EP4087980A1 - Procédé d'installation d'un support pour supporter une structure de charge, telle qu'une éolienne, sur, par exemple, un fond marin - Google Patents

Procédé d'installation d'un support pour supporter une structure de charge, telle qu'une éolienne, sur, par exemple, un fond marin

Info

Publication number
EP4087980A1
EP4087980A1 EP21700096.7A EP21700096A EP4087980A1 EP 4087980 A1 EP4087980 A1 EP 4087980A1 EP 21700096 A EP21700096 A EP 21700096A EP 4087980 A1 EP4087980 A1 EP 4087980A1
Authority
EP
European Patent Office
Prior art keywords
pile
jacket
pile holding
holding section
bed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP21700096.7A
Other languages
German (de)
English (en)
Other versions
EP4087980B1 (fr
EP4087980C0 (fr
Inventor
Paul Marius Antonius Vernimmen
Stefan Petrus Hendrik ERENTS
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Van Oord Offshore Wind BV
Original Assignee
Van Oord Offshore Wind BV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Van Oord Offshore Wind BV filed Critical Van Oord Offshore Wind BV
Priority to EP23205261.3A priority Critical patent/EP4286592A3/fr
Publication of EP4087980A1 publication Critical patent/EP4087980A1/fr
Application granted granted Critical
Publication of EP4087980B1 publication Critical patent/EP4087980B1/fr
Publication of EP4087980C0 publication Critical patent/EP4087980C0/fr
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/02Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
    • E02B17/027Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto steel structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • E02B2017/0043Placing the offshore structure on a pre-installed foundation structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • E02B2017/0047Methods for placing the offshore structure using a barge
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0091Offshore structures for wind turbines

Definitions

  • the present invention relates to a method of installing a support for supporting a load structure, such as a wind turbine or transformer platform or an oil or gas platform, thereon on bed, floor or bottom of, for instance, a sea, ocean, lake, harbor or river.
  • the invention further relates to the offshore support and components thereof, and a method of providing such load structure on the bed, floor or bottom.
  • a commonly used form of offshore support structure consists of a stand-alone multi-legged unit, the offshore jacket, made of steel which is stabbed onto pre-driven or otherwise embedded piles or having post-driven piles and then grouted to fixate it to the sea bed.
  • Jackets are produced and assembled on land and, subsequently, transported to the offshore site and thereby installed.
  • considerable size of the jackets which can reach tens of meters of height, considerable resources and extensive costs are involved in the production, assembly, stocking, logistics and load-out, transportation and installation of these structures.
  • the invention provides for a method of installing a support for supporting a load structure, such as a wind turbine or a transformer platform or an oil or gas platform, thereon on a bed, floor or bottom of, for instance a sea, ocean, lake, harbor or river.
  • a load structure such as a wind turbine or a transformer platform or an oil or gas platform
  • the method comprises positioning a pile guiding frame on the bed, floor or bottom, wherein the pile guiding frame comprises at least three pile holding sections, optionally at an outside perimeter of the pile guiding frame, each pile holding section allows guiding and maintaining a pile along a pile guiding direction in a substantially vertical orientation, and neighbouring and/or opposing pile holding sections are interconnected by mutually crossing diagonal cross-beams; driving a pile through each pile holding section of the pile guiding frame into the bed, floor or bottom such that each pile projects in an upward direction out of the bed, floor or bottom and out of its associated pile holding section over a projection length from each pile holding section, and providing a jointly rigid structure of the pile holding frame and the piles driven through each pile holding section in the bed, floor or bottom, wherein the projection length is in the range of 1 - 10 times, optionally in the range of 2 - 5 times, a diameter of the piles; and providing a jacket on the piles projecting out of the pile holding sections, and securing the jacket to the piles so that the piles
  • each pile is secured to its associated pile holding section to provide the jointly rigid structure.
  • each pile is secured to its associated pile holding section at positions at which a diagonal cross-beam is connected to the associated pile holding section.
  • each pile is secured to its associated pile holding section at each position at which a diagonal cross-beam is connected to the associated pile holding section.
  • each pile is secured to its associated pile holding section of the pile holding frame at a top end and a bottom end of the respective pile holding section.
  • neighbouring and/or opposing pile holding sections are interconnected by two mutually crossing diagonal cross-beams, each connected at a top end and a bottom end of a respective pile holding section.
  • a longitudinal direction of each respective diagonal cross-beam and the pile guiding direction of a pile holding section to which the respective cross-beam is connected enclose an angle in the range of 25 - 65 degrees, optionally in the range of 35 - 55 degrees.
  • a horizontal beam is arranged in between neighbouring and/or opposing pile holding sections and connected to the respective pile holding sections at positions at which a diagonal cross-beam is connected to the pile holding sections.
  • a bottom end of the jacket is provided on the piles.
  • the bottom end of the jacket comprises downward projecting stabbing projections, optionally at an outside perimeter of the jacket, each stabbing projection being provided to couple with a top end of an associated pile of the jointly rigid structure.
  • each stabbing projection is inserted into an inner circumference of the associated pile.
  • each pile is inserted into an inner circumference of the stabbing projection, wherein the stabbing projection has a hollow cylindrical shape.
  • the jacket comprises jacket supporting skirts, each stabbing projection being associated with a jacket supporting skirt, and wherein the jacket is provided onto the piles so that each jacket supporting skirt bears on the associated pile.
  • the pile holding sections comprise hollow columns, optionally fitted with centralizer fittings and an upward tapered pile stabbing cone at a top end of each pile holding section providing a guidance for the associated pile when stabbing the associated pile into a respective pile holding section during piling operations.
  • the pile guiding frame is provided with a footing at each pile holding section for supporting the pile guiding frame on the bed, floor or bottom, optionally the footing including a system for adjusting a vertical position of each pile holding section in order to achieve verticality of all pile holding sections.
  • a pile driven into the bed, floor or bottom is secured to the associated pile holding section of the pile guiding frame by means of at least one of a grouted connection or a mechanical connection.
  • At least one stabbing projection of the jacket is secured to its associated element by at least one of a grouted connection or a mechanical connection.
  • the invention provides for a method for providing a load structure, such as a wind turbine or transformer platform or an oil or gas platform on a bed, floor or bottom of, for instance, a sea, ocean, lake, harbor or river, the method comprising the method of installing an offshore support according to any one of the preceding claims, and providing the load structure onto the jacket of the offshore support structure.
  • a load structure such as a wind turbine or transformer platform or an oil or gas platform on a bed, floor or bottom of, for instance, a sea, ocean, lake, harbor or river
  • a jacket for supporting a load structure such as a wind turbine or transformer platform or an oil or gas platform, on a bed, floor or bottom of, for instance a sea, ocean, lake, harbor or river, and for use in a method referred to above for installing a support
  • the jacket is configured to be provided on a jointly rigid structure of a pile guiding frame, that comprises at least three pile holding sections, optionally at an outside perimeter of the pile guiding frame, each pile holding section allows guiding and maintaining a pile along a pile guiding direction in a substantially vertical orientation, and neighbouring and/or opposing pile holding sections are interconnected by mutually crossing diagonal cross-beams; and of piles driven through each pile holding section of the pile guiding frame in the bed, floor or bottom such that each pile projects in an upward direction out of the bed, floor or bottom and out of associated pile holding sections over a projection length from each pile holding section, wherein the projection length is in the range of 1 - 10 times
  • the jacket comprises at least three, optionally inclined, interconnected pillars, optionally at its outside perimeter, each pillar being configured for providing onto an associated pile driven in the bed, floor or bottom such that the load of the jacket is supported on the piles driven in the bed, floor or bottom.
  • the jacket comprises a stabbing projection provided at a bottom end of each pillar, optionally the stabbing projections being at an outer perimeter of the jacket, wherein each stabbing projection is configured to be provided on a top end of an associated pile or on a top of an associated pile holding section.
  • At least one stabbing projection of the jacket is configured to be secured to the associated pile driven into the bed, floor or bottom by at least one of a grouted connection or a mechanical connection.
  • the stabbing projections are configured to fit into an inner circumference of the associated pile.
  • the stabbing projections have a hollow cylindrical shape and are configured to allow the insertion of an upper portion of the associated pile therein, such that each one of the piles fits into an inner circumference of the associated stabbing projection.
  • at least one stabbing projection comprises a jacket supporting skirt protruding from at least a part of an outer perimeter of the at least one stabbing projection in a substantially radial direction and configured to couple with the associated pile.
  • the jacket is configured to, in its mounted configuration, to project at least partially out of a water surface of a mass of water, such as a sea, ocean, lake, harbor or river, above the bed, floor or bottom.
  • the jacket is configured to, in its mounted configuration, remain totally under a water surface of a mass of water, such as a sea, ocean, lake, harbor or river, above the bed, floor or bottom.
  • the invention provides for a pile guiding frame for use in a method referred to above of installing a support, wherein the pile guiding frame comprises pile holding sections, optionally at an outside perimeter of the pile guiding frame, each pile holding section allows guiding and maintaining a pile along a pile guiding direction in a substantial vertical direction, and neighbouring and/or opposing pile holding sections are interconnected by mutually crossing diagonal cross-beams.
  • the pile holding sections comprise hollow columns, optionally fitted with centralizer fittings and an upward tapered pile stabbing cone at a top end of each pile holding section configured to guide the associated pile when stabbing the associated pile into a respective pile holding section during piling operations.
  • the pile guiding frame comprises at least three pile holding sections arranged such that a perimeter constituted by each pile holding section forms a polygonal shape.
  • neighbouring and/or opposing pile holding sections are interconnected by two mutually crossing diagonal cross-beams, each connected at a top end and a bottom end of a respective pile holding section.
  • the pile holding sections have substantially the same length and wherein bottom ends of the pile holding sections are configured to be coplanar with a plane formed by the bed, floor or bottom.
  • a longitudinal direction of each respective diagonal cross-beam and the pile guiding direction of a pile holding section to which the respective cross-beam is connected enclose an angle in the range of 25 - 65 degrees, optionally in the range of 35 - 55 degrees.
  • a horizontal beam is arranged in between neighbouring and/or opposing pile holding sections and connected to the respective pile holding sections at positions at which a diagonal cross-beam is connected to the pile holding sections.
  • the bottom end of at least one pile holding section is out of a plane formed by the bottom ends of the remaining pile holding sections other than the at least one pile holding section, in order to accommodate unevenness of the bed, floor or bottom.
  • the pile guiding frame is provided with a footing at each pile holding section for supporting the pile guiding frame on the bed, floor or bottom, optionally the footing including a system for adjusting a vertical position of each pile holding section in order to achieve verticality of all pile holding sections.
  • a pile for use in a method referred to above of installing an offshore support structure, the pile having a substantially cylindrical shape and being configured to support the load of an jacket and of any structure mounted thereon.
  • the invention provides for a support for supporting a load structure, such as a wind turbine or a transformer platform or an oil or gas platform, thereon on a bed, floor or bottom of, for instance a sea, ocean, lake, harbor or river.
  • the support structure comprises a pile guiding frame, wherein the pile guiding frame is provided on the bed, floor or bottom, and comprises at least three pile holding sections, optionally at an outside perimeter of the pile guiding frame, each pile holding section allows guiding and maintaining a pile along a pile guiding direction in a substantially vertical orientation, and neighbouring and/or opposing pile holding sections are interconnected by mutually crossing diagonal cross-beams.
  • the support structure also comprises piles, wherein each pile is provided through a respective one of the pile holding sections of the pile holding frame into the bed such that each pile projects in an upward direction out of the bed, floor or bottom and out of its associated pile holding section over a projection length from each pile holding section, and the projection length is in the range of 1 - 10 times, optionally in the range of 2 - 5 times, a diameter of the piles, and wherein the pile holding frame and the piles driven through each pile holding section in the bed, floor or bottom providing a jointly rigid structure.
  • the support structure comprises a jacket, wherein the jacket is provided on the piles driven in the sea bed, floor or bottom, and is secured to the piles, such that the piles will bear the load of the jacket and of the load structure supported on the jacket.
  • Figure 2A shows an isometric view of the support of figures 1 A and 1 B, while figures 2B, 2C and 2D show the isometric views of the jacket, the piles and the pile guiding frame, respectively, of the support depicted in Figure 2A;
  • Figures 3A, 3B and 3C show steps of an embodiment according to the invention of a method to install a support on a sea bed
  • FIGS 4A and 4B show alternative embodiments of details of the support.
  • a support structure 100 for supporting a load structure such as a wind turbine or a transformer platform or an oil or gas platform, thereon on a bed, floor or bottom of, for instance a sea, ocean, lake, harbor or river.
  • a load structure such as a wind turbine or a transformer platform or an oil or gas platform
  • the embodiments will be described with reference to a “sea bed” but generally apply to ocean, lake, harbor, river beds or floors or bottoms as well, or any other relevant bed, bottom or floor or the like.
  • the embodiments will further be described with reference to “offshore” but generally apply to an inshore location, a port, a harbor or equivalents, or any other relevant location as well.
  • FIGs 1A, 1 B and 2B schematically show top and front views ( Figures 1 A and 1 B) and an isometric view ( Figure 2A) of an embodiment of an offshore support 100 which can be installed by using the method to which this invention relates.
  • the offshore support structure 100 comprises an offshore jacket 10, a pile guiding frame 20 and a plurality of piles 30 passing through pile holding sections 21 of the pile guiding frame 20.
  • the piles are configured to support the load of the offshore jacket 10 and of any load structure, such as a wind turbine, mounted on it.
  • the offshore jacket 10 includes at least three pillars 12 interconnected by a plurality of beams (or bracings).
  • the pile guiding frame 20 comprises, at its outside perimeter, a same number of pile holding sections 21 as the number of pillars of the offshore jacket 10, interconnected by diagonal cross-beams 25 and horizontal beams 26.
  • Each of the plurality of the pile holding sections 21 is configured to confine a pile 30 in a horizontal direction, so that the pile is held in a substantially vertical orientation.
  • each pile holding section 21 comprises a pile stabbing cone 22 at the top of each pile holding section providing a guidance of the associated pile 30 when stabbing the associated pile into a respective pile holding section during piling operations.
  • the elements of the offshore support structure 100 i.e. the pile guiding frame 20, the piles 30 and the offshore jacket 10, are transported on vessels or barges to the offshore installation site and there set down on the sea bed by means of cranes or equivalents.
  • the pile guiding frame 20 is lowered onto the sea bed.
  • the pile guiding frame 20 comprises at least three interconnected pile holding sections 21 at an outside perimeter of the pile guiding frame 20 in the embodiment shown, wherein the perimeter constituted by the bottom ends of the pile holding sections, proximal to the sea bed, may have a form of any regular or irregular polygonal shape, reflecting the shape of the offshore jacket to be positioned onto the piles.
  • the pile holding sections 21 are interconnected by diagonal cross-beams 25 and horizontal beams 26 in order to maintain a mutually fixed position and parallelism between the pile holding sections and to provide rigidity.
  • the pile guiding frame 20 is used during piling operations to eliminate the use of a removable piling template.
  • the pile guiding frame 20 provides stiffness and strength to the piles.
  • the use of such a permanent pile guiding frame 20 allows the customization of the spacing of the plurality of piles used to support the offshore jacket 10 to suit the water depth and seabed situation at each individual location.
  • the pile guiding frame 20 comprises a footing 23 configured to contact the sea bed and to give stability to the pile guiding frame 20.
  • the footing 23 includes a system for adjusting the vertical position of each pile holding section 21 in order to achieve verticality of the piles 30 and ultimately the support structure 100, depending on the unevenness of the seabed at the installation location.
  • the footing 23 may be placed in correspondence to each one of the pile holding sections 21 or may be positioned outside or inside the perimeter formed by the bottom ends of the pile holding sections. In these cases, the footing 23 is connected to the pile guiding frame 30 by means of bracings or equivalents.
  • This invention encompasses all embodiments in which the number of pile holding sections is larger than two, i.e. this invention is not limited to three, as shown for the embodiment in Figures 1A to 2D, or to four, as shown for the embodiment in Figures 3A to 4B, pile holding sections 21.
  • the pile holding sections 21 are substantially of the same length and are configured such that their bottom ends, proximal to the seabed, are coplanar with the plane formed by the sea bed.
  • the pile holding sections can be of different lengths in an alternative embodiment.
  • Each pile holding section 21 is configured to allow the guidance of a pile 30 and its maintaining along a guiding direction G in a substantially vertical orientation.
  • the pile holding sections 21 comprise a hollow column, configured to receive the pile and fitted with a centralizer fitting to guide the associated pile when stabbing the associated pile into a respective pile holding section during piling operations.
  • the pile holding sections 21 are fitted with a system for permanent fixation to the pile by means of grout or an alternative mechanical means of fixation such as by using wedges or hydraulic pistons to clamp the pile within a respective pile holding section.
  • the piles 30 are secured to the pile holding sections 21 at the top end and bottom end of the pile holding sections and at positions A at which the diagonal cross-beams 25 are connected to the associated pile holding sections to provide strength and rigidity to the structure of the pile guiding frame 21 and the piles 30 driven through and secured to the pile holding sections.
  • Strength and rigidity is further provided by having the diagonal cross-beams 25 connected at the top end and the bottom end of the respective pile holding sections, and to have a longitudinal direction of each respective diagonal cross-beam 25 and the pile guiding direction G of a pile holding section 21 to which the respective cross-beam is connected enclose an angle a in the range of 25 - 65 degrees, especially in the range of 35 - 55 degrees.
  • the pile guiding frame 21 further has horizontal beams 26 connected in between pile holding sections at those locations where the diagonal cross-beams 25 are connected as well to further add to the strength and rigidity of the jointly rigid structure.
  • the piles 30 are driven into the sea bed so as to extend considerably above the sea bed and to also extend above the pile guiding frame 20, thus, allowing the use of a shorter offshore jacket 10 than the commonly used ones. It also allows a constant and selected distance of the top of the offshore jackets with respect to the surface of the sea with varying sea depth and spread locations of the supports of pile guiding frames, piles and offshore jackets over the sea bed.
  • the projection length P (or stickup length) of the piles above the pile holding sections 21 of the pile guiding frame 20 can be, dependent on the specific application and circumstances, in the range of 1 - 10 times the diameter D of the piles, especially 2 - 5 times the diameter of the piles.
  • the piles stick out over a projection length P of about 3.5 times the pile diameter D above the pile holding sections 21 in the embodiment shown.
  • the jointly rigid structure of the pile guiding frame and the piles secured to the frame allow for a large upward stick out of the piles from the pile guiding frame.
  • the piles can have any diameter but typically will be in the range of 2 - 3 meter, which implies that projection or stickup length P can be up to 20 - 30 meter under favorable conditions. Generally, the projection length P will be in the range of 2 - 10 meter.
  • a pile guiding frame 20 can have a height of, for instance, 20 meter for application at a water depth of, for instance, 45 meter.
  • the fact that piles extend well above the sea bed implies the additional advantage that no emptying of the piles is required before providing the offshore jacket 10 onto the piles.
  • the offshore jacket 10 in the embodiment shown comprises a plurality of legs or pillars 12 interconnected by beams, bracings or equivalents which are configured to maintain a mutually fixed position between the plurality of legs.
  • the offshore jacket 10 may further comprise stabbing projections 11 on its outer perimeter in correspondence to the bottom end of each leg 12.
  • the pile guiding frame 20 and the piles 30 driven through the pile holding sections 21 of the pile guiding frame 20 together form a jointly rigid structure confining movement of the piles.
  • the offshore jacket 10 is lowered from the vessel towards the piles 30 driven through the pile holding sections 21 such that each one of the stabbing projections 11 is provided onto and secured to an associated pile 30 driven into the sea bed and such that the offshore jacket 10 projects at least partially out of the water surface W.
  • Each stabbing projection 11 is connected by means of a grouted connection or a mechanical connection to its associated pile 30.
  • the offshore jacket 10 may be installed in a position below the water surface W.
  • the offshore jacket 10 may be secured to the piles 30 by means of at least one of a grouted connection or a mechanical connection.
  • the piles 30 provide support forthe load of the offshore jacket 10 and of any structure mounted on it.
  • each one of the stabbing projections 11 fits into an inner circumference of the associated pile 30.
  • at least one of the stabbing projections 11 may comprise a jacket supporting skirt 13 protruding from at least a part of an outer perimeter of the stabbing projection 11 in a substantially radial direction and configured to couple with the associated pile 30 and, optionally, to transfer the load of the offshore jacket 10.
  • the stabbing projections 11 have a hollow cylindrical shape and are configured to allow the insertion of an upper portion of the associated piles 30, such that each one of the piles 30 fits into an inner circumference of the associated stabbing projection 11 .

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Wind Motors (AREA)

Abstract

La présente invention concerne un procédé d'installation d'un support pour supporter une structure de charge, telle qu'une éolienne, une plate-forme de transformateur ou une plate-forme de forage pétrolier ou gazier au fond d'une mer, d'un océan, d'un lac, d'un port ou d'une rivière. Le procédé consiste à positionner, sur un fond, un cadre de guidage de pile comprenant au moins trois sections de soutien de piles, chaque section de soutien de piles permettant le guidage et le soutien d'une pile le long d'une direction de guidage de la pile dans une orientation verticale, et des sections de soutien de piles adjacentes et/ou opposées sont interconnectées grâce au croisement mutuel de poutres transversales diagonales; à enfoncer une pile dans chaque section de soutien de piles dans le fond, de telle sorte que chaque pile fasse saillie vers le haut hors du fond et hors de sa section de soutien de piles associée sur une longueur de projection équivalant à une plage comprise entre 1 et 10 fois le diamètre des piles, et à former une structure mutuellement rigide du cadre de soutien de piles et des piles; et à installer une chemise sur les piles faisant saillie hors des sections de soutien de piles.
EP21700096.7A 2020-01-10 2021-01-07 Procédé d'installation d'un support pour supporter une structure de charge, telle qu'une éolienne, sur, par exemple, un fond marin Active EP4087980B1 (fr)

Priority Applications (1)

Application Number Priority Date Filing Date Title
EP23205261.3A EP4286592A3 (fr) 2020-01-10 2021-01-07 Procédé d'installation d'un support pour supporter une structure de charge, telle qu'une éolienne, par exemple sur un fond marin

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NL2024640A NL2024640B1 (en) 2020-01-10 2020-01-10 Method of Installing a Support for Supporting a Load Structure, such as a Wind Turbine, on, for instance, a Sea Bed
PCT/NL2021/050007 WO2021141490A1 (fr) 2020-01-10 2021-01-07 Procédé d'installation d'un support pour supporter une structure de charge, telle qu'une éolienne, sur, par exemple, un fond marin

Related Child Applications (1)

Application Number Title Priority Date Filing Date
EP23205261.3A Division EP4286592A3 (fr) 2020-01-10 2021-01-07 Procédé d'installation d'un support pour supporter une structure de charge, telle qu'une éolienne, par exemple sur un fond marin

Publications (3)

Publication Number Publication Date
EP4087980A1 true EP4087980A1 (fr) 2022-11-16
EP4087980B1 EP4087980B1 (fr) 2023-10-25
EP4087980C0 EP4087980C0 (fr) 2023-10-25

Family

ID=70614508

Family Applications (2)

Application Number Title Priority Date Filing Date
EP23205261.3A Pending EP4286592A3 (fr) 2020-01-10 2021-01-07 Procédé d'installation d'un support pour supporter une structure de charge, telle qu'une éolienne, par exemple sur un fond marin
EP21700096.7A Active EP4087980B1 (fr) 2020-01-10 2021-01-07 Procédé d'installation d'un support pour supporter une structure de charge, telle qu'une éolienne, sur, par exemple, un fond marin

Family Applications Before (1)

Application Number Title Priority Date Filing Date
EP23205261.3A Pending EP4286592A3 (fr) 2020-01-10 2021-01-07 Procédé d'installation d'un support pour supporter une structure de charge, telle qu'une éolienne, par exemple sur un fond marin

Country Status (5)

Country Link
EP (2) EP4286592A3 (fr)
KR (1) KR20220122760A (fr)
NL (1) NL2024640B1 (fr)
TW (1) TWI826763B (fr)
WO (1) WO2021141490A1 (fr)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113622399B (zh) * 2021-08-19 2025-01-24 中交第三航务工程局有限公司 一种海上风电四桩导管架基础施工用装配式平台
KR102693366B1 (ko) * 2022-09-22 2024-08-09 현대건설(주) 상부 및 하부 구조물로 분리된 프리파일링 시공용 자켓 및 인공신경망 모듈을 활용한 그 시공 방법
CN118793053A (zh) * 2023-04-14 2024-10-18 上海佳豪船海工程研究设计有限公司 一种打桩导向架及其施工方法
CN116497784A (zh) * 2023-04-26 2023-07-28 华电重工股份有限公司 深水导管架装置及其施工方法
KR102645338B1 (ko) * 2023-06-07 2024-03-08 롯데건설 주식회사 해저공간 플랫폼 승강시스템
CN119288776B (zh) * 2024-10-31 2025-06-06 三峡新能源(烟台牟平区)有限公司 海上风电风机基础导管架及可视化安装方法

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6299385B1 (en) * 1999-08-04 2001-10-09 Paragon Engineering Services Incorporated Mini-jacket and method for installation using caisson
CN101694093B (zh) * 2009-10-12 2011-08-10 中铁大桥局集团第四工程有限公司 钢管支承桩插打时快速定位和连接系统及其施工方法
WO2013049194A1 (fr) * 2011-09-26 2013-04-04 Horton Wison Deepwater, Inc. Tour de support modulaire déplaçable pour installation en mer
CN102535510A (zh) 2012-02-27 2012-07-04 广东明阳风电产业集团有限公司 海上风机导管架基础安装方法及一体化导管架装置
GB201206400D0 (en) * 2012-04-11 2012-05-23 Offshore Group Newcastle Ltd Offshore structure installation
CN102852154A (zh) * 2012-08-01 2013-01-02 天津大学 一种复合桩基
CN102936888B (zh) * 2012-11-09 2015-01-28 中国水电顾问集团华东勘测设计研究院 自主安装式海上升压站结构及其安装方法

Also Published As

Publication number Publication date
TW202142762A (zh) 2021-11-16
TWI826763B (zh) 2023-12-21
WO2021141490A1 (fr) 2021-07-15
EP4286592A3 (fr) 2024-02-14
EP4087980B1 (fr) 2023-10-25
NL2024640B1 (en) 2021-09-07
EP4087980C0 (fr) 2023-10-25
EP4286592A2 (fr) 2023-12-06
KR20220122760A (ko) 2022-09-02

Similar Documents

Publication Publication Date Title
EP4087980B1 (fr) Procédé d'installation d'un support pour supporter une structure de charge, telle qu'une éolienne, sur, par exemple, un fond marin
EP2836648B1 (fr) Installation de structures offshores
US10612523B1 (en) Offshore monopile wind turbine with triangular support structure
US4902169A (en) Jack-up type platform including adjustable stop assembly
EP2574698B1 (fr) Procédé et dispositif pour entraîner plusieurs piliers au fond de la mer
AU2011200123A1 (en) Method of Providing a Foundation for an Elevated Mass, and Assembly of a Jacked-Up Platform and a Framed Template for Carrying Out the Method
US4372707A (en) Pile installation and removal mechanisms in off-shore rigs and method of using same
JP2011144532A (ja) ジャケットの据え付け方法
EP2558648B1 (fr) Structure de fondations en mer, fondations en mer et son procédé d'établissement
CA1075022A (fr) Materiel d'extraction sous-marine du petrole et du gaz; installation du materiel
KR20130117486A (ko) 탑 사이드 데크 잭업 지지 구조물
WO2001055513A1 (fr) Plate-forme auto-elevatrice comprenant une structure de pont et une seule colonne de support et procede d'installation d'une telle plate-forme auto-elevatrice
DK181343B1 (en) Method for assembling an offshore support structure for a wind turbine
KR102304302B1 (ko) 수중 기초 구조물 시공 방법
US9458592B2 (en) Method for anchoring a structure in a bed of a body of water and underwater foundation
EP4386144B1 (fr) Procédé et appareil associé
DK2931978T3 (en) Method and arrangement for realizing a foundation structure for an on-water system.
KR20140140440A (ko) 하이브리드 지지 구조체 및 이의 시공방법
KR20260026525A (ko) 해상 풍력 터빈용 지지 구조물 및 상기 지지 구조물의 설치 프로세스
WO2015126237A1 (fr) Structure de support en mer et ses procédés d'installation
NL1041327B1 (en) Wind turbine jacket foundation for a wind farm with variable water depth.
EP4646532A1 (fr) Parc éolien
GB2395510A (en) Self piling reusable offshore platform
KR20130117223A (ko) 탑 사이드 데크 잭업 지지 구조물

Legal Events

Date Code Title Description
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: UNKNOWN

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE

PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20220728

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

DAV Request for validation of the european patent (deleted)
DAX Request for extension of the european patent (deleted)
GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20230509

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602021006221

Country of ref document: DE

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

U01 Request for unitary effect filed

Effective date: 20231109

U07 Unitary effect registered

Designated state(s): AT BE BG DE DK EE FI FR IT LT LU LV MT NL PT SE SI

Effective date: 20231115

U20 Renewal fee for the european patent with unitary effect paid

Year of fee payment: 4

Effective date: 20231219

U1N Appointed representative for the unitary patent procedure changed after the registration of the unitary effect

Representative=s name: V.O.; NL

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240126

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240225

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240225

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240126

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240125

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602021006221

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20240726

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20240131

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20240131

U20 Renewal fee for the european patent with unitary effect paid

Year of fee payment: 5

Effective date: 20241119

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20240107

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20240107

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20210107

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20210107

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231025

U20 Renewal fee for the european patent with unitary effect paid

Year of fee payment: 6

Effective date: 20260129

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20260123

Year of fee payment: 6