- Publication number
- EP0484080B1 EP0484080B1 EP19910309935 EP91309935A EP0484080B1 EP 0484080 B1 EP0484080 B1 EP 0484080B1 EP 19910309935 EP19910309935 EP 19910309935 EP 91309935 A EP91309935 A EP 91309935A EP 0484080 B1 EP0484080 B1 EP 0484080B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- bracket
- soldiers
- concrete formwork
- support members
- soldier
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000009415 formwork Methods 0.000 title claims description 30
- 230000014759 maintenance of location Effects 0.000 description 2
- 238000005266 casting Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/14—Bracing or strutting arrangements for formwalls; Devices for aligning forms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
- E04G11/062—Forms for curved walls
- E04G11/065—Forms for curved walls with mechanical means to modify the curvature
Definitions
- This invention relates to concrete formwork. It is particularly concerned with formwork of the type employed to produce walls, especially formwork for producing curved walls.
- One type of concrete formwork is known from British Patent GB-A-2133826. This describes formwork for producing curved walls comprising a deformable panel and a plurality of U-shaped members secured to the panel by their legs and arranged in at least two columns.
- a soldier i.e., a structural member comprising two, spaced connected beams with aligned holes therein, spans across two or more support members in the same column and is connected thereto by a way of the faces of the members.
- the outer faces of two adjacent soldiers are connected by an adjustable tie whereby the distance between the soldiers may be altered to vary the curvature of the panel. Any desired height can be accommodated simply by altering the number of U-shaped members in each column and employing different lengths of soldier.
- the soldiers provide rigidity. In use, two panels, each supported by a plurality of U-shaped members and soldiers, are positioned a distance apart and concrete is cast between them to form a wall.
- ties are employed which extend between, and beyond the outer sides of, the panels. These ties serve to hold the panels together. Generally they are threaded and, once inserted through the panels, correspondingly threaded nuts are attached to their ends. The nuts are screwed down to pull the panels together and enable them to resist the forces generated by the concrete to be poured therebetween.
- the bases of the U-shaped members are formed with holes so that the ties can pass through the members and then between the webs of the soldier.
- the nuts, employed with the ties are bolted down against the outer pair of flanges of the soldier. The soldiers serve to evenly distribute loads generated by the pressure of the concrete acting on the panels which is passed through the ties and the-U-shaped members.
- French Patent FR-A-2613747 describes concrete formwork including a panel supported by support members comprising wooden beams arranged in pairs.
- a bracket is attached to each pair of wooden beams by screws.
- the bracket defines a C-shaped socket for receiving the cross flanges at one end of an I-shaped beam therein.
- the I-beam is formed from two U-beams connected back to back.
- the cross flanges at the end of the I-beam have a fixed stop at one extremity and a releasable stop at the other to permit insertion thereof into, and retention thereof by, the C-shaped sockets of the bracket members.
- I-beams are attached between each adjacent alternate pair of support members, a tie being connected to each beam rather than to each support member.
- each bracket member includes a support post with an aperture therein whereby it may be attached to a soldier by pinning through the aperture and one of the pairs of aligned holes in the soldier and in that each bracket member also provides a second opposing surface for abutment by the opposite side of the beam to retain the beam in position between the soldiers.
- ties to be provided at locations other than at the soldiers, that is, a greater number of possible tie positions are available.
- Known ties are, in fact, capable of supporting greater loads than those to which they are subjected in formwork, such as that known from GB-B-2133826.
- one tie can be used to support a number of soldiers. Therefore the number of ties which has to be employed is less. The resultant reduction in making good which has to be done to a concrete section is significant.
- one tie is employed per alternate adjacent pair of soldiers.
- each bracket member includes an angled portion against the apex of which, in use, the beam abuts.
- the bracket member may be arranged so that the apex of the angled portion lies between the webs of the soldier to which the bracket member is connected, preferably in the median plane of the soldier. Load transferal to the soldier is therefore along its centre line.
- the bracket member may further comprise a circular rod spaced from the apex of the angled member, the beam in use passing between the circular rod and the angled member.
- the distance between the rod and the angled member is made approximately equal to the appropriate beam dimension.
- the panels may be deformable and the soldiers may additionally be connected by adjustable length link means.
- the formwork is then suitable for use in the construction of curved walls.
- Figure 1 shows a section of concrete formwork 2 comprising a panel 4, U-shaped members 6, soldiers 8 and a tie 10.
- the panel 4 forms part of a panelling wall which is connected to a plurality of the U-shaped members 6.
- the U-shaped members 6 basically comprise two inclined legs 12 joined together by a base flange 14.
- the members 6 are secured to the panelling wall through holes in end flanges 16.
- the plurality of U-shaped members 6 are arranged in a series of columns spaced around the panelling wall.
- One soldier 8 spans over the U-shaped members 6 in a column to act as a continuity member therefor.
- the members 6 include support posts (not shown) carried on the base flange 14 thereof. These support posts extend between the webs of the soldiers 8 and are connected thereto. The ends of the support posts extend beyond the soldiers 8 and are arranged to be connected to a turn buckle. Turn buckles are provided between each pair of soldiers and, by employing these to vary the distance between the soldiers, the curvature of the panelling wall can also be varied.
- the complete concrete formwork includes a second panelling wall, supported by U-shaped members and soldiers, which is spaced from the first so the concrete can cast therebetween.
- ties are employed which extend between the panelling walls, the ties being held in place by securing their ends which lie on the outer sides of the panelling walls.
- the ties serve to pull the two sections of the formwork together against the pressure exerted by the concrete to be cast therebetween. Once casting is complete, at least a portion of the ties are removed from the cast concrete with the result that this is left with holes which have to be made good.
- the ties have been attached by way of the panel supports in whatever form these were provided.
- the ties pass through holes in the base flanges 14 of the U-shaped members 6 between the webs of the soldiers 8 and their ends are closed by nuts which are tightened up against the flanges of the soldiers 8.
- At least one tie per column of U-shaped members 6 has to be provided and often two or three per column are necessary.
- a bracket 18 is attached to each soldier.
- the bracket 18 comprises a support post 20 dimensioned to fit between the webs of the soldier 8 and formed with a hole 22.
- the brackets 18 are connected to the soldiers 8 by passing a pin, see 24, through holes in the soldier 8 and the holes 22 in the support post 20 of the bracket 18.
- the support post 20 carries a baseplate 26 from which two trapezoidal shaped wings 28 extend, the long edge of the wings 28 being connected to the baseplate 26. At their free ends the wings 28 are connected by a circular rod 30.
- An angle member 32 is mounted to the baseplate 26 between the other ends of the wings 28.
- a bracket 18 is mounted to each soldier 8 by pinning it thereto. With the brackets 18 in place, a beam 34 can be attached between two of the soldiers 8 by passing it through the apertures of the brackets 18 defined by the wings 28, rods 30 and angled member 32. The distance between the rods 30 and the angle member 32 of the brackets 18 can be so arranged that, no matter at what angle the soldiers 8 are to each other, the beam 34 will be held by the brackets 18 between the apices 36 of the angle members 32 and the rods 30.
- the beams 34 which are preferably hollow sections, include holes therein through which a tie 10 can be passed.
- the beams 34 have a plurality of such holes so that the ties 10 can be provided wherever desired.
- a tie 10 is held in position relative to a beam by attaching a washer 38 and a nut 40 to its free ends.
- the beams 34 provide additional tie locations.
- a tie 10 is capable of supporting more than one soldier 8 and, by providing the beams 34, a tie 10 can be positioned so that it will do this.
- a tie 10 is provided between each alternate adjacent pair of beams 34. Therefore the amount of holes in the concrete cast between the first and second panels of the formwork is halved, with a consequent 50% reduction in the necessary "making good".
