CN115652995A - An overall construction method for a vehicle maintenance base project - Google Patents

An overall construction method for a vehicle maintenance base project Download PDF

Info

Publication number
CN115652995A
CN115652995A CN202211333561.4A CN202211333561A CN115652995A CN 115652995 A CN115652995 A CN 115652995A CN 202211333561 A CN202211333561 A CN 202211333561A CN 115652995 A CN115652995 A CN 115652995A
Authority
CN
China
Prior art keywords
construction
sections
carry out
pouring
running water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202211333561.4A
Other languages
Chinese (zh)
Other versions
CN115652995B (en
Inventor
侯海林
范东东
周六生
赵言
黄尚鑫
宋超
徐明博
王红伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rail Transit Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Rail Transit Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rail Transit Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Rail Transit Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202211333561.4A priority Critical patent/CN115652995B/en
Publication of CN115652995A publication Critical patent/CN115652995A/en
Application granted granted Critical
Publication of CN115652995B publication Critical patent/CN115652995B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明公开了一种车辆检修基地工程总体施工方法,包括步骤:进行车辆基地桩基施工;于桩基内前后均分成三个浇筑段进行浇筑,同时于相邻的两个浇筑段之间设置后浇带,浇筑施工后的三个浇筑段前后依次形成第一、第二和第三施工用的流水段;将地面泥浆、不良质土进行整体清理找平;于第一、第三流水段内进行承台、筏板开挖并施工承台及筏板;于第一、第三流水段内进行组料回填,回填至承台顶标高,并分层压实;能够提高物资周转效率,方便物料运输。

Figure 202211333561

The invention discloses an overall construction method for a vehicle maintenance base project, which comprises the steps of: carrying out the pile foundation construction of the vehicle base; dividing the front and back of the pile foundation into three pouring sections for pouring; After pouring belt, the three pouring sections after pouring construction form the first, second and third construction running water sections in sequence; the ground mud and poor quality soil are cleaned and leveled as a whole; in the first and third running water sections Carry out excavation and construction of caps and rafts; carry out group backfilling in the first and third running water sections, backfill to the elevation of the caps, and compact them in layers; it can improve the turnover efficiency of materials and facilitate material transportation.

Figure 202211333561

Description

一种车辆检修基地工程总体施工方法An overall construction method for a vehicle maintenance base project

技术领域technical field

本发明涉及建筑施工技术领域,特别涉及一种车辆检修基地工程总体施工方法。The invention relates to the technical field of building construction, in particular to an overall construction method of a vehicle maintenance base project.

背景技术Background technique

近年来,随着城市发展,地下空间工程建设快速发展,地铁越来越多,每条地铁线路都包含一座车辆检修基地,车辆检修基地工程最大的特点的单体面积较大,长度400m以上,宽度200m,以上,若采用房建类施工组织方法会存在物料因总面积过大无法运抵工作面,混凝土泵车因距离限制无法泵送至工作面等问题。目前主要采用满布塔吊通过多塔吊转运物料,采用地泵管路浇筑混凝土,型钢开孔方式解决,但是这种方法为总体施工组织带来较大困难,影响建造速度,增大人材机投入成本。In recent years, with the development of the city, the construction of underground space projects has developed rapidly, and there are more and more subways. Each subway line includes a vehicle maintenance base. The biggest feature of the vehicle maintenance base project is the large single area with a length of more than 400m. With a width of 200m or more, if the construction organization method of housing construction is adopted, there will be problems such as the materials cannot be transported to the working face due to the large total area, and the concrete pump truck cannot be pumped to the working face due to the distance limitation. At present, it is mainly used to transfer materials through multi-tower cranes with full-covered tower cranes, and it is solved by pouring concrete with ground pump pipelines and opening holes in section steel. However, this method brings great difficulties to the overall construction organization, affects the construction speed, and increases the input cost of manpower and machinery. .

发明内容Contents of the invention

本发明的目的在于提供一种车辆检修基地工程总体施工方法,能够提高物资周转效率,方便物料运输。The purpose of the present invention is to provide an overall construction method of a vehicle maintenance base project, which can improve material turnover efficiency and facilitate material transportation.

根据本发明提供的一种车辆检修基地工程总体施工方法,包括步骤:According to the overall construction method of a vehicle maintenance base project provided by the present invention, it comprises steps:

进行车辆基地桩基施工;Carry out the pile foundation construction of the vehicle base;

于桩基内前后均分成三个浇筑段进行浇筑,同时于相邻的两个浇筑段之间设置后浇带,浇筑施工后的三个浇筑段前后依次形成第一、第二和第三施工用的流水段;The pile foundation is divided into three pouring sections before and after pouring, and a post-casting belt is set between two adjacent pouring sections at the same time. The three pouring sections after pouring construction form the first, second and third construction sections in sequence The running water section used;

将地面泥浆、不良质土进行整体清理找平;Overall cleaning and leveling of ground mud and poor quality soil;

于第一、第三流水段内进行承台、筏板开挖并施工承台及筏板;Excavate caps and rafts in the first and third water sections and construct caps and rafts;

于第一、第三流水段内进行组料回填,回填至承台顶标高,并分层压实;Carry out group material backfilling in the first and third running water sections, backfill to the level of the cap top, and compact in layers;

于第一、第三流水段内的承台面搭设墙柱操作架;Set up a wall column operation frame on the platform surface in the first and third running water sections;

于第一、第三流水段内进行第一节墙柱施工,同步进行第二流水段内承台和筏板的开挖及施工;Carry out the construction of the first wall column in the first and third running water sections, and simultaneously carry out the excavation and construction of the inner cap and raft in the second running water section;

于第一、第三流水段内继续进行柱墙操作架搭设,进行第二节墙柱施工,同时于第二流水段内进行柱墙操作架搭设、墙柱施工及组料回填;In the first and third flow sections, continue to erect the column wall operation frame, carry out the second section wall column construction, and at the same time carry out the column wall operation frame erection, wall column construction and group material backfill in the second flow section;

于第一、第三流水段内进行顶板施工,第二流水段进行第二节柱墙操作架搭设及墙柱施工;The roof construction is carried out in the first and third flow sections, and the second column wall operation frame erection and wall column construction are carried out in the second flow section;

于第二流水段内将剩余柱墙操作架搭设完成;Complete the erection of the remaining column wall operation frame in the second flow section;

于第二流水段内进行分段顶板浇筑作业;Carry out segmental roof pouring operations in the second flow section;

检查楼板强度是否达到要求,符合要求后进行墙柱操作架拆除,拆除完成后进行CFG桩开挖,进行桩帽及褥垫层施工;Check whether the strength of the floor slab meets the requirements. After meeting the requirements, remove the wall column operation frame. After the removal is completed, excavate the CFG piles and carry out pile cap and mattress construction;

进行检修坑施工及后续回填作业。Carry out maintenance pit construction and subsequent backfilling operations.

在桩基混凝土浇筑过程中,因设计要求或施工需要分段浇筑,而在先、后浇筑的混凝土之间预留后浇带,于桩基内均分六大施工用的流水段,依次进行分段施工,能够大大提高整体施工效率。During the concrete pouring process of the pile foundation, due to design requirements or construction needs to be poured in sections, a post-pouring belt is reserved between the concrete poured first and later, and six construction flow sections are evenly divided into six construction flow sections in the pile foundation, which are carried out sequentially. Sectional construction can greatly improve the overall construction efficiency.

进一步的,于第二流水段内施工设置一条用于物料运输的临时道路。Further, a temporary road for material transportation is constructed and set up in the second running water section.

预留临时通道,其他流水段在施工时可借此进行物料运输,以此可以提高物料运输的效率,提高整体施工的速度。Temporary channels are reserved for other flow sections to carry out material transportation during construction, which can improve the efficiency of material transportation and increase the speed of overall construction.

进一步的,所述组料回填采用细粒土含量大于30%的土体进行回填。Further, the backfilling of the group materials is backfilling with soil with a fine-grained soil content greater than 30%.

细粒土含量大于30%的土体即普通的土,其来源丰富,容易获得,能够大大降低施工成本。The soil with a fine-grained soil content greater than 30% is ordinary soil, which is rich in sources and easy to obtain, which can greatly reduce construction costs.

附图说明Description of drawings

为了更清楚地说明本发明实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings that need to be used in the description of the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present invention. For those skilled in the art, other drawings can also be obtained based on these drawings without creative effort.

图1为本发明于桩基内前后均分成三个浇筑段进行浇筑的结构平面图;Fig. 1 is the structure plan view that the present invention is divided into three pouring sections before and after in the pile foundation and pours;

图2为本发明于第一、第三流水段内进行承台、筏板开挖并施工承台及筏板后的结构平面图;Fig. 2 is the structural plan view of the present invention after the excavation of caps and rafts in the first and third running water sections and construction of caps and rafts;

图3为本发明于第一、第三流水段内进行组料回填,回填至承台顶标高,并分层压实后的结构平面图;Fig. 3 is a plan view of the structure of the present invention after backfilling the first and third running water sections, backfilling to the elevation of the cap top, and compacting in layers;

图4为本发明于第一、第三流水段内进行第一节墙柱施工,同步进行第二流水段内承台和筏板的开挖及施工后的结构平面图;Fig. 4 is the structural plan view of the present invention after carrying out the construction of the first wall column in the first and third flow sections, and simultaneously carrying out the excavation and construction of the cap platform and the raft in the second flow section;

图5为本发明于第一、第三流水段内进行第二节墙柱施工,同时于第二流水段内进行柱墙操作架搭设、墙柱施工及组料回填后的结构平面图;Fig. 5 is the structure plan view of the present invention after carrying out the construction of the second section of wall columns in the first and third flow sections, and at the same time erecting the column wall operation frame, construction of the wall columns and backfilling of the group materials in the second flow section;

图6为本发明于第一、第三流水段内进行顶板施工,第二流水段进行第二节柱墙操作架搭设及墙柱施工后的结构平面图;Fig. 6 is the structure plan view of the present invention after the roof construction is carried out in the first and third flow sections, and the second section column wall operation frame is erected and the wall column construction is carried out in the second flow section;

图7为本发明于第二流水段内将剩余柱墙操作架搭设完成后的结构平面图。Fig. 7 is a structural plan view of the present invention after erecting the remaining column wall operating frame in the second flow section.

图中,1-第一流水段;2-第二流水段;3-第三流水段;4-承台;5-筏板;6-柱墙操作架。In the figure, 1-the first flow section; 2-the second flow section; 3-the third flow section; 4-cap; 5-raft; 6-column wall operation frame.

具体实施方式Detailed ways

下面结合附图对本发明的具体实施方式作进一步说明。在此需要说明的是,对于这些实施方式的说明用于帮助理解本发明,但并不构成对本发明的限定。此外,下面所描述的本发明各个实施方式中所涉及的技术特征只要彼此之间未构成冲突就可以相互组合。The specific embodiments of the present invention will be further described below in conjunction with the accompanying drawings. It should be noted here that the descriptions of these embodiments are used to help understand the present invention, but are not intended to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below may be combined with each other as long as they do not constitute a conflict with each other.

参见图1,示出了本发明的一种车辆检修基地工程总体施工方法,包括步骤:Referring to Fig. 1, a kind of overall construction method of vehicle overhaul base project of the present invention is shown, comprises steps:

进行车辆基地桩基施工;Carry out the pile foundation construction of the vehicle base;

于桩基内前后均分成三个浇筑段进行浇筑,同时于相邻的两个浇筑段之间设置后浇带,浇筑施工后的三个浇筑段前后依次形成第一、第二和第三施工用的流水段;The pile foundation is divided into three pouring sections before and after pouring, and a post-casting belt is set between two adjacent pouring sections at the same time. The three pouring sections after pouring construction form the first, second and third construction sections in sequence The running water section used;

将地面泥浆、不良质土进行整体清理找平;Overall cleaning and leveling of ground mud and poor quality soil;

于第一、第三流水段内进行承台、筏板开挖并施工承台及筏板;Excavate caps and rafts in the first and third water sections and construct caps and rafts;

于第一、第三流水段内进行组料回填,回填至承台顶标高,并分层压实;Carry out group material backfilling in the first and third running water sections, backfill to the level of the cap top, and compact in layers;

于第一、第三流水段内的承台面搭设墙柱操作架;Set up a wall column operation frame on the platform surface in the first and third running water sections;

于第一、第三流水段内进行第一节墙柱施工,同步进行第二流水段内承台和筏板的开挖及施工;Carry out the construction of the first wall column in the first and third running water sections, and simultaneously carry out the excavation and construction of the inner cap and raft in the second running water section;

于第一、第三流水段内继续进行柱墙操作架搭设,进行第二节墙柱施工,同时于第二流水段内进行柱墙操作架搭设、墙柱施工及组料回填;In the first and third flow sections, continue to erect the column wall operation frame, carry out the second section wall column construction, and at the same time carry out the column wall operation frame erection, wall column construction and group material backfill in the second flow section;

于第一、第三流水段内进行顶板施工,第二流水段进行第二节柱墙操作架搭设及墙柱施工;The roof construction is carried out in the first and third flow sections, and the second column wall operation frame erection and wall column construction are carried out in the second flow section;

于第二流水段内将剩余柱墙操作架搭设完成;Complete the erection of the remaining column wall operation frame in the second flow section;

于第二流水段内进行分段顶板浇筑作业;Carry out segmental roof pouring operations in the second flow section;

检查楼板强度是否达到要求,符合要求后进行墙柱操作架拆除,拆除完成后进行CFG桩开挖,进行桩帽及褥垫层施工;Check whether the strength of the floor slab meets the requirements. After meeting the requirements, remove the wall column operation frame. After the removal is completed, excavate the CFG piles and carry out pile cap and mattress construction;

进行检修坑施工及后续回填作业。Carry out maintenance pit construction and subsequent backfilling operations.

在桩基混凝土浇筑过程中,因设计要求或施工需要分段浇筑,每个浇筑段之间预留有后浇带,前后依次划分为第一、第二、第三流水段,三个流水段分段施工,能够大大提高整体施工效率,在本实施例中,浇筑总长为240米,每段的浇筑设计长度为40米,均分为六段浇筑段,后浇带为80公分,前三段和后三段浇筑段施工完全相同,因而整体可以分成两步施工,前三段和后三段可以先后按照上述施工方法进行施工,因此,上述施工方法不仅仅局限于划分三段流水段进而进行施工,也适用于其他任一可以采用上述分段施工的场景之中。During the pile foundation concrete pouring process, due to the design requirements or construction needs to be poured in sections, a post-casting zone is reserved between each pouring section, and the front and back are divided into the first, second, and third flow sections in turn, and the three flow sections Sectional construction can greatly improve the overall construction efficiency. In this embodiment, the total pouring length is 240 meters, and the pouring design length of each section is 40 meters. The construction of the pouring section and the last three sections is exactly the same, so the whole can be divided into two-step construction, and the first three sections and the last three sections can be constructed successively according to the above construction method. Therefore, the above construction method is not limited to dividing the three sections of flowing water and Construction is also applicable to any other scene where the above-mentioned segmented construction can be used.

于第二流水段内施工设置一条用于物料运输的临时道路,将第二流水段内设置道路作为临时通道,其他流水段在施工时可借此进行物料运输,以此可以提高物料运输的效率,提高整体施工的速度,作为本发明优选的实施例,所述临时道路采用20cm厚级配即20cm厚度的级配碎石垫层。A temporary road for material transportation is set up in the second flow section, and the road in the second flow section is used as a temporary passage, which can be used for material transportation in other flow sections during construction, so as to improve the efficiency of material transportation , improve the overall construction speed, as a preferred embodiment of the present invention, the temporary road adopts 20cm thick gradation, that is, a 20cm thick gradation crushed stone cushion.

所述组料回填采用细粒土含量大于30%的土体进行回填,细粒土含量大于30%即普通的土,其来源丰富,容易获得,能够大大降低施工成本。The backfilling of the group materials uses soil with a fine-grained soil content greater than 30% for backfilling. The fine-grained soil content is greater than 30%, that is, ordinary soil, which has abundant sources and is easy to obtain, which can greatly reduce construction costs.

在本发明的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should be noted that unless otherwise specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection. Connected, or integrally connected; it can be directly connected, or indirectly connected through an intermediary, and it can be the internal communication of two elements. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention in specific situations.

在本发明的描述中,需要理解的是,术语“上”、“下”、“竖直”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that the orientation or positional relationship indicated by the terms "upper", "lower", "vertical", "inner", "outer" etc. is based on the orientation or position shown in the drawings The relationship is only for the convenience of describing the present invention and simplifying the description, but does not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as a limitation of the present invention.

术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。The terms "first" and "second" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance or implicitly specifying the quantity of indicated technical features. Thus, a feature defined as "first" and "second" may explicitly or implicitly include one or more of these features.

以上结合附图对本发明的实施方式作了详细说明,但本发明不限于所描述的实施方式。对于本领域的技术人员而言,在不脱离本发明原理和精神的情况下,对这些实施方式进行多种变化、修改、替换和变型,仍落入本发明的保护范围内。The embodiments of the present invention have been described in detail above with reference to the accompanying drawings, but the present invention is not limited to the described embodiments. For those skilled in the art, without departing from the principle and spirit of the present invention, various changes, modifications, substitutions and modifications to these embodiments still fall within the protection scope of the present invention.

Claims (3)

1.一种车辆检修基地工程总体施工方法,其特征在于,包括步骤:1. A vehicle overhaul base engineering general construction method, is characterized in that, comprises steps: 进行车辆基地桩基施工;Carry out the pile foundation construction of the vehicle base; 于桩基内前后均分成三个浇筑段进行浇筑,同时于相邻的两个浇筑段之间设置后浇带,浇筑施工后的三个浇筑段前后依次形成第一、第二和第三施工用的流水段;The pile foundation is divided into three pouring sections before and after pouring, and a post-casting belt is set between two adjacent pouring sections at the same time. The three pouring sections after pouring construction form the first, second and third construction sections in sequence The running water section used; 将地面泥浆、不良质土进行整体清理找平;Overall cleaning and leveling of ground mud and poor quality soil; 于第一、第三流水段内进行承台、筏板开挖并施工承台及筏板;Excavate caps and rafts in the first and third water sections and construct caps and rafts; 于第一、第三流水段内进行组料回填,回填至承台顶标高,并分层压实;Carry out group material backfilling in the first and third running water sections, backfill to the level of the cap top, and compact in layers; 于第一、第三流水段内的承台面搭设墙柱操作架;Set up a wall column operation frame on the platform surface in the first and third running water sections; 于第一、第三流水段内进行第一节墙柱施工,同步进行第二流水段内承台和筏板的开挖及施工;Carry out the construction of the first wall column in the first and third running water sections, and simultaneously carry out the excavation and construction of the inner cap and raft in the second running water section; 于第一、第三流水段内继续进行柱墙操作架搭设,进行第二节墙柱施工,同时于第二流水段内进行柱墙操作架搭设、墙柱施工及组料回填;In the first and third flow sections, continue to erect the column wall operation frame, carry out the second section wall column construction, and at the same time carry out the column wall operation frame erection, wall column construction and group material backfill in the second flow section; 于第一、第三流水段内进行顶板施工,第二流水段进行第二节柱墙操作架搭设及墙柱施工;The roof construction is carried out in the first and third flow sections, and the second column wall operation frame erection and wall column construction are carried out in the second flow section; 于第二流水段内将剩余柱墙操作架搭设完成;Complete the erection of the remaining column wall operation frame in the second flow section; 于第二流水段内进行分段顶板浇筑作业;Carry out segmental roof pouring operations in the second flow section; 检查楼板强度是否达到要求,符合要求后进行墙柱操作架拆除,拆除完成后进行CFG桩开挖,进行桩帽及褥垫层施工;Check whether the strength of the floor slab meets the requirements. After meeting the requirements, remove the wall column operation frame. After the removal is completed, excavate the CFG piles and carry out pile cap and mattress construction; 进行检修坑施工及后续回填作业。Carry out maintenance pit construction and subsequent backfilling operations. 2.根据权利要求1所述的车辆检修基地工程总体施工方法,其特征在于,于第二流水段内施工设置一条用于物料运输的临时道路。2. The overall construction method of the vehicle maintenance base project according to claim 1, characterized in that a temporary road for material transportation is set up in the second flow section. 3.根据权利要求1所述的车辆检修基地工程总体施工方法,其特征在于,所述组料回填采用细粒土含量大于30%的土体进行回填。3. The overall construction method of the vehicle maintenance base project according to claim 1, characterized in that, the backfilling of the set of materials is carried out with soil with a fine-grained soil content greater than 30%.
CN202211333561.4A 2022-10-28 2022-10-28 Overall construction method for vehicle overhaul base engineering Active CN115652995B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211333561.4A CN115652995B (en) 2022-10-28 2022-10-28 Overall construction method for vehicle overhaul base engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211333561.4A CN115652995B (en) 2022-10-28 2022-10-28 Overall construction method for vehicle overhaul base engineering

Publications (2)

Publication Number Publication Date
CN115652995A true CN115652995A (en) 2023-01-31
CN115652995B CN115652995B (en) 2025-09-19

Family

ID=84992885

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211333561.4A Active CN115652995B (en) 2022-10-28 2022-10-28 Overall construction method for vehicle overhaul base engineering

Country Status (1)

Country Link
CN (1) CN115652995B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2632705A1 (en) * 1988-06-09 1989-12-15 Matiere Marcel Tubular duct
US5468098A (en) * 1993-07-19 1995-11-21 Babcock; John W. Segmental, anchored, vertical precast retaining wall system
US6234716B1 (en) * 1995-11-17 2001-05-22 Carlo Chiaves Underground structural work including prefabricated elements associated with piles and a process for its production
CN1982546A (en) * 2005-12-12 2007-06-20 上海市第七建筑有限公司 Direct local skirt border reversing construction for central island
CN203429661U (en) * 2013-04-02 2014-02-12 东南大学 Basement with additional downward layers
WO2016156778A1 (en) * 2015-04-01 2016-10-06 Russell Harrison Limited Modular building
CN106065668A (en) * 2016-08-01 2016-11-02 中建八局第四建设有限公司 A kind of construction techniques
CN111622263A (en) * 2020-04-22 2020-09-04 上海二十冶建设有限公司 Comprehensive pipe gallery construction method based on composite material combined type template system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2632705A1 (en) * 1988-06-09 1989-12-15 Matiere Marcel Tubular duct
US5468098A (en) * 1993-07-19 1995-11-21 Babcock; John W. Segmental, anchored, vertical precast retaining wall system
US6234716B1 (en) * 1995-11-17 2001-05-22 Carlo Chiaves Underground structural work including prefabricated elements associated with piles and a process for its production
CN1982546A (en) * 2005-12-12 2007-06-20 上海市第七建筑有限公司 Direct local skirt border reversing construction for central island
CN203429661U (en) * 2013-04-02 2014-02-12 东南大学 Basement with additional downward layers
WO2016156778A1 (en) * 2015-04-01 2016-10-06 Russell Harrison Limited Modular building
CN106065668A (en) * 2016-08-01 2016-11-02 中建八局第四建设有限公司 A kind of construction techniques
CN111622263A (en) * 2020-04-22 2020-09-04 上海二十冶建设有限公司 Comprehensive pipe gallery construction method based on composite material combined type template system

Also Published As

Publication number Publication date
CN115652995B (en) 2025-09-19

Similar Documents

Publication Publication Date Title
JP2024037138A (en) Construction method of large-span station with open wings and semi-top-down excavation and semi-reverse drilling
CN106088650B (en) A kind of method and building suitable for building with brick-concrete structure underground increasing layer
CN105544575B (en) A kind of bottom concrete construction method under water of use steel truss reinforcement
CN106761768B (en) A kind of steel pipe curtain structure support system and its construction method
CN113062354A (en) Assembly method for prefabricated subway station of open-cut pile support system
CN206545215U (en) A kind of precast spliced sinking type garage parking
CN104234082A (en) Jump-layer reversed construction method for deep foundation pit
CN112095626A (en) Foundation pit supporting structure serving as corridor underpinning pile foundation and construction method thereof
CN115288694A (en) A method for controlling the deformation of subway tunnels by ultra-short-range excavation above the subway
CN104652444A (en) Construction method for overall reverse operation of ultra-large type deep foundation pit center island type alternative earth excavation
CN101498133B (en) The Method and Supporting Structure of Enlarging the Excavation Space of Basement with Top-down Method
CN211172070U (en) Assembled type suspended wall retaining wall structure of reinforced concrete member
CN216407913U (en) A water intake pipe jacking structure crossing the Linjiang Railway
CN113790054B (en) Multifunctional push pipe fitted with tunnel section
CN115012982A (en) A water-passing box culvert structure and construction method spanning the subway shield section and overlapping with the tunnel
CN112726624B (en) Efficient excavation construction method for deep foundation pit
CN217601487U (en) Dredging well plugging construction node
CN115652995A (en) An overall construction method for a vehicle maintenance base project
CN218911435U (en) A Supporting Structure for the Cover Plate of Half-cover Excavated Foundation Pit Applicable to Non-horizontal Terrain Conditions
CN102518142B (en) Pile-wall integrated water-stop system and its construction method
CN110331654A (en) A kind of bridge structure and its construction method that space is stacked
CN113293766B (en) Comprehensive earth excavation method for large-scale cover-excavation top-down T-shaped transfer subway station
CN115492069A (en) A combined water drilling platform system and its construction method
CN108708309A (en) A kind of the rectangular channel structure and its installation method of precast assembly
CN207143970U (en) A kind of foundation pit enclosure stake

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant