CN118564105A - Method for rebuilding newly-added floor slab when interference exists in original bearing outer wall - Google Patents

Method for rebuilding newly-added floor slab when interference exists in original bearing outer wall Download PDF

Info

Publication number
CN118564105A
CN118564105A CN202411049995.0A CN202411049995A CN118564105A CN 118564105 A CN118564105 A CN 118564105A CN 202411049995 A CN202411049995 A CN 202411049995A CN 118564105 A CN118564105 A CN 118564105A
Authority
CN
China
Prior art keywords
wall
floor slab
newly
layer
old building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202411049995.0A
Other languages
Chinese (zh)
Other versions
CN118564105B (en
Inventor
张莉莉
陈达非
王亮
赵来柱
王杨
杨化军
王磊
姚俊琴
李汀滢
孙汉霖
李萌
苏婕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jinyu Xingfa Technology Co ltd
Beijing Fourth Construction & Engineering Co ltd
Original Assignee
Beijing Jinyu Xingfa Technology Co ltd
Beijing Fourth Construction & Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jinyu Xingfa Technology Co ltd, Beijing Fourth Construction & Engineering Co ltd filed Critical Beijing Jinyu Xingfa Technology Co ltd
Priority to CN202411049995.0A priority Critical patent/CN118564105B/en
Publication of CN118564105A publication Critical patent/CN118564105A/en
Application granted granted Critical
Publication of CN118564105B publication Critical patent/CN118564105B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00—Working measures on existing buildings
    • E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0266—Enlarging
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00—Working measures on existing buildings
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00—Working measures on existing buildings
    • E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00—Working measures on existing buildings
    • E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明涉及对现有建筑物的施工措施技术领域,公开了一种原有承重外墙存在干涉时的新增楼板改建方法,本发明中,通过把旧建筑改建所需要开的门窗洞都集中在一起,形成竖条状的跨层门窗洞,提供了各层施工所需要的施工洞的同时最小化了对旧建筑外墙承载能力的破坏,且可用少量的过梁和暗柱来克服开洞造成的影响,从而克服了旧建筑外墙对内部大改施工造成的干涉;通过贴靠旧建筑外墙施工一层新增可靠层作为新的承重墙,新增可靠层能可靠地承载新增的楼板,且有能够与新增楼板可靠连接的接口,还拉住了旧承重墙防止其倒塌,同时使旧承重墙无须翻新防水结构。

The invention relates to the technical field of construction measures for existing buildings, and discloses a method for rebuilding a new floor slab when interference exists in an original load-bearing outer wall. In the invention, all the door and window holes required for rebuilding an old building are gathered together to form vertical cross-layer door and window holes, thereby providing the construction holes required for the construction of each layer and minimizing the damage to the bearing capacity of the outer wall of the old building. A small amount of lintels and hidden columns can be used to overcome the influence caused by the opening of the holes, thereby overcoming the interference caused by the outer wall of the old building on the major internal reconstruction construction. A new reliable layer is constructed close to the outer wall of the old building as a new load-bearing wall, the new reliable layer can reliably bear the new floor slab, has an interface that can be reliably connected to the new floor slab, and also holds the old load-bearing wall to prevent it from collapsing, and at the same time, the waterproof structure of the old load-bearing wall does not need to be renovated.

Description

一种原有承重外墙存在干涉时的新增楼板改建方法A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall

技术领域Technical Field

本发明涉及对现有建筑物的施工措施技术领域,特别是涉及一种原有承重外墙存在干涉时的新增楼板改建方法。The invention relates to the technical field of construction measures for existing buildings, and in particular to a method for rebuilding a new floor slab when interference exists in an original load-bearing exterior wall.

背景技术Background Art

绝大部分旧建筑的归宿是被拆除后腾出空地用于修建新建筑,但存在一些有特殊意义的旧建筑,需要在保留其原貌的前提下改变建筑用途,为此需要对建筑进行深度改造。The fate of most old buildings is to be demolished to make way for the construction of new buildings, but there are some old buildings with special significance that need to be changed in use while retaining their original appearance, which requires in-depth renovation of the buildings.

考虑到旧建筑本身已发生严重的老化,其结构强度严重下降,且外观已非常破旧。这些问题难以在不对建筑本身进行深度改造的前提下解决,因此对旧建筑的改造往往需要采用拆为零件后重新组装的形式进行,拆为零件的过程中可对建筑零件分别进行检测并更换其中强度不达标或破损严重的零件,并在内部进行补强处理或改变建筑内部布局,从而适应建筑用途的变化。Considering that the old building itself has been seriously aged, its structural strength has seriously declined, and its appearance has become very dilapidated. These problems are difficult to solve without deep transformation of the building itself. Therefore, the transformation of old buildings often needs to be carried out in the form of dismantling into parts and reassembling. During the dismantling process, the building parts can be tested separately and the parts that do not meet the strength standards or are seriously damaged can be replaced. The internal reinforcement treatment or the internal layout of the building can be changed to adapt to the changes in the building's use.

但若旧建筑主要靠承重墙来承载的话,这种施工方式并不适用。无论是钢筋混凝土材质的承重墙还是砌体结构的承重墙,均无法在不造成破坏的前提下被拆为零件。此时旧建筑的承重墙对于建筑内部改建而言,已经不是一种可以利用的资源,而是一种深重的负担。因为建筑内部的改建势必要涉及到布局以及荷载的变更。但这种承重墙本身由于时间的关系,存在各种各样的缺陷,不仅受力上不可靠,而且防水上亦不可靠。因此不仅不能把新增的荷载交由旧承重墙来承载,而且还需要对旧承重墙进行修补。其次,即使不想依靠旧承重墙,而是在建筑内新设置其他的承重构件来承载建筑内新增的荷载,这些旧承重墙还会阻挡包括承重构件在内的大尺寸建筑构件(梁、柱、型钢、钢筋、板等)进出建筑内部。而如果旧建筑本身是仓储性质的建筑类型,该问题还会更加严重(这种建筑上的洞少且小)。However, if the old building mainly relies on load-bearing walls to bear the load, this construction method is not applicable. Whether it is a load-bearing wall made of reinforced concrete or a load-bearing wall of masonry structure, it cannot be dismantled into parts without causing damage. At this time, the load-bearing wall of the old building is no longer a resource that can be used for the reconstruction of the interior of the building, but a heavy burden. Because the reconstruction of the interior of the building will inevitably involve changes in layout and load. However, due to the relationship of time, this load-bearing wall itself has various defects. It is not only unreliable in force, but also unreliable in waterproofing. Therefore, not only can the new load not be carried by the old load-bearing wall, but the old load-bearing wall also needs to be repaired. Secondly, even if you do not want to rely on the old load-bearing wall, but also set up other load-bearing components in the building to bear the new load in the building, these old load-bearing walls will also block large-sized building components (beams, columns, steel, steel bars, plates, etc.) including load-bearing components from entering and exiting the building. If the old building itself is a storage building type, the problem will be even more serious (there are few and small holes in this kind of building).

以本发明涉及的北京怀柔科学城北区金隅兴发科技园项目为例,该项目所在地为兴发水泥厂,兴建于90年代初,为北京的城建贡献了大量的建材,是一处重要的工业遗址。因此,该处的建筑需要在保留外形的情况下改造为附近北京雁栖湖应用数学研究院的研究设施。其中的水泥筒仓需要改造为专家住宅楼。水泥筒仓的层高对于住宅而言过大(接近20米高,会使住户无法装修天花板)且过于浪费,需要在内部新增几层楼板。该水泥筒仓原有的物料洞口不允许运入建筑内部大概所需要用到的大尺寸建筑构件,也不允许混凝土泵管就近进入到浇筑面,本身不能可靠地承载新增的楼板,更没有能够与新增楼板可靠连接的接口。Taking the Jinyu Xingfa Science Park project in the northern area of Beijing Huairou Science City as an example, the project site is the Xingfa Cement Factory, which was built in the early 1990s and contributed a large amount of building materials to Beijing's urban construction. It is an important industrial heritage site. Therefore, the buildings there need to be transformed into research facilities of the nearby Beijing Yanqi Lake Institute of Applied Mathematics while retaining their appearance. The cement silo needs to be transformed into an expert residential building. The floor height of the cement silo is too large for a residence (close to 20 meters high, which will make it impossible for residents to decorate the ceiling) and is too wasteful, so several floors need to be added inside. The original material opening of the cement silo does not allow the large-sized building components that are probably needed inside the building to be transported in, nor does it allow the concrete pump pipe to enter the casting surface nearby. It cannot reliably carry the newly added floor slabs, and there is no interface that can be reliably connected to the newly added floor slabs.

发明内容Summary of the invention

本发明提供一种原有承重外墙存在干涉时的新增楼板改建方法。The invention provides a method for rebuilding a new floor slab when interference exists in an original load-bearing exterior wall.

解决的技术问题是:旧建筑外墙为承重墙时,建筑内部新增楼板等大改施工会受到外墙的干涉,同时旧建筑外墙既不能有效承载新增构件,也不能与新增构件有效连接。The technical problem to be solved is: when the exterior walls of an old building are load-bearing walls, major renovations such as new floor slabs inside the building will be interfered with by the exterior walls. At the same time, the exterior walls of the old building can neither effectively bear the newly added components nor effectively connect with the newly added components.

为解决上述技术问题,本发明采用如下技术方案:一种原有承重外墙存在干涉时的新增楼板改建方法,用于在旧建筑的外墙均为承重墙时克服外墙对施工的干涉在旧建筑内新增楼板,包括以下步骤:In order to solve the above technical problems, the present invention adopts the following technical solutions: a method for rebuilding a new floor slab when there is interference with the original load-bearing external walls, which is used to overcome the interference of the external walls on the construction and add a new floor slab in the old building when the external walls of the old building are all load-bearing walls, comprising the following steps:

步骤一:规划旧建筑改造后的门窗位置,将门窗集中在跨层门窗洞中,所述跨层门窗洞满足以下条件:Step 1: Plan the doors and windows positions after the renovation of the old building, and concentrate the doors and windows in the cross-layer door and window openings, which meet the following conditions:

条件1.1:设置在旧建筑无遮挡的侧面;Condition 1.1: Set up on the unobstructed side of the old building;

条件1.2:顶部高于最高的新增楼板,且顶部与最高的新增楼板之间的间隙能够容纳至少一扇门与一扇窗;底部低于最低的新增楼板,且底部与最低的新增楼板之间的间隙能够容纳至少一根混凝土泵管;Condition 1.2: The top is higher than the highest new floor slab, and the gap between the top and the highest new floor slab can accommodate at least one door and one window; the bottom is lower than the lowest new floor slab, and the gap between the bottom and the lowest new floor slab can accommodate at least one concrete pump pipe;

步骤二:在跨层门窗洞顶部开槽施工过梁,所述过梁两端落在跨层门窗洞左右两侧开槽后施工新增暗柱上;Step 2: A lintel is constructed by cutting a groove at the top of the cross-layer door and window opening, and the two ends of the lintel fall on the newly added hidden columns after the grooves are cut on the left and right sides of the cross-layer door and window opening;

步骤三:在旧建筑外墙上切割出跨层门窗洞;Step 3: Cut out cross-layer door and window holes on the exterior wall of the old building;

步骤四:剔凿旧建筑的外墙内壁面;然后贴靠外墙施工新增可靠层,所述新增可靠层为满足以下条件的承重墙:Step 4: Chisel the inner wall of the exterior wall of the old building; then construct a new reliable layer close to the exterior wall. The new reliable layer is a load-bearing wall that meets the following conditions:

条件4.1:与旧建筑的外墙固定连接为一体;Condition 4.1: Fixedly connected to the exterior wall of the old building;

条件4.2:预留有用于安装新增楼板的接口;Condition 4.2: An interface is reserved for installing the new floor slab;

条件4.3:可在旧建筑外墙不存在的前提下稳定存在;Condition 4.3: Can be stable without the existing exterior wall of the old building;

条件4.4:防水;Condition 4.4: Waterproof;

步骤五:自下而上逐层在新增可靠层上安装新增楼板。Step 5: Install new floor slabs on the newly added reliable layer layer by layer from bottom to top.

进一步,若旧建筑有多个且成排设置,则在步骤四的施工开始前,预先在成排的旧建筑一侧安装外挑施工连廊,且步骤一规划的跨层门窗洞中,每个旧建筑都至少有一个跨层门窗洞通向外挑施工连廊;旧建筑改造完成后的装修阶段,所述外挑施工连廊外包玻璃幕墙与顶棚,形成供住户使用的走廊。Furthermore, if there are multiple old buildings and they are arranged in a row, then before the construction of step 4 begins, an externally projecting construction corridor is installed on one side of the row of old buildings in advance, and among the cross-layer door and window openings planned in step 1, each old building has at least one cross-layer door and window opening leading to the externally projecting construction corridor; during the decoration stage after the renovation of the old buildings is completed, the externally projecting construction corridor is covered with glass curtain walls and ceilings to form a corridor for use by residents.

进一步,所述新增楼板的钢筋穿透新增可靠层植入到旧建筑的外墙中。Furthermore, the steel bars of the newly added floor slab penetrate the newly added reliable layer and are implanted into the outer wall of the old building.

进一步,步骤四包含如下分步骤:Further, step 4 includes the following sub-steps:

步骤4.1:剔凿旧建筑的外墙内壁面;Step 4.1: Chisel the inner wall of the old building's exterior wall;

步骤4.2:在旧建筑的外墙内壁面上植入新增楼板的甩筋,所述甩筋穿过新增可靠层延伸到旧建筑内部;Step 4.2: implanting the reinforcement of the newly added floor slab on the inner wall surface of the outer wall of the old building, wherein the reinforcement passes through the newly added reliable layer and extends to the interior of the old building;

步骤4.3:绑扎新增可靠层的钢筋笼,并在新增楼板位置下方安装用于和新增楼板的梁连接的预埋件,所述新增楼板的梁相互连接为网格状;Step 4.3: Tie up the steel cage of the newly added reliable layer, and install embedded parts for connecting with the beams of the newly added floor below the position of the newly added floor, wherein the beams of the newly added floor are connected to each other in a grid shape;

步骤4.4:浇筑新增可靠层的混凝土,浇筑时在新增楼板位置预留内表面为毛面的凹槽;Step 4.4: Pour the concrete of the newly added reliable layer, and reserve a groove with a rough inner surface at the location of the newly added floor slab during pouring;

步骤五每层新增楼板的施工过程如下:Step 5 The construction process of each new floor slab is as follows:

安装新增楼板的梁——绑扎新增楼板的钢筋笼并与步骤4.2的甩筋固定连接——浇筑混凝土。Install the beams of the new floor slab - tie the reinforcement cage of the new floor slab and fix it with the reinforcement in step 4.2 - pour concrete.

进一步,所述新增可靠层为钢筋混凝土剪力墙,且在新增楼板下方向外突出形成用于承托新增楼板边沿的环梁,所述环梁中以及新增楼板边沿中设置有绕整个旧建筑一周的连续钢筋或型钢。Furthermore, the newly added reliable layer is a reinforced concrete shear wall, and a ring beam is protruded outward from the bottom of the newly added floor to support the edge of the newly added floor. Continuous steel bars or steel sections are arranged in the ring beam and the edge of the new floor, which surround the entire old building.

进一步,所述跨层门窗洞中,所有门窗均沿竖直方向排列;且同一楼层的门窗中,自上而下分别为通风用的百叶窗、采光用到玻璃窗、以及通行用的门。Furthermore, in the cross-layer door and window openings, all doors and windows are arranged in the vertical direction; and in the doors and windows on the same floor, from top to bottom, there are shutters for ventilation, glass windows for lighting, and doors for passage.

进一步,在步骤二施工前,检查并修补旧建筑的外墙表面混凝土的缺陷;其中,裂缝灌浆修补,裂缝之外的缺陷采用剔凿缺陷部位形成V形槽后填补新混凝土的方式修补。Furthermore, before the construction of step 2, the defects of the concrete on the outer wall surface of the old building are checked and repaired; cracks are repaired by grouting, and defects other than cracks are repaired by chiseling the defective parts to form V-shaped grooves and then filling them with new concrete.

本发明一种原有承重外墙存在干涉时的新增楼板改建方法与现有技术相比,具有如下有益效果:Compared with the prior art, the method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall of the present invention has the following beneficial effects:

本发明中,通过把旧建筑改建所需要开的门窗洞都集中在一起,形成竖条状的跨层门窗洞(这种洞允许各种大尺寸的梁/板/柱进入,内部浇筑混凝土用的泵管也可以沿着洞上下滑动到任何位置),提供了各层施工所需要的施工洞的同时最小化了对旧建筑外墙承载能力的破坏,且可用少量的过梁和暗柱来克服开洞造成的影响,从而克服了旧建筑外墙对内部大改施工造成的干涉;In the present invention, by gathering all the door and window holes needed for the reconstruction of the old building together, vertical strip-shaped cross-layer door and window holes are formed (such holes allow various large-sized beams/slabs/columns to enter, and the pump pipe for pouring concrete inside can also slide up and down along the hole to any position), the construction holes required for the construction of each floor are provided while minimizing the damage to the bearing capacity of the outer wall of the old building, and a small number of lintels and hidden columns can be used to overcome the impact of the opening, thereby overcoming the interference of the outer wall of the old building on the internal major reconstruction construction;

通过贴靠旧建筑外墙施工一层新增可靠层作为新的承重墙,新增可靠层能可靠地承载新增的楼板,且有能够与新增楼板可靠连接的接口,还拉住了旧承重墙防止其倒塌,同时使旧承重墙无须翻新防水结构。By constructing a new reliable layer against the outer wall of the old building as a new load-bearing wall, the new reliable layer can reliably bear the new floor slab, and has an interface that can be reliably connected to the new floor slab. It also holds the old load-bearing wall to prevent it from collapsing, and at the same time makes it unnecessary to renovate the waterproof structure of the old load-bearing wall.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1为采用本发明的建筑改造后的平面图;FIG1 is a plan view of a building remodeled using the present invention;

图2为采用本发明的建筑改造后的立面图,图中跨层门窗洞中已安装门窗;FIG2 is a elevation view of a building after renovation using the present invention, in which doors and windows have been installed in the cross-story door and window holes;

图中,1-旧建筑,2-跨层门窗洞,3-过梁,4-新增可靠层,5-外挑施工连廊。In the figure, 1-old building, 2-cross-story door and window openings, 3-lintel, 4-newly added reliable floor, 5-externally projecting construction corridor.

具体实施方式DETAILED DESCRIPTION

以本发明涉及的北京怀柔科学城北区金隅兴发科技园项目的水泥筒仓为例,如图1-2所示,一种原有承重外墙存在干涉时的新增楼板改建方法,用于在旧建筑1的外墙为承重墙时克服外墙对施工的干涉在旧建筑1内新增楼板,包括以下步骤:Taking the cement silo of the Jinyuxingfa Science Park project in the northern area of Huairou Science City, Beijing, as an example, as shown in FIG1-2, a method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall is used to overcome the interference of the exterior wall on the construction when the exterior wall of the old building 1 is a load-bearing wall and add a new floor slab in the old building 1, comprising the following steps:

步骤一:规划旧建筑1改造后的门窗位置,将门窗集中在跨层门窗洞2中,跨层门窗洞2满足以下条件:Step 1: Plan the doors and windows positions of the renovated old building 1, and concentrate the doors and windows in the cross-layer door and window opening 2. The cross-layer door and window opening 2 meets the following conditions:

条件1.1:设置在旧建筑1无遮挡的侧面;Condition 1.1: Set up on the unobstructed side of the old building 1;

该条件是为了满足建筑改建过程中沿跨层门窗洞2向建筑内转运建筑物料以及改建后建筑的通风采光需求。开着有遮挡物的地方的话,影响吊装也影响通风采光。This condition is to meet the needs of transporting building materials into the building along the cross-layer door and window openings 2 during the building reconstruction process and the ventilation and lighting needs of the reconstructed building. If there are obstructions, it will affect the hoisting and ventilation and lighting.

条件1.2:顶部高于最高的新增楼板,且顶部与最高的新增楼板之间的间隙能够容纳至少一扇门与一扇窗;底部低于最低的新增楼板,且底部与最低的新增楼板之间的间隙能够容纳至少一根混凝土泵管;Condition 1.2: The top is higher than the highest new floor slab, and the gap between the top and the highest new floor slab can accommodate at least one door and one window; the bottom is lower than the lowest new floor slab, and the gap between the bottom and the lowest new floor slab can accommodate at least one concrete pump pipe;

也就是说本申请中的跨层门窗洞2是一个非常长的长条状洞,不仅能够顾及到所有的楼层施工,而且各种大型梁/柱/板均可直接吊入,包括混凝土浇筑过程中用到的叠合板以及模板。同时混凝土泵管可以沿着跨层门窗洞2上下滑动到楼层各位置。除了对施工的便利之外,这种结构对旧建筑1的破坏也最小,开洞过程中不会有危险,且只需要少量的暗柱和过梁3即可完成补强。That is to say, the cross-layer door and window hole 2 in the present application is a very long strip-shaped hole, which can not only take into account the construction of all floors, but also various large beams/columns/slabs can be directly hoisted in, including the composite slabs and templates used in the concrete pouring process. At the same time, the concrete pump pipe can slide up and down along the cross-layer door and window hole 2 to various positions on the floor. In addition to the convenience of construction, this structure also causes minimal damage to the old building 1, there is no danger during the hole opening process, and only a small number of hidden columns and lintels 3 are needed to complete the reinforcement.

同时这样的结构在外观上有优势,相较于现有的门窗布局,这种布局的门窗更美观。其美观性和舒适性得到了入住的北京雁栖湖应用数学研究院的专家教授的认可。At the same time, this structure has advantages in appearance. Compared with the existing door and window layout, this layout of doors and windows is more beautiful. Its beauty and comfort have been recognized by the experts and professors of the Beijing Yanqi Lake Institute of Applied Mathematics who have stayed there.