- the angled member 32 of the brackets 18 is positioned so that, when a bracket 18 is connected to a soldier 8, its apex 36 lies on the centre line of the soldier which passes between the webs thereof. Loading on the beam 34 will therefore be transmitted, by the contact thereof with the apices 36 of the brackets 18, through the middle of the soldiers 8. This maximises the strengthening effect of the beams 34.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Claims (7)
- Eine Betonverschalung (2), umfassend eine oder mehrere Platten (4), mindestens Zwei Abstützelemente (6, 8) zum Abstützen der Platte(n) (4) und Mittel zum Verbinden der Abstützelemente (6, 8) mit der (den) Platte(n) (4), an den Abstützelementen (6, 8) befestigte Halterungsmittel (18), wobei mindestens ein Träger (34) zwischen den beiden Abstützelementen (6, 8) angeordnet ist und die Halterungsmittel ein Halterungselement (18) umfassen, das an jedem Abstützelement (6, 8) für den oder jeden der dazwischen angeordneten Träger (34) angebracht ist, so daß mit Hilfe der besagten Halterungselemente (18) der (die) Träger (34) an den Abstützelementen (6, 8) befestigt ist (sind), wobei jedes Halterungselement (18) eine erste Oberfläche (36) zum Anlegen der Seite des Trägers (34) aufweist, der dadurch anschließend an die Abstützelemente (6, 8) angeordnet ist, während der bzw. jeder Träger (34) mit dem Ende einer Zugstange (10) verbunden werden kann, dadurch gekennzeichnet, daß die Abstützelemente (6, 8) Stützrahmenvorrichtungen (8) umfassen, wobei die besagte Stützrahmenvorrichtung ein zwei mit Abstand verbundene Träger mit darin befindlichen ausgerichteten Löchern umfaßt, daß jedes Halterungselement (18) eine Stütze (20) mit einer darin befindlichen Öffnung (22) umfaßt, mit deren Hilfe das besagte Halterungselement an eine Stützrahmenvorrichtung (8) angebracht werden kann, indem man durch die Öffnung (22) und eines der Paare ausgerichteter Löcher in der Stützrahmenvorrichtung (8) einen Stift einsetzt, sowie daß jedes Halterungselement (18) auch eine zweite entgegengesetzte Oberfläche (30) zum Anlegen der entgegengesetzten Seite des Trägers (34) bietet, um den Träger (34) zwischen den Stützrahmenvorrichtungen (8) in Position zu halten.
- Betonverschalung nach Anspruch 1, bei der der Träger (34) zwecks Aufnahme eines Endes einer Zugstange (10) mit einer Mehrzahl von Löchern versehen ist.
- Betonverschalung nach Anspruch 1 oder Anspruch 2, bei der eine Mehrzahl von Stützrahmenvorrichtungen (8) vorgesehen ist, wobei an jeder der besagten Stützrahmenvorrichtungen ein Halterungselement (18) angebracht ist, während zwischen jedem zweiten anschließenden Paar der Stützrahmenvorrichtungen (8) mit Hilfe des Halterungsmittels (18) mindestens ein Träger (34) angeordnet ist.
- Betonverschalung nach einem der vorstehenden Ansprüche, bei der jedes Halterungselement (18) ein abgewinkeltes Element (32) einschließt, dessen Scheitel (36) die erste Oberfläche umfaßt.
- Betonverschalung nach Anspruch 4, bei der jedes Halterungselement (18) so angeordnet ist, daß der Scheitel (36) des abgewinkelten Elements (32) davon in der Mittelebene der Stützrahmenvorrichtung (8) liegt, an der es befestigt ist.
- Betonverschalung nach Anspruch 5, bei der jedes Halterungselement (18) eine runde Stange (30) umfaßt, die die zweite Oberfläche bildet.
- Betonverschalung nach einem der vorstehenden Ansprüche, bei der jedes Halterungselement (18) eine Öffnung abgrenzt, wobei die ersten und zweiten Oberflächen (30, 36) entgegengesetzte Wände der Öffnung umfassen.
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| GB9023699 | 1990-10-31 | ||
| GB909023699A GB9023699D0 (en) | 1990-10-31 | 1990-10-31 | Improvements in and relating to concrete formwork |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| EP0484080A1 EP0484080A1 (de) | 1992-05-06 |
| EP0484080B1 true EP0484080B1 (de) | 1995-07-19 |
Family
ID=10684663
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| EP19910309935 Expired - Lifetime EP0484080B1 (de) | 1990-10-31 | 1991-10-28 | Verbesserungen an Betonschalungen |
Country Status (5)
| Country | Link |
|---|---|
| EP (1) | EP0484080B1 (de) |
| DE (1) | DE69111373T2 (de) |
| ES (1) | ES2076480T3 (de) |
| GB (1) | GB9023699D0 (de) |
| IE (1) | IE71213B1 (de) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE4116439C1 (de) * | 1991-05-18 | 1992-08-27 | Maier G Paschal Werk | |
| ES2124105B1 (es) * | 1994-02-17 | 1999-11-16 | Perez Antonio Navarro | Sistema de encofrado curvilineo. |
| CN104863360B (zh) * | 2015-06-08 | 2017-04-05 | 中冶建工集团有限公司 | 曲面模板支撑体系及采用该支撑体系安装曲面模板的方法 |
| CN112962958A (zh) * | 2021-01-23 | 2021-06-15 | 陕西创宜建筑科技有限公司 | 一种卫生间吊模用圆弧模板 |
| CN113374256B (zh) * | 2021-06-23 | 2022-05-13 | 中国十七冶集团有限公司 | 一种弧形墙体模板加固装置和使用方法 |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2613747B1 (fr) * | 1987-04-10 | 1990-10-19 | Ricard Coffrages | Traverse a appuis mobiles et orientables pour l'execution de banches, et banches realisees a l'aide de cette traverse |
-
1990
- 1990-10-31 GB GB909023699A patent/GB9023699D0/en active Pending
-
1991
- 1991-10-28 EP EP19910309935 patent/EP0484080B1/de not_active Expired - Lifetime
- 1991-10-28 ES ES91309935T patent/ES2076480T3/es not_active Expired - Lifetime
- 1991-10-28 DE DE1991611373 patent/DE69111373T2/de not_active Expired - Fee Related
- 1991-10-30 IE IE378891A patent/IE71213B1/en not_active IP Right Cessation
Also Published As
| Publication number | Publication date |
|---|---|
| IE913788A1 (en) | 1992-05-22 |
| DE69111373T2 (de) | 1996-03-07 |
| IE71213B1 (en) | 1997-02-12 |
| ES2076480T3 (es) | 1995-11-01 |
| EP0484080A1 (de) | 1992-05-06 |
| GB9023699D0 (en) | 1990-12-12 |
| DE69111373D1 (de) | 1995-08-24 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| AU630774B2 (en) | Beam member for concrete forming system | |
| US2936051A (en) | Metal structural unit | |
| US5230197A (en) | Adjustable space frames | |
| JP2002536574A (ja) | 構造部材 | |
| GB2133826A (en) | Adjusting curvature of formwork | |
| EP0484080B1 (de) | Verbesserungen an Betonschalungen | |
| US5029803A (en) | Device for adapting a formwork element to given radii of a circular formwork | |
| JPH03233061A (ja) | ラチス柱 | |
| JPH03233062A (ja) | 柱の構成方法 | |
| JP3452600B2 (ja) | 型枠パネル | |
| US4522000A (en) | Earthquake safety support for transportable building | |
| JP2004263383A (ja) | X型交差張弦梁構造体 | |
| JPS63500877A (ja) | 調節自在のスペ−スフレ−ム | |
| JP2790817B2 (ja) | 架構構造 | |
| JP2617751B2 (ja) | 柱型枠装置 | |
| EP0485095B1 (de) | Verbesserungen an Verbindungen für Bauträger | |
| EP0067251A1 (de) | Modulares Raumfachwerk und dazu verwendete Modulareinheiten | |
| JPH07189217A (ja) | ア−チコンクリ−ト施工用型枠支保工 | |
| JPS581558Y2 (ja) | スラブ型枠板支持装置 | |
| JPH021394Y2 (de) | ||
| JPH0453226B2 (de) | ||
| JPH11165819A (ja) | 構造物一体型自動倉庫 | |
| JPH022811Y2 (de) | ||
| JPS621905A (ja) | ア−チコンクリ−ト施工用の型枠支保工 | |
| EP0392628B1 (de) | Schalung für zu schüttende Wände, sowie Vertikalträger dafür |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
| AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): DE ES GB |
|
| 17P | Request for examination filed |
Effective date: 19921026 |
|
| 17Q | First examination report despatched |
Effective date: 19930210 |
|
| RAP1 | Party data changed (applicant data changed or rights of an application transferred) |
Owner name: LEADA ACROW LIMITED (REG. N 2766044) |
|
| GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
| AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): DE ES GB |
|
| REF | Corresponds to: |
Ref document number: 69111373 Country of ref document: DE Date of ref document: 19950824 |
|
| REG | Reference to a national code |
Ref country code: ES Ref legal event code: FG2A Ref document number: 2076480 Country of ref document: ES Kind code of ref document: T3 |
|
| PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
| 26N | No opposition filed | ||
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: ES Payment date: 19991020 Year of fee payment: 9 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 19991102 Year of fee payment: 9 |
|
| REG | Reference to a national code |
Ref country code: GB Ref legal event code: 732E |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20001025 Year of fee payment: 10 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20001029 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20010703 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20011028 |
|
| REG | Reference to a national code |
Ref country code: GB Ref legal event code: IF02 |
|
| GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20011028 |
|
| REG | Reference to a national code |
Ref country code: ES Ref legal event code: FD2A Effective date: 20011113 |