.4m,
Pipe canopy circumferential direction spacing refers to the linear distance at two adjacent tubes canopy centers.
Specifically, in above-mentioned steps S2, when carrying out 2 top bar of transverse passage-way excavation, along the use of 150 ° of the arch of transverse passage-way 2
Pneumatic drilling machine drill injected hole, and pushed Grouting Pipe 4 into injected hole with the jacking force of air rock drill.To injected hole using close
Sealing of hole mouth retrusive slip casting forms the first fixing collar 7 of high 5m in 2 arch of transverse passage-way after the completion of slip casting.
It should be noted that controlling bore angle using inclinometer, Grouting Pipe should abut excavation face when being drilled with injected hole
Grid steel frame is squeezed into.
As shown in figure 4, Grouting Pipe 4 uses long φ 108mm, the hot rolled seamless steel tube of wall thickness 5mm, length 3m, before Grouting Pipe 4
End is cone-shaped convenient in Grouting Pipe insertion country rock.As shown in Fig. 2, injected hole includes centre bore and annular distance, centre bore is arranged in
Tunnel center position is the concentric round edge in the center of circle as concentric ring using centre bore, and annular distance is arranged on concentric ring.
The circumferential spacing 0.4m of Grouting Pipe 4, longitudinal pitch 2m, pitch of holes 1.5m arrangement.The tube wall surrounding of Grouting Pipe 4 according to
75cm spacing is drilled with a ring, is drilled with 9 rings in the present embodiment altogether, the quantity, tilt angle of injected hole and inclination length on each ring
Degree is different.The quantity of injected hole is successively increased from inner ring to outer ring on each ring, and the tilt angle of injected hole is outside by inner ring
Ring successively increases, and tilt length is first gradually increased from inner ring to outer ring and is gradually reduced again.By multiple to being arranged in the present embodiment
Concentric ring, the quantity of the injected hole on concentric ring, tilt angle and tilt length setting are different, so that passing through what Grouting Pipe was injected
Slurries can be penetrated into uniformly in country rock.
Specifically, in above-mentioned steps S3: before transverse passage-way enters main tunnel, applying pipe canopy in main tunnel arch.It include: horizontal logical
Before road 2 enters main tunnel 6,108 pipe canopy 3 of φ is performed for 150 ° along main tunnel arch, L=10m, 1 ° ~ 3 ° of outer limb, circumferential spacing 0.4m is right
The main tunnel arch soil body is first reinforced.
It should be noted that the present embodiment, using main tunnel center as the center of circle, main tunnel arch is as circular arc, in circular arc both ends and circle
The central angle that heart line is formed is that the main tunnel arch within the scope of 150 ° applies pipe canopy, main tunnel arch center position and the center of circle
Line be the central angle angular bisector.
Specifically, above-mentioned steps S4: when main tunnel is excavated, using front pre-grouting reinforcing mode in tunnel arch construction the
Two fixing collars, comprising: when main tunnel is excavated, on the basis of above-mentioned injected hole 5 being drilled with, by the way of front pre-grouting reinforcing,
5 diameter of injected hole is not less than 108mm;Orifice tube uses φ 108mm, the hot rolled seamless steel tube of wall thickness 5mm, length 3m.Injected hole 5
It is arranged by dilation angle 2m, pitch of holes 1.5m.
Specifically, the slurries of injection use cement-water-clay system, the cement grout ratio of mud be 1:1.07, cement slurry with
Waterglass volume ratio is 1:0.65, grouting pressure 0.4-0.8MPa.Using seal orifice retrusive slip casting, in tunnel after the completion of slip casting
Road arch forms the second fixing collar 8 of high 5m.
The present embodiment stratum according to locating for tunnel is rich water completely decomposed argillaceous siltstoue, increases water in terms of slip casting proportion
The dosage of mud suitably reduces waterglass ratio, can be shortened slurries setting time, effectively improves grouting consolidation effect, more suitable
For being in the geology characteristic of soap-free emulsion polymeization, the layer of sand of self-stable ability difference and gravel (ovum) rock layers.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all in spirit of the invention and
Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.