步骤二:在跨层门窗洞2顶部开槽施工过梁3,过梁3两端落在跨层门窗洞2左右两侧开槽后施工新增暗柱上;Step 2: groove the top of the cross-layer door and window opening 2 to construct the lintel 3, and the two ends of the lintel 3 fall on the newly added hidden columns after the grooves are cut on the left and right sides of the cross-layer door and window opening 2;

也就是说这里是在开洞前完成的暗柱和过梁3的施工,且先施工暗柱,然后施工过梁3。在弥补开洞对旧建筑1竖向承载能力的不利影响的同时,使施工安全性得到保证。这里在开槽的时候可保留槽内一部分水平钢筋,用于和暗柱及过梁3的水平钢筋连接,以增加强度。具体做法为开槽的时候在槽的左右两侧留一部分欠挖墙体,之后剔凿掉欠挖墙体中的混凝土。That is to say, the construction of the hidden column and the lintel 3 is completed before the opening, and the hidden column is constructed first, and then the lintel 3 is constructed. While compensating for the adverse effect of the opening on the vertical bearing capacity of the old building 1, the construction safety is guaranteed. Here, when the groove is opened, a part of the horizontal steel bars in the groove can be retained for connection with the horizontal steel bars of the hidden column and the lintel 3 to increase the strength. The specific method is to leave a part of the under-excavated wall on the left and right sides of the groove when the groove is opened, and then chisel out the concrete in the under-excavated wall.

步骤三:在旧建筑1外墙上切割出跨层门窗洞2;Step 3: Cut out cross-layer door and window holes 2 on the exterior wall of the old building 1;

这里选用水锯切割的方式切出门窗洞,在使得洞口规整方便后续安装门窗的同时,避免对旧建筑1中墙体造成附加伤害。Here, a water saw is used to cut the door and window holes, which makes the holes regular and convenient for the subsequent installation of doors and windows, while avoiding additional damage to the walls of the old building 1.

步骤四:剔凿旧建筑1的外墙内壁面;然后贴靠外墙施工新增可靠层4,新增可靠层4为满足以下条件的承重墙:Step 4: Chisel the inner wall of the exterior wall of the old building 1; then construct a new reliable layer 4 close to the exterior wall. The new reliable layer 4 is a load-bearing wall that meets the following conditions:

条件4.1:与旧建筑1的外墙固定连接为一体;Condition 4.1: Fixedly connected to the outer wall of the old building 1;

这里的目的在于拉住旧建筑1的外墙,使其在开洞后不发生倒塌。The purpose here is to hold the outer wall of the old building 1 so that it does not collapse after the hole is opened.

条件4.2:预留有用于安装新增楼板的接口;Condition 4.2: An interface is reserved for installing the new floor slab;

这里的接口指的是用来安装梁的预埋件、用来安连接楼板钢筋的甩筋、以及用来与楼板的混凝土连接的毛面和凹槽。The interface here refers to the embedded parts used to install beams, the rebars used to connect the floor slab steel bars, and the rough surfaces and grooves used to connect to the concrete of the floor slab.

旧建筑1的外墙即使承载力合格,也无法在不进行大规模破拆的前提下安装楼板,且破拆是横向的,相当于直接打断了旧建筑1,安全性上完全不可行。因此这里选择把新增楼板安装在新增可靠层4上。Even if the outer wall of the old building 1 has a qualified bearing capacity, it is impossible to install the floor slab without large-scale demolition, and the demolition is horizontal, which is equivalent to directly interrupting the old building 1, which is completely unfeasible in terms of safety. Therefore, it is chosen here to install the new floor slab on the new reliable layer 4.

条件4.3:可在旧建筑1外墙不存在的前提下稳定存在;Condition 4.3: Can be stable without the existence of the exterior wall of the old building 1;

也就是说这里旧建筑1的外墙不对新增的各种建筑构件起到承载作用,新增可靠层4可以脱离旧建筑1的外墙而稳定承载上面新增的楼板,并满足建筑规范的各种要求。That is to say, the outer wall of the old building 1 does not bear the newly added building components, and the newly added reliable layer 4 can be separated from the outer wall of the old building 1 and stably bear the newly added floor slab thereon, and meet various requirements of building specifications.

条件4.4:防水;Condition 4.4: Waterproof;

旧建筑1的外墙上的防水已经不可靠了,且漏水位置是未知的,对其翻新不能保证效果。这里选择让新增可靠层4是防水的,这样不需要额外的工作量就能确保建筑改建后有可靠的防水效果。The waterproofing on the outer wall of the old building 1 is no longer reliable, and the location of the leak is unknown, so the renovation cannot guarantee the effect. Here, the newly added reliable layer 4 is chosen to be waterproof, so that no additional work is required to ensure a reliable waterproofing effect after the building reconstruction.

步骤五:自下而上逐层在新增可靠层4上安装新增楼板。Step 5: Install new floor slabs on the newly added reliable layer 4 layer by layer from bottom to top.

若旧建筑1有多个且成排设置,则在步骤四的施工开始前,预先在成排的旧建筑1一侧安装外挑施工连廊5,且步骤一规划的跨层门窗洞2中,每个旧建筑1都至少有一个跨层门窗洞2通向外挑施工连廊5;旧建筑1改造完成后的装修阶段,外挑施工连廊5外包玻璃幕墙与顶棚,形成供住户使用的走廊。If there are multiple old buildings 1 and they are arranged in a row, then before the construction of step 4 begins, an externally projected construction corridor 5 is pre-installed on one side of the row of old buildings 1, and among the cross-layer door and window openings 2 planned in step 1, each old building 1 has at least one cross-layer door and window opening 2 leading to the externally projected construction corridor 5; in the decoration stage after the renovation of the old building 1 is completed, the externally projected construction corridor 5 is covered with a glass curtain wall and a ceiling to form a corridor for residents to use.

如果旧建筑1成排设置的话,那么它们之间的连通可能存在困难,且施工过程中也可能有不同旧建筑1之间物料/人员交换的需求。因此这里选择悬挑一个施工平台(悬挑可避免对地面造成干涉),同时满足不同旧建筑1之间在施工中的物料/人员交换需求以及施工后不同旧建筑1连通的需求。If the old buildings 1 are arranged in a row, it may be difficult to connect them, and there may be a need to exchange materials/personnel between different old buildings 1 during construction. Therefore, a construction platform is cantilevered here (cantilevering can avoid interference with the ground), which can meet the needs of material/personnel exchange between different old buildings 1 during construction and the need to connect different old buildings 1 after construction.

新增楼板的钢筋穿透新增可靠层4植入到旧建筑1的外墙中。The reinforcement of the newly added floor slab penetrates the newly added reliable layer 4 and is implanted into the outer wall of the old building 1.

植筋这种操作可以在不对旧建筑1外墙造成影响强度的破坏的前提下进行,同时又能提升甩筋的抗拔力。如果不植入旧建筑1的外墙的话,那么甩筋就需要额外的固定措施,以确保在新增可靠层4混凝土浇筑的时候不发生歪斜,同时考虑到新增可靠层4较薄,抗拔力若想达标就需要在甩筋上增加附加结构。The operation of planting reinforcement can be carried out without damaging the exterior wall of the old building 1, which affects its strength, while improving the pull-out resistance of the rebar. If the rebar is not planted in the exterior wall of the old building 1, the rebar needs additional fixing measures to ensure that it does not tilt when the concrete of the newly added reliable layer 4 is poured. At the same time, considering that the newly added reliable layer 4 is relatively thin, additional structures need to be added to the rebar if the pull-out resistance is to meet the standard.

步骤四包含如下分步骤:Step 4 includes the following sub-steps:

步骤4.1:剔凿旧建筑1的外墙内壁面;Step 4.1: Chisel the inner wall surface of the outer wall of the old building 1;

为了确保旧建筑1的外墙与新增可靠层4有效连接,这里不仅要凿毛,需要剔凿到旧建筑1的外墙露出钢筋,也即剔凿掉一层混凝土保护层,这层混凝土主要起保护内部钢筋的作用,基本不受力,不会影响安全。In order to ensure that the outer wall of the old building 1 is effectively connected with the newly added reliable layer 4, it is necessary not only to roughen the surface, but also to chisel away until the outer wall of the old building 1 exposes the steel bars, that is, to chisel away a layer of concrete protective layer. This layer of concrete mainly serves to protect the internal steel bars and is basically not subjected to stress, so it will not affect safety.

步骤4.2:在旧建筑1的外墙内壁面上植入新增楼板的甩筋,甩筋穿过新增可靠层4延伸到旧建筑1内部;Step 4.2: implant the reinforcement of the newly added floor slab on the inner wall surface of the outer wall of the old building 1, and the reinforcement passes through the newly added reliable layer 4 and extends to the interior of the old building 1;

后续新增楼板的钢筋在绑扎的时候需要与甩筋连接。The steel bars of the newly added floor slabs need to be connected with the loose bars when binding.

步骤4.3:绑扎新增可靠层4的钢筋笼,并在新增楼板位置下方安装用于和新增楼板的梁连接的预埋件,所述新增楼板的梁相互连接为网格状;Step 4.3: Tie up the steel cage of the newly added reliable layer 4, and install embedded parts for connecting with the beams of the newly added floor below the position of the newly added floor, wherein the beams of the newly added floor are connected to each other in a grid shape;

这里的预埋件可以是钢梁需要用到的连接板,或者是为钢筋混凝土柱施工用的甩筋。这里的梁连接成网格状,是为了拉住外墙。The embedded parts here can be the connecting plates needed for steel beams, or the rebars used for the construction of reinforced concrete columns. The beams here are connected in a grid shape to hold the exterior wall.

步骤4.4:浇筑新增可靠层4的混凝土,浇筑时在新增楼板位置预留内表面为毛面的凹槽;Step 4.4: pouring concrete for the newly added reliable layer 4, and reserving a groove with a rough inner surface at the location of the newly added floor slab during pouring;

步骤五每层新增楼板的施工过程如下:Step 5 The construction process of each new floor slab is as follows:

安装新增楼板的梁——绑扎新增楼板的钢筋笼并与步骤4.2的甩筋固定连接——浇筑混凝土。Install the beams of the new floor slab - tie the reinforcement cage of the new floor slab and fix it with the reinforcement in step 4.2 - pour concrete.

新增可靠层4为钢筋混凝土剪力墙,且在新增楼板下方向外突出形成用于承托新增楼板边沿的环梁,环梁中以及新增楼板边沿中设置有绕整个旧建筑1一周的连续钢筋或型钢。The newly added reliable layer 4 is a reinforced concrete shear wall, and protrudes outward from the bottom of the newly added floor to form a ring beam for supporting the edge of the newly added floor. Continuous steel bars or steel sections are arranged in the ring beam and the edge of the newly added floor, which surround the entire old building 1.

新增可靠层4中的这种结构,除了提升承载楼板的效果外,另一个作用是使新增可靠层4更加连续完整,像隧道的衬砌那样更好地受力。This structure in the newly added reliable layer 4, in addition to improving the effect of the load-bearing floor, also has another function of making the newly added reliable layer 4 more continuous and complete, so that it can bear stress better like the lining of a tunnel.

跨层门窗洞2中,所有门窗均沿竖直方向排列;这样是为了使跨城门窗洞尽可能窄,从而减少对旧建筑1的强度的影响。In the cross-layer door and window openings 2 , all doors and windows are arranged in the vertical direction; this is to make the cross-layer door and window openings as narrow as possible, thereby reducing the impact on the strength of the old building 1 .

同一楼层的门窗中,自上而下分别为通风用的百叶窗、采光用到玻璃窗、以及通行用的门。这种排布方式是为了满足使用需求,百叶窗为了满足抽油烟机以及新风空调的需求,平时不需要开合,因此设置在最高处。而门设置在最低处以确保能够正常使用,采光用的玻璃窗设置在门上方,可以借助辅助的手柄开合。The doors and windows on the same floor are arranged from top to bottom, including blinds for ventilation, glass windows for lighting, and doors for passage. This arrangement is to meet the needs of use. The blinds do not need to be opened or closed at ordinary times in order to meet the needs of range hoods and fresh air air conditioners, so they are set at the highest position. The door is set at the lowest position to ensure normal use. The glass window for lighting is set above the door and can be opened and closed with the help of an auxiliary handle.

在步骤二施工前,检查并修补旧建筑1的外墙表面混凝土的缺陷;其中,裂缝灌浆修补,裂缝之外的缺陷采用剔凿缺陷部位形成V形槽后填补新混凝土的方式修补。Before the construction of step 2, the defects of the concrete on the outer wall surface of the old building 1 are checked and repaired; cracks are repaired by grouting, and defects other than cracks are repaired by chiseling the defective parts to form V-shaped grooves and then filling with new concrete.

这里修补缺陷主要是为了满足外观的需求,对强度的影响仅体现在避免旧建筑1的外墙上混凝土的缺陷影响与新增可靠层4的连接上。当然这里修补缺陷,一定程度上也能提升旧建筑1的外墙的强度,但这里对此不做要求。The purpose of repairing defects here is mainly to meet the requirements of appearance, and the impact on strength is only reflected in avoiding the impact of defects on the concrete on the exterior wall of the old building 1 on the connection with the newly added reliable layer 4. Of course, repairing defects here can also improve the strength of the exterior wall of the old building 1 to a certain extent, but this is not required here.

以上所述的实施例仅仅是对本发明的优选实施方式进行描述,并非对本发明的范围进行限定,在不脱离本发明设计精神的前提下,本领域普通技术人员对本发明的技术方案作出的各种变形和改进,均应落入本发明权利要求书确定的保护范围内。The embodiments described above are merely descriptions of preferred implementation modes of the present invention and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.

Claims (7)

1. A new floor reconstruction method when the interference exists in the original bearing outer wall is used for overcoming the interference of the outer wall to the construction when the outer wall of the old building (1) is the bearing wall, and is characterized in that: the method comprises the following steps:
Step one: planning the door and window position of an old building (1) after transformation, and concentrating the door and window in a cross-layer door and window hole (2), wherein the cross-layer door and window hole (2) meets the following conditions:
Condition 1.1: the device is arranged on the non-shielding side surface of the old building (1);
condition 1.2: the top is higher than the highest newly-added floor slab, and the gap between the top and the highest newly-added floor slab can accommodate at least one door and one window; the bottom is lower than the lowest newly-added floor slab, and a gap between the bottom and the lowest newly-added floor slab can accommodate at least one concrete pump pipe;
step two: a lintel (3) is constructed on the top of the cross-layer door and window hole (2) in a slotting way, and two ends of the lintel (3) fall on newly added dark columns after slotting on the left side and the right side of the cross-layer door and window hole (2);
step three: cutting a cross-layer door and window hole (2) on the outer wall of the old building (1);
step four: picking and chiseling the inner wall surface of the outer wall of the old building (1); then, a new reliable layer (4) is constructed by being attached to an outer wall, and the new reliable layer (4) is a bearing wall meeting the following conditions:
condition 4.1: is fixedly connected with the outer wall of the old building (1) into a whole;
Condition 4.2: reserving an interface for installing a newly added floor slab;
Condition 4.3: the building can stably exist on the premise that the outer wall of the old building (1) does not exist;
Condition 4.4: waterproof;
step five: and installing the newly added floor slab on the newly added reliable layer (4) layer by layer from bottom to top.
2. The method for rebuilding the newly added floor slab when the original bearing outer wall is interfered according to claim 1, which is characterized in that: if the old buildings (1) are arranged in a plurality of rows, before the construction of the fourth step is started, the overhanging construction corridor (5) is arranged on one side of the row of old buildings (1) in advance, and in the step one, at least one cross-layer door and window hole (2) of each old building (1) is led to the overhanging construction corridor (5); and in the decoration stage after the reconstruction of the old building (1), the overhanging construction corridor (5) is covered with the glass curtain wall and the ceiling to form a corridor for households.
3. The method for rebuilding the newly added floor slab when the original bearing outer wall is interfered according to claim 1, which is characterized in that: the steel bars of the newly added floor slabs penetrate through the newly added reliable layers (4) and are implanted into the outer wall of the old building (1).
4. The method for rebuilding the newly added floor slab when the original bearing outer wall is interfered according to claim 3, which is characterized in that: step four comprises the following sub-steps:
Step 4.1: picking and chiseling the inner wall surface of the outer wall of the old building (1);
step 4.2: the method comprises the steps of implanting a throwing rib of a newly-added floor slab on the inner wall surface of the outer wall of an old building (1), wherein the throwing rib penetrates through a newly-added reliable layer (4) and extends into the old building (1);
step 4.3: binding a reinforcement cage of the newly-added reliable layer (4), and installing an embedded part used for being connected with a beam of the newly-added floor below the position of the newly-added floor, wherein the beams of the newly-added floor are connected into a grid shape;
step 4.4: pouring concrete of the newly added reliable layer (4), and reserving grooves with rough surfaces on the inner surfaces at the positions of the newly added floors during pouring;
the construction process of each layer of newly added floor slab is as follows:
And (3) installing the beam of the newly added floor slab, binding the reinforcement cage of the newly added floor slab, and fixedly connecting with the throwing rib in the step (4.2), and pouring concrete.
5. The method for rebuilding the newly added floor slab when the original bearing outer wall is interfered according to claim 4, which is characterized in that: the new-added reliable layer (4) is a reinforced concrete shear wall, and a ring beam for supporting the edges of the new-added floor slab is formed by protruding outwards below the new-added floor slab, and continuous steel bars or section steel which winds the whole old building (1) for a circle are arranged in the ring beam and the edges of the new-added floor slab.
6. The method for rebuilding the newly added floor slab when the original bearing outer wall is interfered according to claim 1, which is characterized in that: in the cross-layer door window hole (2), all doors and windows are arranged along the vertical direction; and doors and windows on the same floor are respectively provided with a shutter for ventilation, a glass window for lighting and a door for passing from top to bottom.
7. The method for rebuilding the newly added floor slab when the original bearing outer wall is interfered according to claim 1, which is characterized in that: before the second construction, checking and repairing the defects of the concrete on the outer wall surface of the old building (1); and grouting and repairing the cracks, wherein defects outside the cracks are repaired by adopting a mode of filling new concrete after V-shaped grooves are formed at the defect positions by chiseling.
CN202411049995.0A 2024-08-01 2024-08-01 A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall Active CN118564105B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202411049995.0A CN118564105B (en) 2024-08-01 2024-08-01 A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202411049995.0A CN118564105B (en) 2024-08-01 2024-08-01 A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall

Publications (2)

Publication Number Publication Date
CN118564105A true CN118564105A (en) 2024-08-30
CN118564105B CN118564105B (en) 2024-11-12

Family

ID=92468456

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202411049995.0A Active CN118564105B (en) 2024-08-01 2024-08-01 A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall

Country Status (1)

Country Link
CN (1) CN118564105B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008025265A (en) * 2006-07-24 2008-02-07 Takenaka Komuten Co Ltd Reconstruction method
CN215830079U (en) * 2021-07-02 2022-02-15 北京首钢国际工程技术有限公司 Reinforcing node system for retaining high and large masonry wall of outer vertical face by original appearance of historical building
CN114673377A (en) * 2022-04-09 2022-06-28 中建八局第三建设有限公司 Reservation of exterior walls of historic buildings and construction methods for interior hollowing out and remaking
CN117468748A (en) * 2023-10-16 2024-01-30 中震(北京)工程检测股份有限公司 Adding new corner columns and ring beams to the indoor floor of industrial plants and their construction methods
CN117868556A (en) * 2024-03-13 2024-04-12 北京建工四建工程建设有限公司 Building dismantling and modifying support system taking building as bearing member
CN117967092A (en) * 2024-03-13 2024-05-03 北京建工四建工程建设有限公司 Construction method for removing and modifying building without temporary support of building
CN118208066A (en) * 2024-05-22 2024-06-18 上海建工一建集团有限公司 Construction method for layer-adding transformation of interior of existing cylindrical structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008025265A (en) * 2006-07-24 2008-02-07 Takenaka Komuten Co Ltd Reconstruction method
CN215830079U (en) * 2021-07-02 2022-02-15 北京首钢国际工程技术有限公司 Reinforcing node system for retaining high and large masonry wall of outer vertical face by original appearance of historical building
CN114673377A (en) * 2022-04-09 2022-06-28 中建八局第三建设有限公司 Reservation of exterior walls of historic buildings and construction methods for interior hollowing out and remaking
CN117468748A (en) * 2023-10-16 2024-01-30 中震(北京)工程检测股份有限公司 Adding new corner columns and ring beams to the indoor floor of industrial plants and their construction methods
CN117868556A (en) * 2024-03-13 2024-04-12 北京建工四建工程建设有限公司 Building dismantling and modifying support system taking building as bearing member
CN117967092A (en) * 2024-03-13 2024-05-03 北京建工四建工程建设有限公司 Construction method for removing and modifying building without temporary support of building
CN118208066A (en) * 2024-05-22 2024-06-18 上海建工一建集团有限公司 Construction method for layer-adding transformation of interior of existing cylindrical structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
胡力友;: "上海某民国历史保护建筑加固设计研究", 工程抗震与加固改造, no. 04, 5 August 2017 (2017-08-05) *

Also Published As

Publication number Publication date
CN118564105B (en) 2024-11-12

Similar Documents

Publication Publication Date Title
CN106013811B (en) A kind of installation method of assembled architecture
CN105089178B (en) A kind of pre-splicing Standard formula building of prefabricated steel reinforced concrete shear walls
CN103306497B (en) Shock prevention and strengthening construction method for existing brickwork dwelling house fabricated structure
CN103669905A (en) Lightweight composite prefabricated panel combined type house and building method thereof
CN115247508A (en) Construction method of large-scale tank body structure of sewage treatment station
Zanni et al. Application of CLT prefabricated exoskeleton for an integrated renovation of existing buildings and continuous structural monitoring
CN108755968A (en) Assembling synthesis building and its construction method
CN209855277U (en) A transfer floor structure used for underground addition of existing buildings
KR101242017B1 (en) The simultaneous construction method of ground and underground structure using ground core pre-construction and latticed lintel beam in core
WO2026001483A1 (en) Floor reinforcement construction method for old building renovation
CN114934588A (en) Efficient alternate flow construction method for building construction
CN118564104B (en) New and old building nested composite structure capable of utilizing old and stable in internal environment
CN118564105B (en) A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall
CN112049432A (en) Fractal theory-based large-span steel frame structure combination construction method
CN107190989A (en) Shaped steel partition plate external wall construction method
CN107401214A (en) A kind of installation method of assembled architecture
CN111254937A (en) Installation method of fabricated building
Liu et al. Prefabrication construction in residential building of Vanke real estate company China
CN118564103B (en) A method for renovating and utilizing a large-scale old building while retaining its appearance
CN210086744U (en) A prefabricated pipeline well for high-rise buildings
RU2336399C1 (en) Method for rebuilding of large-panel apartment house
CN118601374A (en) A method for reconstructing rows of small-section buildings by making full use of old buildings
CN111576681A (en) FS composite heat-preservation construction integrated technology construction process
TWI823712B (en) Steel-structure building envelope
CN211523554U (en) Prefabricated outer wall window hole waterproof node of assembly type structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant