CN118564105B - A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall - Google Patents

A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall Download PDF

Info

Publication number
CN118564105B
CN118564105B CN202411049995.0A CN202411049995A CN118564105B CN 118564105 B CN118564105 B CN 118564105B CN 202411049995 A CN202411049995 A CN 202411049995A CN 118564105 B CN118564105 B CN 118564105B
Authority
CN
China
Prior art keywords
wall
floor slab
newly
layer
old building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202411049995.0A
Other languages
Chinese (zh)
Other versions
CN118564105A (en
Inventor
张莉莉
陈达非
王亮
赵来柱
王杨
杨化军
王磊
姚俊琴
李汀滢
孙汉霖
李萌
苏婕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jinyu Xingfa Technology Co ltd
Beijing Fourth Construction & Engineering Co ltd
Original Assignee
Beijing Jinyu Xingfa Technology Co ltd
Beijing Fourth Construction & Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jinyu Xingfa Technology Co ltd, Beijing Fourth Construction & Engineering Co ltd filed Critical Beijing Jinyu Xingfa Technology Co ltd
Priority to CN202411049995.0A priority Critical patent/CN118564105B/en
Publication of CN118564105A publication Critical patent/CN118564105A/en
Application granted granted Critical
Publication of CN118564105B publication Critical patent/CN118564105B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00—Working measures on existing buildings
    • E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0266—Enlarging
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00—Working measures on existing buildings
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00—Working measures on existing buildings
    • E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00—Working measures on existing buildings
    • E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明涉及对现有建筑物的施工措施技术领域,公开了一种原有承重外墙存在干涉时的新增楼板改建方法,本发明中,通过把旧建筑改建所需要开的门窗洞都集中在一起,形成竖条状的跨层门窗洞,提供了各层施工所需要的施工洞的同时最小化了对旧建筑外墙承载能力的破坏,且可用少量的过梁和暗柱来克服开洞造成的影响,从而克服了旧建筑外墙对内部大改施工造成的干涉;通过贴靠旧建筑外墙施工一层新增可靠层作为新的承重墙,新增可靠层能可靠地承载新增的楼板,且有能够与新增楼板可靠连接的接口,还拉住了旧承重墙防止其倒塌,同时使旧承重墙无须翻新防水结构。

The invention relates to the technical field of construction measures for existing buildings, and discloses a method for rebuilding a new floor slab when interference exists in an original load-bearing outer wall. In the invention, all the door and window holes required for rebuilding an old building are gathered together to form vertical cross-layer door and window holes, thereby providing the construction holes required for the construction of each layer and minimizing the damage to the bearing capacity of the outer wall of the old building. A small amount of lintels and hidden columns can be used to overcome the influence caused by the opening of the holes, thereby overcoming the interference caused by the outer wall of the old building on the major internal reconstruction construction. A new reliable layer is constructed close to the outer wall of the old building as a new load-bearing wall, and the new reliable layer can reliably bear the new floor slab, and has an interface that can be reliably connected to the new floor slab, and also holds the old load-bearing wall to prevent it from collapsing, and at the same time, the waterproof structure of the old load-bearing wall does not need to be renovated.

Description

Method for rebuilding newly-added floor slab when interference exists in original bearing outer wall
Technical Field
The invention relates to the technical field of construction measures of existing buildings, in particular to a method for rebuilding a newly added floor slab when interference exists on an original bearing outer wall.
Background
The vast majority of old buildings are left empty for new building construction after being dismantled, but some old buildings with special significance exist, and the purposes of the buildings need to be changed on the premise of keeping the original appearance of the old buildings, so that the deep reconstruction of the buildings is needed.
Considering that the old building itself has undergone serious aging, its structural strength is severely reduced, and its appearance has been very worn out. These problems are difficult to solve without deep modification of the building itself, so modification of the old building is often required to be performed in a form of reassembling after disassembling the building into parts, and in the process of disassembling the building parts, the building parts can be detected and replaced respectively, parts with unqualified strength or serious damage can be replaced, reinforcement treatment can be performed inside or the internal layout of the building can be changed, so that the building is adapted to the change of the use of the building.
However, this construction method is not suitable if the old building is mainly supported by the bearing wall. Whether the bearing wall is made of reinforced concrete or the bearing wall is of masonry structure, the bearing wall cannot be disassembled into parts on the premise of not causing damage. The load-bearing walls of old buildings are now not an available resource for the reconstruction of the interior of the building, but a heavy burden. As the reconstruction of the interior of the building will necessarily involve a change in layout and load. However, such a load-bearing wall itself has various drawbacks due to the time relationship, not only being unreliable in stress but also being unreliable in waterproofing. Therefore, not only can the newly added load not be carried by the old bearing wall, but also the old bearing wall needs to be repaired. Second, even if it is not intended to rely on old load bearing walls, but instead to newly install other load bearing members in the building to carry the newly added load in the building, these old load bearing walls also block the access of large-sized building elements (beams, columns, sections, bars, plates, etc.) including the load bearing members into and out of the building interior. The problem is further exacerbated if the old building itself is a type of building of a warehouse nature (fewer and smaller holes are made in such a building).
Taking Beijing Huaiyou science urban and north area Jin Yuxing of the invention as an example, the project is in Xingfu cement factory, which is established in the early 90 s, and contributes a large amount of building materials to Beijing urban construction, which is an important industrial site. Therefore, the construction in this place needs to be modified to a research facility of the applied mathematics institute of Beijing Yan perch lake nearby while retaining the external shape. The cement silo needs to be transformed into an expert residential building. The floor height of the cement silo is too large for the house (approaching 20 meters high, which can make the house unable to finish the ceiling) and too wasteful, requiring several floors to be added inside. The original material hole of the cement silo does not allow the concrete pump pipe to enter the pouring surface nearby and cannot reliably bear the newly added floor slab, and an interface capable of being reliably connected with the newly added floor slab is not provided.
Disclosure of Invention
The invention provides a newly added floor reconstruction method when interference exists in an original bearing outer wall.
The technical problems to be solved are as follows: when the outer wall of the old building is a bearing wall, the construction of the new floor slab and other large changes in the building can be interfered by the outer wall, and meanwhile, the outer wall of the old building cannot effectively bear the new components and cannot be effectively connected with the new components.
In order to solve the technical problems, the invention adopts the following technical scheme: a new floor reconstruction method when the original bearing outer wall is interfered is used for overcoming the interference of the outer wall to the construction when the outer wall of the old building is the bearing wall, and the new floor is added in the old building, and comprises the following steps:
step one: planning the positions of doors and windows after the old building is transformed, and concentrating the doors and windows in a cross-layer door and window hole, wherein the cross-layer door and window hole meets the following conditions:
condition 1.1: the building is arranged on the non-shielding side surface of the old building;
condition 1.2: the top is higher than the highest newly-added floor slab, and the gap between the top and the highest newly-added floor slab can accommodate at least one door and one window; the bottom is lower than the lowest newly-added floor slab, and a gap between the bottom and the lowest newly-added floor slab can accommodate at least one concrete pump pipe;
Step two: grooving construction lintel at the top of the cross-layer door and window hole, wherein two ends of the lintel fall on newly added dark columns after grooving at the left side and the right side of the cross-layer door and window hole;
Step three: cutting a cross-layer door and window hole on the outer wall of the old building;
Step four: picking and chiseling the inner wall surface of the outer wall of the old building; then, a new reliable layer is constructed by being attached to an outer wall, wherein the new reliable layer is a bearing wall meeting the following conditions:
condition 4.1: fixedly connected with the outer wall of the old building into a whole;
Condition 4.2: reserving an interface for installing a newly added floor slab;
condition 4.3: the building external wall can stably exist on the premise that the old building external wall does not exist;
Condition 4.4: waterproof;
Step five: and installing the newly added floor slab on the newly added reliable layer by layer from bottom to top.
Further, if a plurality of old buildings are arranged in a row, before the construction of the fourth step is started, installing an overhanging construction corridor on one side of the row of old buildings in advance, and in the step one, planning cross-layer door and window holes, at least one cross-layer door and window hole of each old building is led to the overhanging construction corridor; and in the decoration stage after the old building is transformed, the overhanging construction corridor is covered with the glass curtain wall and the ceiling to form a corridor for households.
Further, the reinforcing steel bars of the newly added floor slab penetrate through the newly added reliable layer and are implanted into the outer wall of the old building.
Further, the fourth step comprises the following sub-steps:
Step 4.1: picking and chiseling the inner wall surface of the outer wall of the old building;
Step 4.2: the method comprises the steps of implanting a throwing rib of a newly-added floor slab on the inner wall surface of an outer wall of an old building, wherein the throwing rib penetrates through a newly-added reliable layer and extends into the old building;
Step 4.3: binding a reinforcement cage of a newly-added reliable layer, and installing an embedded part used for being connected with a beam of the newly-added floor below the position of the newly-added floor, wherein the beams of the newly-added floor are connected into a grid shape;
step 4.4: pouring concrete with a newly added reliable layer, and reserving grooves with rough surfaces on the inner surfaces at the positions of the newly added floors during pouring;
The construction process of each layer of newly added floor slab is as follows:
And (3) installing the beam of the newly added floor slab, binding the reinforcement cage of the newly added floor slab, and fixedly connecting with the throwing rib in the step (4.2), and pouring concrete.
Furthermore, the newly-increased reliable layer is a reinforced concrete shear wall, and a ring beam for supporting the edge of the newly-increased floor slab is formed by protruding outwards below the newly-increased floor slab, and continuous steel bars or section steel which winds the whole old building for a circle are arranged in the ring beam and the edge of the newly-increased floor slab.
Further, in the cross-layer door and window hole, all doors and windows are arranged along the vertical direction; and doors and windows on the same floor are respectively provided with a shutter for ventilation, a glass window for lighting and a door for passing from top to bottom.
Further, before the second construction step, checking and repairing the defects of the concrete on the outer wall surface of the old building; and grouting and repairing the cracks, wherein defects outside the cracks are repaired by adopting a mode of filling new concrete after V-shaped grooves are formed at the defect positions by chiseling.
Compared with the prior art, the method for rebuilding the newly added floor slab when the original bearing outer wall is interfered has the following beneficial effects:
According to the invention, the door and window holes required to be opened by reconstruction of the old building are all concentrated together to form the vertical strip-shaped cross-layer door and window hole (the hole allows various large-size beams/plates/columns to enter, and a pump pipe for pouring concrete inside can slide up and down to any position along the hole), so that the construction holes required by construction of each layer are provided, meanwhile, the damage to the bearing capacity of the outer wall of the old building is minimized, and the influence caused by opening the hole can be overcome by a small number of lintels and hidden columns, so that the interference caused by the construction of the outer wall of the old building on the interior major transformation is overcome;
The new layer of reliability is constructed by being attached to the outer wall of the old building to serve as a new bearing wall, the new layer of reliability can reliably bear the newly added floor slab, an interface which can be reliably connected with the new floor slab is arranged, the old bearing wall is pulled to prevent collapse, and meanwhile, the old bearing wall does not need to be retreaded to have a waterproof structure.
Drawings
FIG. 1 is a plan view of a building retrofitted with the present invention;
FIG. 2 is an elevation view of a building modified according to the present invention with doors and windows installed in the cross-floor door and window cavity;
In the figure, 1-old building, 2-cross-layer door and window holes, 3-lintel, 4-newly added reliable layer and 5-overhanging construction corridor.
Detailed Description
Taking a cement silo of a scientific urban and north area Jin Yuxing of Beijing-Huai-rou science, which is related to the invention, as shown in fig. 1-2, as an example, a new floor reconstruction method when the interference exists on the original bearing outer wall is used for overcoming the interference of the outer wall on the construction when the outer wall of the old building 1 is the bearing wall, and the new floor is added in the old building 1, which comprises the following steps:
step one: planning the door and window position of the old building 1 after transformation, and concentrating the door and window in a cross-layer door and window cavity 2, wherein the cross-layer door and window cavity 2 meets the following conditions:
condition 1.1: the device is arranged on the non-shielding side surface of the old building 1;
The condition is to meet the requirements of transporting building materials along the cross-layer door and window holes 2 into the building during the reconstruction of the building and ventilating and lighting the reconstructed building. When a place with a shielding object is opened, the lifting is influenced, and ventilation and lighting are also influenced.
Condition 1.2: the top is higher than the highest newly-added floor slab, and the gap between the top and the highest newly-added floor slab can accommodate at least one door and one window; the bottom is lower than the lowest newly-added floor slab, and a gap between the bottom and the lowest newly-added floor slab can accommodate at least one concrete pump pipe;
That is, the cross-layer door and window hole 2 is a very long strip hole, not only can all floor construction be considered, but also various large beams/columns/plates can be directly hung in, including superimposed sheets and templates used in the concrete pouring process. Simultaneously, the concrete pump pipe can slide up and down to each floor position along the cross-layer door and window hole 2. Besides the convenience of construction, the damage of the structure to the old building 1 is minimum, no danger exists in the process of opening a hole, and the reinforcement can be finished by only needing a small number of hidden columns and lintels 3.
Meanwhile, the structure has the advantage in appearance, and compared with the existing door and window layout, the door and window with the layout is more attractive. Beijing with its aesthetic and comfort features the Yansha lake uses acceptance of expert professors of the mathematics institute.
Step two: a lintel 3 is constructed on the top of the cross-layer door and window hole 2 in a slotting way, and two ends of the lintel 3 fall on newly added dark columns after slotting on the left side and the right side of the cross-layer door and window hole 2;
That is, the construction of the hidden column and the lintel 3 is completed before the opening of the hole, and the hidden column is constructed first and then the lintel 3 is constructed. The construction safety is ensured while the adverse effect of the opening on the vertical bearing capacity of the old building 1 is made up. Here, a part of the horizontal bars in the groove can be reserved for connection with the horizontal bars of the hidden post and the lintel 3 during grooving, so as to increase the strength. The concrete method comprises the steps of reserving a part of underexcavated wall bodies on the left side and the right side of a groove during grooving, and then picking and chiseling concrete in the underexcavated wall bodies.
Step three: cutting a cross-layer door and window hole 2 on the outer wall of the old building 1;
The water saw cutting mode is selected to cut out the door and window holes, so that the holes are regular, the subsequent installation of doors and windows is convenient, and the additional damage to the wall body in the old building 1 is avoided.
Step four: picking and chiseling the inner wall surface of the outer wall of the old building 1; then, a new reliable layer 4 is constructed by being attached to an outer wall, and the new reliable layer 4 is a bearing wall meeting the following conditions:
Condition 4.1: fixedly connected with the outer wall of the old building 1 into a whole;
the aim here is to pull the outer wall of the old building 1 so that it does not collapse after the opening.
Condition 4.2: reserving an interface for installing a newly added floor slab;
the joints are embedded parts for installing beams, throwing ribs for installing floor steel bars, and rough surfaces and grooves for connecting the joints with concrete of the floor.
Even if the bearing capacity of the outer wall of the old building 1 is qualified, the floor cannot be installed on the premise that large-scale breaking and disassembly are not performed, and the breaking and disassembly are transverse, which is equivalent to directly breaking the old building 1, and is completely infeasible in safety. The option is therefore here to install a new floor on the new added reliability layer 4.
Condition 4.3: the building can stably exist on the premise that the outer wall of the old building 1 does not exist;
That is, the outer wall of the old building 1 does not bear the load of the newly added building components, and the newly added reliable layer 4 can be separated from the outer wall of the old building 1 to stably bear the newly added floor slab, and meet various requirements of building specifications.
Condition 4.4: waterproof;
The waterproofing of the outer wall of the old building 1 is already unreliable and the water leakage position is unknown, and the effect cannot be guaranteed for its renovation. The newly added reliable layer 4 is chosen to be waterproof, so that a reliable waterproof effect after reconstruction of the building can be ensured without additional effort.
Step five: and installing the newly added floor slab on the newly added reliable layer 4 layer by layer from bottom to top.
If a plurality of old buildings 1 are arranged in a row, before the construction of the fourth step is started, the overhanging construction corridor 5 is arranged on one side of the row of old buildings 1 in advance, and in the step one planned cross-layer door and window holes 2, each old building 1 is provided with at least one cross-layer door and window hole 2 leading to the overhanging construction corridor 5; and in the decoration stage after the old building 1 is transformed, the construction corridor 5 is externally covered with the glass curtain wall and the ceiling to form a corridor for households.
Communication between old buildings 1 may be difficult if they are arranged in rows and there may be a need for material/personnel exchange between different old buildings 1 during construction. Therefore, a construction platform is selected to be overhanging (the overhanging can avoid interference to the ground), and meanwhile, the material/personnel exchange requirements in construction between different old buildings 1 and the communication requirements of different old buildings 1 after construction are met.
The reinforcing steel bars of the newly added floor slab penetrate through the newly added reliable layer 4 and are implanted into the outer wall of the old building 1.
The operation of planting the rib can be performed on the premise of not influencing the damage of the strength of the outer wall of the old building 1, and the pulling resistance of the rib can be improved. If the external wall of the old building 1 is not implanted, extra fixing measures are needed for the throwing rib so as to ensure that no deflection occurs during the concrete pouring of the newly added reliable layer 4, and meanwhile, the additional structure is needed to be added on the throwing rib if the pulling resistance is up to the standard in consideration of the fact that the newly added reliable layer 4 is thinner.
Step four comprises the following sub-steps:
step 4.1: picking and chiseling the inner wall surface of the outer wall of the old building 1;
In order to ensure that the outer wall of the old building 1 is effectively connected with the newly added reliable layer 4, not only is roughening needed, but also the exposed reinforcing steel bars of the outer wall of the old building 1 need to be chiseled, namely a concrete protection layer is chiseled, and the layer of concrete mainly plays a role in protecting the inner reinforcing steel bars, is basically not stressed and does not influence safety.
Step 4.2: the inner wall surface of the outer wall of the old building 1 is implanted with a throwing rib of the newly added floor slab, and the throwing rib penetrates through the newly added reliable layer 4 to extend into the old building 1;
the steel bars of the subsequent newly added floor slab need to be connected with the throwing bars during binding.
Step 4.3: binding a reinforcement cage of the newly-added reliable layer 4, and installing an embedded part used for being connected with a beam of the newly-added floor below the position of the newly-added floor, wherein the beams of the newly-added floor are connected into a grid shape;
The embedded part can be a connecting plate which is needed by a steel beam or a throwing rib for the construction of the reinforced concrete column. The beams are connected in a grid pattern to hold the exterior wall.
Step 4.4: pouring concrete of the newly added reliable layer 4, and reserving grooves with rough surfaces on the inner surfaces at the positions of the newly added floors during pouring;
The construction process of each layer of newly added floor slab is as follows:
And (3) installing the beam of the newly added floor slab, binding the reinforcement cage of the newly added floor slab, and fixedly connecting with the throwing rib in the step (4.2), and pouring concrete.
The newly-added reliable layer 4 is a reinforced concrete shear wall, and a ring beam for supporting the edge of the newly-added floor slab is formed by protruding outwards below the newly-added floor slab, and continuous steel bars or section steel which winds the whole old building for 1 week are arranged in the ring beam and the edge of the newly-added floor slab.
The structure in the newly added reliable layer 4 has the other function of enabling the newly added reliable layer 4 to be more continuous and complete and better stressed like the lining of a tunnel besides the effect of lifting the bearing floor slab.
In the cross-layer door window hole 2, all doors and windows are arranged along the vertical direction; this is to make the cross-urban door and window openings as narrow as possible, thereby reducing the impact on the strength of the old building 1.
The doors and windows on the same floor are respectively a shutter for ventilation, a glass window for lighting and a door for passing from top to bottom. The arrangement mode is to meet the use requirement, and the shutter is not required to be opened or closed at ordinary times to meet the requirements of the smoke exhaust ventilator and the fresh air conditioner, so that the shutter is arranged at the highest position. The door is arranged at the lowest position to ensure normal use, and the glass window for lighting is arranged above the door and can be opened and closed by an auxiliary handle.
Before the second construction, checking and repairing the defects of the concrete on the outer wall surface of the old building 1; and grouting and repairing the cracks, wherein defects outside the cracks are repaired by adopting a mode of filling new concrete after V-shaped grooves are formed at the defect positions by chiseling.
The repairing defect is mainly to meet the appearance requirement, and the influence on the strength is only reflected on the connection between the defect influence of the concrete on the outer wall of the old building 1 and the newly added reliable layer 4. The defect is repaired, and the strength of the outer wall of the old building 1 can be improved to a certain extent, but the defect is not required here.
The above examples are only illustrative of the preferred embodiments of the present invention and are not intended to limit the scope of the present invention, and various modifications and improvements made by those skilled in the art to the technical solution of the present invention should fall within the scope of protection defined by the claims of the present invention without departing from the spirit of the present invention.

Claims (7)

1. A new floor reconstruction method when the interference exists in the original bearing outer wall is used for overcoming the interference of the outer wall to the construction when the outer wall of the old building (1) is the bearing wall, and is characterized in that: the method comprises the following steps:
step one: planning the door and window position of an old building (1) after transformation, and concentrating the door and window in a cross-layer door and window hole (2), wherein the cross-layer door and window hole (2) meets the following conditions:
condition 1.1: the device is arranged on the non-shielding side surface of the old building (1);
condition 1.2: the top is higher than the highest newly-added floor slab, and the gap between the top and the highest newly-added floor slab can accommodate at least one door and one window; the bottom is lower than the lowest newly-added floor slab, and a gap between the bottom and the lowest newly-added floor slab can accommodate at least one concrete pump pipe;
step two: a lintel (3) is constructed on the top of the cross-layer door and window hole (2) in a slotting way, and two ends of the lintel (3) fall on newly added dark columns after slotting on the left side and the right side of the cross-layer door and window hole (2);
step three: cutting a cross-layer door and window hole (2) on the outer wall of the old building (1);
step four: picking and chiseling the inner wall surface of the outer wall of the old building (1); then, a new reliable layer (4) is constructed by being attached to an outer wall, and the new reliable layer (4) is a bearing wall meeting the following conditions:
Condition 4.1: is fixedly connected with the outer wall of the old building (1) into a whole;
Condition 4.2: reserving an interface for installing a newly added floor slab;
Condition 4.3: the building can stably exist on the premise that the outer wall of the old building (1) does not exist;
Condition 4.4: waterproof;
step five: and installing the newly added floor slab on the newly added reliable layer (4) layer by layer from bottom to top.
2. The method for rebuilding the newly added floor slab when the original bearing outer wall is interfered according to claim 1, which is characterized in that: if the old buildings (1) are arranged in a plurality of rows, before the construction of the fourth step is started, the overhanging construction corridor (5) is arranged on one side of the row of old buildings (1) in advance, and in the step one, at least one cross-layer door and window hole (2) of each old building (1) is led to the overhanging construction corridor (5); and in the decoration stage after the reconstruction of the old building (1), the overhanging construction corridor (5) is covered with the glass curtain wall and the ceiling to form a corridor for households.
3. The method for rebuilding the newly added floor slab when the original bearing outer wall is interfered according to claim 1, which is characterized in that: the steel bars of the newly added floor slabs penetrate through the newly added reliable layers (4) and are implanted into the outer wall of the old building (1).
4. The method for rebuilding the newly added floor slab when the original bearing outer wall is interfered according to claim 3, which is characterized in that: step four comprises the following sub-steps:
step 4.1: picking and chiseling the inner wall surface of the outer wall of the old building (1);
step 4.2: the method comprises the steps of implanting a throwing rib of a newly-added floor slab on the inner wall surface of the outer wall of an old building (1), wherein the throwing rib penetrates through a newly-added reliable layer (4) and extends into the old building (1);
Step 4.3: binding a reinforcement cage of the newly-added reliable layer (4), and installing an embedded part used for being connected with a beam of the newly-added floor below the position of the newly-added floor, wherein the beams of the newly-added floor are connected into a grid shape;
Step 4.4: pouring concrete of the newly added reliable layer (4), and reserving grooves with rough surfaces on the inner surfaces at the positions of the newly added floors during pouring;
The construction process of each layer of newly added floor slab is as follows:
And (3) installing the beam of the newly added floor slab, binding the reinforcement cage of the newly added floor slab, and fixedly connecting with the throwing rib in the step (4.2), and pouring concrete.
5. The method for rebuilding the newly added floor slab when the original bearing outer wall is interfered according to claim 4, which is characterized in that: the new-added reliable layer (4) is a reinforced concrete shear wall, and a ring beam for supporting the edges of the new-added floor slab is formed by protruding outwards below the new-added floor slab, and continuous steel bars or section steel which winds the whole old building (1) for a circle are arranged in the ring beam and the edges of the new-added floor slab.
6. The method for rebuilding the newly added floor slab when the original bearing outer wall is interfered according to claim 1, which is characterized in that: in the cross-layer door window hole (2), all doors and windows are arranged along the vertical direction; and doors and windows on the same floor are respectively provided with a shutter for ventilation, a glass window for lighting and a door for passing from top to bottom.
7. The method for rebuilding the newly added floor slab when the original bearing outer wall is interfered according to claim 1, which is characterized in that: before the second construction, checking and repairing the defects of the concrete on the outer wall surface of the old building (1); and grouting and repairing the cracks, wherein defects outside the cracks are repaired by adopting a mode of filling new concrete after V-shaped grooves are formed at the defect positions by chiseling.
CN202411049995.0A 2024-08-01 2024-08-01 A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall Active CN118564105B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202411049995.0A CN118564105B (en) 2024-08-01 2024-08-01 A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202411049995.0A CN118564105B (en) 2024-08-01 2024-08-01 A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall

Publications (2)

Publication Number Publication Date
CN118564105A CN118564105A (en) 2024-08-30
CN118564105B true CN118564105B (en) 2024-11-12

Family

ID=92468456

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202411049995.0A Active CN118564105B (en) 2024-08-01 2024-08-01 A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall

Country Status (1)

Country Link
CN (1) CN118564105B (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114673377A (en) * 2022-04-09 2022-06-28 中建八局第三建设有限公司 Reservation of exterior walls of historic buildings and construction methods for interior hollowing out and remaking
CN117468748A (en) * 2023-10-16 2024-01-30 中震(北京)工程检测股份有限公司 Adding new corner columns and ring beams to the indoor floor of industrial plants and their construction methods

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5129465B2 (en) * 2006-07-24 2013-01-30 株式会社竹中工務店 Reconstruction method
CN215830079U (en) * 2021-07-02 2022-02-15 北京首钢国际工程技术有限公司 Reinforcing node system for retaining high and large masonry wall of outer vertical face by original appearance of historical building
CN117967092B (en) * 2024-03-13 2024-09-17 北京建工四建工程建设有限公司 Construction method for removing and modifying building without temporary support of building
CN117868556B (en) * 2024-03-13 2024-06-25 北京建工四建工程建设有限公司 Building dismantling and modifying support system taking building as bearing member
CN118208066B (en) * 2024-05-22 2024-07-12 上海建工一建集团有限公司 Construction method for layer-adding transformation of interior of existing cylindrical structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114673377A (en) * 2022-04-09 2022-06-28 中建八局第三建设有限公司 Reservation of exterior walls of historic buildings and construction methods for interior hollowing out and remaking
CN117468748A (en) * 2023-10-16 2024-01-30 中震(北京)工程检测股份有限公司 Adding new corner columns and ring beams to the indoor floor of industrial plants and their construction methods

Also Published As

Publication number Publication date
CN118564105A (en) 2024-08-30

Similar Documents

Publication Publication Date Title
US9382709B2 (en) Premanufactured structures for constructing buildings
CA2801287C (en) Lift-slab construction system and method for constructing multi-story buildings using pre-manufactured structures
US9027307B2 (en) Construction system and method for constructing buildings using premanufactured structures
CN103669905A (en) Lightweight composite prefabricated panel combined type house and building method thereof
JP2004285691A (en) Earthquake-resisting reinforced extension method of building and earthquake-resisting reinforced extension building
CN108755968A (en) Assembling synthesis building and its construction method
CN111927249B (en) Integral prefabricated embedded bay window, connecting node and manufacturing method
CN103669707A (en) Light composite prefabricated wallboard for house and preparation method thereof
CN118564104B (en) New and old building nested composite structure capable of utilizing old and stable in internal environment
CN104153576B (en) Construction method of building combined type building
CN208650272U (en) Assembling synthesis building
CN107401214A (en) A kind of installation method of assembled architecture
CN111254937A (en) Installation method of fabricated building
RU2140509C1 (en) Domestic house of the first mass series with attic floor of volumetric block-rooms, method for arrangement of attic floor and complex reconstruction of house
CN118564105A (en) Method for rebuilding newly-added floor slab when interference exists in original bearing outer wall
CN114135092B (en) House construction fully interspersed anti-collision system
CN118564103B (en) A method for renovating and utilizing a large-scale old building while retaining its appearance
CN208934122U (en) A kind of assembling synthesis building
RU2336399C1 (en) Method for rebuilding of large-panel apartment house
CN118601374A (en) A method for reconstructing rows of small-section buildings by making full use of old buildings
CN106088643B (en) A kind of planning and designing method of Old building earthquake-resistant structure group
CN211523554U (en) Prefabricated outer wall window hole waterproof node of assembly type structure
Antoniou Restoration Study of late Ottoman Terzakis House in Nafplion
Nowogońska et al. Maintenance Management in an Un-renovated Building
Díaz et al. Rehabilitation Operations in Residential Buildings in La Mina Neighborhood (S. Adrià del Besòs, Barcelona)

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant