Auxiliary excavation construction method for vertical shaft main tunnel three-dimensional intersection
Technical Field
The invention relates to the technical field of urban rail transit underground excavation tunnel construction, in particular to an auxiliary excavation construction method for a vertical shaft main tunnel vertical intersection.
Background
When the urban rail transit underground excavation tunnel needs to penetrate through a water-rich layer, particularly a thicker water-rich layer exists above a tunnel vault, geological disasters such as water inrush and mud inrush often occur, particularly underground excavation construction at the vertical shaft and main tunnel three-dimensional intersection of a water-rich muddy siltstone stratum is complex in construction procedure at the position, once the geological disasters occur, underground water carries a large amount of silt to gush out, and the tunnel construction progress and safety are seriously influenced.
Therefore, how to prevent geological disasters from occurring in underground excavation construction at the vertical crossing of the vertical shaft main hole in the water-rich stratum and ensure the safe construction of the main hole becomes a difficult problem to be solved urgently.
Disclosure of Invention
The invention aims to provide an auxiliary excavation construction method for a vertical shaft main hole vertical crossing so as to effectively prevent water inrush and mud inrush caused by underground excavation construction in a water-rich stratum.
In order to realize the purpose, the invention adopts an auxiliary excavation construction method for the vertical shaft main tunnel three-dimensional intersection, which comprises the following construction steps:
when the vertical shaft is constructed downwards to the position below the top of the transverse channel, a pipe shed is applied to the top of the transverse channel for pre-reinforcement;
when a transverse channel is excavated, a grouting hole is drilled in the arch part of the transverse channel, a grouting pipeline is constructed in the grouting hole, and slurry is injected to form a first reinforcing ring;
before the transverse channel enters the main tunnel, constructing a pipe shed at the arch part of the main tunnel;
and when the main tunnel is excavated, constructing a second reinforcing ring at the arch part of the transverse channel by adopting an advanced pre-grouting reinforcing mode.
Preferably, when the vertical shaft is constructed downwards to the position below the top of the transverse channel, the pipe shed is applied to the top of the transverse channel for pre-reinforcement, and the method comprises the following steps:
and when the vertical shaft is constructed downwards to a position 2m below the top of the transverse passage, constructing a pipe shed to the top of the transverse passage for pre-reinforcement, wherein the external insertion angle of the pipe shed is 1-3 degrees, and the circumferential interval of the pipe shed is 0.4 m.
Preferably, when the transverse channel is excavated, a grouting hole is drilled in an arch part of the transverse channel, a grouting pipe is constructed in the grouting hole, and grout is injected into the grouting hole to form the first reinforcing ring, and the method includes:
when the upper step of the transverse channel is excavated, grouting holes are drilled along the arch part of the transverse channel at 150 degrees;
inserting a grouting pipe into the grouting hole, and injecting cement-water glass slurry into the grouting pipe;
and forming the first reinforcing ring after grouting is finished.
Preferably, the grouting holes comprise a central hole and ring holes, the central hole is arranged at the central position of the transverse channel, concentric circle edges with the central hole as the center serve as concentric rings, and the ring holes are arranged on the concentric rings.
Preferably, before the transverse passage enters the main tunnel, the tunnel arch is constructed as a pipe shed, and the method comprises the following steps:
before the transverse channel enters the main tunnel, the center of the main tunnel is taken as the center of a circle, the arch part of the main tunnel is taken as an arc, the arch part of the main tunnel, which is formed by connecting the two ends of the arc with the center of a circle, forms a central angle of 150 degrees, is used as a pipe shed, wherein the external insertion angle of the pipe shed is 1-3 degrees, and the circumferential interval of the pipe shed is 0.4 m.
Preferably, a connecting line between the central point position of the arch part of the main tunnel and the center of the circle is an angular bisector of the central angle.
Preferably, when grouting into the grouting hole, the method comprises the following steps:
sequentially grouting from the grouting holes on the outer ring to the grouting holes on the inner ring, and grouting at intervals from the grouting holes on the same ring.
Preferably, retreating type grouting is adopted when the grouting holes are grouted.
Preferably, the cement slurry water cement ratio of the slurry is 1: 1.07, the volume ratio of cement paste to water glass is 1: 0.65.
compared with the prior art, the invention has the following technical effects: the auxiliary excavation method has the advantages that the grouting reinforcement range is large (5 m above the arch part), the using amount of cement is increased in the aspect of grouting proportion according to the fact that the stratum where the tunnel is located is the water-rich completely weathered argillaceous siltstone, the proportion of water glass is properly reduced, the slurry setting time can be shortened, and the grouting reinforcement effect is effectively improved. The method can effectively prevent the generation of unfavorable geological disasters in the underground excavation construction of the water-rich stratum.
Drawings
The following detailed description of embodiments of the invention refers to the accompanying drawings in which:
FIG. 1 is a schematic flow chart of an auxiliary excavation construction method at a vertical shaft main tunnel vertical crossing;
FIG. 2 is a schematic cross-sectional view of a grouting;
FIG. 3 is a schematic longitudinal section of grouting;
fig. 4 is a schematic view of a slip pipe.
In the figure: 1: a shaft; 2: a transverse channel; 3: a pipe shed; 4: a grouting pipe; 5: grouting holes; 6: correcting the hole; 7: a first reinforcing ring; 8: and a second reinforcing ring.
Detailed Description
To further illustrate the features of the present invention, refer to the following detailed description of the invention and the accompanying drawings. The drawings are for reference and illustration purposes only and are not intended to limit the scope of the present disclosure.
As shown in fig. 1, the embodiment discloses an auxiliary excavation construction method for a vertical shaft main tunnel solid intersection, which includes the following construction steps S1 to S4:
s1, when the vertical shaft is constructed downwards to the position below the top of the transverse channel, constructing a pipe shed on the top of the transverse channel for pre-reinforcing;
s2, when a transverse channel is excavated, drilling grouting holes in the arch part of the transverse channel, constructing grouting pipelines in the grouting holes and injecting grout to form a first reinforcing ring;
s3, before the transverse channel enters the main tunnel, constructing a pipe shed at the arch part of the main tunnel;
and S4, when the main tunnel is excavated, constructing a second reinforcing ring at the arch part of the transverse channel by adopting an advanced pre-grouting reinforcing mode.
After grouting is completed, excavation is performed after the second reinforcing ring is formed, a grid steel frame is erected, and C25 spray concrete is sprayed. When construction needs, C25 sprayed concrete with the thickness of 50mm can be used for sealing the tunnel face. The grouting reinforcement range of the embodiment is large, the grouting reinforcement range can be 5m above the arch part, and the generation of unfavorable geological disasters in the underground excavation construction of the water-rich stratum is effectively prevented.
Specifically, as shown in fig. 2 to 3, in step S1, when the shaft 1 is constructed downwards to a position 2m below the top of the horizontal passage 2, a pipe shed 3 with a diameter of phi 108 is constructed on the top of the horizontal passage 2, the length L of the pipe shed is 10m, the extrapolation angle is 1 to 3 degrees, the circumferential distance is 0.4m, and the circumferential distance of the pipe shed is the straight line distance between the centers of two adjacent pipe sheds.
Specifically, in step S2, when the lateral passage 2 is excavated to form the upper step, a grouting hole is drilled along the 150 ° arch of the lateral passage 2 by using a pneumatic rock drill, and the grouting pipe 4 is pushed into the grouting hole by the top thrust of the pneumatic rock drill. And (3) performing sealing orifice retreating type grouting on the grouting hole, and forming a first reinforcing ring 7 with the height of 5m at the arch part of the transverse channel 2 after grouting is finished.
It should be noted that, when drilling the grouting hole, the drilling angle is controlled by the inclinometer, and the grouting pipe should be driven into the hole close to the grid steel frame of the excavation face.
As shown in figure 4, the grouting pipe 4 is a hot-rolled seamless steel pipe with the length of 108mm and the wall thickness of 5mm, the length is 3m, and the front end of the grouting pipe 4 is in a taper shape, so that the grouting pipe can be inserted into surrounding rocks conveniently. As shown in fig. 2, the grouting holes include a central hole disposed at the center of the lateral passage, concentric circles around the central hole as a center as concentric rings, and annular holes disposed on the concentric rings.
The circumferential distance of the grouting pipes 4 is 0.4m, the longitudinal distance is 2m, and the hole distance is 1.5 m. A ring is drilled at the periphery of the pipe wall of the grouting pipe 4 according to the interval of 75cm, 9 rings are drilled in the embodiment, and the number, the inclination angle and the inclination length of grouting holes on each ring are different. The number of the grouting holes on each ring is sequentially increased from the inner ring to the outer ring, the inclination angles of the grouting holes are sequentially increased from the inner ring to the outer ring, and the inclination lengths are gradually increased and then gradually decreased from the inner ring to the outer ring. Through setting up a plurality of concentric rings in this embodiment, the quantity, inclination and the slope length setting of the injected hole on the concentric ring are different for the thick liquid that injects through the slip casting pipe can be even infiltrates in the country rock.
Specifically, in step S3 described above: before the transverse channel enters the main tunnel, a tunnel arch is constructed. The method comprises the following steps: before the transverse channel 2 enters the main tunnel 6, a phi 108 pipe shed 3 is constructed along the arch part of the main tunnel at 150 degrees, L is 10m, the external insertion angle is 1-3 degrees, the annular interval is 0.4m, and the soil body of the arch part of the main tunnel is firstly reinforced.
It should be noted that, in this embodiment, the center of the main tunnel is taken as the center of a circle, the arch of the main tunnel is taken as an arc, the arch of the main tunnel, which is formed by connecting the two ends of the arc with the center of a circle, forms a central angle of 150 ° and serves as a pipe shed, and the connecting line between the center point position of the arch of the main tunnel and the center of a circle is the angular bisector of the central angle.
Specifically, the above step S4: when just hole excavation, adopt advance slip casting reinforcing mode in advance at tunnel hunch portion construction second reinforcing ring, include: when the main tunnel is excavated, on the basis of the drilled grouting hole 5, an advanced pre-grouting reinforcement mode is adopted, and the diameter of the grouting hole 5 is not less than 108 mm; the orifice pipe is a hot-rolled seamless steel pipe with the diameter of 108mm and the wall thickness of 5mm, and the length of the pipe is 3 m. The grouting holes 5 are arranged according to the diffusion radius of 2m and the hole spacing of 1.5 m.
Specifically, the injected slurry is cement-water glass slurry, and the water cement ratio of the cement slurry is 1: 1.07, the volume ratio of cement paste to water glass is 1: 0.65 and the grouting pressure is 0.4-0.8 MPa. And (3) adopting the sealing hole retreating type grouting, and forming a second reinforcing ring 8 with the height of 5m at the arch part of the tunnel after the grouting is finished.
The embodiment is rich water completely weathered argillaceous siltstone according to the stratum of the tunnel, increases the using amount of cement in the aspect of grouting proportion, properly reduces the proportion of water glass, can shorten the slurry setting time, effectively improves the grouting reinforcement effect, and is more suitable for the geological characteristics of a sand layer and a gravel (gravel) stone layer which are not bonded and have poor self-stability.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.