JP2000211027A - Channel facility lining method - Google Patents
Channel facility lining methodInfo
- Publication number
- JP2000211027A JP2000211027A JP1596699A JP1596699A JP2000211027A JP 2000211027 A JP2000211027 A JP 2000211027A JP 1596699 A JP1596699 A JP 1596699A JP 1596699 A JP1596699 A JP 1596699A JP 2000211027 A JP2000211027 A JP 2000211027A
- Authority
- JP
- Japan
- Prior art keywords
- lining material
- camera
- lining
- pipe
- closed space
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L58/00—Protection of pipes or pipe fittings against corrosion or incrustation
- F16L58/02—Protection of pipes or pipe fittings against corrosion or incrustation by means of internal or external coatings
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Protection Of Pipes Against Damage, Friction, And Corrosion (AREA)
- Lining Or Joining Of Plastics Or The Like (AREA)
Abstract
(57)【要約】
【目的】 ライニング材の硬化前にライニング材の内面
の状況を確認することができ、ライニング材におけるし
わの発生を確実に抑えるとともに、施工中のライニング
材内部のトラブルを事前に発見することができる流路施
設ライニング工法を提供すること。
【構成】 樹脂吸着材に未硬化の硬化性樹脂を含浸せし
めて成る管ライニング材(ライニング材)3を管路(流
路施設)1内に挿入した後、該管ライニング材3の内部
を含む密閉空間S内に供給される流体圧によって管ライ
ニング材3を膨張させてこれを管路1の内壁に押圧した
状態で、該管ライニング材3に含浸された前記硬化性樹
脂を硬化させるようにした流路施設ライニング工法にお
いて、前記密閉空間S内にTVカメラ20を挿入し、該
TVカメラ20によって密閉空間S内の状況を密閉空間
S外からモニタリングする。
(57) [Summary] [Purpose] Before hardening the lining material, the condition of the inner surface of the lining material can be checked, wrinkles in the lining material are surely suppressed, and problems inside the lining material during construction are checked in advance To provide a flow path facility lining method that can be found in Japan. After inserting a pipe lining material (lining material) 3 formed by impregnating a resin adsorbent with an uncured curable resin into a pipe (flow path facility) 1, the inside of the pipe lining material 3 is included. While the pipe lining material 3 is expanded by the fluid pressure supplied into the closed space S and pressed against the inner wall of the pipe 1, the curable resin impregnated in the pipe lining material 3 is cured. In the flow path facility lining method described above, the TV camera 20 is inserted into the closed space S, and the situation inside the closed space S is monitored from outside the closed space S by the TV camera 20.
Description
【0001】[0001]
【発明の属する技術分野】本発明は、老朽化した下水管
等の管路やマンホール或は枝管等の流路施設の内壁をラ
イニング材によってライニングして補修する流路施設ラ
イニング工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of lining a flow path facility for lining and repairing pipes such as aged sewer pipes and inner walls of flow path facilities such as manholes or branch pipes with a lining material.
【0002】[0002]
【従来の技術】老朽化した下水管等の管路やマンホール
或は枝管等の流路施設の内壁をライニング材によってラ
イニングして補修する流路施設ライニング工法が提案さ
れ、既に実用に供されている。2. Description of the Related Art A flow path facility lining method has been proposed in which an inner wall of a flow path facility such as an aged sewer pipe or a manhole or a branch pipe is lined and repaired with a lining material, and has already been put into practical use. ing.
【0003】上記流路施設ライニング工法は、樹脂吸着
材に未硬化の硬化性樹脂を含浸せしめて成るライニング
材を流路施設内に挿入した後、該ライニング材の内部を
含む密閉空間内に供給される流体圧によってライニング
材を膨張させてこれを流路施設の内壁に押圧した状態
で、該ライニング材に含浸された前記硬化性樹脂を硬化
させる工法であって、これによれば流路施設を地中から
屈出することなくこれを補修することができるという利
点が得られる。[0003] In the above-mentioned flow path facility lining method, a lining material obtained by impregnating a resin adsorbent with an uncured curable resin is inserted into a flow path facility, and then supplied into an enclosed space including the inside of the lining material. A method of curing the curable resin impregnated in the lining material in a state where the lining material is expanded by the applied fluid pressure and pressed against the inner wall of the flow path facility, and according to this, the flow path facility Can be repaired without sagging from the ground.
【0004】[0004]
【発明が解決しようとする課題】しかしながら、曲がり
を有する管路や枝管、レデューサ部を有するマンホール
或はボックスカルバートや馬蹄形等の非円形断面を有す
る管路に対してライニングを行った場合、管路やマンホ
ール等の内周壁の状況によってはライニング材の内面に
しわが発生する。そして、このしわはライニング終了後
にライニング材の内部を確認することによって発見され
ていた。However, when lining is performed on a pipe or a branch pipe having a bend, a manhole having a reducer portion, or a pipe having a non-circular cross section such as a box culvert or a horseshoe, Wrinkles may occur on the inner surface of the lining material depending on the condition of the inner peripheral wall such as a road or a manhole. The wrinkles were found by checking the inside of the lining material after the lining was completed.
【0005】而して、ライニング材のしわの発生を抑え
る種々の手法が今までに提案されている。例えば、ライ
ニング材を流路施設の内周寸法より僅か(3%〜15
%)に小さく製作してこれを流体圧によって引き伸ばし
たり、流体圧が作用したライニング材の内部で平ベルト
を牽引し或は別体のホースやバルーンを膨張させてしわ
を押さえる手法が提案されている。[0005] Various techniques have been proposed to suppress wrinkling of the lining material. For example, the lining material is slightly smaller (3% to 15%) than the inner peripheral dimension of the flow path facility.
%), Which is stretched by fluid pressure, or a flat belt is pulled inside a lining material to which fluid pressure is applied, or a separate hose or balloon is inflated to suppress wrinkles. I have.
【0006】ところが、上記手法を施した場合であって
もしわの発生の確認はライニング材の硬化後でしか行う
ことができず、しわの発生を確実に抑えることは不可能
であった。However, even when the above method is applied, the occurrence of wrinkles can be confirmed only after the lining material is cured, and it has not been possible to reliably suppress the occurrence of wrinkles.
【0007】本発明は上記問題に鑑みてなされたもの
で、その目的とする処は、ライニング材の硬化前にライ
ニング材の内面の状況を確認することができ、ライニン
グ材におけるしわの発生を確実に抑えるとともに、施工
中のライニング材内部のトラブルを事前に発見すること
ができる流路施設ライニング工法を提供することにあ
る。SUMMARY OF THE INVENTION The present invention has been made in view of the above problems, and an object thereof is to check the condition of the inner surface of a lining material before the lining material is cured, thereby ensuring that wrinkles in the lining material are not generated. Another object of the present invention is to provide a flow path facility lining method capable of detecting in advance the trouble inside the lining material during construction.
【0008】[0008]
【課題を解決するための手段】上記目的を達成するた
め、請求項1記載の発明は、樹脂吸着材に未硬化の硬化
性樹脂を含浸せしめて成るライニング材を流路施設内に
挿入した後、該ライニング材の内部を含む密閉空間内に
供給される流体圧によってライニング材を膨張させてこ
れを流路施設の内壁に押圧した状態で、該ライニング材
に含浸された前記硬化性樹脂を硬化させるようにした流
路施設ライニング工法において、前記密閉空間内にTV
カメラを挿入し、該TVカメラによって密閉空間内の状
況を密閉空間外からモニタリングするようにしたことを
特徴とする。In order to achieve the above object, according to the first aspect of the present invention, a lining material obtained by impregnating a resin adsorbent with an uncured curable resin is inserted into a flow path facility. The hardening resin impregnated in the lining material is cured in a state where the lining material is expanded by the fluid pressure supplied into the closed space including the inside of the lining material and pressed against the inner wall of the flow path facility. In the channel facility lining method, the TV is installed in the closed space.
A camera is inserted, and the situation inside the sealed space is monitored from outside the sealed space by the TV camera.
【0009】請求項2記載の発明は、請求項1記載の発
明において、前記TVカメラに接続されたケーブルをT
Vカメラの外径と同等若しくはそれよりも大きな外径を
有するケーブル被覆材で被覆したことを特徴とする。According to a second aspect of the present invention, in the first aspect of the present invention, the cable connected to the TV camera is
It is characterized in that it is covered with a cable covering material having an outer diameter equal to or larger than the outer diameter of the V camera.
【0010】請求項3記載の発明は、請求項2記載の発
明において、前記ケーブル被覆材を押圧に対して耐力を
有する天然ゴム、金属又はプラスチックで構成したこと
を特徴とする。A third aspect of the present invention is characterized in that, in the second aspect of the present invention, the cable covering material is made of natural rubber, metal, or plastic having strength against pressure.
【0011】請求項4記載の発明は、請求項2又は3記
載の発明において、前記TVカメラの密閉空間への挿入
口の内面形状を円形とし、該挿入口に前記ケーブル被覆
材の外周面と気密的に接触するシール部を設けたことを
特徴とする。According to a fourth aspect of the present invention, in the second or third aspect of the present invention, the inner shape of the insertion port into the closed space of the TV camera is circular, and the insertion port is provided with the outer peripheral surface of the cable covering material. It is characterized in that a seal portion that comes into airtight contact is provided.
【0012】請求項5記載の発明は、請求項4記載の発
明において、前記挿入口を前記ライニング材の一部に刺
し込まれたTVカメラ挿入パイプで構成したことを特徴
とする。A fifth aspect of the present invention is characterized in that, in the fourth aspect of the present invention, the insertion port is constituted by a TV camera insertion pipe inserted into a part of the lining material.
【0013】請求項6記載の発明は、請求項4又は5記
載の発明において、前記挿入口に流体圧を閉止する閉止
部を設けたことを特徴とする。According to a sixth aspect of the present invention, in the fourth or fifth aspect, a closing portion for closing a fluid pressure is provided at the insertion port.
【0014】請求項7記載の発明は、請求項6記載の発
明において、前記閉止部をボールバルブで構成したこと
を特徴とする。According to a seventh aspect of the present invention, in the sixth aspect of the invention, the closing portion is constituted by a ball valve.
【0015】従って、本発明によれば、硬化中のライニ
ング材の内部の状況を該ライニング材の内部に挿入され
たTVカメラによって撮像してその内部状況を密閉空間
外の地上においてモニタリングするようにしたため、ラ
イニング材が硬化する以前にその内面の状況を確認する
ことができ、ライニング材におけるしわの発生を確実に
抑えることができるとともに、施工中のライニング材内
での種々のトラブルを事前に発見することができる。Therefore, according to the present invention, the inside condition of the lining material being cured is imaged by a TV camera inserted into the inside of the lining material, and the inside condition is monitored on the ground outside the closed space. As a result, the condition of the inner surface of the lining material can be checked before the lining material hardens, wrinkles in the lining material can be reliably suppressed, and various problems in the lining material during construction are discovered in advance. can do.
【0016】[0016]
【発明の実施の形態】以下に本発明の実施の形態を添付
図面に基づいて説明する。Embodiments of the present invention will be described below with reference to the accompanying drawings.
【0017】<実施の形態1>図1は地中に埋設された
下水管等の管路(本管)1に対するライニング工法を示
す断面図であり、同図において、2は地上に開口するマ
ンホール、3は管路1内に反転挿入されて管路1の内壁
に押圧されている管ライニング材であ。<Embodiment 1> FIG. 1 is a sectional view showing a lining method for a pipe (main pipe) 1 such as a sewer pipe buried in the ground. In FIG. Reference numeral 3 denotes a pipe lining material which is inserted in the pipe 1 upside down and pressed against the inner wall of the pipe 1.
【0018】上記管ライニング材3は、外表面が気密性
の高いプラスチックフィルムで被覆された管状樹脂吸着
材に熱硬化性樹脂を含浸せしめて構成されている。尚、
管状樹脂吸着材としてはポリエステル、ビニロン、アク
リル等のプラスチックファイバーから成る不織布が用い
られ、これの外表面に被覆される前記プラスチックフィ
ルムとしてはポリウレタン、ポリエチレン、ビニロン、
EVA又はEVOHを含む複合フィルムが用いられる。
又、管状樹脂吸着材に含浸される前記熱硬化性樹脂とし
ては不飽和ポリエステル樹脂、エポキシ樹脂、ビニール
エステル樹脂等が用いられる。The tube lining material 3 is formed by impregnating a thermosetting resin into a tubular resin adsorbent whose outer surface is covered with a highly airtight plastic film. still,
As the tubular resin adsorbent, a non-woven fabric made of a plastic fiber such as polyester, vinylon and acrylic is used, and as the plastic film coated on the outer surface thereof, polyurethane, polyethylene, vinylon,
A composite film containing EVA or EVOH is used.
As the thermosetting resin impregnated in the tubular resin adsorbent, an unsaturated polyester resin, an epoxy resin, a vinyl ester resin or the like is used.
【0019】而して、管ライニング材3の一端は外側へ
折り曲げられて地上に設置された密閉ノズル4の上端外
周部に取り付けられている。そして、密閉ノズル4の上
部には密閉キャップ5が複数のGクランプ6によって被
着されており、密閉キャップ5と管ライニング材3の内
部には密閉空間Sが形成されている。Thus, one end of the pipe lining material 3 is bent outward and attached to the outer periphery of the upper end of a closed nozzle 4 installed on the ground. A sealing cap 5 is attached to the upper part of the sealing nozzle 4 by a plurality of G clamps 6, and a sealing space S is formed inside the sealing cap 5 and the pipe lining material 3.
【0020】ところで、図1は管路1内に反転挿入され
た管ライニング材3の硬化作業を示す図であり、管ライ
ニング材3が管路1内に反転挿入されると該管ライニン
グ材3の内部には温水ホース7が引き込まれる。この温
水ホース7は前記密閉キャップ5を気密に貫通して密閉
空間S外へ延出している。尚、管ライニング材3の管路
1内への反転挿入は、コンプレッサー8からエアーホー
ス9を経て密閉空間S内に供給される圧縮エアーの圧力
によってなされる。FIG. 1 is a view showing a hardening operation of the pipe lining material 3 which has been reversely inserted into the pipe line 1. When the pipe lining material 3 is reversely inserted into the pipe line 1, the pipe lining material 3 is hardened. The hot water hose 7 is drawn into the inside of the inside. The hot water hose 7 extends airtightly through the closed cap 5 to the outside of the closed space S. The pipe lining material 3 is inserted into the pipe 1 by the pressure of the compressed air supplied from the compressor 8 into the closed space S via the air hose 9.
【0021】又、管ライニング材3内の底部には圧縮エ
アーで駆動される排水ポンプ10が設置されており、該
排水ポンプ10に接続された2本のエアーホース11,
12は密閉キャップ5を気密に貫通して密閉空間S外へ
延出し、一方のエアーホース11は地上に設置されたコ
ンプレッサー13に接続され、他方のエアーホース12
は大気中に開口している。そして、排水ポンプ10から
導出する排水ホース14も密閉キャップ5を気密に貫通
して密閉空間S外へ延出し、地上に設置された温水タン
ク15の上方に開口している。A drainage pump 10 driven by compressed air is installed at the bottom of the pipe lining material 3. Two air hoses 11 connected to the drainage pump 10 are provided.
Numeral 12 extends airtightly through the sealing cap 5 and extends out of the sealed space S. One air hose 11 is connected to a compressor 13 installed on the ground, and the other air hose 12
Is open to the atmosphere. A drain hose 14 derived from the drain pump 10 also extends through the hermetic cap 5 to the outside of the closed space S in an airtight manner, and is opened above the hot water tank 15 installed on the ground.
【0022】上記温水タンク15内には温水が収容され
ており、該温水タンク15の側壁から導出する温水パイ
プ16には温水ポンプ17の吸入側が接続されており、
該温水ポンプ17の吐出側には前記温水ホース7が接続
され、温水ホース7の途中にはボイラー18が設けられ
ている。Hot water is stored in the hot water tank 15, and a suction side of a hot water pump 17 is connected to a hot water pipe 16 extending from a side wall of the hot water tank 15.
The hot water hose 7 is connected to the discharge side of the hot water pump 17, and a boiler 18 is provided in the middle of the hot water hose 7.
【0023】一方、前記密閉キャップ5の上面にはTV
カメラ挿入パイプ19が立設されており、該TVカメラ
挿入パイプ19の内部には断面円形の内面形状を有する
挿入口19aが形成されており、この挿入口19aを通
して管ライニング材3の内部にTVカメラ20が挿入さ
れている。On the other hand, a TV
A camera insertion pipe 19 is provided upright. An insertion port 19a having a circular inner surface is formed inside the TV camera insertion pipe 19, and a TV is inserted into the tube lining material 3 through the insertion port 19a. Camera 20 is inserted.
【0024】上記TVカメラ20は図2に示すように有
底円筒状のケース21内に収容されており、その周囲に
は照明用の複数のライト22が配設されている。尚、ケ
ース21の前面にはレンズ23が被着されている。The TV camera 20 is housed in a cylindrical case 21 having a bottom as shown in FIG. 2, and a plurality of lights 22 for illumination are arranged around the case 21. Note that a lens 23 is attached to the front surface of the case 21.
【0025】そして、TVカメラ20とライト22にそ
れぞれ接続されたケーブル24,25は集合されて1本
のケーブル26としてケース21を気密に貫通してケー
ス21外へ延出しており、このケーブル26はTVカメ
ラ20(正確にはケース21)の外径dと同等若しくは
それよりも大きな外径D(≧d)を有する可撓性のケー
ブル被覆材27で被覆されている。尚、ケーブル被覆材
27は押圧に対して耐力を有する天然ゴム、金属又はプ
ラスチックで構成されている。又、図2において、28
はコネクターである。The cables 24 and 25 connected to the TV camera 20 and the light 22, respectively, are gathered and airtightly penetrate the case 21 as a single cable 26 and extend out of the case 21. Is covered with a flexible cable covering material 27 having an outer diameter D (≧ d) equal to or larger than the outer diameter d of the TV camera 20 (more precisely, the case 21). The cable covering material 27 is made of natural rubber, metal, or plastic having strength against pressure. Also, in FIG.
Is a connector.
【0026】ところで、図1に示すように、密閉キャッ
プ5に立設されたTVカメラ挿入パイプ19の挿入口1
9aの上下にはシール部を構成するOリング29と閉止
部を構成するボールバルブ30が設けられており、ボー
ルバルブ30を開いた状態でTVカメラ20とこれに連
なるケーブル被覆材27を挿入口19aに通してこれら
を管ライニング材3の内部に押し込んで挿入する。この
とき、挿入口19aに設けられた前記Oリング29はケ
ーブル被覆材27の外周面に気密的に接触して高いシー
ル性を発揮し、密閉空間Sからの圧縮エアーの漏出を防
いで密閉空間Sの内圧低下を防ぐ。As shown in FIG. 1, the insertion port 1 of the TV camera insertion pipe 19 erected on the sealing cap 5
Above and below 9a, an O-ring 29 forming a seal portion and a ball valve 30 forming a closing portion are provided. With the ball valve 30 opened, the TV camera 20 and a cable coating material 27 connected to the TV camera 20 are inserted. These are pushed into the inside of the pipe lining material 3 and inserted through the pipe 19a. At this time, the O-ring 29 provided in the insertion port 19a comes into airtight contact with the outer peripheral surface of the cable covering material 27 to exhibit a high sealing property, and prevents leakage of compressed air from the sealed space S to prevent the sealed space. Prevent the internal pressure of S from dropping.
【0027】そして、TVカメラ20が図1に示すよう
に管ライニング材3内の所定位置(硬化中の管ライニン
グ材3内の状況をモニタリングするに適した位置)に達
すると、ボールバルブ30を閉じて挿入口19aを完全
に閉止して密閉空間Sの圧縮エアーの漏出を防いで密閉
空間Sの内圧低下を防ぐ。When the TV camera 20 reaches a predetermined position in the tube lining material 3 (a position suitable for monitoring the condition in the tube lining material 3 during curing) as shown in FIG. The closed space S is completely closed to prevent the compressed air from leaking from the sealed space S and prevent the internal pressure of the sealed space S from decreasing.
【0028】而して、管ライニング材3の硬化は以下の
要領でなされる。The hardening of the pipe lining material 3 is performed in the following manner.
【0029】即ち、温水ポンプ17とボイラー18が駆
動されて温水タンク15内の温水がボイラー18にて所
定温度に加熱されて温水ホース7に送り込まれると、温
水は温水ホース7に形成された不図示の噴射口から図示
のように管ライニング材3の内部にシャワリングされて
管ライニング材3の加熱に供され、管ライニング材3の
加熱に供されて温度の下がった温水は管ライニング材3
内の底部に溜る。そして、管ライニング材3内の底部に
溜った温水は、コンプレッサー13から供給される圧縮
エアーによって駆動される排水ポンプ10によって吸引
されて排水ホース14へと送り出され、排水ホース14
から温水タンク15に戻される。以下、同様にして温水
が循環されて管ライニング材3が温水によって加熱さ
れ、該管ライニング材3に含浸された熱硬化性樹脂が硬
化し、硬化した管ライニング材3によって管路1がライ
ニングされて補修される。That is, when the hot water pump 17 and the boiler 18 are driven and the hot water in the hot water tank 15 is heated to a predetermined temperature by the boiler 18 and sent to the hot water hose 7, the hot water is removed from the hot water hose 7. As shown in the drawing, the injection port is showered into the inside of the pipe lining material 3 and is used for heating the pipe lining material 3.
Collect at the bottom inside. Then, the hot water collected at the bottom in the pipe lining material 3 is sucked by the drain pump 10 driven by the compressed air supplied from the compressor 13 and sent out to the drain hose 14.
From the hot water tank 15. Thereafter, similarly, hot water is circulated, the pipe lining material 3 is heated by the hot water, the thermosetting resin impregnated in the pipe lining material 3 is hardened, and the hardened pipe lining material 3 lines the pipe 1. To be repaired.
【0030】而して、硬化中の管ライニング材3の内部
の状況は該管ライニング材3の内部に挿入されたTVカ
メラ20によって撮像され、その状況は密閉空間S外の
地上においてモニター装置31によってモニタリングさ
れる。The situation inside the hardened pipe lining material 3 is imaged by the TV camera 20 inserted into the inside of the hardened pipe lining material 3, and the status is monitored on the ground outside the closed space S by the monitor device 31. Monitored by
【0031】従って、本実施の形態によれば、管ライニ
ング材3が硬化する以前にその内面の状況を確認するこ
とができ、管ライニング材3におけるしわの発生を確実
に抑えることができるとともに、施工中の管ライニング
材3内での種々のトラブルを事前に発見することができ
る。尚、施工中の管ライニング材3内でのトラブルとし
ては、温水ホース7、排水ホース14等の捩れや絡み付
き或は弛み、温水のシャワリング不良等が挙げられる。Therefore, according to the present embodiment, the condition of the inner surface of the pipe lining material 3 can be confirmed before the pipe lining material 3 hardens, and wrinkles in the pipe lining material 3 can be reliably suppressed, and Various troubles in the pipe lining material 3 during construction can be found in advance. In addition, as troubles in the pipe lining material 3 during construction, twisting or entanglement or looseness of the hot water hose 7, the drain hose 14, and the like, poor hot water showering, and the like can be given.
【0032】ところで、図3に示すように硬化中の管ラ
イニング材3の端部にマンホール2からTVカメラ挿入
パイプ32を斜めに差し込み、或は図4に示すように先
端に向かって先細のテーパ管状のTVカメラ挿入パイプ
33を管ライニング材3の一部に略垂直に差し込み、各
TVカメラ挿入パイプ32,33の内部に形成された挿
入口32a,33aにTVカメラ20とこれに連なるケ
ーブル被覆材27を通して図示のようにTVカメラ20
を管ライニング材3内の所定位置に配置し、各挿入口3
2a,33aと各ケーブル被覆材27との間をOリング
29とボールバルブ30によってそれぞれ気密にシール
するようにしても良い。By the way, as shown in FIG. 3, a TV camera insertion pipe 32 is inserted obliquely from the manhole 2 into the end of the tube lining material 3 which is being cured, or as shown in FIG. A tubular TV camera insertion pipe 33 is inserted substantially vertically into a part of the pipe lining material 3, and the TV camera 20 and a cable coating connected thereto are inserted into insertion ports 32 a, 33 a formed inside the TV camera insertion pipes 32, 33. TV camera 20 as shown in FIG.
Is placed at a predetermined position in the pipe lining material 3, and each insertion port 3
An O-ring 29 and a ball valve 30 may be used to hermetically seal the space between the cable covering members 27 and 2a, 33a.
【0033】而して、上記方法によっても、TVカメラ
20によって硬化中の管ライニング材3の内部の状況を
地上でモニタリングすることができ、前記と同様の効果
が得られる。Thus, according to the above-described method, the condition inside the hardened pipe lining material 3 can be monitored on the ground by the TV camera 20, and the same effect as described above can be obtained.
【0034】尚、管ライニング材の内部に複数のTVカ
メラを挿入してこれら複数のTVカメラによって管ライ
ニング材の内部の状況をモニタリングしても良く、TV
カメラとライトを別体としてこれらを管ライニング材の
内部に別々に挿入するようにしても良い。It is to be noted that a plurality of TV cameras may be inserted inside the pipe lining material, and the status inside the pipe lining material may be monitored by the plurality of TV cameras.
The camera and the light may be separated and inserted separately into the tube lining material.
【0035】<実施の形態2>次に、本発明の実施の形
態2を図5に基づいて説明する。Second Embodiment Next, a second embodiment of the present invention will be described with reference to FIG.
【0036】図5は枝管34に対するライニング工法を
示す断面図であり、図示のように枝管34内には枝管ラ
イニング材35が管路1側から地上に向かって反転挿入
され、該枝管ライニング材35は枝管34内で膨張して
枝管34の内壁に押圧されている。FIG. 5 is a sectional view showing a lining method for the branch pipe 34. As shown, a branch pipe lining material 35 is inserted into the branch pipe 34 from the pipe line 1 side to the ground, and The pipe lining material 35 expands in the branch pipe 34 and is pressed against the inner wall of the branch pipe 34.
【0037】上記枝管ライニング材35は前記実施の形
態1における管ライニング材3と同様に構成され、その
一端には管路1の内面形状に沿った鍔35aが形成され
ており、この鍔35aは管路34内に導入された作業ロ
ボット36に設けられた鍔押圧カラー37によって管路
1の枝管開口部(枝管34が管路1に開口する部分)の
周縁に密着されている。The branch pipe lining material 35 is constructed in the same manner as the pipe lining material 3 in the first embodiment. One end of the branch pipe lining material 35 is formed with a flange 35a that conforms to the inner shape of the pipeline 1. Is in close contact with the peripheral edge of the branch pipe opening (the part where the branch pipe 34 opens into the pipe 1) of the pipe 1 by a collar pressing collar 37 provided on the working robot 36 introduced into the pipe 34.
【0038】ところで、上記鍔押圧カラー37には圧力
バッグ取付ノズル38が挿通固着されており、この圧力
バッグ取付ノズル38の外周部には圧力バッグ39の一
端が取り付けられている。尚、圧力バッグ39の他端は
閉止されており、この部分にはエアーホース40が取り
付けられるとともに、牽引ロープ41が取り付けられて
いる。又、前記作業用ロボット36は油圧で駆動される
ものであって、これの上部にはモニター用のTVカメラ
42と固定アーム43が設けられており、TVカメラ4
2に接続されたケーブル44と作業ロボット36に接続
された油圧ホース45及び牽引ロープ46は地上まで延
設されて不図示のモニター装置、油圧ポンプ、ウインチ
にそれぞれ接続されている。そして、この作業ロボット
36と前記圧力バッグ39とはロープ47によって互い
に連結されている。A pressure bag mounting nozzle 38 is inserted and fixed to the collar pressing collar 37. One end of a pressure bag 39 is mounted on the outer periphery of the pressure bag mounting nozzle 38. The other end of the pressure bag 39 is closed, and an air hose 40 and a tow rope 41 are attached to this portion. The work robot 36 is driven by hydraulic pressure, and a monitor TV camera 42 and a fixed arm 43 are provided on the upper part of the work robot 36.
2 and a hydraulic hose 45 and a towing rope 46 connected to the work robot 36 are extended to the ground and connected to a monitor device, a hydraulic pump, and a winch (not shown). The working robot 36 and the pressure bag 39 are connected to each other by a rope 47.
【0039】而して、反転前の枝管ライニング材35は
圧力バッグ39内に収容されており、不図示のコンプレ
ッサーからエアーホース40を経て圧力バッグ39内に
圧縮エアーが供給されると、枝管ライニング材35は圧
縮エアーの圧力を受けて枝管34内を管路1側から地上
に向かって反転挿入される。The branch pipe lining material 35 before inversion is housed in the pressure bag 39. When compressed air is supplied from the compressor (not shown) into the pressure bag 39 via the air hose 40, the branch pipe lining material 35 is branched. The pipe lining material 35 is reversely inserted in the branch pipe 34 from the pipe line 1 side to the ground under the pressure of the compressed air.
【0040】そして、図5に示すように枝管ライニング
材35がその全長に亘って枝管34内に反転挿入される
と、該枝管ライニング材35の上端開口部が密閉ノズル
48によって塞がれ、該密閉ノズル48と枝管ライニン
グ材35の内部には密閉空間Sが形成される。尚、密閉
ノズル48にはコンプレッサー8から導出するエアーホ
ース9と不図示の温水タンクから導出する温水ホース7
が接続されるとともに、密閉空間Sの内圧を検出するた
めの圧力計49が取り付けられており、温水ホース7の
途中には温水ポンプ17とバルブ50が設けられてい
る。As shown in FIG. 5, when the branch pipe lining material 35 is inserted upside down into the branch pipe 34 over its entire length, the upper end opening of the branch pipe lining material 35 is closed by the sealing nozzle 48. Thus, a closed space S is formed inside the closed nozzle 48 and the branch pipe lining material 35. The closed nozzle 48 has an air hose 9 derived from the compressor 8 and a hot water hose 7 derived from a hot water tank (not shown).
Is connected, and a pressure gauge 49 for detecting the internal pressure of the closed space S is attached. A hot water pump 17 and a valve 50 are provided in the middle of the hot water hose 7.
【0041】而して、密閉ノズル48の上面にはカメラ
挿入パイプ51が立設されており、このカメラ挿入パイ
プ51の内部には断面円形の内面形状を有する挿入口5
1aが形成されており、この挿入口51aを通してTV
カメラ20が枝管ライニング材35の内部に挿入され
る。A camera insertion pipe 51 is provided upright on the upper surface of the sealed nozzle 48. Inside the camera insertion pipe 51, an insertion port 5 having a circular inner cross section is provided.
1a is formed, and the TV is inserted through the insertion port 51a.
The camera 20 is inserted inside the branch pipe lining material 35.
【0042】即ち、前記実施の形態1と同様にボールバ
ルブ30を開いた状態でTVカメラ20とこれに連なる
ケーブル被覆材27を挿入口51aに通してこれらを図
5に破線にて示すように枝管ライニング材35の内部に
押し込んで挿入する。このとき、挿入口51aに設けら
れたOリング29はケーブル被覆材27の外周面に気密
的に接触して高いシール性を発揮し、密閉空間Sからの
圧縮エアーの漏出を防いで密閉空間Sの内圧低下を防
ぐ。That is, as in the first embodiment, the TV camera 20 and the cable covering material 27 connected to the TV camera 20 are passed through the insertion port 51a with the ball valve 30 opened, as shown by broken lines in FIG. It is pushed into the inside of the branch pipe lining material 35 and inserted. At this time, the O-ring 29 provided in the insertion port 51a is in airtight contact with the outer peripheral surface of the cable covering material 27 to exhibit a high sealing property, and prevents leakage of compressed air from the closed space S to prevent the sealed space S from being closed. To prevent the internal pressure from dropping.
【0043】そして、TVカメラ20が図5に示すよう
に枝管ライニング材35内の所定位置(硬化中の枝管ラ
イニング材35内の状況をモニタリングするに適した位
置)に達すると、ボールバルブ30を閉じて挿入口51
aを完全に閉止して密閉空間Sの圧縮エアーの漏出を防
いで密閉空間Sの内圧低下を防ぐ。When the TV camera 20 reaches a predetermined position in the branch pipe lining material 35 (a position suitable for monitoring the situation in the branch pipe lining material 35 during curing) as shown in FIG. Close 30 and insert 51
a is completely closed to prevent leakage of the compressed air in the closed space S, thereby preventing a decrease in the internal pressure of the closed space S.
【0044】その後、温水ポンプ17が駆動されて温水
が温水ホース7から密閉空間S内に供給されると、枝管
34の内壁に押圧されている枝管ライニング材35は温
水によって加熱され、これに含浸された熱硬化性樹脂が
硬化し、硬化した枝管ライニング材35によって枝管3
4がライニングされて補修される。Thereafter, when the hot water pump 17 is driven and hot water is supplied from the hot water hose 7 into the closed space S, the branch pipe lining material 35 pressed against the inner wall of the branch pipe 34 is heated by the hot water. The thermosetting resin impregnated in the branch pipe is cured, and the cured branch pipe lining material 35 is used to cure the branch pipe 3.
4 is lined and repaired.
【0045】而して、硬化中の枝管ライニング材35の
内部の状況は該枝管ライニング材35の内部に挿入され
たTVカメラ20によって撮像され、その状況は密閉空
間S外の地上において不図示のモニター装置によってモ
ニタリングされる。The inside of the hardened branch pipe lining material 35 is imaged by the TV camera 20 inserted into the inside of the branched pipe lining material 35. It is monitored by the illustrated monitor device.
【0046】従って、本実施の形態においても、前記実
施の形態1と同様に枝管ライニング材35が硬化する以
前にその内面の状況を確認することができ、枝管ライニ
ング材35におけるしわの発生を確実に抑えることがで
きるとともに、施工中の枝管ライニング材35内での種
々のトラブルを事前に発見することができる。Therefore, also in the present embodiment, the condition of the inner surface of the branch pipe lining material 35 can be checked before the hardening of the branch pipe lining material 35 as in the first embodiment, and the generation of wrinkles in the branch pipe lining material 35 is possible. Can be reliably suppressed, and various troubles in the branch pipe lining material 35 during construction can be found in advance.
【0047】<実施の形態3>次に、本発明の実施の形
態3を図6に基づいて説明する。<Third Embodiment> Next, a third embodiment of the present invention will be described with reference to FIG.
【0048】図6はマンホール2に対するライニング工
法を示す断面図であり、図示のようにマンホール2内に
はマンホールライニング材52が挿入されており、その
上端には密閉ノズル4が取り付けられている。FIG. 6 is a sectional view showing a lining method for the manhole 2, in which a manhole lining material 52 is inserted into the manhole 2 as shown, and a closed nozzle 4 is attached to the upper end thereof.
【0049】上記マンホールライニング材52は前記実
施の形態1における管ライニング材3と同様に構成され
ており、これはコンプレッサー8からエアーホース9を
経て密閉空間S内に供給される圧縮エアーの圧力によっ
て膨張して図示のようにマンホール2の内壁に押圧され
ている。The manhole lining material 52 is configured in the same manner as the pipe lining material 3 in the first embodiment. The manhole lining material 52 is formed by the pressure of compressed air supplied from the compressor 8 through the air hose 9 into the closed space S. It expands and is pressed against the inner wall of the manhole 2 as shown.
【0050】そして、マンホールライニング材52はそ
の内部に引き込まれた温水ホース7からシャワリングさ
れる温水によって加熱され、これに含浸された熱硬化性
樹脂が硬化するが、このマンホールライニング材52の
硬化作業及び硬化中の該マンホールライニング材52の
内部状況のTVカメラ20によるモニタリング作業は実
施の形態1と同様に行われる。従って、図6においては
図1に示したと同一要素には同一符号を付しており、以
下、それらについての説明は省略する。Then, the manhole lining material 52 is heated by hot water being showered from the hot water hose 7 drawn into the inside thereof, and the thermosetting resin impregnated therein is hardened. The monitoring operation of the inside state of the manhole lining material 52 during the operation and the hardening by the TV camera 20 is performed in the same manner as in the first embodiment. Therefore, in FIG. 6, the same elements as those shown in FIG. 1 are denoted by the same reference numerals, and description thereof will be omitted below.
【0051】而して、本実施の形態においても、実施の
形態1と同様にマンホールライニング材52の内部状況
はTVカメラ20によって撮像され、その内部状況は密
閉空間S外の地上においてモニター装置31によってモ
ニタリングされる。Thus, also in the present embodiment, as in the first embodiment, the inside state of the manhole lining material 52 is imaged by the TV camera 20, and the inside state is monitored by the monitor device 31 on the ground outside the closed space S. Monitored by
【0052】従って、本実施の形態によれば、マンホー
ルライニング材52が硬化する以前にその内面の状況を
確認することができ、マンホールライニング材52にお
けるしわの発生を確実に抑えることができるとともに、
施工中のマンホールライニング材52内での種々のトラ
ブルを事前に発見することができる。Therefore, according to the present embodiment, the condition of the inner surface of the manhole lining material 52 can be confirmed before the manhole lining material 52 is hardened, and wrinkles in the manhole lining material 52 can be reliably suppressed.
Various troubles in the manhole lining material 52 during construction can be found in advance.
【0053】尚、以上の実施の形態では各種ライニング
材を加熱する方式として温水のシャワリングを用いた
が、温水、スチーム、熱風等の熱媒を循環させる方式を
採用しても良い。In the above embodiment, hot water showering is used as a method of heating various lining materials, but a method of circulating a heat medium such as hot water, steam, or hot air may be employed.
【0054】[0054]
【発明の効果】以上の説明で明らかなように、本発明に
よれば、硬化中のライニング材の内部の状況を該ライニ
ング材の内部に挿入されたTVカメラによって撮像して
その内部状況を密閉空間外の地上においてモニタリング
するようにしたため、ライニング材が硬化する以前にそ
の内面の状況を確認することができ、ライニング材にお
けるしわの発生を確実に抑えることができるとともに、
施工中のライニング材内での種々のトラブルを事前に発
見することができるという効果が得られる。As is apparent from the above description, according to the present invention, the situation inside the lining material being cured is imaged by a TV camera inserted inside the lining material, and the inside situation is sealed. Because we monitor on the ground outside the space, we can check the condition of the inner surface before the lining material hardens, and it is possible to reliably suppress the occurrence of wrinkles in the lining material,
An effect is obtained that various troubles in the lining material during construction can be found in advance.
【図1】管路に対するライニング工法を示す断面図であ
る。FIG. 1 is a sectional view showing a lining method for a pipeline.
【図2】TVカメラ部分の断面図である。FIG. 2 is a sectional view of a TV camera part.
【図3】本発明の別形態を示す部分断面図である。FIG. 3 is a partial sectional view showing another embodiment of the present invention.
【図4】本発明の別形態を示す部分断面図である。FIG. 4 is a partial sectional view showing another embodiment of the present invention.
【図5】枝管に対するライニング工法を示す断面図であ
る。FIG. 5 is a sectional view showing a lining method for a branch pipe.
【図6】マンホールに対するライニング工法を示す断面
図である。FIG. 6 is a sectional view showing a lining method for a manhole.
1 管路(流路施設) 2 マンホール(流路施設) 3 管ライニング材(ライニング材) 19 TVカメラ挿入パイプ 19a 挿入口 20 TVカメラ 26 ケーブル 27 ケーブル被覆材 29 Oリング(シール部) 30 ボールバルブ(閉止部) 31 モニター装置 32,33 TVカメラ挿入パイプ 32a,33a 挿入口 34 枝管(流路施設) 35 枝管ライニング材(ライニング材) 51 TVカメラ挿入パイプ 51a 挿入口 52 マンホールライニング材(ライニン
グ材) S 密閉空間DESCRIPTION OF SYMBOLS 1 Pipe (flow path facility) 2 Manhole (flow path facility) 3 Pipe lining material (lining material) 19 TV camera insertion pipe 19a Insertion port 20 TV camera 26 Cable 27 Cable coating material 29 O-ring (seal part) 30 Ball valve (Closed part) 31 Monitor device 32, 33 TV camera insertion pipe 32a, 33a Insertion port 34 Branch pipe (flow path facility) 35 Branch pipe lining material (lining material) 51 TV camera insertion pipe 51a insertion port 52 Manhole lining material (lining) Material) S Closed space
───────────────────────────────────────────────────── フロントページの続き (71)出願人 592004301 株式会社オール 埼玉県所沢市林1丁目194番地の4 (72)発明者 神山 隆夫 神奈川県平塚市代官町31番27号株式会社湘 南合成樹脂製作所内 (72)発明者 横島 康弘 茨城県結城郡石下町大字篠山175−3有限 会社 横島内 (72)発明者 遠藤 茂 茨城県つくば市花畑2−12−4株式会社ゲ ット内 (72)発明者 青木 啓之 埼玉県所沢市林1丁目194番地の4株式会 社オール内 Fターム(参考) 3H024 EA01 EB08 EC07 ED02 ED05 ED06 EE05 4F211 AD05 AD12 AD16 AD20 AG03 AG08 AH43 SA13 SA14 SC03 SD04 SD11 SN03 SP12 SP15 SP47 ──────────────────────────────────────────────────続 き Continuation of the front page (71) Applicant 592004301 All Co., Ltd. 1-194, Hayashi, Tokorozawa-shi, Saitama 4 (72) Inventor Takao Kamiyama 31-27 Daikancho, Hiratsuka-shi, Kanagawa Shonan Synthetic Resin Co., Ltd. In-house (72) Inventor Yasuhiro Yokoshima 175-3 Shinoyama, Ishishita-cho, Yuki-gun, Ibaraki Pref.Yokoshimanai Co., Ltd. (72) Inventor Shigeru Endo 2-12-4 Hanahata, Tsukuba, Ibaraki Pref. Inventor Hiroyuki Aoki 1-194, Hayashi, Tokorozawa-shi, Saitama F-term in all four companies (reference) 3H024 EA01 EB08 EC07 ED02 ED05 ED06 EE05 4F211 AD05 AD12 AD16 AD20 AG03 AG08 AH43 SA13 SA14 SC03 SD04 SD11 SN03 SP12 SP15 SP47
Claims (7)
せしめて成るライニング材を流路施設内に挿入した後、
該ライニング材の内部を含む密閉空間内に供給される流
体圧によってライニング材を膨張させてこれを流路施設
の内壁に押圧した状態で、該ライニング材に含浸された
前記硬化性樹脂を硬化させるようにした流路施設ライニ
ング工法において、 前記密閉空間内にTVカメラを挿入し、該TVカメラに
よって密閉空間内の状況を密閉空間外からモニタリング
するようにしたことを特徴とする流路施設ライニング工
法。After inserting a lining material obtained by impregnating a resin adsorbent with an uncured curable resin into a flow path facility,
The curable resin impregnated in the lining material is cured while the lining material is expanded by the fluid pressure supplied into the closed space including the inside of the lining material and pressed against the inner wall of the flow path facility. In the above-mentioned flow path facility lining method, a TV camera is inserted into the closed space, and the situation in the closed space is monitored from outside the closed space by the TV camera. .
TVカメラの外径と同等若しくはそれよりも大きな外径
を有するケーブル被覆材で被覆したことを特徴とする請
求項1記載の流路施設ライニング工法。2. The channel facility lining according to claim 1, wherein the cable connected to the TV camera is covered with a cable coating material having an outer diameter equal to or larger than the outer diameter of the TV camera. Construction method.
を有する天然ゴム、金属又はプラスチックで構成したこ
とを特徴とする請求項2記載の流路施設ライニング工
法。3. The lining method according to claim 2, wherein the cable covering material is made of natural rubber, metal or plastic having a resistance to pressing.
内面形状を円形とし、該挿入口に前記ケーブル被覆材の
外周面と気密的に接触するシール部を設けたことを特徴
とする請求項2又は3記載の流路施設ライニング工法。4. The TV camera according to claim 1, wherein an inner surface of the insertion port of the TV camera into the closed space is circular, and the insertion port is provided with a seal portion that comes into air-tight contact with the outer peripheral surface of the cable covering material. Item 4. The flow path facility lining method according to item 2 or 3.
刺し込まれたTVカメラ挿入パイプで構成したことを特
徴とする請求項4記載の流路施設ライニング工法。5. The lining method according to claim 4, wherein said insertion opening is formed by a TV camera insertion pipe inserted into a part of said lining material.
設けたことを特徴とする請求項4又は5記載の流路施設
ライニング工法。6. The lining method according to claim 4, wherein a closing portion for closing a fluid pressure is provided at the insertion port.
とを特徴とする請求項6記載の流路施設ライニング工
法。7. The lining method according to claim 6, wherein the closing portion is constituted by a ball valve.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1596699A JP2000211027A (en) | 1999-01-25 | 1999-01-25 | Channel facility lining method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1596699A JP2000211027A (en) | 1999-01-25 | 1999-01-25 | Channel facility lining method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JP2000211027A true JP2000211027A (en) | 2000-08-02 |
Family
ID=11903468
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1596699A Pending JP2000211027A (en) | 1999-01-25 | 1999-01-25 | Channel facility lining method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2000211027A (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008530464A (en) * | 2005-02-09 | 2008-08-07 | アイエヌエイ アクイジション コーポレーション | Discharge port and / or condensation port for on-site curing type liner and installation method and apparatus |
| KR101393690B1 (en) | 2013-09-09 | 2014-05-27 | 홍석인 | Pipeline repairing device having a control function for setting temperature of tube end and trenchless, inner, whole repairing method using therefor |
| JP2017056392A (en) * | 2015-09-15 | 2017-03-23 | 栗田工業株式会社 | Water tank and visual recognition method in the water tank |
| EP3683371A1 (en) * | 2018-10-03 | 2020-07-22 | Sami Hämäläinen | Liner drain for repairing concrete drain |
-
1999
- 1999-01-25 JP JP1596699A patent/JP2000211027A/en active Pending
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008530464A (en) * | 2005-02-09 | 2008-08-07 | アイエヌエイ アクイジション コーポレーション | Discharge port and / or condensation port for on-site curing type liner and installation method and apparatus |
| JP4896042B2 (en) * | 2005-02-09 | 2012-03-14 | アイエヌエイ アクイジション コーポレーション | Non-open-cut rehabilitation method for existing transportation pipelines |
| KR101393690B1 (en) | 2013-09-09 | 2014-05-27 | 홍석인 | Pipeline repairing device having a control function for setting temperature of tube end and trenchless, inner, whole repairing method using therefor |
| JP2017056392A (en) * | 2015-09-15 | 2017-03-23 | 栗田工業株式会社 | Water tank and visual recognition method in the water tank |
| EP3683371A1 (en) * | 2018-10-03 | 2020-07-22 | Sami Hämäläinen | Liner drain for repairing concrete drain |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4995761A (en) | Method and apparatus for repairing ruptures in underground conduits | |
| JP4904039B2 (en) | Branch pipe lining method | |
| KR100199645B1 (en) | Branch line lining method | |
| US6641687B2 (en) | Apparatus for repairing a pipeline and method for using same | |
| EP0887584B1 (en) | Apparatus for repairing a pipeline and method for using same | |
| US5049003A (en) | Method and apparatus for repairing ruptures in underground conduits | |
| US6024910A (en) | Method for lining a tubular conduit | |
| US8807172B2 (en) | Method and device for repairing piping | |
| JPH06297573A (en) | Pipe repair method | |
| WO2004104469A1 (en) | A lining device for renovating the branch lines of pipelines by way of eversion | |
| US7311122B2 (en) | Lining material for rehabilitating an existing pipe and a manhole, and barrier liner and method for rehabilitating a pipe and a manhole | |
| JP2000211027A (en) | Channel facility lining method | |
| US8256468B1 (en) | Methods and apparatus for lining a passageway | |
| JPH0814476A (en) | Pipe partially repairing member and pipe partial repair construction method | |
| JP2690716B2 (en) | Equipment for pipe repair and pipe repair method | |
| JP3395991B2 (en) | Repair equipment for large diameter pipes | |
| JP3827348B2 (en) | Repair material, fixing structure of repair material, and repair method of pipeline | |
| AU742515B2 (en) | Apparatus for repairing a pipeline and method for using same | |
| JP4560370B2 (en) | Branch pipe lining material and branch pipe lining method | |
| JP2605150B2 (en) | Pipeline repair method | |
| JPH01192524A (en) | Partial repairing technique of branch pipe | |
| AU2015202384B2 (en) | Apparatus for repairing a damaged junction between a main line sewer pipe and a lateral sewer pipe | |
| JPH01242232A (en) | Construction method for repairing pipeline | |
| JP2665493B2 (en) | Manufacturing method of branch pipe lining material | |
| JPH09193247A (en) | Pipe lining material and its manufacturing method and pipe lining method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A131 | Notification of reasons for refusal |
Effective date: 20050830 Free format text: JAPANESE INTERMEDIATE CODE: A131 |
|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20060110 |