CN111663451A - Construction method of ultra-high towers for long-span top-up continuous steel truss bridges in alpine valleys - Google Patents

Construction method of ultra-high towers for long-span top-up continuous steel truss bridges in alpine valleys Download PDF

Info

Publication number
CN111663451A
CN111663451A CN202010562575.8A CN202010562575A CN111663451A CN 111663451 A CN111663451 A CN 111663451A CN 202010562575 A CN202010562575 A CN 202010562575A CN 111663451 A CN111663451 A CN 111663451A
Authority
CN
China
Prior art keywords
steel
pile foundation
super
column
steel column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010562575.8A
Other languages
Chinese (zh)
Other versions
CN111663451B (en
Inventor
方继
曹晗
丁仕洪
谢露
邢文彬
王炳岩
蒋志
易中楼
张伟
黄晨东
康志凯
高金平
王永涛
李亚飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Steel Structure Construction Co Ltd of CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Steel Structure Construction Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group, Steel Structure Construction Co Ltd of CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN202010562575.8A priority Critical patent/CN111663451B/en
Publication of CN111663451A publication Critical patent/CN111663451A/en
Application granted granted Critical
Publication of CN111663451B publication Critical patent/CN111663451B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D6/00Truss-type bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明属于桥梁施工技术领域,公开了一种高山峡谷大跨度上承式连续钢桁梁桥的超高塔架施工方法,为了解决高山峡谷处施工超高塔架难度大的问题。本发明的适用于高山峡谷的超高塔架施工方法,超高临时塔架采用集双塔型钢支架(即钢立柱和连接系形成的双塔型结构)与山体防护为一体的综合设计方法,钢立柱之间腹杆采用“米”字型,提高了设计方案的安全性和经济性;并且超高临时塔架桩基和桩基承台采用单桩单柱单承台形式,桩基和桩基承台沿着山体坡度进行设置,减少了对山体的破坏,也降低了施工难度。

Figure 202010562575

The invention belongs to the technical field of bridge construction, and discloses a construction method for a super-high tower of a long-span top-supported continuous steel truss girder bridge in high mountains and canyons, in order to solve the problem of difficulty in constructing super high towers in high mountains and canyons. The super-high tower construction method of the present invention is suitable for high mountains and canyons. The super-high temporary tower adopts a comprehensive design method integrating double-tower-shaped steel supports (that is, a double-tower-shaped structure formed by a steel column and a connection system) and mountain protection. The web between the steel columns adopts the "m" shape, which improves the safety and economy of the design scheme; and the pile foundation and pile foundation cap of the super high temporary tower adopt the form of single pile, single column and single cap, and the pile foundation and The pile foundation cap is set along the slope of the mountain, which reduces the damage to the mountain and reduces the difficulty of construction.

Figure 202010562575

Description

高山峡谷大跨度上承式连续钢桁梁桥的超高塔架施工方法Construction method of ultra-high towers for long-span top-up continuous steel truss bridges in alpine valleys

技术领域technical field

本发明属于桥梁施工技术领域,具体涉及一种高山峡谷大跨度上承式连续钢桁梁桥的超高塔架施工方法。The invention belongs to the technical field of bridge construction, and in particular relates to a construction method for an ultra-high tower of a large-span top-supported continuous steel truss girder bridge in alpine valleys.

背景技术Background technique

上承式连续钢桁梁桥作为大跨度桥梁的一种结构形式,具有跨越能力大,结构自重轻,结构受力明确,建筑造型美观等优点,经常被应用在一些跨越公路、铁路、大跨度河流的桥梁中。由于主桥梁架设多采用由边跨向主跨双向悬臂架设的施工方法,为了辅助钢桁梁悬臂架设,减小钢桁梁悬臂架设长度,依据高山峡谷的地形地貌特征、环境因素、边界条件,在次边跨设置一组超高临时塔架。As a structural form of long-span bridges, the top-loaded continuous steel truss bridge has the advantages of large spanning capacity, light structure weight, clear structural force and beautiful architectural appearance. in the bridge of the river. Since the main bridge is mostly erected by two-way cantilever erection from side span to main span, in order to assist the cantilever erection of steel truss girder and reduce the cantilever erection length of steel truss girder, according to the topographic features, environmental factors and boundary conditions of mountains and valleys, Set up a set of super high temporary towers on the secondary side span.

结合附图1,主桥梁架设采用由边跨向主跨双向悬臂架设的施工方法,为了辅助钢桁梁悬臂架设,减小钢桁梁悬臂架设长度,在1#~2#墩及3#~4#墩之间各设置一组超高临时塔架,超高临时塔架位置如图1所示。对于一种高山峡谷条件下大跨度上承式连续钢桁梁桥超高临时塔架,在1#~2#墩及3#~4#墩之间的临时塔架高度分别为110.9m、133.1m,主桥梁架设采用由边跨向主跨双向悬臂架设的施工方法,由于桥梁跨越红河深V型峡谷,现场地形地貌复杂,地势高差较大,现场道路狭窄,两侧超高临时塔架位于陡峭山坡上,并且由于超高临时塔架高度分别达到110.9米和133.1米,承受荷载达4000吨,使得施工难度非常巨大。In conjunction with accompanying drawing 1, the main bridge erection adopts the construction method of bidirectional cantilever erection from side span to main span. A group of super-high temporary towers are set between the 4# piers, and the positions of the super-high temporary towers are shown in Figure 1. For a super-high temporary tower of a long-span top-up continuous steel truss bridge under the conditions of high mountains and valleys, the heights of the temporary towers between piers 1#~2# and piers 3#~4# are 110.9m and 133.1m respectively. m. The main bridge is erected using the construction method of bidirectional cantilever erection from side span to main span. Since the bridge spans the deep V-shaped canyon of the Red River, the site topography is complex, the terrain height difference is large, the site road is narrow, and the temporary towers on both sides are super high. It is located on a steep hillside, and because the height of the super-high temporary towers reaches 110.9 meters and 133.1 meters respectively and bears a load of 4,000 tons, the construction is very difficult.

发明内容SUMMARY OF THE INVENTION

本发明为了解决在高山峡谷处施工超高塔架难度大的问题,而提供一种适用于高山峡谷的超高塔架施工方法,在降低施工难度的前提下,兼顾了安全性和经济性,确保施工的安全。In order to solve the problem of the difficulty of constructing an ultra-high tower in a high mountain canyon, the present invention provides a construction method for an ultra-high tower suitable for a high mountain canyon. Ensure the safety of construction.

为解决技术问题,本发明所采用的技术方案是:For solving the technical problem, the technical scheme adopted in the present invention is:

一种适用于高山峡谷的超高塔架施工方法,其特征在于,包括如下步骤:A super-high tower construction method suitable for high mountains and canyons is characterized in that, comprising the following steps:

(1)对超高塔架施工位置进行测量放线,并平整出桩基平台和地面汽车吊的站位平台;(1) Measure and lay out the construction position of the super-high tower, and level out the pile foundation platform and the station platform of the ground truck crane;

(2)在桩基平台上进行桩基施工和桩基承台施工,桩基沿着山体坡度进行设置;(2) The pile foundation construction and the pile foundation bearing platform construction are carried out on the pile foundation platform, and the pile foundation is set along the slope of the mountain;

(3)在拼装场内加工制作好的钢立柱,并且在拼装场内在钢立柱上安装安全作业平台和直爬梯,然后一起运输至施工场地;(3) The fabricated steel column is processed in the assembly yard, and a safe working platform and a straight ladder are installed on the steel column in the assembly yard, and then transported to the construction site together;

(4)根据地面汽车吊的站位平台的高度、桩基平台的高度和地面汽车吊自身的起吊高度确定好地面汽车吊的高度作业范围,在地面汽车吊的高度作业范围内,使用地面汽车吊对钢立柱进行分节段吊装;(4) Determine the height operation range of the ground truck crane according to the height of the station platform of the ground truck crane, the height of the pile foundation platform and the lifting height of the ground truck crane itself. Within the height operation range of the ground truck crane, use the ground truck crane. Hoist the steel column segment by segment;

(5)待同一节段的钢立柱安装完成后,使用地面汽车吊吊装钢立柱之间的腹杆,并将腹杆与钢立柱的连接处进行焊接连接;(5) After the steel columns of the same segment are installed, use the ground truck to hoist the web rods between the steel columns, and weld the joints between the web rods and the steel columns;

(6)待同一节段的钢立柱和腹杆安装完成后,安装本节段钢立柱之间用于人员上下爬行的斜爬梯;(6) After the installation of the steel column and the web of the same section is completed, install the inclined ladder between the steel columns of this section for people to climb up and down;

(7)继续分节段安装钢立柱达到直至连接系的设计标高即可进行连接系的安装,连接系包括三组横向桁架连接系,三组横向桁架连接系分别先在拼装场内的胎架上组拼焊接呈整体,然后依次将三组横向桁架连接系采用地面汽车吊至相应的标高位置,随即对连接系和钢立柱连接处进行焊接,三组横向桁架连接系焊接完成后,将三组横向桁架连接系之间的腹杆进行焊接;(7) Continue to install the steel columns in sections until the design elevation of the connection system is reached, and then the connection system can be installed. The connection system includes three sets of transverse truss connection systems. The upper group is welded as a whole, and then the three sets of transverse truss connection systems are hoisted to the corresponding elevation positions by ground trucks in turn, and then the connection systems and the steel column connection are welded. After the three sets of transverse truss connection systems are welded, the three Weld the webs between the transverse truss connection systems;

(8)继续分节段安装钢立柱和按照设计标高安装连接系直至达到地面汽车吊的高度作业范围,余下的钢立柱和连接系采用桥面架梁吊机进行分节段安装钢立柱和按照设计标高安装连接系直至钢立柱的高度达到设计标高;(8) Continue to install the steel columns in sections and install the connection system according to the design elevation until the height of the ground truck crane is reached. Install the connection system at the design elevation until the height of the steel column reaches the design elevation;

(9)在钢立柱的顶面上固定安装柱头板,然后使用桥面吊梁吊机在柱头板的顶部依次设置三层箱型分配梁,箱型分配梁与柱头板之间、箱型分配梁与箱型分配梁之间均采用满焊连接。(9) Fix and install the column head plate on the top surface of the steel column, and then use the bridge deck hanging beam crane to set up three layers of box-type distribution beams on the top of the column head plate in turn. The beams and box distribution beams are all connected by full welding.

在一些实施例中,地面汽车吊的站位平台的后方边坡、前方边坡分别进行土钉墙和锚杆框架梁防护,桩基平台的前方边坡进行锚索框架梁防护,地面汽车吊的站位平台和桩基平台的其余边坡进行混喷砼防护,并且在边坡的顶部设置有施工截水沟。In some embodiments, the rear side slope and the front side slope of the station platform of the ground vehicle crane are protected by soil nailing walls and anchor frame beams respectively, the front side slope of the pile foundation platform is protected by anchor cable frame beams, and the ground vehicle crane is protected by the anchor frame beam. The remaining side slopes of the station platform and the pile foundation platform shall be protected by mixed shotcrete, and a construction intercepting ditch is set on the top of the side slope.

在一些实施例中,桩基和桩基承台采用单桩单柱单桩基承台结构形式,并且桩基承台的侧面设置有预埋件,相邻的桩基承台之间利用钢管和预埋件连接在一起。In some embodiments, the pile foundation and the pile foundation cap are in the form of a single pile, single column and single pile foundation cap, and the side surface of the pile foundation cap is provided with embedded parts, and steel pipes are used between adjacent pile caps. connected with the embedded parts.

在一些实施例中,在钢立柱与钢立柱对位安装时,采用定位码板连接固定上下两根钢立柱,采用千斤顶和楔形铁对钢立柱进行垂直度和标高的校正,调整好后对钢立柱进行焊接。In some embodiments, when the steel column is installed in alignment with the steel column, a positioning code plate is used to connect and fix the upper and lower steel columns, and a jack and a wedge-shaped iron are used to calibrate the verticality and elevation of the steel column. The column is welded.

在一些实施例中,同一节段的钢立柱之间的腹杆包括水平腹杆和斜腹杆,先安装水平腹杆再安装斜腹杆,水平腹杆和斜腹杆连接在一起后呈“米”字型。In some embodiments, the webs between the steel columns of the same segment include horizontal webs and inclined webs, the horizontal webs are installed first and then the diagonal webs are installed, and the horizontal webs and the diagonal webs are connected together to form a " m" font.

在一些实施例中,所述三层箱型分配梁包括底层分配梁、中层分配梁和顶层分配梁,所述顶层分配梁的顶部设置有至少一层抄垫钢板,位于最上方的抄垫钢板的上方设置有抄垫橡胶垫,所述抄垫钢板的四周分别设置有装配式温变限位装置。In some embodiments, the three-layer box-type distribution beam includes a bottom distribution beam, a middle layer distribution beam and a top distribution beam, and at least one layer of backing steel plate is provided on the top of the top distribution beam, and the uppermost backing steel plate is disposed A pad rubber pad is arranged above the pad, and an assembled temperature change limiting device is respectively arranged around the pad steel plate.

在一些实施例中,所述装配式温变限位装置包括横向装配式温变限位装置和纵向装配式温变限位装置,所述横向装配式温变限位装置和纵向装配式温变限位装置分别设置在抄垫钢板和抄垫橡胶板的四周并对抄垫钢板进行限位。In some embodiments, the assembled temperature change limiting device includes a laterally assembled temperature change limit device and a longitudinally assembled temperature change limit device, the laterally assembled temperature change limit device and the longitudinally assembled temperature change limiter The limiting devices are respectively arranged around the padding steel plate and the padding rubber plate and limit the position of the padding steel plate.

在一些实施例中,所述横向装配式温变限位装置包括钢柱,所述钢柱的上端连接有牛腿,所述牛腿连接有钢板;所述纵向装配式温变限位装置包括钢柱,所述钢柱的上端连接有钢板。In some embodiments, the laterally assembled temperature change limiting device includes a steel column, the upper end of the steel column is connected with a corbel, and the corbel is connected with a steel plate; the longitudinally assembled temperature change limiting device includes A steel column, the upper end of the steel column is connected with a steel plate.

在一些实施例中,在步骤(1)至(9)中,根据不同的施工阶段,在钢立柱的底部、中部和顶部布置有应变片用于实施监测受力情况。In some embodiments, in steps (1) to (9), according to different construction stages, strain gauges are arranged at the bottom, middle and top of the steel column for monitoring the stress condition.

与现有技术相比,本发明具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:

本发明的适用于高山峡谷的超高塔架施工方法,超高临时塔架采用双塔型钢支架(即钢立柱和连接系形成的双塔型结构)与山体防护为一体的综合设计方法,钢立柱之间腹杆采用“米”字型,提高了设计方案的安全性和经济性;并且超高临时塔架桩基和桩基承台采用单桩单柱单承台形式,桩基和桩基承台沿着山体坡度进行设置,减少了对山体的破坏,也降低了施工难度。解决了现有技术在高山峡谷地区施工超高塔架时施工周期长、施工成本高以及对山体破坏大的问题。The super-high tower construction method of the present invention is suitable for high mountains and canyons. The super-high temporary tower adopts a comprehensive design method in which double-tower-shaped steel brackets (that is, a double-tower-shaped structure formed by a steel column and a connection system) are integrated with mountain protection. The web between the columns adopts the "m" shape, which improves the safety and economy of the design scheme; and the pile foundation and pile foundation cap of the super high temporary tower adopt the form of single pile, single column and single cap, and the pile foundation and pile The base cap is set along the slope of the mountain, which reduces the damage to the mountain and reduces the difficulty of construction. It solves the problems of long construction period, high construction cost and large damage to the mountain when constructing an ultra-high tower in a high mountain and valley area in the prior art.

本发明的超高临时塔架采用地面汽车吊和桥面架梁吊机协同完成,相比于现有技术采用塔吊的方式,不仅能够降低施工的成本,同时也提高了施工安全和可靠性。The ultra-high temporary tower of the present invention is completed by the ground truck crane and the bridge deck girder crane, which can not only reduce the construction cost, but also improve the construction safety and reliability compared with the tower crane in the prior art.

本发明的超高临时塔架在施工过程中依据施工分段,以及对钢立柱施工安全防护设施进行了专项设计(安全作业平台、直爬梯和斜爬梯、应变片)保障了施工的安全。The ultra-high temporary tower of the present invention is specially designed according to the construction section and the steel column construction safety protection facilities (safety work platform, straight and inclined ladders, strain gauges) during the construction process to ensure the safety of construction.

本发明在超高塔架墩顶设置三层箱型结构的分配梁,确保竖向力的均匀分布到每根柱顶。同时本发明利用橡胶垫与钢材的刚度比,协调支点反力均匀分布,并通过装配式温变限位装置,避免钢桥纵移产生的钢板滑动,同时采用多层分配梁系统使竖向力均分,提高桥梁架设的安全性。同时采用阶梯式多层分配梁,在钢桁梁架设时可减少大型构件的投入,减少成本,也提高了超高塔架对大型架设荷载的适应性。In the present invention, the distribution beams of the three-layer box-type structure are arranged on the top of the super-high tower pier to ensure that the vertical force is evenly distributed to the top of each column. At the same time, the present invention utilizes the rigidity ratio of the rubber pad and the steel to coordinate the uniform distribution of the reaction force of the fulcrum, avoids the steel plate sliding caused by the longitudinal movement of the steel bridge through the assembled temperature-change limiting device, and adopts a multi-layer distribution beam system to make the vertical force Equal distribution to improve the safety of bridge erection. At the same time, the use of stepped multi-layer distribution beams can reduce the investment of large-scale components and costs when erecting steel trusses, and also improve the adaptability of ultra-high towers to large erection loads.

本发明通过设置抄垫钢板的层数,适应不同的架设方案的抄垫高度,在悬臂架设方案中,较低的抄垫高度可减小抄垫反力,从而减小成本投入。通过抄垫橡胶垫的弹性调节悬臂架设端产生的竖向反力在抄垫上分布,避免局部应力集中产生抄垫构件破坏,确保构件的反复利用,减少投入成本。通过装配式温度限位装置减少钢桁梁架设时产生的温度侧移,减少偏心弯矩,确保安全性,同时能够适应钢梁桁架的节点尺寸变化。The invention adapts to the pad heights of different erection schemes by setting the number of layers of the padding steel plates. In the cantilever erection scheme, the lower padding height can reduce the padding reaction force, thereby reducing the cost input. The vertical reaction force generated by the cantilever erection end is adjusted by the elasticity of the pad rubber pad to distribute on the pad, avoiding the damage of the pad components caused by local stress concentration, ensuring the repeated use of the components and reducing the input cost. The prefabricated temperature limit device reduces the temperature side shift during the erection of the steel truss girder, reduces the eccentric bending moment, ensures safety, and can adapt to the change of the joint size of the steel girder truss.

附图说明Description of drawings

图1为本发明的超高临时塔架的布置示意图;Fig. 1 is the arrangement schematic diagram of the super high temporary tower of the present invention;

图2为本发明的超高临时塔架的结构示意图,其中该图中的左侧部分为主视图示意图,该图中的右侧部位为侧视图示意图;Fig. 2 is the structural schematic diagram of the super high temporary tower of the present invention, wherein the left part in the figure is a schematic front view, and the right part in the figure is a side view schematic;

图3为本发明的钢立柱上安装安全作业平台、直爬梯和斜爬梯的分布示意图;3 is a schematic diagram of the distribution of the safety work platform, the straight ladder and the inclined ladder installed on the steel column of the present invention;

图4为本发明的超高临时塔架上的应变片安装分布示意图;4 is a schematic diagram of the installation and distribution of strain gauges on the ultra-high temporary tower of the present invention;

图5为本发明的超高临时塔架的施工过程中的一示意图;Fig. 5 is a schematic diagram in the construction process of the ultra-high temporary tower of the present invention;

图6为本发明的超高临时塔架的施工过程中的一示意图;Fig. 6 is a schematic diagram in the construction process of the super high temporary tower of the present invention;

图7为本发明的超高临时塔架的施工过程中的一示意图;Fig. 7 is a schematic diagram in the construction process of the ultra-high temporary tower of the present invention;

图8为本发明的超高临时塔架的施工过程中的一示意图;Fig. 8 is a schematic diagram in the construction process of the ultra-high temporary tower of the present invention;

图9为本发明的三层箱型分配梁的结构示意图;9 is a schematic structural diagram of a three-layer box-type distribution beam of the present invention;

图10为本发明的三层箱型分配梁的另一角度的结构示意图;10 is a schematic structural diagram of another angle of the three-layer box-type distribution beam of the present invention;

图11为三层箱型分配梁的上部安装有抄垫钢板和抄垫橡胶板时的结构示意图;Figure 11 is a schematic diagram of the structure when the upper part of the three-layer box-type distribution beam is installed with a padding steel plate and a padding rubber plate;

图12为三层箱型分配梁的上部安装有抄垫钢板和抄垫橡胶板时的另一角度结构示意图;Fig. 12 is another angular structural schematic diagram when the upper part of the three-layer box-type distribution beam is installed with a padding steel plate and a padding rubber plate;

图13为本发明的纵向装配式温变限位装置的结构示意图;13 is a schematic structural diagram of a longitudinally assembled temperature-change limiting device of the present invention;

图14为本发明的横向装配式温变限位装置的结构示意图;14 is a schematic structural diagram of a laterally assembled temperature-change limiting device of the present invention;

图15为本发明的控制点和棱镜安装分布示意图;15 is a schematic diagram of the control point and prism installation distribution of the present invention;

图16为本发明的钢立柱底部反光贴的布置示意图;16 is a schematic diagram of the arrangement of the reflective stickers at the bottom of the steel column of the present invention;

图17为本发明对钢立柱的下段进行观测和测量的示意图;17 is a schematic diagram of the present invention observing and measuring the lower section of the steel column;

图18为本发明的钢立柱顶部反光贴的布置示意图;18 is a schematic diagram of the arrangement of the reflective stickers on the top of the steel column of the present invention;

图19为本发明对钢立柱的上段进行观测和测量的示意图;Figure 19 is a schematic diagram of the present invention observing and measuring the upper section of the steel column;

图中标记:01、第一超高临时塔架,02、第一超高临时塔架,03、施工便道,04、桩基平台,05、地面汽车吊的站位平台,06、土钉墙,07、锚杆框架梁,08、锚索框架梁,09、地面汽车吊,10、桥面架梁吊机,11、三层箱型分配梁,12、顶层分配梁,13、中层分配梁,14、底层分配梁,15、钢立柱,16、腹杆,17、连接系,18、安全作业平台,19、斜爬梯,20、直爬梯,21、应变片,22、抄垫钢板,23、抄垫橡胶板,24、纵向装配式温变限位装置,25、横向装配式温变限位装置,26、钢柱,27、牛腿,28、钢板,29、控制点,30、棱镜,31反光贴。Marked in the picture: 01, the first super high temporary tower, 02, the first super high temporary tower, 03, the construction access road, 04, the pile foundation platform, 05, the station platform of the ground truck crane, 06, the soil nail wall , 07, anchor frame beam, 08, anchor cable frame beam, 09, ground truck crane, 10, bridge deck beam crane, 11, three-layer box distribution beam, 12, top distribution beam, 13, middle layer distribution beam , 14, bottom distribution beam, 15, steel column, 16, web rod, 17, connection system, 18, safe working platform, 19, inclined ladder, 20, straight ladder, 21, strain gauge, 22, copy pad steel plate, 23 , Copy pad rubber plate, 24, Vertically assembled temperature change limit device, 25, Horizontally assembled temperature change limit device, 26, Steel column, 27, Corbel, 28, Steel plate, 29, Control point, 30, Prism , 31 reflective stickers.

具体实施方式Detailed ways

下面结合实施例对本发明作进一步的描述,所描述的实施例仅仅是本发明一部分实施例,并不是全部的实施例。基于本发明中的实施例,本领域的普通技术人员在没有做出创造性劳动前提下所获得的其他所用实施例,都属于本发明的保护范围。The present invention will be further described below with reference to the embodiments, and the described embodiments are only a part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, other used embodiments obtained by persons of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

在本发明的描述中,需要说明的是,术语“中心”、“上”、“下”、“左”、“右”、“竖直”、“水平”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制;术语“第一”、“第二”、“第三”仅用于描述目的,而不能理解为指示或暗示相对重要性;此外,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. The indicated orientation or positional relationship is based on the orientation or positional relationship shown in the accompanying drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the indicated device or element must have a specific orientation or a specific orientation. construction and operation, and therefore should not be construed as limiting the invention; the terms "first", "second", "third" are used for descriptive purposes only and should not be construed as indicating or implying relative importance; furthermore, unless otherwise Clearly stipulated and defined, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it may be a fixed connection, a detachable connection, or an integral connection; it may be a mechanical connection or a Electrical connection; it can be directly connected, or indirectly connected through an intermediate medium, and it can be the internal connection of two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood in specific situations.

结合附图,本发明的适用于高山峡谷的超高塔架施工方法,包括如下步骤:With reference to the accompanying drawings, the super-high tower construction method applicable to the alpine canyon of the present invention comprises the following steps:

(1)对超高塔架施工位置进行测量放线,并平整出桩基平台04和地面汽车吊的站位平台05;即是说线对第一超高临时塔架01和第一超高临时塔架02的施工位置进行测量放线,其中,在测量放线后,可以先施工出施工便道03,然后再施工桩基和桩基平台。施工便道03便于设备的运输以及工作人员操作。(1) Measure and lay out the construction position of the super high tower, and level out the pile foundation platform 04 and the station platform 05 of the ground truck crane; The construction position of the temporary tower 02 is measured and laid out. After the measurement and lay out, the construction access road 03 can be constructed first, and then the pile foundation and the pile foundation platform can be constructed. The construction access road 03 is convenient for the transportation of equipment and the operation of the staff.

(2)在桩基平台04上进行桩基施工和桩基承台施工,其中,先施工桩基,然后再在桩基的顶部浇筑桩基承台;其中对于桩基的施工以及桩基承台的施工均属于现有技术,本领域的技术人员都能明白和理解,在此不再赘述;桩基沿着山体坡度进行设置,即是桩基沿着山体坡度的变化进行布置,其中第一超高临时塔架01和第二超高临时塔架02分别对应于多根桩基,每根桩基的顶部均浇筑有桩基承台,即采用单桩单承台的形式,能够减少对山体的破坏,同时也能够降低施工难度。(2) The pile foundation construction and the pile foundation bearing platform construction are carried out on the pile foundation platform 04, wherein the pile foundation is constructed first, and then the pile foundation bearing platform is poured on the top of the pile foundation; wherein the construction of the pile foundation and the pile foundation bearing platform The construction of the platform belongs to the prior art, which can be understood and understood by those skilled in the art, and will not be repeated here; the pile foundation is arranged along the slope of the mountain, that is, the pile foundation is arranged along the change of the slope of the mountain. A super-high temporary tower 01 and a second super-high temporary tower 02 correspond to a plurality of pile foundations respectively, and a pile foundation cap is poured on the top of each pile foundation, that is, the form of a single pile and a single cap is adopted, which can reduce the number of pile foundations. The damage to the mountain can also reduce the difficulty of construction.

(3)在拼装场内加工制作好的钢立柱15,并且在拼装场内在钢立柱15上安装安全作业平台和直爬梯,然后将拼装有安全作业平台18和直爬梯20的钢立柱15一起运输至施工场地:(3) The steel column 15 processed and manufactured in the assembly yard, and the safety work platform and the straight ladder are installed on the steel column 15 in the assembly yard, and then the steel column 15 assembled with the safety work platform 18 and the straight ladder 20 is transported together To the construction site:

(4)根据地面汽车吊的站位平台05的高度、桩基平台04的高度和地面汽车吊09自身的起吊高度确定好地面汽车吊的高度作业范围,在地面汽车吊09的高度作业范围内,使用地面汽车吊09对钢立柱15进行分节段吊装;即是说,地面汽车吊的高度作为范围为:地面汽车吊的站位平台05的高度与桩基平台04的高度之差再加上地面汽车吊的自身的起吊高度,从而确定地面汽车吊09的高度作业范围。(4) According to the height of the station platform 05 of the ground truck crane, the height of the pile foundation platform 04 and the lifting height of the ground truck crane 09 itself, determine the height operation range of the ground truck crane, within the height operation range of the ground truck crane 09 , Use the ground truck crane 09 to hoist the steel column 15 in sections; that is to say, the height of the ground truck crane is used as the range: the difference between the height of the station platform 05 of the ground truck crane and the height of the pile foundation platform 04 plus The lifting height of the truck crane on the ground itself is used to determine the height operation range of the truck crane 09 on the ground.

(5)待同一节段的钢立柱安装完成后,使用地面汽车吊09吊装钢立柱15之间的腹杆16,并将腹杆16与钢立柱15的连接处进行焊接连接;(5) After the installation of the steel column of the same segment is completed, use the ground vehicle crane 09 to hoist the web rod 16 between the steel column 15, and weld the connection between the web rod 16 and the steel column 15;

(6)待同一节段的钢立柱15和腹杆16安装完成后,安装本节段钢立柱15之间用于人员上下爬行的斜爬梯19;(6) After the installation of the steel column 15 and the web rod 16 of the same section is completed, install the inclined ladder 19 for people to climb up and down between the steel columns 15 of this section;

(7)继续分节段安装钢立柱15达到直至连接系的设计标高即可进行连接系17的安装,连接系17包括三组横向桁架连接系,三组横向桁架连接系分别先在拼装场内的胎架上组拼焊接呈整体,然后依次将三组横向桁架连接系采用地面汽车吊19至相应的标高位置,随即对连接系17和钢立柱15连接处进行焊接,三组横向桁架连接系焊接完成后,将三组横向桁架连接系之间的腹杆进行焊接;其中钢立柱15与腹杆之间形成一个钢立柱单元,连接系17用于连接相邻的钢立柱单元,从而将各个钢立柱单元形成一个整体结构,其中一个钢立柱单元均包括多根钢立柱,同一钢立柱单元之间的钢立柱之间通过腹杆连接形成一个整体。优选的,本发明采用双塔型钢支架,即是说两个钢立柱单元之间经过连接系连接在一起形成一个双塔型钢支架,能够保障安全性,同时能够降低施工成本。(7) Continue to install the steel column 15 in sections until the design elevation of the connection system is reached, and then the connection system 17 can be installed. The connection system 17 includes three sets of transverse truss connection systems, and the three sets of transverse truss connection systems are first in the assembly yard respectively. The upper group of the tire frame is assembled and welded as a whole, and then the three groups of transverse truss connection systems are successively connected to the corresponding elevation position by the ground truck 19, and then the connection between the connection system 17 and the steel column 15 is welded. After the welding is completed, the web members between the three sets of transverse truss connection systems are welded; a steel column unit is formed between the steel column 15 and the web member, and the connection system 17 is used to connect the adjacent steel column units, so as to connect each The steel column units form an integral structure, wherein each of the steel column units includes a plurality of steel columns, and the steel columns between the same steel column units are connected by web rods to form a whole. Preferably, the present invention adopts a double-tower shaped steel support, that is to say, two steel column units are connected together through a connection system to form a double-tower shaped steel support, which can ensure safety and reduce construction costs.

(8)继续分节段安装钢立柱15和按照设计标高安装连接系17直至达到地面汽车吊19的高度作业范围,余下的钢立柱15和连接系17采用桥面架梁吊机10进行分节段安装钢立柱15和按照设计标高安装连接系17直至钢立柱的高度达到设计标高;其中在采用桥面架梁吊机10进行分阶段安装钢立柱和连接系的步骤与采用地面汽车吊09进行钢立柱和连接系的安装步骤和流程相同,在此不再赘述。(8) Continue to install the steel column 15 in sections and install the connection system 17 according to the design elevation until the height of the ground truck crane 19 is reached. The remaining steel columns 15 and the connection system 17 are segmented by the bridge deck girder crane 10 Install the steel column 15 in sections and install the connection system 17 according to the design elevation until the height of the steel column reaches the design elevation; wherein the steps of using the bridge deck girder crane 10 to install the steel column and the connection system in stages are the same as using the ground truck crane 09. The installation steps and processes of the steel column and the connection system are the same, and will not be repeated here.

(9)在钢立柱15的顶面上固定安装柱头板,然后使用桥面吊梁吊机10在柱头板的顶部依次设置三层箱型分配梁,其中,箱型分配梁与柱头板之间、箱型分配梁与箱型分配梁之间均采用满焊连接。本发明在超高塔架墩顶设置三层箱型结构的分配梁,确保竖向力的均匀分布到每根柱顶。同时本发明利用橡胶垫与钢材的刚度比,协调支点反力均匀分布,并通过装配式温变限位装置,避免钢桥纵移产生的钢板滑动,同时采用多层分配梁系统使竖向力均分,提高桥梁架设的安全性。同时采用阶梯式多层分配梁,在钢桁梁架设时可减少大型构件的投入,减少成本,也提高了超高塔架对大型架设荷载的适应性。(9) Fix and install the column head plate on the top surface of the steel column 15, and then use the bridge deck hanging beam crane 10 to sequentially set up three layers of box-type distribution beams on the top of the column head plate, wherein, between the box-type distribution beam and the column head plate , The box-type distribution beam and the box-type distribution beam are all connected by full welding. In the present invention, the distribution beams of the three-layer box-type structure are arranged on the top of the super-high tower pier to ensure that the vertical force is evenly distributed to the top of each column. At the same time, the present invention utilizes the rigidity ratio of the rubber pad and the steel to coordinate the uniform distribution of the reaction force of the fulcrum, avoids the steel plate sliding caused by the longitudinal movement of the steel bridge through the assembled temperature-change limiting device, and adopts a multi-layer distribution beam system to make the vertical force Equal distribution to improve the safety of bridge erection. At the same time, the use of stepped multi-layer distribution beams can reduce the investment of large-scale components and costs when erecting steel trusses, and also improve the adaptability of ultra-high towers to large erection loads.

在一些实施例中,地面汽车吊的站位平台05的后方边坡、前方边坡分别进行土钉墙和锚杆框架梁防护,桩基平台的前方边坡进行锚索框架梁防护,地面汽车吊的站位平台05和桩基平台的其余边坡进行混喷砼防护,并且在边坡的顶部设置有施工截水沟,从而确保桩基、地面汽车吊的站位平台05的安全和稳固,降低高山峡谷地区边坡出现滑坡、垮塌等安全隐患。In some embodiments, the rear side slope and the front side slope of the station platform 05 of the ground vehicle crane are respectively protected by soil nailing walls and anchor frame beams, the front side slope of the pile foundation platform is protected by anchor cable frame beams, and the ground vehicle crane is protected by anchor cable frame beams. The station platform 05 of the crane and the remaining slopes of the pile platform are protected by mixed-spray concrete, and a construction intercepting ditch is set on the top of the slope to ensure the safety and stability of the pile foundation and the station platform 05 of the ground truck crane. , to reduce the safety hazards such as landslides and collapses on the slopes in the alpine and canyon areas.

在一些实施例中,桩基和桩基承台采用单桩单柱单桩基承台结构形式,即是说,一根桩基对应一个桩基承台和一根钢立柱15,每一个桩基承台上安装有一根钢立柱15;并且桩基承台的侧面设置有预埋件,相邻的桩基承台之间利用钢管和预埋件连接在一起。从而将各个桩基承台连接在一起形成一个整体结构,既能够提高超高塔架的安全性和稳定性,同时又能够降低施工量、减少对山体的破坏。In some embodiments, the pile foundation and the pile foundation cap are in the form of single pile, single column and single pile foundation cap, that is to say, one pile foundation corresponds to one pile foundation cap and one steel column 15, and each pile A steel column 15 is installed on the foundation cap; and the side surface of the pile foundation cap is provided with embedded parts, and the adjacent pile foundation caps are connected together by steel pipes and embedded parts. Therefore, each pile cap is connected together to form an integral structure, which can not only improve the safety and stability of the super-high tower, but also reduce the construction amount and the damage to the mountain.

在一些实施例中,在钢立柱15与钢立柱15对位安装时,采用定位码板连接固定上下两根钢立柱,采用千斤顶和楔形铁对钢立柱进行垂直度和标高的校正,调整好后对钢立柱进行焊接,从而确保上下相邻的两根钢立柱15均处于垂直状态,确保超高塔架承受的压力能够竖向压力能够依次传给钢立柱15、桩基承台和桩基,最终利用桩基和土体之间的作用力承受竖向压力。In some embodiments, when the steel column 15 is installed in alignment with the steel column 15, a positioning code plate is used to connect and fix the upper and lower steel columns, and a jack and a wedge iron are used to calibrate the verticality and elevation of the steel column. The steel column is welded to ensure that the two adjacent steel columns 15 are in a vertical state, ensuring that the pressure on the ultra-high tower can be transmitted to the steel column 15, the pile foundation cap and the pile foundation in turn. Finally, the force between the pile foundation and the soil body is used to bear the vertical pressure.

在一些实施例中,同一节段的钢立柱15之间的腹杆16包括水平腹杆和斜腹杆,先安装水平腹杆再安装斜腹杆,水平腹杆和斜腹杆连接在一起后呈“米”字型,其中水平腹杆和倾腹杆与钢立柱15之间均采用焊接连接,水平腹杆与斜腹杆之间也采用焊接的方式进行固定连接。In some embodiments, the web rod 16 between the steel columns 15 of the same segment includes a horizontal web rod and a diagonal web rod, the horizontal web rod is installed first and then the diagonal web rod is installed, and after the horizontal web rod and the diagonal web rod are connected together It is in the shape of "meter", in which the horizontal web rod and the inclined web rod and the steel column 15 are all connected by welding, and the horizontal web rod and the inclined web rod are also fixedly connected by welding.

在一些实施例中,所述三层箱型分配梁包括底层分配梁14、中层分配梁13和顶层分配梁12,底层分配梁14、中层分配梁13和顶层分配梁12形成阶梯状结构,所述顶层分配梁12的顶部设置有至少一层抄垫钢板22,位于最上方的抄垫钢板22的上方设置有抄垫橡胶垫23,所述至少一层抄垫钢板22的四周分别设置有装配式温变限位装置。In some embodiments, the three-layer box distribution beam includes a bottom distribution beam 14, a middle layer distribution beam 13 and a top layer distribution beam 12, and the bottom layer distribution beam 14, the middle layer distribution beam 13 and the top layer distribution beam 12 form a stepped structure, so The top of the top distribution beam 12 is provided with at least one layer of padding steel plate 22, the top of the padding steel plate 22 at the top is provided with a padding rubber pad 23, and the surrounding of the at least one layer of padding steel plate 22 is respectively provided with an assembly. Type temperature limit device.

在一些实施例中,所述装配式温变限位装置包括横向装配式温变限位装置25和纵向装配式温变限位装置24,所述横向装配式温变限位装置25和纵向装配式温变限位装置24分别设置在抄垫钢板和抄垫橡胶板23的四周并对抄垫钢板22进行限位。In some embodiments, the assembled temperature change limiting device includes a laterally assembled temperature change limit device 25 and a longitudinally assembled temperature change limit device 24 , the laterally assembled temperature change limit device 25 and the longitudinally assembled temperature limit device 24 . The temperature change limiting device 24 is respectively arranged around the padding steel plate and the padding rubber plate 23 and limits the position of the padding steel plate 22 .

在一些实施例中,所述横向装配式温变限位装置25包括钢柱26,所述钢柱26的上端连接有牛腿27,所述牛腿27连接有钢板28,其中钢柱26用于与抄垫钢板22接触并对抄垫钢板22进行限位,所述牛腿27和钢板28用于对安装在上方的钢桁架进行限位。In some embodiments, the laterally assembled temperature change limiting device 25 includes a steel column 26, the upper end of the steel column 26 is connected with a corbel 27, and the corbel 27 is connected with a steel plate 28, wherein the steel column 26 uses In order to contact with the padding steel plate 22 and limit the position of the padding steel plate 22, the corbel 27 and the steel plate 28 are used to limit the position of the steel truss installed above.

在一些实施例中,所述纵向装配式温变限位装置24包括钢柱26,所述钢柱26的上端连接有钢板28,所述钢柱26和钢板28均用于对抄垫钢板22进行限位。In some embodiments, the longitudinally assembled temperature change limiting device 24 includes a steel column 26 , and a steel plate 28 is connected to the upper end of the steel column 26 , and both the steel column 26 and the steel plate 28 are used for aligning the steel plate 22 Limit.

本发明通过设置抄垫钢板的层数,适应不同的架设方案的抄垫高度,在悬臂架设方案中,较低的抄垫高度可减小抄垫反力,从而减小成本投入。通过抄垫橡胶垫的弹性调节悬臂架设端产生的竖向反力在抄垫上分布,避免局部应力集中产生抄垫构件破坏,确保构件的反复利用,减少投入成本。通过装配式温度限位装置减少钢桁梁架设时产生的温度侧移,减少偏心弯矩,确保安全性,同时能够适应钢梁桁架的节点尺寸变化。The invention adapts to the pad heights of different erection schemes by setting the number of layers of the padding steel plates. In the cantilever erection scheme, the lower padding height can reduce the padding reaction force, thereby reducing the cost input. The vertical reaction force generated by the cantilever erection end is adjusted by the elasticity of the pad rubber pad to distribute on the pad, avoiding the damage of the pad components caused by local stress concentration, ensuring the repeated use of the components and reducing the input cost. The prefabricated temperature limit device reduces the temperature side shift during the erection of the steel truss girder, reduces the eccentric bending moment, ensures safety, and can adapt to the change of the joint size of the steel girder truss.

在一些实施例中,在步骤(1)至(9)中,根据不同的施工阶段,在钢立柱的底部、中部和顶部布置有应变片用于实施监测受力情况。In some embodiments, in steps (1) to (9), according to different construction stages, strain gauges are arranged at the bottom, middle and top of the steel column for monitoring the stress condition.

在一些实例中,在步骤(1)至(9)中,还需根据不同的施工阶段,对超高塔架进行观测和测量,所述对超高塔架进行观测和测量方法包括:In some instances, in steps (1) to (9), it is also necessary to observe and measure the ultra-high tower according to different construction stages, and the method for observing and measuring the ultra-high tower includes:

(1)在超高塔架底部施工作业区域周围设置三个或者三个以上的控制点29,并确保各个控制点通视良好并不会被破坏,同时在边墩(如图1中的1#墩、2#墩、3#墩和4#墩)的顶部设置一个控制点29;如图15所示,超高塔架底部施工作业区域周围设置有三个控制点29,其中2个控制点在底部施工作业区域的外围、1个控制点29设置在边墩的底部,并且在该边墩的顶部也同样设置有一个控制点29。其中,控制点29的选取应当根据地理位置及地势合理布设,所选控制点点位要充分考虑到施工需要和施工方便。(1) Set up three or more control points 29 around the construction work area at the bottom of the super-high tower, and ensure that each control point has good visibility and will not be damaged. A control point 29 is set at the top of #pier, 2#pier, 3#pier and 4#pier); as shown in Figure 15, three control points 29 are set around the construction work area at the bottom of the ultra-high tower, of which 2 are On the periphery of the bottom construction work area, a control point 29 is provided at the bottom of the side pier, and a control point 29 is also provided on the top of the side pier. Among them, the selection of control points 29 should be reasonably arranged according to the geographical location and terrain, and the selected control points should fully consider the construction needs and convenience of construction.

(2)当对超高塔架的桩基进行定位时,结合附图15,将全站仪架设在超高塔架底部施工作业区域周围中任一一个控制点29上,采用测站定向测量,复核其中另外一个点,以此方法完成其余桩位定位。(2) When positioning the pile foundation of the super-high tower, in conjunction with accompanying drawing 15, erect the total station on any one of the control points 29 around the construction operation area at the bottom of the super-high tower, and use the station orientation Measure and check one of the other points, and complete the rest of the pile positioning in this way.

(3)当对钢立柱的下段(即地面汽车吊09的高度作业范围内)进行垂直度、标高、沉降量进行测量时:结合附图16和附图17,在钢立柱15柱顶中心安装棱镜30,在钢立柱的底部安装反光贴31作为沉降观测点,将测量仪器架设在方便观察的控制点29上(结合附图17,该控制点在边墩的底部),即将测量仪器架设在边墩的底部,并通过棱镜对钢立柱中心进行垂直度和标高测量;同时通过反光贴31定期进行沉降观测。(3) When measuring the verticality, elevation and settlement of the lower section of the steel column (that is, within the height operating range of the ground truck crane 09): in conjunction with the accompanying drawings 16 and 17, install at the center of the top of the steel column 15 Prism 30, install reflective stickers 31 at the bottom of the steel column as a settlement observation point, and erect the measuring instrument on the control point 29 for easy observation (in conjunction with accompanying drawing 17, the control point is at the bottom of the side pier), and the measuring instrument is erected on the The bottom of the side pier, and the verticality and elevation of the center of the steel column are measured through a prism;

(4)当对钢立柱的上端(即采用桥面架梁吊机的作业范围)进行垂直度、标高、沉降量进行测量时:结合附图18和附图19,在钢立柱15柱顶中心安装棱镜30,在钢立柱的顶部安装反光贴31作为沉降观测点,将测量仪器架设在方便观察的控制点29上(结合附图17,该控制点在边墩的顶部),即将测量仪器架设在边墩的顶部,并通过棱镜30对钢立柱中心进行垂直度和标高测量;同时通过反光贴31定期进行沉降观测。(4) When measuring the verticality, elevation and settlement of the upper end of the steel column (that is, the operating range of the bridge deck girder crane): in conjunction with the accompanying drawings 18 and 19, at the center of the top of the steel column 15 Install the prism 30, install the reflective stickers 31 on the top of the steel column as a settlement observation point, set up the measuring instrument on the control point 29 for easy observation (in conjunction with accompanying drawing 17, the control point is on the top of the side pier), about to set up the measuring instrument On the top of the side pier, the verticality and elevation of the center of the steel column are measured through the prism 30;

本发明的超高塔架进行观测和测量方法,能够降低施工测量难度,确保施工作业面在测量控制网观测范围内,便于后期进行定期沉降观测。同时本发明的观测和测量方法相比于现有技术,减少了施工测量中测站建立次数,在通视的条件下完成施工测量,确保了超高临时墩塔架施工测量的质量和准确性。The observation and measurement method for the ultra-high tower of the invention can reduce the difficulty of construction measurement, ensure that the construction work surface is within the observation range of the measurement control network, and facilitate regular settlement observation in the later stage. At the same time, compared with the prior art, the observation and measurement method of the present invention reduces the number of station establishments in the construction measurement, completes the construction measurement under the condition of visibility, and ensures the quality and accuracy of the construction measurement of the super-high temporary pier tower. .

以上,并非对本发明任何形式上和实质上的限制,应当指出,对于本技术领域的普通技术人员,在不脱离本发明方法的前提下,还将可以做出若干改进和补充,这些改进和补充也应视为本发明的保护范围。凡熟悉本专业的技术人员,在不脱离本发明的精神和范围的情况下,当可利用以上所揭示的技术内容而做出的些许更动、修饰与演变的等同变化,均为本发明的等效实施例;同时,凡依据本发明的实质技术对上述实施例所作的任何等同变化的更动、修饰与演变,均仍属于本发明的技术方案的范围内。The above is not intended to limit the present invention in any form and substance. It should be pointed out that for those of ordinary skill in the art, without departing from the method of the present invention, several improvements and supplements can be made. These improvements and supplements It should also be regarded as the protection scope of the present invention. All those skilled in the art, without departing from the spirit and scope of the present invention, can utilize the above-disclosed technical content to make some changes, modifications and equivalent changes of evolution, all belong to the present invention. Equivalent embodiments; at the same time, any modification, modification and evolution of any equivalent changes made to the above embodiments according to the essential technology of the present invention still fall within the scope of the technical solutions of the present invention.

Claims (8)

1.高山峡谷大跨度上承式连续钢桁梁桥的超高塔架施工方法,其特征在于,包括如下步骤:1. the super-high tower construction method of the large-span upper bearing type continuous steel truss girder bridge in alpine canyons, is characterized in that, comprises the steps: (1)对超高塔架施工位置进行测量放线,并平整出桩基平台和地面汽车吊的站位平台;(1) Measure and lay out the construction position of the super-high tower, and level out the pile foundation platform and the station platform of the ground truck crane; (2)在桩基平台上进行桩基施工和桩基承台施工,桩基沿着山体坡度进行设置;(2) The pile foundation construction and the pile foundation bearing platform construction are carried out on the pile foundation platform, and the pile foundation is set along the slope of the mountain; (3)在拼装场内加工制作好的钢立柱,并且在拼装场内在钢立柱上安装安全作业平台和直爬梯,然后一起运输至施工场地;(3) The fabricated steel column is processed in the assembly yard, and a safe working platform and a straight ladder are installed on the steel column in the assembly yard, and then transported to the construction site together; (4)根据地面汽车吊的站位平台的高度、桩基平台的高度和地面汽车吊自身的起吊高度确定好地面汽车吊的高度作业范围,在地面汽车吊的高度作业范围内,使用地面汽车吊对钢立柱进行分节段吊装;(4) Determine the height operation range of the ground truck crane according to the height of the station platform of the ground truck crane, the height of the pile foundation platform and the lifting height of the ground truck crane itself. Within the height operation range of the ground truck crane, use the ground truck crane. Hoist the steel column segment by segment; (5)待同一节段的钢立柱安装完成后,使用地面汽车吊吊装钢立柱之间的腹杆,并将腹杆与钢立柱的连接处进行焊接连接;(5) After the steel columns of the same segment are installed, use the ground truck to hoist the web rods between the steel columns, and weld the joints between the web rods and the steel columns; (6)待同一节段的钢立柱和腹杆安装完成后,安装本节段钢立柱之间用于人员上下爬行的斜爬梯;(6) After the installation of the steel column and the web of the same section is completed, install the inclined ladder between the steel columns of this section for people to climb up and down; (7)继续分节段安装钢立柱达到直至连接系的设计标高即可进行连接系的安装,连接系包括三组横向桁架连接系,三组横向桁架连接系分别先在拼装场内的胎架上组拼焊接呈整体,然后依次将三组横向桁架连接系采用地面汽车吊至相应的标高位置,随即对连接系和钢立柱连接处进行焊接,三组横向桁架连接系焊接完成后,将三组横向桁架连接系之间的腹杆进行焊接;(7) Continue to install the steel columns in sections until the design elevation of the connection system is reached, and then the connection system can be installed. The connection system includes three sets of transverse truss connection systems. The upper group is welded as a whole, and then the three sets of transverse truss connection systems are hoisted to the corresponding elevation positions by ground trucks in turn, and then the connection systems and the steel column connection are welded. After the three sets of transverse truss connection systems are welded, the three Weld the webs between the transverse truss connection systems; (8)继续分节段安装钢立柱和按照设计标高安装连接系直至达到地面汽车吊的高度作业范围,余下的钢立柱和连接系采用桥面架梁吊机进行分节段安装钢立柱和按照设计标高安装连接系直至钢立柱的高度达到设计标高;(8) Continue to install the steel columns in sections and install the connection system according to the design elevation until the height of the ground truck crane is reached. Install the connection system at the design elevation until the height of the steel column reaches the design elevation; (9)在钢立柱的顶面上固定安装柱头板,然后使用桥面吊梁吊机在柱头板的顶部依次设置三层箱型分配梁,箱型分配梁与柱头板之间、箱型分配梁与箱型分配梁之间均采用满焊连接。(9) Fix and install the column head plate on the top surface of the steel column, and then use the bridge deck hanging beam crane to set up three layers of box-type distribution beams on the top of the column head plate in turn. The beams and box distribution beams are all connected by full welding. 2.根据权利要求1所述的高山峡谷大跨度上承式连续钢桁梁桥的超高塔架施工方法,其特征在于,地面汽车吊的站位平台的后方边坡、前方边坡分别进行土钉墙和锚杆框架梁防护,桩基平台的前方边坡进行锚索框架梁防护,地面汽车吊的站位平台和桩基平台的其余边坡进行混喷砼防护,并且在边坡的顶部设置有施工截水沟。2. the super-high tower construction method of the high-mountain canyon large-span top-supporting continuous steel truss girder bridge according to claim 1, is characterized in that, the rear side slope and the front side slope of the station platform of the ground truck crane are carried out respectively. Soil nail wall and anchor frame beam protection, the front slope of the pile platform is protected by anchor cable frame beam, the station platform of the ground truck crane and the remaining slopes of the pile platform are protected by mixed shotcrete, and the side slopes of the slope are protected by concrete. There is a construction intercepting ditch at the top. 3.根据权利要求1所述的高山峡谷大跨度上承式连续钢桁梁桥的超高塔架施工方法,其特征在于,桩基和桩基承台采用单桩单柱单桩基承台结构形式,并且桩基承台的侧面设置有预埋件,相邻的桩基承台之间利用钢管和预埋件连接在一起。3. the super-high tower construction method of the high-mountain canyon large-span top-supported continuous steel truss girder bridge according to claim 1, it is characterized in that, pile foundation and pile foundation cap adopt single pile single column single pile foundation cap In addition, the side surface of the pile foundation cap is provided with embedded parts, and the adjacent pile foundation caps are connected together by steel pipes and embedded parts. 4.根据权利要求1所述的高山峡谷大跨度上承式连续钢桁梁桥的超高塔架施工方法,其特征在于,在钢立柱与钢立柱对位安装时,采用定位码板连接固定上下两根钢立柱,采用千斤顶和楔形铁对钢立柱进行垂直度和标高的校正,调整好后对钢立柱进行焊接。4. The super-high tower construction method of the long-span top-supported continuous steel truss girder bridge in the alpine valley according to claim 1, is characterized in that, when the steel column and the steel column are aligned and installed, the positioning code plate is used to connect and fix For the upper and lower steel columns, the verticality and elevation of the steel columns are corrected by using a jack and a wedge iron. After the adjustment, the steel columns are welded. 5.根据权利要求1所述的高山峡谷大跨度上承式连续钢桁梁桥的超高塔架施工方法,其特征在于,同一节段的钢立柱之间的腹杆包括水平腹杆和斜腹杆,先安装水平腹杆再安装斜腹杆,水平腹杆和斜腹杆连接在一起后呈“米”字型。5. The super-high tower construction method of the large-span top-supported continuous steel truss girder bridge in the alpine valley according to claim 1, wherein the web between the steel columns of the same segment comprises a horizontal web and an oblique web. For the web rod, install the horizontal web rod first and then install the inclined web rod. The horizontal web rod and the diagonal web rod are connected together to form a "meter" shape. 6.根据权利要求1-5中任一项所述的高山峡谷大跨度上承式连续钢桁梁桥的超高塔架施工方法,其特征在于,所述三层箱型分配梁包括底层分配梁、中层分配梁和顶层分配梁,所述顶层分配梁的顶部设置有至少一层抄垫钢板,位于最上方的抄垫钢板的上方设置有抄垫橡胶垫,所述抄垫钢板的四周分别设置有装配式温变限位装置。6. The super-high tower construction method of the long-span top-supported continuous steel truss girder bridge in the alpine valley according to any one of claims 1-5, wherein the three-layer box-type distribution beam comprises a bottom distribution The beam, the middle-level distribution beam and the top-level distribution beam, the top of the top-level distribution beam is provided with at least one layer of padding steel plate, and the top of the padding steel plate located at the top is provided with a padding rubber pad, and the surrounding areas of the padding steel plate are respectively A prefabricated temperature change limiting device is provided. 7.根据权利要求6所述的高山峡谷大跨度上承式连续钢桁梁桥的超高塔架施工方法,其特征在于,所述装配式温变限位装置包括横向装配式温变限位装置和纵向装配式温变限位装置,所述横向装配式温变限位装置和纵向装配式温变限位装置分别设置在抄垫钢板和抄垫橡胶板的四周并对抄垫钢板进行限位。7. The super-high tower construction method of the long-span top-supported continuous steel truss bridge in the alpine valley according to claim 6, wherein the assembled temperature change limiting device comprises a laterally assembled temperature change limit The device and the longitudinally assembled temperature change limit device, the laterally assembled temperature change limit device and the longitudinally assembled temperature change limit device are respectively arranged around the pad steel plate and the pad rubber plate and limit the pad steel plate. bit. 8.根据权利要求1所述的高山峡谷大跨度上承式连续钢桁梁桥的超高塔架施工方法,其特征在于,在步骤(1)至(9)中,根据不同的施工阶段,在钢立柱的底部、中部和顶部布置有应变片用于实施监测受力情况。8. the super-high tower construction method of the high-mountain canyon large-span top-supporting continuous steel truss girder bridge according to claim 1, is characterized in that, in steps (1) to (9), according to different construction stages, Strain gauges are arranged at the bottom, middle and top of the steel column to monitor the stress.
CN202010562575.8A 2020-06-18 2020-06-18 Construction method of ultrahigh tower of long-span bearing type continuous steel truss girder bridge in high mountain canyon Active CN111663451B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010562575.8A CN111663451B (en) 2020-06-18 2020-06-18 Construction method of ultrahigh tower of long-span bearing type continuous steel truss girder bridge in high mountain canyon

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010562575.8A CN111663451B (en) 2020-06-18 2020-06-18 Construction method of ultrahigh tower of long-span bearing type continuous steel truss girder bridge in high mountain canyon

Publications (2)

Publication Number Publication Date
CN111663451A true CN111663451A (en) 2020-09-15
CN111663451B CN111663451B (en) 2022-04-08

Family

ID=72388749

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010562575.8A Active CN111663451B (en) 2020-06-18 2020-06-18 Construction method of ultrahigh tower of long-span bearing type continuous steel truss girder bridge in high mountain canyon

Country Status (1)

Country Link
CN (1) CN111663451B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112921828A (en) * 2021-02-07 2021-06-08 中铁四局集团有限公司 Flexible landing pad device for erecting ultrahigh bearing support on cantilever of large-span railway steel truss girder bridge
CN115949079A (en) * 2022-12-26 2023-04-11 中铁四局集团有限公司 A system and method for slope protection of super-high temporary supports in mountains and valleys

Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08209629A (en) * 1995-01-31 1996-08-13 Mitsubishi Heavy Ind Ltd Overhanging type construction device for bridge
JPH10131130A (en) * 1996-10-29 1998-05-19 Sumikura Kozai Kk Arrangement method of RC structure
JP3718033B2 (en) * 1997-09-10 2005-11-16 株式会社三井三池製作所 Precast block erection device
KR100729391B1 (en) * 2006-11-20 2007-06-15 주식회사 누리플랜 Temporary bridge and installation method
CN101117792A (en) * 2007-08-22 2008-02-06 中铁大桥局股份有限公司 Erection method of long-span continuous steel truss arch
CN101122115A (en) * 2007-08-03 2008-02-13 中铁一局集团有限公司 A construction method for tower crane displacement
CN101210419A (en) * 2007-12-21 2008-07-02 中铁大桥局股份有限公司 Small radius curved concrete box girder construction machine with internal and external girder system and its construction method
CN101324054A (en) * 2008-08-01 2008-12-17 中铁大桥局集团第三工程有限公司 Construction Method of Pushing into Place for Temporary Piers of Segmental Beams of Bridges
CN202000316U (en) * 2011-03-23 2011-10-05 葛洲坝集团第五工程有限公司 Temporary structure for diversion tunnel gate-closing and blocking
KR101126081B1 (en) * 2011-10-04 2012-03-29 주식회사 케이에스씨건설 A truss temporary bridge structure using across-beam bracket
CN102587291A (en) * 2012-03-27 2012-07-18 中交四航局第一工程有限公司 Walking type multipoint pushing construction method and walking type multipoint pushing construction system for steel box girder
CN202705924U (en) * 2012-07-18 2013-01-30 中铁二十三局集团有限公司 Assembling platform arranged in the middle of bridge span
CN203346798U (en) * 2013-07-03 2013-12-18 中交二公局第四工程有限公司 Reverse dragging device for large span steel truss girder dragging construction
CN107653781A (en) * 2017-09-20 2018-02-02 龙元建设集团股份有限公司 Big steel pipe truss and construction method for bent cap cast-in-place construction
CN207828792U (en) * 2018-01-12 2018-09-07 九冶建设有限公司 Removable support for the installation of urban steel bridges beam
CN108827672A (en) * 2018-03-29 2018-11-16 中国矿业大学 Multi-point equispaced load flexible connection space multistage distribution beam system and its implementation method
CN110258294A (en) * 2019-04-30 2019-09-20 安徽省公路桥梁工程有限公司 Steel truss arch bridge installs system and its construction method
CN209703316U (en) * 2019-01-18 2019-11-29 中铁三局集团有限公司 A kind of steel truss girder platform for lining big suitable for environmental restrictions
CN111119059A (en) * 2019-12-31 2020-05-08 四川交投建设工程股份有限公司 Ultrahigh composite support system for high-pier cast-in-place box girder and construction method
CN111139749A (en) * 2020-01-08 2020-05-12 中铁四局集团有限公司 A construction method of a large-span top-supported continuous steel truss girder cantilever frame
CN210658011U (en) * 2019-04-30 2020-06-02 安徽省公路桥梁工程有限公司 Steel truss arch bridge installation system

Patent Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08209629A (en) * 1995-01-31 1996-08-13 Mitsubishi Heavy Ind Ltd Overhanging type construction device for bridge
JPH10131130A (en) * 1996-10-29 1998-05-19 Sumikura Kozai Kk Arrangement method of RC structure
JP3718033B2 (en) * 1997-09-10 2005-11-16 株式会社三井三池製作所 Precast block erection device
KR100729391B1 (en) * 2006-11-20 2007-06-15 주식회사 누리플랜 Temporary bridge and installation method
CN101122115A (en) * 2007-08-03 2008-02-13 中铁一局集团有限公司 A construction method for tower crane displacement
CN101117792A (en) * 2007-08-22 2008-02-06 中铁大桥局股份有限公司 Erection method of long-span continuous steel truss arch
CN101210419A (en) * 2007-12-21 2008-07-02 中铁大桥局股份有限公司 Small radius curved concrete box girder construction machine with internal and external girder system and its construction method
CN101324054A (en) * 2008-08-01 2008-12-17 中铁大桥局集团第三工程有限公司 Construction Method of Pushing into Place for Temporary Piers of Segmental Beams of Bridges
CN202000316U (en) * 2011-03-23 2011-10-05 葛洲坝集团第五工程有限公司 Temporary structure for diversion tunnel gate-closing and blocking
KR101126081B1 (en) * 2011-10-04 2012-03-29 주식회사 케이에스씨건설 A truss temporary bridge structure using across-beam bracket
CN102587291A (en) * 2012-03-27 2012-07-18 中交四航局第一工程有限公司 Walking type multipoint pushing construction method and walking type multipoint pushing construction system for steel box girder
CN202705924U (en) * 2012-07-18 2013-01-30 中铁二十三局集团有限公司 Assembling platform arranged in the middle of bridge span
CN203346798U (en) * 2013-07-03 2013-12-18 中交二公局第四工程有限公司 Reverse dragging device for large span steel truss girder dragging construction
CN107653781A (en) * 2017-09-20 2018-02-02 龙元建设集团股份有限公司 Big steel pipe truss and construction method for bent cap cast-in-place construction
CN207828792U (en) * 2018-01-12 2018-09-07 九冶建设有限公司 Removable support for the installation of urban steel bridges beam
CN108827672A (en) * 2018-03-29 2018-11-16 中国矿业大学 Multi-point equispaced load flexible connection space multistage distribution beam system and its implementation method
CN209703316U (en) * 2019-01-18 2019-11-29 中铁三局集团有限公司 A kind of steel truss girder platform for lining big suitable for environmental restrictions
CN110258294A (en) * 2019-04-30 2019-09-20 安徽省公路桥梁工程有限公司 Steel truss arch bridge installs system and its construction method
CN210658011U (en) * 2019-04-30 2020-06-02 安徽省公路桥梁工程有限公司 Steel truss arch bridge installation system
CN111119059A (en) * 2019-12-31 2020-05-08 四川交投建设工程股份有限公司 Ultrahigh composite support system for high-pier cast-in-place box girder and construction method
CN111139749A (en) * 2020-01-08 2020-05-12 中铁四局集团有限公司 A construction method of a large-span top-supported continuous steel truss girder cantilever frame

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
于俊英等: "《建筑结构试验》", 31 August 2003, 天津大学出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112921828A (en) * 2021-02-07 2021-06-08 中铁四局集团有限公司 Flexible landing pad device for erecting ultrahigh bearing support on cantilever of large-span railway steel truss girder bridge
CN115949079A (en) * 2022-12-26 2023-04-11 中铁四局集团有限公司 A system and method for slope protection of super-high temporary supports in mountains and valleys

Also Published As

Publication number Publication date
CN111663451B (en) 2022-04-08

Similar Documents

Publication Publication Date Title
CN108457188B (en) A walking multi-point synchronous jacking construction method
CN101935987B (en) Construction method for integrally sliding large-span steel pipe arch of curved bridge
CN112921827A (en) Construction method for hoisting large-span steel bridge box girder and hoisting and installing special-shaped component
CN103410322B (en) The parallel Truss Steel corridor construction method of large span
CN115748413B (en) Continuous steel truss web-plate truss double-layer combined swivel bridge structure
CN110387822B (en) Cast-in-situ bent cap assembly type steel pipe support and construction method thereof
CN101736697A (en) Construction method for pushing and furling complete bracket of steel box girders
CN111155383A (en) Large-span self-anchored steel box girder suspension bridge track lofting and measuring method
CN102808383A (en) Construction process for back-sloping and jacking curved bridge
CN211947993U (en) Support for large-span cast-in-situ bridge construction
CN110409624B (en) Reverse calculation and construction method for large equipment installation and main body structure
CN114134823A (en) Upper-span high-speed rail asymmetric rigid frame bridge swivel construction method
CN112854004A (en) Fish-bellied box girder column type support construction method
CN119041315A (en) Pushing construction method for large-span steel box girder bridge crossing river channel
CN115928608A (en) A reverse construction method of continuous steel truss web-plate truss double-layer combined swivel bridge
CN101122115A (en) A construction method for tower crane displacement
CN111622091B (en) Stress test method for prefabricated bridge pier
CN111663451A (en) Construction method of ultra-high towers for long-span top-up continuous steel truss bridges in alpine valleys
CN101324054A (en) Construction Method of Pushing into Place for Temporary Piers of Segmental Beams of Bridges
CN116770980A (en) Extra-long variable-height V-shaped large-span steel structure corridor and its construction method
CN114086473B (en) High pier cast-in-situ beam bracket and construction method thereof
CN114319079B (en) Double-deck steel bridge girder falling structure and girder falling method for highway bridge and railway bridge
CN115406604A (en) Steel box girder mid-span line shape and stress monitoring method
CN111535158A (en) Temporary pier for installation of box girder jacking equipment and its construction method
CN116856298A (en) Construction technology of wide-width and large-tonnage swivel T-structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant