CN110106830A - One kind having hole mold-bagged concrete ecological bank protection structure and construction method - Google Patents

One kind having hole mold-bagged concrete ecological bank protection structure and construction method Download PDF

Info

Publication number
CN110106830A
CN110106830A CN201910364805.7A CN201910364805A CN110106830A CN 110106830 A CN110106830 A CN 110106830A CN 201910364805 A CN201910364805 A CN 201910364805A CN 110106830 A CN110106830 A CN 110106830A
Authority
CN
China
Prior art keywords
concrete
slope
bamboo tube
anchor rod
ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910364805.7A
Other languages
Chinese (zh)
Other versions
CN110106830B (en
Inventor
叶建军
姜泉泉
刘德富
肖衡林
刘瑛
王琴
马强
陈阳阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei University of Technology
Original Assignee
Hubei University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei University of Technology filed Critical Hubei University of Technology
Priority to CN201910364805.7A priority Critical patent/CN110106830B/en
Publication of CN110106830A publication Critical patent/CN110106830A/en
Application granted granted Critical
Publication of CN110106830B publication Critical patent/CN110106830B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Revetment (AREA)

Abstract

一种有孔模袋混凝土生态护岸结构及施工方法,主要包括混凝土条、竹管和锚杆,所述混凝土条采用模袋自密实混凝土,其长度方向与坡面等高线成一定角度,混凝土条之间留有与其长度和宽度方向分别平行的斜沟;锚杆一端插入边坡中,一端固定巢穴竹管和植被竹管并埋在混凝土条中。本发明能适应复杂地形,施工效率高,可应用于岩质水岸或消落带,在对水岸或消落带进行有效的防护的同时,为野生动物提供巢穴,为植物提供生长环境。

An ecological revetment structure and construction method of mold bag concrete with holes, mainly including concrete strips, bamboo pipes and anchor rods, the concrete strips are self-compacting concrete with mold bags, the length direction of which is at a certain angle to the slope contour, and the concrete There are oblique grooves parallel to the length and width directions between the strips; one end of the anchor rod is inserted into the slope, and the other end fixes the nest bamboo tube and the vegetation bamboo tube and is buried in the concrete strip. The invention can adapt to complex terrain and has high construction efficiency, and can be applied to rocky water banks or ebb zones, and can provide nests for wild animals and growth environments for plants while effectively protecting water banks or ebb zones.

Description

一种有孔模袋混凝土生态护岸结构及施工方法A kind of perforated mold bag concrete ecological revetment structure and construction method

技术领域technical field

本发明涉及一种有孔模袋混凝土生态护岸结构及施工方法,属于生态环境保护领域。The invention relates to a perforated mold bag concrete ecological revetment structure and a construction method, belonging to the field of ecological environment protection.

背景技术Background technique

现有护坡技术中通常会根据消落带水位涨落对植物进行分阶梯布置和设置自动漂浮装置的方法对消落带进行防护。植物分阶梯布置的方案根据不同植物的耐水、耐旱能力等生物学特性区分不同的梯级,可以在一定程度上解决消落带绿化的问题,但是大多数岩质边坡缺乏植物、动物以及微生物生活的条件,植物不易存活,且汛期时间的长短直接影响到植物的生长;自动漂浮装置通过设置伐垫能够对消落带边坡有效防护,能够消波防浪,减小侵蚀,但是无法适应复杂的地形,缺乏对动物生境的考虑,使生态平衡遭到破坏。In the existing slope protection technology, plants are usually arranged in steps according to the fluctuation of the water level in the water-fluctuation zone and an automatic floating device is installed to protect the water-fluctuation zone. The step-by-step arrangement of plants distinguishes different steps according to the biological characteristics of different plants such as water resistance and drought tolerance, which can solve the problem of greening in the water-fluctuating zone to a certain extent, but most rocky slopes lack plants, animals and microorganisms Living conditions, plants are not easy to survive, and the length of the flood season directly affects the growth of plants; the automatic floating device can effectively protect the slope of the water-fluctuating zone by setting cutting mats, and can eliminate waves and waves, and reduce erosion, but it cannot adapt The complex topography and the lack of consideration for animal habitats have disrupted the ecological balance.

发明内容Contents of the invention

本发明针对上述问题,能够对边坡进行有效防护,使种植的植物易存活,克服汛期时间的长短对植物的影响,提出了一种有孔模袋混凝土生态护岸结构及施工方法。Aiming at the above problems, the invention can effectively protect the slope, make the planted plants easy to survive, and overcome the influence of the length of the flood season on the plants, and proposes an ecological revetment structure and construction method of mold bag concrete with holes.

本发明采取的技术方案如下:The technical scheme that the present invention takes is as follows:

一种有孔模袋混凝土生态护岸结构,包括混凝土条,在混凝土条中预埋有巢穴竹管、植被竹管,所述混凝土条之间留有与其长度和宽度方向分别平行的间隙形成相互交叉的斜沟;巢穴竹管绑扎固定于圆环锚杆上,其管口开口于斜沟,至少有两根相互贯通;圆环锚杆的一端插在边坡中,另一端埋在混凝土条中;植被竹管插在圆环锚杆的圆环中,植被竹管的空腔中有基质及植物。An ecological revetment structure of molded bag concrete with holes, including concrete strips in which nest bamboo tubes and vegetation bamboo tubes are pre-embedded, and gaps parallel to the length and width directions of the concrete strips are left to cross each other the inclined ditch; the nest bamboo tube is tied and fixed on the ring anchor rod, and its mouth is opened in the inclined ditch, and at least two of them are connected to each other; one end of the ring anchor rod is inserted in the slope, and the other end is buried in the concrete strip The vegetation bamboo tube is inserted in the ring of the ring anchor rod, and the cavity of the vegetation bamboo tube has matrix and plants.

斜沟长度方向与坡面等高线成β角,12°≤β≤30°。The length direction of the inclined ditch forms an angle of β with the contour line of the slope, 12°≤β≤30°.

所述植被竹管与坡面成α角,60°≤α≤80°。The vegetation bamboo tube forms an angle α with the slope, 60°≤α≤80°.

所述植被竹管空腔中的基质为:耕植土、腐熟木屑、河沙和土壤粘合剂充分拌合后的混合物,以体积比计:耕植土:腐熟木屑:河沙=70-90:5-12:5-15;土壤粘合剂的用量为0.016-0.019 g/L;植物为狗牙根(Cynodon dactylon (L.) Pers.)、鬼针草(Bidens pilosa L.)、苍耳(Xanthium sibiricum Patrin ex Widder)或蓼草(Ludwigia prostrata Roxb)中的一种或几种。The matrix in the cavity of the vegetation bamboo tube is: a mixture of cultivated soil, decomposed sawdust, river sand and soil binder fully mixed, in volume ratio: cultivated soil: decomposed sawdust: river sand=70- 90: 5-12: 5-15; the dosage of soil binder is 0.016-0.019 g/L; the plants are bermudagrass (Cynodon dactylon (L.) Pers.) , ghost needle grass (Bidens pilosa L.) , One or more of ear (Xanthium sibiricum Patrin ex Widder) or Polygonum (Ludwigia prostrata Roxb) .

圆环锚杆插入坡面的深度不小于15 cm,伸出坡面的长度不小于20 cm。The depth of the ring anchor inserted into the slope is not less than 15 cm, and the length of the protruding slope is not less than 20 cm.

所述的圆环锚杆包括竖向钢筋以及与竖向钢筋连接的圆环,圆环穿过竖向钢筋并固定在竖向钢筋上。The ring anchor rod includes a vertical steel bar and a ring connected with the vertical steel bar, and the ring passes through the vertical steel bar and is fixed on the vertical steel bar.

有孔模袋混凝土生态护岸结构的施工方法,包括以下步骤:The construction method of the concrete ecological revetment structure with hole mold bags comprises the following steps:

(1)准备材料,准备竹管、圆环锚杆、螺纹锚杆、垫片、螺帽、土工模袋和压条等材料:将巢穴竹管和植被竹管的内腔打通,管口用加厚塑料薄膜封口,然后将巢穴竹管管壁开口;在光圆钢筋上焊上圆环形成圆环锚杆;土工模袋在加工时预留未缝合的边B及混凝土灌注口,在其与坡面接触平面的两个相邻的边上缝制定位环;(1) Prepare materials, prepare materials such as bamboo tubes, ring anchors, threaded anchors, gaskets, nuts, geomold bags and layering strips: open the inner cavity of the nest bamboo tube and the vegetation bamboo tube, The thick plastic film is sealed, and then the bamboo tube wall of the nest is opened; a ring is welded on the light round steel bar to form a ring anchor; Seam positioning rings on two adjacent sides of the slope contact plane;

(2)清坡放样,清理坡面滚石、浮土及枯树枝,并测量放线;(2) Slope clearing and setting out, cleaning rolling stones, floating soil and dead branches on the slope surface, and measuring and setting out;

(3)钻锚孔,在坡面上钻锚孔;(3) Drill anchor holes and drill anchor holes on the slope;

(4)安装螺纹锚杆,把螺纹锚杆插入锚孔中,用水泥注浆填充螺纹锚杆与孔隙之间的间隙;(4) Install the threaded anchor rod, insert the threaded anchor rod into the anchor hole, and fill the gap between the threaded anchor rod and the hole with cement grouting;

(5)安装土工模袋,待水泥硬化后,将螺纹锚杆穿过定位环,然后把压条压在土工模袋上,在压条上钻孔,接着将螺纹锚杆穿过垫片和压条插入坡体,最后拧紧螺帽;(5) Install the geotechnical bag. After the cement hardens, pass the threaded anchor rod through the positioning ring, then press the bead on the geotechnical bag, drill holes on the bead, and then insert the threaded anchor rod through the gasket and the bead. slope body, and finally tighten the nut;

(6)安装竹管,把圆环锚杆刺穿土工模袋插入锚孔中,用水泥注浆填充锚杆与孔隙之间的间隙,待水泥硬化后,把植被竹管插入圆环锚杆的圆环中,将其顶端粘接在土工模袋内表面,接着把巢穴竹管绑扎固定在圆环锚杆上,两巢穴竹管之间在接口E处粘接,拼装完成后缝合土工模袋;(6) Install the bamboo tube, insert the ring anchor rod through the geomold bag into the anchor hole, fill the gap between the anchor rod and the hole with cement grouting, and insert the vegetation bamboo tube into the ring anchor rod after the cement hardens In the circular ring, glue its top to the inner surface of the geomembrane bag, then bind and fix the nest bamboo tube on the ring anchor rod, bond the two nest bamboo tubes at the interface E, and sew the geomembrane after the assembly is completed bag;

(7)浇筑混凝土,采用泵送混凝土的技术施工混凝土条,混凝土条的施工顺序是从坡顶到坡脚依次进行;每一个混凝土条施工时,从土工模袋混凝土灌注口浇注自密实混凝土;(7) Pouring concrete, adopting the technology of pumping concrete to construct concrete strips, the construction sequence of concrete strips is to carry out sequentially from the top of the slope to the foot of the slope; during the construction of each concrete strip, pour self-compacting concrete from the concrete filling port of the geomold bag;

(8)养护,砂浆终凝后开始洒水养护,养护期间要求护坡表面处于湿润状态,待混凝土强度达到75%以上时,剪开与巢穴竹管相连的模袋的侧边使管口露出,成为动物通行的入口;(8) maintenance, start sprinkling maintenance after the final setting of the mortar, require slope protection surface to be in a wet state during the maintenance, when the concrete strength reaches more than 75%, cut the side of the mold bag connected to the nest bamboo tube to expose the nozzle, and become entrances for the passage of animals;

(9)植被竹管施工,剪开与植被竹管相连的模袋上表面,使管口露出并在管中放入基质及植物种子。(9) Vegetation bamboo tube construction, cut open the mold bag upper surface that links to each other with vegetation bamboo tube, make the mouth of the tube expose and put matrix and plant seed in the tube.

本发明提供的有孔模袋混凝土生态护岸结构及施工方法具有以下有益效果:The ecological revetment structure and construction method provided by the present invention have the following beneficial effects:

1) 通过模袋混凝土和预埋竹管形成的有孔混凝土结构,一体化解决了消落带或河岸的防护、绿化和生物巢穴构建,增加了消落带或河岸的稳定和生物多样性,美化了景观。1) The porous concrete structure formed by molded concrete and pre-embedded bamboo tubes integratedly solves the protection, greening and biological nest construction of the water-fluctuation zone or river bank, and increases the stability and biodiversity of the water-fluctuation zone or river bank. Beautified the landscape.

2) 使用土工模袋和泵送自密实混凝土技术,降低了施工成本,方便施工。2) The use of geotechnical mold bags and pumped self-compacting concrete technology reduces construction costs and facilitates construction.

3) 模袋混凝土能适应边坡的凹凸不平的地形,可对边坡有效防护。3) The mold bag concrete can adapt to the uneven terrain of the slope and can effectively protect the slope.

4) 通过预埋不同直径的竹管,可以供多种生物栖息,在水下时,可供鱼虾等栖息;在水上时,可供蛙、蛇、龟等栖息。4) By pre-embedding bamboo tubes of different diameters, it can provide habitat for various organisms. When underwater, it can be used for fish and shrimp; when above water, it can be used for frogs, snakes, turtles, etc. to inhabit.

5)混凝土条之间的斜沟,坡度较小,可以排水的同时,为动物活动提供通道。5) The slope between the concrete strips has a small slope, which can drain water and provide passages for animal activities.

6) 圆环锚杆和螺纹锚杆植入边坡中,加固岩体强度和自稳能力,增加了竹管的固定强度,使混凝土、土工模袋和岩体形成共同的体系。6) The ring bolts and threaded bolts are implanted into the slope to strengthen the strength and self-stabilization of the rock mass, increase the fixing strength of the bamboo tube, and make the concrete, geotechnical bag and rock mass form a common system.

综上,本发明能够对边坡进行有效防护,在岩质边坡为植物、动物以及微生物提供了存活条件,使种植的植物易存活,解决了陡峭岩石边坡同时防护和绿化的难题。In summary, the present invention can effectively protect slopes, provide living conditions for plants, animals and microorganisms on rocky slopes, make planted plants easy to survive, and solve the problem of simultaneous protection and greening of steep rocky slopes.

附图说明Description of drawings

图1是安装在坡面上已浇筑混凝土但未拆除土工模袋的平面示意图。Figure 1 is a schematic plan view of the geomembrane bag that has been poured on the slope but has not been removed.

图2是安装在坡面上已安装竹管但未浇筑混凝土的单个土工模袋的立体示意图。Fig. 2 is a three-dimensional schematic diagram of a single geomembrane bag installed with bamboo pipes but not poured concrete on the slope.

图3是图1的A-A剖面图。Fig. 3 is a cross-sectional view along line A-A of Fig. 1 .

图4是图3中螺纹锚杆安装部位Z处详图。Fig. 4 is a detailed view of the installation position Z of the threaded anchor rod in Fig. 3 .

图5是图2中巢穴竹管拼接部位C处详图。Fig. 5 is a detailed view of the splicing part C of the nest bamboo tube in Fig. 2 .

图6是未缝合的单个土工模袋示意图。Figure 6 is a schematic view of an unsewn single geoform pocket.

图中:圆环锚杆1,混凝土条2,巢穴竹管3,定位环4,边坡5,植被竹管6,斜沟7,混凝土灌注口8,压条9,螺纹锚杆10,垫片11,螺帽12,巢穴竹管接口E,土工模袋未缝合的边B,土工模袋已加工的边D。In the figure: ring anchor rod 1, concrete strip 2, nest bamboo tube 3, positioning ring 4, slope 5, vegetation bamboo tube 6, inclined ditch 7, concrete pouring port 8, layering strip 9, threaded anchor rod 10, gasket 11. Nut 12, nest bamboo tube interface E, unsewn side B of the geotechnical mold bag, processed side D of the geotechnical mold bag.

具体实施方式Detailed ways

下面结合附图和实施例对本发明作进一步说明。下述实施例的说明只是用于帮助理解本发明,但并不因此限制本发明的保护范围。应当指出,以上技术方案的某些技术特征的简单替换和组合,如用塑料或铁管代替竹管,用塑料杆或木杆代替锚杆所形成的技术方案,都包含在本发明的技术方案之内。The present invention will be further described below in conjunction with drawings and embodiments. The descriptions of the following examples are only used to help understand the present invention, but do not limit the protection scope of the present invention. It should be pointed out that the simple replacement and combination of certain technical features of the above technical solutions, such as the technical solutions formed by replacing bamboo pipes with plastic or iron pipes and replacing anchor rods with plastic rods or wooden rods, are all included in the technical solutions of the present invention. within.

本发明的的圆环锚杆1包括竖向钢筋以及与竖向钢筋连接的圆环,圆环穿过竖向钢筋并固定在竖向钢筋上。The ring anchor 1 of the present invention includes a vertical steel bar and a ring connected to the vertical steel bar, and the ring passes through the vertical steel bar and is fixed on the vertical steel bar.

土工模袋袋体为两层全丙纶高强机织布制成的产品。The bag body of the geotechnical mold bag is a product made of two layers of full polypropylene high-strength woven fabric.

自密实混凝土的重量配比为水泥:矿粉:粉煤灰:水:砂:碎石:外加剂为17:4.5:2.5:6.5:30:39:0.5。其中,水泥为普通硅酸盐水泥P.042.5;矿粉型号为S95级;粉煤灰为Ⅱ级;砂为Ⅱ区中砂;碎石为石灰岩碎石,石子粒径为5-20 mm;外加剂为聚羟酸高性能减水剂和膨胀剂的混合物。The weight ratio of self-compacting concrete is cement: mineral powder: fly ash: water: sand: gravel: admixture is 17:4.5:2.5:6.5:30:39:0.5. Among them, the cement is ordinary Portland cement P.042.5; the type of mineral powder is S95 grade; the fly ash is grade II; the sand is sand in zone II; the gravel is limestone gravel with a particle size of 5-20 mm; The admixture is a mixture of polyhydroxy acid high-performance water reducer and expansion agent.

钻机型号为手持ZQSJ-140/4.1钻机。The drilling rig model is a handheld ZQSJ-140/4.1 drilling rig.

焊机型号为NB-315Y气体焊机。The welding machine model is NB-315Y gas welding machine.

实施例1Example 1

某地为岩质边坡,坡度30°,坡高为3 m,拟采用本发明进行防护。A certain place is a rocky slope with a slope of 30° and a slope height of 3 m. It is planned to adopt the present invention for protection.

土工模袋形状如图6所示,长度为2 m,宽度为1 m,最高点与土工模袋底面的垂直高度H为40 cm;定位环材料为不锈钢材质,其安装位置距土工模袋侧边的距离为15 cm,直径为15 mm,厚度为8 mm,两定位环之间的间距为30 cm。The shape of the geotechnical bag is shown in Figure 6. The length is 2 m, the width is 1 m, and the vertical height H between the highest point and the bottom surface of the geotechnical bag is 40 cm. The distance between the sides is 15 cm, the diameter is 15 mm, the thickness is 8 mm, and the distance between the two positioning rings is 30 cm.

圆环锚杆中的竖向钢筋为HPB300级光圆钢筋,直径为10 mm,间距为50 cm,其上的圆环为为实心圆钢,外直径为10 cm;螺纹锚杆为HRB400E级螺纹钢筋,直径为12 mm,间距为30 cm。The vertical steel bar in the ring anchor is HPB300 grade smooth round steel bar with a diameter of 10 mm and a spacing of 50 cm, and the ring on it is solid round steel with an outer diameter of 10 cm; the threaded anchor rod is HRB400E grade Steel bars with a diameter of 12 mm and a spacing of 30 cm.

有孔模袋混凝土生态护岸结构,包括混凝土条2,在混凝土条2中预埋有巢穴竹管3、植被竹管6,所述混凝土条2之间留有与其长度和宽度方向分别平行的间隙形成相互交叉的斜沟7,其长度方向与坡面等高线成12°角;巢穴竹管3绑扎固定于圆环锚杆1上,其管口开口于斜沟7,至少有两根相互贯通;圆环锚杆1的一端插在边坡中,另一端埋在混凝土条2中;植被竹管6插在圆环锚杆1的圆环中,植被竹管6的空腔中有基质及植物并与坡面成60°角。Concrete ecological revetment structure with hole mold bags, including concrete strips 2, nest bamboo tubes 3 and vegetation bamboo tubes 6 are pre-embedded in the concrete strips 2, gaps parallel to the length and width directions of the concrete strips 2 are left Form intersecting inclined grooves 7, and its length direction forms an angle of 12° with the slope contour; the nest bamboo tube 3 is tied and fixed on the ring anchor rod 1, and its nozzle is opened in the inclined groove 7, and at least two mutually Through; one end of the ring anchor rod 1 is inserted in the slope, and the other end is buried in the concrete strip 2; the vegetation bamboo tube 6 is inserted in the ring of the ring anchor rod 1, and the cavity of the vegetation bamboo tube 6 has matrix And plants and form a 60° angle with the slope.

所述单个混凝土条2内的巢穴竹管3设有3根,直径分别为5 cm,10 cm,15 cm;植被竹管6长度为40 cm,直径为5 cm。The nest bamboo tubes 3 in the single concrete strip 2 are provided with 3 pieces with diameters of 5 cm, 10 cm and 15 cm respectively; the vegetation bamboo tubes 6 are 40 cm in length and 5 cm in diameter.

所述植被竹管6空腔中的基质为:耕植土、腐熟木屑、河沙和土壤粘合剂的混合物,以体积比计:耕植土:腐熟木屑:河沙=70:5:5;土壤粘合剂的用量为0.016 g/L;植物为狗牙根(Cynodon dactylon (L.) Pers.)和鬼针草(Bidens pilosa L.)The matrix in the cavity of the vegetation bamboo tube 6 is: a mixture of cultivated soil, decomposed sawdust, river sand and soil binder, in volume ratio: cultivated soil: decomposed sawdust: river sand=70:5:5 The amount of soil binder is 0.016 g/L; the plants are bermudagrass (Cynodon dactylon (L.) Pers.) and ghost needle grass (Bidens pilosa L.) .

所述斜沟7的宽度为30 cm。The width of the inclined groove 7 is 30 cm.

所述圆环锚杆1插入坡面的长度为15 cm,伸出坡面的长度为20 cm。The length of the circular anchor rod 1 inserted into the slope is 15 cm, and the length extending out of the slope is 20 cm.

所述混凝土条2采用泵送C25自密实混凝土浇筑而成。The concrete strip 2 is poured by pumping C25 self-compacting concrete.

上述一种有孔模袋混凝土生态护岸结构的施工方法,包括以下步骤:The construction method of the above-mentioned a kind of perforated mold bag concrete ecological revetment structure comprises the following steps:

(1)准备材料,准备竹管、圆环锚杆、螺纹锚杆、垫片、螺帽、土工模袋和压条等材料:将巢穴竹管和植被竹管的内腔打通,管口用加厚塑料薄膜封口,然后将巢穴竹管管壁开口;在光圆钢筋上焊上圆环形成圆环锚杆;土工模袋在加工时预留未缝合的边B及混凝土灌注口,在其与坡面接触平面的两个相邻的边上缝制定位环。(1) Prepare materials, prepare materials such as bamboo tubes, ring anchors, threaded anchors, gaskets, nuts, geomold bags and layering strips: open the inner cavity of the nest bamboo tube and the vegetation bamboo tube, The thick plastic film is sealed, and then the bamboo tube wall of the nest is opened; a ring is welded on the light round steel bar to form a ring anchor; Sewn retaining rings on two adjacent edges where the slope touches the plane.

(2)清坡放样,清理坡面滚石、浮土及枯树枝,并测量放线。(2) Slope clearing and setting out, cleaning rolling stones, floating soil and dead branches on the slope surface, and measuring and setting out.

(3)钻锚孔,在坡面上钻锚孔。(3) Drill the anchor hole and drill the anchor hole on the slope.

(4)安装螺纹锚杆,把螺纹锚杆插入锚孔中并用水泥注浆填充螺纹锚杆与孔隙之间的间隙,螺纹锚杆插入坡面的深度为15 cm。(4) Install the threaded anchor rod, insert the threaded anchor rod into the anchor hole and fill the gap between the threaded anchor rod and the hole with cement grouting. The depth of the threaded anchor rod inserted into the slope is 15 cm.

(5)安装模袋,待水泥硬化后,将螺纹锚杆穿过定位环,然后把压条压在土工模袋上,然后在压条上钻孔,压条为橡胶实心,其宽度为10 cm,厚度为8 mm,接着将螺纹锚杆穿过垫片和压条插入坡体,最后拧紧螺帽。(5) Install the mold bag. After the cement hardens, pass the threaded anchor rod through the positioning ring, then press the bead on the geotechnical mold bag, and then drill holes on the bead. The bead is solid rubber with a width of 10 cm and a thickness of 10 cm. 8 mm, then insert the threaded anchor rod through the gasket and bead into the slope body, and finally tighten the nut.

(6)安装竹管,把圆环锚杆刺穿土工模袋插入锚孔中,用水泥注浆填充钢筋与孔隙之间的间隙,待水泥硬化后,把植被竹管插入圆环锚杆的圆环中,采用胶粘的方式将其顶端固定在土工模袋内表面,接着把巢穴竹管绑扎固定在圆环锚杆上,两巢穴竹管之间通过巢穴竹管接口E固定,为加强接口处的强度,可辅以乳胶固定,防止巢穴竹管松动,接着把巢穴竹管和植被竹管用铁丝固定在锚杆上,拼装完成后缝合土工模袋。(6) Install the bamboo tube, insert the ring anchor rod through the geotechnical mold bag into the anchor hole, fill the gap between the steel bar and the hole with cement grouting, and insert the vegetation bamboo tube into the ring anchor rod after the cement hardens In the ring, the top end is fixed on the inner surface of the geomembrane bag by gluing, and then the nest bamboo tube is bound and fixed on the ring anchor rod, and the two nest bamboo tubes are fixed through the nest bamboo tube interface E, in order to strengthen The strength of the interface can be fixed with latex to prevent the nest bamboo tube from loosening, and then the nest bamboo tube and vegetation bamboo tube are fixed on the anchor rod with iron wire, and the geomembrane bag is sewed after the assembly is completed.

(7)浇筑混凝土,采用泵送混凝土的技术施工混凝土条,混凝土条的施工顺序是从坡顶到坡脚依次进行;每一个混凝土条施工时,从土工模袋混凝土灌注口浇注自密实的C25泵送混凝土。(7) Pouring concrete, using the technology of pumping concrete to construct concrete strips, the construction sequence of concrete strips is from the top of the slope to the foot of the slope; when constructing each concrete strip, pour self-compacting C25 from the concrete pouring port of the geomold bag Pump concrete.

(8)养护,砂浆终凝后开始洒水养护,养护期间要求护坡表面处于湿润状态,养护时间为7天,待混凝土强度达到75%时,剪开与巢穴竹管相连的模袋的侧边使管口露出,成为动物通行的入口。(8) maintenance, start sprinkling maintenance after the final setting of the mortar, require slope protection surface to be in a wet state during the maintenance, and the maintenance time is 7 days, when the concrete strength reaches 75%, cut the side of the mold bag that is connected with the nest bamboo pipe to use The mouth of the nozzle is exposed and becomes the entrance for animals to pass through.

(9)植被竹管施工,剪开与植被竹管相连的模袋上表面,使管口露出并在竹管的空腔中放入基质及植物种子。(9) Vegetation bamboo tube construction, cut open the mold bag upper surface that links to each other with vegetation bamboo tube, make nozzle expose and put matrix and plant seed in the cavity of bamboo tube.

实施案例2Implementation Case 2

某地为消落带土夹石边坡,坡度45°,坡高为4 m,拟采用本发明进行防护。A certain place is a soil-rock slope in a water-fluctuating zone, with a slope of 45° and a slope height of 4 m. The invention is proposed to be used for protection.

土工模袋形状如图6所示,长度为2.5 m,宽度为1.5 m,最高点与土工模袋底面的垂直高度H为50 cm;定位环材料为不锈钢材质,其安装位置距土工模袋侧边的距离为25cm,直径为15 mm,厚度为10 mm,两定位环之间的间距为35 cm。The shape of the geotechnical bag is shown in Figure 6. The length is 2.5 m, the width is 1.5 m, and the vertical height H between the highest point and the bottom of the geotechnical bag is 50 cm. The distance between the sides is 25cm, the diameter is 15mm, the thickness is 10mm, and the distance between the two positioning rings is 35cm.

圆环锚杆中的竖向钢筋为HPB300级光圆钢筋,直径为10 mm,间距为55 cm,其上的圆环为为实心圆钢,外直径为12 cm;螺纹锚杆为HRB400E级螺纹钢筋,直径为12 mm,间距为35 cm。The vertical steel bar in the ring anchor is HPB300 grade smooth round steel bar with a diameter of 10 mm and a spacing of 55 cm. The ring on it is solid round steel with an outer diameter of 12 cm; the threaded anchor rod is HRB400E grade thread Steel bars with a diameter of 12 mm and a spacing of 35 cm.

有孔模袋混凝土生态护岸结构,包括混凝土条2,在混凝土条2中预埋有巢穴竹管3、植被竹管6,所述混凝土条2之间留有与其长度和宽度方向分别平行的间隙形成相互交叉的斜沟7,其长度方向与坡面等高线成20°角;巢穴竹管3绑扎固定于圆环锚杆1上,其管口开口于斜沟7,至少有两根相互贯通;圆环锚杆1的一端插在边坡中,另一端埋在混凝土条2中;植被竹管6插在圆环锚杆1的圆环中,植被竹管6的空腔中有基质及植物并与坡面成70°角。Concrete ecological revetment structure with hole mold bags, including concrete strips 2, nest bamboo tubes 3 and vegetation bamboo tubes 6 are pre-embedded in the concrete strips 2, gaps parallel to the length and width directions of the concrete strips 2 are left Form intersecting inclined grooves 7, and its length direction forms an angle of 20° with the slope contour; the nest bamboo tube 3 is bound and fixed on the ring anchor rod 1, and its nozzle is opened in the inclined groove 7, and at least two mutually Through; one end of the ring anchor rod 1 is inserted in the slope, and the other end is buried in the concrete strip 2; the vegetation bamboo tube 6 is inserted in the ring of the ring anchor rod 1, and the cavity of the vegetation bamboo tube 6 has matrix And plants and form a 70° angle with the slope.

所述单个混凝土条2内的巢穴竹管3设有4根,直径分别为5 cm,10 cm,15 cm,20cm。The nest bamboo tubes 3 in the single concrete strip 2 are provided with 4 pieces with diameters of 5 cm, 10 cm, 15 cm and 20 cm respectively.

所述植被竹管6长度为50 cm,直径为10 cm。The vegetation bamboo tube 6 has a length of 50 cm and a diameter of 10 cm.

所述植被竹管6空腔中的基质为:耕植土、腐熟木屑、河沙和土壤粘合剂的混合物,以体积比计:耕植土:腐熟木屑:河沙=80:10:10;土壤粘合剂的用量为0.018 g/L;植物为狗牙根(Cynodon dactylon (L.) Pers.)、鬼针草(Bidens pilosa L.)和苍耳(Xanthium sibiricum Patrin ex Widder)The matrix in the cavity of the vegetation bamboo tube 6 is: a mixture of cultivated soil, decomposed sawdust, river sand and soil binder, in volume ratio: cultivated soil: decomposed sawdust: river sand=80:10:10 The amount of soil binder is 0.018 g/L; the plants are Bermudagrass (Cynodon dactylon (L.) Pers.) , ghost needle grass (Bidens pilosa L.) and cocklebur (Xanthium sibiricum Patrin ex Widder) .

所述斜沟7的宽度为40 cm。The width of the inclined groove 7 is 40 cm.

所述圆环锚杆1插入坡面的长度为18 cm,伸出坡面的长度为25 cm。The length of the circular anchor rod 1 inserted into the slope is 18 cm, and the length extending out of the slope is 25 cm.

所述混凝土条2为泵送C25自密实混凝土。The concrete strip 2 is pumped C25 self-compacting concrete.

所述的一种有孔模袋混凝土生态护岸结构的施工方法,包括以下步骤:The construction method of the described a kind of perforated mold bag concrete ecological revetment structure comprises the following steps:

(1)准备材料,准备竹管、圆环锚杆、螺纹锚杆、垫片、螺帽、土工模袋和压条等材料:将巢穴竹管和植被竹管的内腔打通,管口用加厚塑料薄膜封口,然后将巢穴竹管管壁开口;在光圆钢筋上焊上圆环形成圆环锚杆;土工模袋在加工时预留未缝合的边B及混凝土灌注口,在其与坡面接触平面的两个相邻的边上缝制定位环。(1) Prepare materials, prepare materials such as bamboo tubes, ring anchors, threaded anchors, gaskets, nuts, geomold bags and layering strips: open the inner cavity of the nest bamboo tube and the vegetation bamboo tube, The thick plastic film is sealed, and then the bamboo tube wall of the nest is opened; a ring is welded on the light round steel bar to form a ring anchor; Sewn retaining rings on two adjacent edges where the slope touches the plane.

(2)清坡放样,清理坡面滚石、浮土及枯树枝,并测量放线。(2) Slope clearing and setting out, cleaning rolling stones, floating soil and dead branches on the slope surface, and measuring and setting out.

(3)钻锚孔,在坡面上钻锚孔。(3) Drill the anchor hole and drill the anchor hole on the slope.

(4)安装螺纹锚杆,把螺纹锚杆插入锚孔中并用水泥注浆填充螺纹锚杆与孔隙之间的间隙,螺纹锚杆插入坡面的深度为18 cm。(4) Install the threaded anchor rod, insert the threaded anchor rod into the anchor hole and fill the gap between the threaded anchor rod and the hole with cement grouting. The depth of the threaded anchor rod inserted into the slope is 18 cm.

(5)安装模袋,待水泥硬化后,将螺纹锚杆穿过定位环,然后把压条压在土工模袋上,然后在压条上钻孔,压条的材料为不锈钢片,其宽度为15 cm,厚度为10 mm,接着将螺纹锚杆穿过垫片和压条插入坡体,最后拧紧螺帽。(5) Install the mold bag. After the cement is hardened, pass the threaded anchor rod through the positioning ring, then press the bead on the geotechnical mold bag, and then drill holes on the bead. The material of the bead is stainless steel sheet with a width of 15 cm. , with a thickness of 10 mm, then insert the threaded anchor rod through the gasket and the bead into the slope body, and finally tighten the nut.

(6)安装竹管,把圆环锚杆刺穿土工模袋插入锚孔中,用水泥注浆填充钢筋与孔隙之间的间距,待水泥硬化后,把植被竹管插入圆环锚杆的圆环中,采用胶粘的方式将其顶端固定在土工模袋内表面,接着把巢穴竹管绑扎固定在圆环锚杆上,两巢穴竹管之间通过巢穴竹管接口E固定,为加强接口处的强度,可辅以乳胶固定,防止巢穴竹管松动,接着把巢穴竹管和植被竹管用铁丝固定在锚杆上,拼装完成后缝合模袋。(6) Install the bamboo tube, insert the ring anchor rod through the geomembrane bag into the anchor hole, fill the space between the steel bar and the hole with cement grouting, and insert the vegetation bamboo tube into the ring anchor rod after the cement hardens In the ring, the top end is fixed on the inner surface of the geomembrane bag by gluing, and then the nest bamboo tube is bound and fixed on the ring anchor rod, and the two nest bamboo tubes are fixed through the nest bamboo tube interface E, in order to strengthen The strength of the interface can be fixed with latex to prevent the nest bamboo tube from loosening, and then the nest bamboo tube and the vegetation bamboo tube are fixed on the anchor rod with iron wire, and the mold bag is sewed after the assembly is completed.

(7)浇筑混凝土,采用泵送混凝土的技术施工混凝土条,混凝土条的施工顺序是从坡顶到坡脚依次进行;每一个混凝土条施工时,从土工模袋混凝土灌注口浇注自密实的C25泵送混凝土。(7) Pouring concrete, using the technology of pumping concrete to construct concrete strips, the construction sequence of concrete strips is from the top of the slope to the foot of the slope; when constructing each concrete strip, pour self-compacting C25 from the concrete pouring port of the geomold bag Pump concrete.

(8)养护,砂浆终凝后开始洒水养护,养护期间要求护坡表面处于湿润状态,养护时间为7天,待混凝土强度达到80%时,剪开与巢穴竹管相连的模袋的侧边使管口露出,成为动物通行的入口。(8) Maintenance, after the final setting of the mortar, start sprinkling maintenance. During the maintenance, the surface of the slope protection is required to be in a wet state. The maintenance time is 7 days. When the concrete strength reaches 80%, cut the side of the mold bag connected to the nest bamboo tube to use The mouth of the nozzle is exposed and becomes the entrance for animals to pass through.

(9)植被竹管施工,剪开与植被竹管相连的模袋上表面,使管口露出并在竹管的空腔中放入基质及植物种子。(9) Vegetation bamboo tube construction, cut open the mold bag upper surface that links to each other with vegetation bamboo tube, make nozzle expose and put matrix and plant seed in the cavity of bamboo tube.

实施案例3Implementation Case 3

某地为破碎岩质边坡,坡度60°,坡高为5 m,拟采用本发明进行防护。A certain place is a broken rock slope with a slope of 60° and a slope height of 5 m. It is planned to adopt the present invention for protection.

土工模袋形状如图6所示,长度为3 m,宽度为2 m,最高点与土工模袋底面的垂直高度H为60 cm;定位环材料为不锈钢材质,其安装位置距土工模袋侧边的距离为35 cm,直径为15 mm,厚度为12 mm,两定位环之间的间距为40 cm。The shape of the geotechnical bag is shown in Figure 6. The length is 3 m, the width is 2 m, and the vertical height H between the highest point and the bottom surface of the geotechnical bag is 60 cm. The distance between the sides is 35 cm, the diameter is 15 mm, the thickness is 12 mm, and the distance between the two positioning rings is 40 cm.

圆环锚杆中的竖向钢筋为HPB300级光圆钢筋,直径为10 mm,间距为60 cm,其上的圆环为为实心圆钢,外直径为16 cm;螺纹锚杆为HRB400E级螺纹钢筋,直径为12 mm,间距为40 cm。The vertical steel bar in the ring anchor is HPB300 grade smooth round steel bar with a diameter of 10 mm and a spacing of 60 cm, and the ring on it is solid round steel with an outer diameter of 16 cm; the threaded anchor rod is HRB400E grade Steel bars with a diameter of 12 mm and a spacing of 40 cm.

有孔模袋混凝土生态护岸结构,包括混凝土条2,在混凝土条2中预埋有巢穴竹管3、植被竹管6,所述混凝土条2之间留有与其长度和宽度方向分别平行的间隙形成相互交叉的斜沟7,其长度方向与坡面等高线成30°角;巢穴竹管3绑扎固定于圆环锚杆1上,其管口开口于斜沟7,至少有两根相互贯通;圆环锚杆1的一端插在边坡中,另一端埋在混凝土条2中;植被竹管6插在圆环锚杆1的圆环中,植被竹管6的空腔中有基质及植物并与坡面成80°角。Concrete ecological revetment structure with hole mold bags, including concrete strips 2, nest bamboo tubes 3 and vegetation bamboo tubes 6 are pre-embedded in the concrete strips 2, gaps parallel to the length and width directions of the concrete strips 2 are left Form intersecting inclined grooves 7, and its length direction forms an angle of 30° with the slope contour; the nest bamboo tube 3 is bound and fixed on the ring anchor rod 1, and its nozzle is opened in the inclined groove 7, and at least two mutually Through; one end of the ring anchor rod 1 is inserted in the slope, and the other end is buried in the concrete strip 2; the vegetation bamboo tube 6 is inserted in the ring of the ring anchor rod 1, and the cavity of the vegetation bamboo tube 6 has matrix And plants and form an 80° angle with the slope.

所述单个土工模袋2内的巢穴竹管3设有5根,直径分别为5 cm,10 cm,15 cm,20cm,25 cm。The nest bamboo tube 3 in the single geotechnical mold bag 2 is provided with 5, and diameter is respectively 5 cm, 10 cm, 15 cm, 20 cm, 25 cm.

所述植被竹管6长度为60 cm,直径为15 cm。The vegetation bamboo tube 6 has a length of 60 cm and a diameter of 15 cm.

所述植被竹管6空腔中的基质为:耕植土、腐熟木屑、河沙和土壤粘合剂的混合物,以体积比计:耕植土:腐熟木屑:河沙=90:12:15;土壤粘合剂的用量为0.019 g/L;植物为狗牙根(Cynodon dactylon (L.) Pers.)、鬼针草(Bidens pilosa L.)、苍耳(Xanthium sibiricum Patrin ex Widder)和蓼草(Ludwigia prostrata Roxb)The matrix in the cavity of the vegetation bamboo tube 6 is: a mixture of cultivated soil, decomposed sawdust, river sand and soil binder, in volume ratio: cultivated soil: decomposed sawdust: river sand=90:12:15 ; the amount of soil binder is 0.019 g/L; the plants are Bermudagrass (Cynodon dactylon (L.) Pers.) , ghost needle grass (Bidens pilosa L.) , cocklebur (Xanthium sibiricum Patrin ex Widder) and Polygonum (Ludwigia prostrata Roxb) .

所述斜沟7的宽度为45 cm。The width of the inclined groove 7 is 45 cm.

所述圆环锚杆1插入坡面的长度为20 cm,伸出坡面的长度为30 cm。The length of the circular anchor rod 1 inserted into the slope is 20 cm, and the length extending out of the slope is 30 cm.

所述混凝土条2为泵送C25自密实混凝土。The concrete strip 2 is pumped C25 self-compacting concrete.

所述的一种有孔模袋混凝土生态护岸结构的施工方法,包括以下步骤:The construction method of the described a kind of perforated mold bag concrete ecological revetment structure comprises the following steps:

(1)准备材料,准备竹管、圆环锚杆、螺纹锚杆、垫片、螺帽、土工模袋和压条等材料:将巢穴竹管和植被竹管的内腔打通,管口用加厚塑料薄膜封口,然后将巢穴竹管管壁开口;在光圆钢筋上焊上圆环形成圆环锚杆;土工模袋在加工时预留未缝合的边B及混凝土灌注口,在其与坡面接触平面的两个相邻的边上缝制定位环。(1) Prepare materials, prepare materials such as bamboo tubes, ring anchors, threaded anchors, gaskets, nuts, geomold bags and layering strips: open the inner cavity of the nest bamboo tube and the vegetation bamboo tube, The thick plastic film is sealed, and then the bamboo tube wall of the nest is opened; a ring is welded on the light round steel bar to form a ring anchor; Sewn retaining rings on two adjacent edges where the slope touches the plane.

(2)清坡放样,清理坡面滚石、浮土及枯树枝,并测量放线。(2) Slope clearing and setting out, cleaning rolling stones, floating soil and dead branches on the slope surface, and measuring and setting out.

(3)钻锚孔,在坡面上钻锚孔。(3) Drill the anchor hole and drill the anchor hole on the slope.

(4)安装螺纹锚杆,把螺纹锚杆插入锚孔中并用水泥注浆填充螺纹锚杆与孔隙之间的间隙,螺纹锚杆插入坡面的深度为20 cm。(4) Install the threaded anchor rod, insert the threaded anchor rod into the anchor hole and fill the gap between the threaded anchor rod and the hole with cement grouting. The depth of the threaded anchor rod inserted into the slope is 20 cm.

(5)安装模袋,待水泥硬化后,将螺纹锚杆穿过定位环,然后把压条压在土工模袋上,然后在压条上钻孔,压条的材料为铁片,其宽度为20 cm,厚度为12 mm,接着将螺纹锚杆穿过垫片和压条插入坡体,最后拧紧螺帽。(5) Install the mold bag. After the cement is hardened, pass the threaded anchor rod through the positioning ring, then press the bead on the geotechnical mold bag, and then drill holes on the bead. The material of the bead is iron sheet, and its width is 20 cm , with a thickness of 12 mm, then insert the threaded anchor rod through the gasket and the bead into the slope body, and finally tighten the nut.

(6)安装竹管,把圆环锚杆刺穿土工模袋插入锚孔中,用水泥注浆填充钢筋与孔隙之间的间隙,待水泥硬化后,把植被竹管插入圆环锚杆的圆环中,采用胶粘的方式将其顶端固定在土工模袋内表面,接着把巢穴竹管绑扎固定在圆环锚杆上,两巢穴竹管之间通过巢穴竹管接口E固定,为加强接口处的强度,可辅以乳胶固定,防止巢穴竹管松动,接着把巢穴竹管和植被竹管用铁丝固定在锚杆上,拼装完成后缝合模袋。(6) Install the bamboo tube, insert the ring anchor rod through the geotechnical mold bag into the anchor hole, fill the gap between the steel bar and the hole with cement grouting, and insert the vegetation bamboo tube into the ring anchor rod after the cement hardens In the ring, the top end is fixed on the inner surface of the geomembrane bag by gluing, and then the nest bamboo tube is bound and fixed on the ring anchor rod, and the two nest bamboo tubes are fixed through the nest bamboo tube interface E, in order to strengthen The strength of the interface can be fixed with latex to prevent the nest bamboo tube from loosening, and then the nest bamboo tube and the vegetation bamboo tube are fixed on the anchor rod with iron wire, and the mold bag is sewed after the assembly is completed.

(7)浇筑混凝土,采用泵送混凝土的技术施工混凝土条,混凝土条的施工顺序是从坡顶到坡脚依次进行;每一个混凝土条施工时,从土工模袋混凝土灌注口浇注自密实的C25泵送混凝土。(7) Pouring concrete, using the technology of pumping concrete to construct concrete strips, the construction sequence of concrete strips is from the top of the slope to the foot of the slope; when constructing each concrete strip, pour self-compacting C25 from the concrete pouring port of the geomold bag Pump concrete.

(8)养护,砂浆终凝后开始洒水养护,养护期间要求护坡表面处于湿润状态,养护时间为7天,待混凝土强度达到85%时,剪开与巢穴竹管相连的模袋的侧边使管口露出,成为动物通行的入口。(8) maintenance, start sprinkling maintenance after the final setting of the mortar, during the maintenance, the surface of the slope protection is required to be in a wet state, and the maintenance time is 7 days. When the concrete strength reaches 85%, cut the side of the mold bag connected with the nest bamboo pipe to use The mouth of the nozzle is exposed and becomes the entrance for animals to pass through.

(9)植被竹管施工,剪开与植被竹管相连的模袋上表面,使管口露出并在竹管的空腔中放入基质及植物种子。(9) Vegetation bamboo tube construction, cut open the mold bag upper surface that links to each other with vegetation bamboo tube, make nozzle expose and put matrix and plant seed in the cavity of bamboo tube.

Claims (8)

1.一种有孔模袋混凝土生态护岸结构,其特征在于:包括混凝土条(2),在混凝土条(2)中预埋有巢穴竹管(3)、植被竹管(6),所述混凝土条(2)之间留有与其长度和宽度方向分别平行的间隙形成相互交叉的斜沟(7);巢穴竹管(3)绑扎固定于圆环锚杆(1)上,其管口开口于斜沟(7),至少有两根相互贯通;圆环锚杆(1)的一端插在边坡中,另一端埋在混凝土条(2)中;植被竹管(6)插在圆环锚杆(1)的圆环中;植被竹管(6)的空腔中有基质及植物。1. a kind of perforated mold bag concrete ecological revetment structure is characterized in that: comprise concrete strip (2), in concrete strip (2), be pre-embedded with nest bamboo tube (3), vegetation bamboo tube (6), described There are gaps between the concrete strips (2) parallel to their length and width directions respectively to form intersecting inclined grooves (7); the nest bamboo tube (3) is bound and fixed on the ring anchor rod (1), and its nozzle opening is In the inclined ditch (7), there are at least two interconnected ones; one end of the ring anchor rod (1) is inserted in the slope, and the other end is buried in the concrete strip (2); the vegetation bamboo pipe (6) is inserted in the ring In the ring of the anchor rod (1); in the cavity of the vegetation bamboo tube (6) there are substrates and plants. 2.根据权利要求1所述的一种有孔模袋混凝土生态护岸结构,其特征在于:斜沟(7)长度方向与坡面等高线成β角,12°≤β≤30°。2. A kind of perforated mold bag concrete ecological bank revetment structure according to claim 1, characterized in that: the length direction of the inclined ditch (7) forms an angle β with the contour line of the slope surface, and 12°≤β≤30°. 3.根据权利要求1所述的一种有孔模袋混凝土生态护岸结构,其特征在于:所述植被竹管(6)与坡面成α角,60°≤α≤80°。3. The ecological bank revetment structure with holed mold bag concrete according to claim 1, characterized in that: the vegetation bamboo tube (6) forms an angle α with the slope, 60°≤α≤80°. 4. 根据权利要求1或3所述的一种有孔模袋混凝土生态护岸结构,其特征在于:所述植被竹管(6)空腔中的基质为:耕植土、腐熟木屑、河沙和土壤粘合剂充分拌合后的混合物,以体积比计:耕植土:腐熟木屑:河沙=70-90:5-12:5-15;土壤粘合剂的用量为0.016-0.019g/L。4. according to claim 1 or 3 described a kind of perforated mold bag concrete ecological revetment structure, it is characterized in that: the substrate in the cavity of described vegetation bamboo tube (6) is: cultivation soil, decomposed sawdust, river sand The mixture fully mixed with soil binder, in terms of volume ratio: cultivated soil: decomposed sawdust: river sand = 70-90: 5-12: 5-15; the amount of soil binder is 0.016-0.019g /L. 5.根据权利要求1所述的一种有孔模袋混凝土生态护岸结构,其特征在于:所述的植物为狗牙根(Cynodon dactylon (L.) Pers.)、鬼针草(Bidens pilosa L.)、苍耳(Xanthium sibiricum Patrin ex Widder)或蓼草(Ludwigia prostrata Roxb)中的一种或几种。5. A kind of perforated mold bag concrete ecological revetment structure according to claim 1, is characterized in that: described plant is bermudagrass (Cynodon dactylon (L.) Pers.) , ghost needle grass (Bidens pilosa L. ) , Xanthium sibiricum Patrin ex Widder or Ludwigia prostrata Roxb . 6. 根据权利要求1所述的一种有孔模袋混凝土生态护岸结构,其特征在于:圆环锚杆(1)插入坡面的深度不小于15 cm,伸出坡面的长度不小于20 cm。6. A kind of perforated mold bag concrete ecological revetment structure according to claim 1, is characterized in that: the depth of the circular anchor rod (1) inserted into the slope is not less than 15 cm, and the length extending out of the slope is not less than 20 cm. cm. 7.根据权利要求1所述的一种有孔模袋混凝土生态护岸结构,其特征在于:所述的圆环锚杆包括竖向钢筋以及与竖向钢筋连接的圆环,圆环穿过竖向钢筋并固定在竖向钢筋上。7. A kind of perforated mold pocket concrete ecological revetment structure according to claim 1, characterized in that: said circular anchor rod comprises a vertical steel bar and a circular ring connected with the vertical steel bar, and the circular ring passes through the vertical To the reinforcement and fixed on the vertical reinforcement. 8.权利要求1-7任一所述的有孔模袋混凝土生态护岸结构的施工方法,其特征在于包括以下步骤:8. The construction method of the arbitrary described perforated mold bag concrete ecological revetment structure of claim 1-7, is characterized in that comprising the following steps: (1)准备材料,准备竹管、圆环锚杆、螺纹锚杆、垫片、螺帽、土工模袋和压条等材料:将巢穴竹管和植被竹管的内腔打通,管口用加厚塑料薄膜封口,然后将巢穴竹管管壁开口;在光圆钢筋上焊上圆环形成圆环锚杆;土工模袋在加工时预留未缝合的边B及混凝土灌注口,在其与坡面接触平面的两个相邻的边上缝制定位环;(1) Prepare materials, prepare materials such as bamboo tubes, ring anchors, threaded anchors, gaskets, nuts, geomold bags and layering strips: open the inner cavity of the nest bamboo tube and the vegetation bamboo tube, The thick plastic film is sealed, and then the bamboo tube wall of the nest is opened; a ring is welded on the light round steel bar to form a ring anchor; Seam positioning rings on two adjacent sides of the slope contact plane; (2)清坡放样,清理坡面滚石、浮土及枯树枝,并测量放线;(2) Slope clearing and setting out, cleaning rolling stones, floating soil and dead branches on the slope surface, and measuring and setting out; (3)钻锚孔,在坡面上钻锚孔;(3) Drill anchor holes and drill anchor holes on the slope; (4)安装螺纹锚杆,把螺纹锚杆插入锚孔中,用水泥注浆填充螺纹锚杆与孔隙之间的间隙;(4) Install the threaded anchor rod, insert the threaded anchor rod into the anchor hole, and fill the gap between the threaded anchor rod and the hole with cement grouting; (5)安装土工模袋,待水泥硬化后,将螺纹锚杆穿过定位环,然后把压条压在土工模袋上,在压条上钻孔,接着将螺纹锚杆穿过垫片和压条插入坡体,最后拧紧螺帽;(5) Install the geotechnical bag. After the cement hardens, pass the threaded anchor rod through the positioning ring, then press the bead on the geotechnical bag, drill holes on the bead, and then insert the threaded anchor rod through the gasket and the bead. slope body, and finally tighten the nut; (6)安装竹管,把圆环锚杆刺穿土工模袋插入锚孔中,用水泥注浆填充锚杆与孔隙之间的间隙,待水泥硬化后,把植被竹管插入圆环锚杆的圆环中,将其顶端粘接在土工模袋内表面,接着把巢穴竹管绑扎固定在圆环锚杆上,两巢穴竹管之间在接口E处粘接,拼装完成后缝合土工模袋;(6) Install the bamboo tube, insert the ring anchor rod through the geomold bag into the anchor hole, fill the gap between the anchor rod and the hole with cement grouting, and insert the vegetation bamboo tube into the ring anchor rod after the cement hardens In the ring, glue its top to the inner surface of the geomembrane bag, then tie the nest bamboo tube to the ring anchor rod, bond the two nest bamboo tubes at the interface E, and sew the geomembrane after the assembly is completed bag; (7)浇筑混凝土,采用泵送混凝土的技术施工混凝土条,混凝土条的施工顺序是从坡顶到坡脚依次进行;每一个混凝土条施工时,从土工模袋混凝土灌注口浇注自密实混凝土;(7) Pouring concrete, adopting the technology of pumping concrete to construct concrete strips, the construction sequence of concrete strips is to carry out sequentially from the top of the slope to the foot of the slope; during the construction of each concrete strip, pour self-compacting concrete from the concrete filling port of the geomold bag; (8)养护,砂浆终凝后开始洒水养护,养护期间要求护坡表面处于湿润状态,待混凝土强度达到75%以上时,剪开与巢穴竹管相连的模袋的侧边使管口露出,成为动物通行的入口;(8) maintenance, start sprinkling maintenance after the final setting of the mortar, require slope protection surface to be in a wet state during the maintenance, when the concrete strength reaches more than 75%, cut the side of the mold bag connected to the nest bamboo tube to expose the nozzle, and become entrances for the passage of animals; (9)植被竹管施工,剪开与植被竹管相连的模袋上表面,使管口露出并在竹管的空腔中放入基质及植物种子。(9) Vegetation bamboo tube construction, cut open the mold bag upper surface that links to each other with vegetation bamboo tube, make nozzle expose and put matrix and plant seed in the cavity of bamboo tube.
CN201910364805.7A 2019-04-30 2019-04-30 A kind of perforated mould bag concrete ecological bank protection structure and construction method Active CN110106830B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910364805.7A CN110106830B (en) 2019-04-30 2019-04-30 A kind of perforated mould bag concrete ecological bank protection structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910364805.7A CN110106830B (en) 2019-04-30 2019-04-30 A kind of perforated mould bag concrete ecological bank protection structure and construction method

Publications (2)

Publication Number Publication Date
CN110106830A true CN110106830A (en) 2019-08-09
CN110106830B CN110106830B (en) 2020-11-27

Family

ID=67488022

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910364805.7A Active CN110106830B (en) 2019-04-30 2019-04-30 A kind of perforated mould bag concrete ecological bank protection structure and construction method

Country Status (1)

Country Link
CN (1) CN110106830B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112554133A (en) * 2020-11-27 2021-03-26 袁慧超 Water conservancy construction is with supplementary type pay-off
CN114016466A (en) * 2021-12-09 2022-02-08 山东科技大学 Anchored geomembrane bag slope protection system and construction method thereof
CN114622518A (en) * 2022-02-21 2022-06-14 中国长江三峡集团有限公司 Hydro-fluctuation belt rock slope ram rock ecological nest and construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08296232A (en) * 1995-04-25 1996-11-12 Nouken:Kk Greening block and construction method for greening
JPH1037157A (en) * 1996-07-27 1998-02-10 Nisshoku Corp Protection and greening construction method of river immersion region
JPH1121897A (en) * 1997-07-05 1999-01-26 Takenaka Komuten Co Ltd Greening vegetation mat structure
KR20110009351A (en) * 2009-07-22 2011-01-28 장성근 Shore block for masonry retaining wall construction
CN103225309A (en) * 2013-04-03 2013-07-31 葛加君 Construction method for concrete matrix planting protective slope
CN105178248A (en) * 2015-07-30 2015-12-23 葛加君 Concrete plant planting and slope protecting method for soft soil river slope
KR101582443B1 (en) * 2015-06-17 2016-01-12 (주) 일신네이쳐 Ecological gabion having place for fishes
CN108708350A (en) * 2018-05-18 2018-10-26 长沙理工大学 An ecological slope protection structure and its construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08296232A (en) * 1995-04-25 1996-11-12 Nouken:Kk Greening block and construction method for greening
JPH1037157A (en) * 1996-07-27 1998-02-10 Nisshoku Corp Protection and greening construction method of river immersion region
JPH1121897A (en) * 1997-07-05 1999-01-26 Takenaka Komuten Co Ltd Greening vegetation mat structure
KR20110009351A (en) * 2009-07-22 2011-01-28 장성근 Shore block for masonry retaining wall construction
CN103225309A (en) * 2013-04-03 2013-07-31 葛加君 Construction method for concrete matrix planting protective slope
KR101582443B1 (en) * 2015-06-17 2016-01-12 (주) 일신네이쳐 Ecological gabion having place for fishes
CN105178248A (en) * 2015-07-30 2015-12-23 葛加君 Concrete plant planting and slope protecting method for soft soil river slope
CN108708350A (en) * 2018-05-18 2018-10-26 长沙理工大学 An ecological slope protection structure and its construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112554133A (en) * 2020-11-27 2021-03-26 袁慧超 Water conservancy construction is with supplementary type pay-off
CN114016466A (en) * 2021-12-09 2022-02-08 山东科技大学 Anchored geomembrane bag slope protection system and construction method thereof
CN114622518A (en) * 2022-02-21 2022-06-14 中国长江三峡集团有限公司 Hydro-fluctuation belt rock slope ram rock ecological nest and construction method
CN114622518B (en) * 2022-02-21 2023-05-09 中国长江三峡集团有限公司 An ecological nest and its construction method of picking slabs and rockfills on rocky slopes in the hydrofluctuation zone

Also Published As

Publication number Publication date
CN110106830B (en) 2020-11-27

Similar Documents

Publication Publication Date Title
CN105544460B (en) Cast-in-place plant growing type eco-concrete slope protection construction method
KR100917790B1 (en) Grid-shaped hollow block for ecological restoration of dike and construction method of dike using them
CN101649608B (en) Ecological slope protection structure
CN102071697A (en) Hard reinforced concrete revetment slope biological repairing method
CN105625263B (en) A kind of environmental combination bank protection of assembled and construction method
CN109763504B (en) Slope ecological reinforcement and greening method
CN105113518A (en) Construction method for ecological slope protecting base material by arranging slot pits in slope surface
CN110106830B (en) A kind of perforated mould bag concrete ecological bank protection structure and construction method
CN205296069U (en) Cast -in -place ecological concrete bank protection of living type of planting
CN103774627B (en) The construction process of the ecological channel of irrigated area antiseepage type
CN207392127U (en) A kind of bank protection barricade applied to hydraulic engineering
CN104775395B (en) It is applicable to the method for construction of the arcuately ecological flexible shore protection in middle-size and small-size cheuch river course
CN104213537A (en) Combined design of substrate applicable to slope ecological transformation and construction method of substrate
CN213741138U (en) Self-embedded ecological retaining wall
CN110725277A (en) A scour-resistant ecological management method for the riparian zone
CN217325247U (en) Ecological shore protection structure combining ecological shore fixing cage and broken line type lattice
CN209277095U (en) A kind of cast-in-place counterfort virescence concrete structure
CN103572778B (en) The greening of rope catching device formula alkali resistant becomes the mutual embedding retaining wall block in inclination angle and rope fixing means
JP2511775Y2 (en) Firefly larva habitation concrete waterway
CN214993495U (en) Slope type ecological sea wall structure assembled with grid net
CN109629510A (en) An ecological revetment system and its construction method
CN204780773U (en) Ecological bank protection system
CN102493394A (en) Ecological embankment for protecting river bank and construction method for ecological embankment
CN115680018A (en) Ecological concrete protection system and its construction method on cast-in-place concrete base
CN210507515U (en) A greening gravity retaining wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant