JP2000297429A - Construction method of cast-in-place concrete pile - Google Patents

Construction method of cast-in-place concrete pile

Info

Publication number
JP2000297429A
JP2000297429A JP11107777A JP10777799A JP2000297429A JP 2000297429 A JP2000297429 A JP 2000297429A JP 11107777 A JP11107777 A JP 11107777A JP 10777799 A JP10777799 A JP 10777799A JP 2000297429 A JP2000297429 A JP 2000297429A
Authority
JP
Japan
Prior art keywords
slime
hole
cast
place concrete
concrete pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11107777A
Other languages
Japanese (ja)
Other versions
JP3615082B2 (en
Inventor
Noriaki Isemoto
昇昭 伊勢本
Yoshitoshi Yasui
美敏 保井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toda Corp
Original Assignee
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toda Corp filed Critical Toda Corp
Priority to JP10777799A priority Critical patent/JP3615082B2/en
Publication of JP2000297429A publication Critical patent/JP2000297429A/en
Application granted granted Critical
Publication of JP3615082B2 publication Critical patent/JP3615082B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

(57)【要約】 【課題】 孔底のスライム処理を簡単、かつ隅々まで行
うことができる現場打ちコンクリート杭の施工方法を提
供することである。 【解決手段】 現場打ちコンクリート杭用の孔2の底部
に小孔4を削孔し、該小孔4内にスライム6を沈積させ
つつ、前記孔2内に鉄筋籠5を建て込み、前記小孔4か
らトレミー管8でスライム6を吸い上げてコンクリート
9を孔2内に打設する。
(57) [Summary] [PROBLEMS] To provide a method for constructing a cast-in-place concrete pile that can easily and slime-treat the bottom of a hole. SOLUTION: A small hole 4 is drilled at the bottom of a hole 2 for cast-in-place concrete pile, and a slime 6 is deposited in the small hole 4 while a reinforcing cage 5 is erected in the hole 2. The slime 6 is sucked up from the hole 4 by the tremy tube 8 and the concrete 9 is poured into the hole 2.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は現場打ちコンクリー
ト杭の施工方法に関するものである。
The present invention relates to a method for constructing a cast-in-place concrete pile.

【0002】[0002]

【従来の技術】現場打ちコンクリート杭を施工する際に
削孔の孔底処理として、一次孔底処理と二次孔底処理を
行う。前記一次孔底処理は、削孔完了直後と沈殿待ち終
了後に、底ざらいバケットでスライムを除去する。また
二次孔底処理は、鉄筋籠建て込み後およびコンクリート
打設直前に、図4の(1)に示すように、水中ポンプ方
式あるいはエアリフト方式により孔底21のスライム2
2を除去する。
2. Description of the Related Art When a cast-in-place concrete pile is constructed, a primary hole bottom treatment and a secondary hole bottom treatment are performed as a hole bottom treatment for drilling. In the primary hole bottom treatment, the slime is removed with a rough bottom bucket immediately after the completion of the drilling and after the end of the settling wait. In addition, as shown in FIG. 4A, the secondary hole bottom treatment is performed after the reinforcing bars are built and immediately before the concrete is cast, by the submersible pump method or the air lift method.
Remove 2.

【0003】[0003]

【発明が解決しようとする課題】しかし、上記のような
スライムの除去方法では、スライムが孔底面にかなり広
く沈積しているため、水中ポンプなどでは除去しにくか
った。特に、図4の(2)に示すように、拡底杭の削孔
では特殊機械などでスライムを処理する必要があるた
め、隅々まで除去することが難しかった。
However, in the slime removing method as described above, since the slime is considerably widely deposited on the bottom of the hole, it is difficult to remove the slime using a submersible pump or the like. In particular, as shown in (2) of FIG. 4, it is difficult to remove the slime by drilling of the expanded pile because it is necessary to treat the slime with a special machine or the like.

【0004】本発明は、このような問題に鑑みてなされ
たものであり、その目的は、孔底のスライム処理を簡
単、かつ隅々まで行うことができる現場打ちコンクリー
ト杭の施工方法を提供することである。
The present invention has been made in view of such a problem, and an object of the present invention is to provide a method of constructing a cast-in-place concrete pile capable of easily performing slime treatment of a hole bottom and all corners. That is.

【0005】[0005]

【課題を解決するための手段】以上の課題を解決するた
めの手段は、請求項1の発明が、現場打ちコンクリート
杭用の孔の底部に小孔を削孔し、該小孔内にスライムを
沈積させつつ、前記孔内に鉄筋籠を建て込み、前記小孔
からトレミー管でスライムを吸い上げてコンクリートを
孔内に打設することを特徴とする。
According to a first aspect of the present invention, a small hole is drilled at the bottom of a hole for a cast-in-place concrete pile, and a slime is formed in the small hole. The steel cage is erected in the hole while depositing concrete, and slime is sucked up from the small hole with a tremy tube and concrete is poured into the hole.

【0006】請求項1の発明によれば、小孔に集めたス
ライムをトレミー管で吸い上げるので、スライムを施工
順序に沿って少しも残すことなく簡単に除去することが
できる。
According to the first aspect of the present invention, the slime collected in the small holes is sucked up by the tremy tube, so that the slime can be easily removed without leaving any in the construction order.

【0007】また請求項2の発明が、現場打ちコンクリ
ート杭用の孔の底部に小孔を削孔し、該小孔内に、スラ
イム収容筒の上部に水中ポンプを設け、該水中ポンプで
スライムをスライム収容筒に集積するスライム除去装置
を挿入し、該スライム除去装置によりスライムをスライ
ム収容筒内に集積しつつ、前記孔内に鉄筋籠を建て込ん
だ後、前記スライム除去装置を引き上げてコンクリート
を打設することを特徴とする。
According to a second aspect of the present invention, a small hole is drilled at the bottom of the hole for the cast-in-place concrete pile, and a submersible pump is provided in the small hole above the slime storage cylinder, and the submersible pump is used for the slime. Insert a slime removing device that accumulates the slime in the slime container, and while the slime is being accumulated in the slime container by the slime removing device, rebar baskets are built in the holes, and then the slime removing device is pulled up to concrete. Is characterized by being cast.

【0008】請求項2の発明によれば、スライムをスラ
イム収容筒に集めて簡単に除去することができるととも
に、スライムを孔底から撤去した後もスライム収容筒に
入れたままで廃棄処理することができる。
According to the second aspect of the present invention, the slime can be collected in the slime container and easily removed, and the slime can be disposed of in the slime container even after being removed from the bottom of the hole. it can.

【0009】また請求項3の発明が、請求項1または2
において、現場打ちコンクリート杭用の孔の底部は、中
央部側に10〜30の角度で傾斜していることを特徴と
する。
The invention of claim 3 is the first or second invention.
Wherein the bottom of the hole for the cast-in-place concrete pile is inclined at an angle of 10 to 30 toward the center.

【0010】請求項3の発明によれば、底部が中央部側
に10〜30の角度で傾斜したことにより、底部に沈下
したスライムが小孔に集積しやすくなる。
According to the third aspect of the present invention, since the bottom is inclined toward the center at an angle of 10 to 30, the slime settled at the bottom is easily accumulated in the small holes.

【0011】また請求項4の発明が、請求項2におい
て、前記スライム除去装置は間欠運転することを特徴と
する。
According to a fourth aspect of the present invention, in the second aspect, the slime removing device is operated intermittently.

【0012】請求項4の発明によれば、スライム除去装
置の間欠運転によって、孔底に沈下したスライムがスラ
イム収容筒に収容しやすくなる。
According to the fourth aspect of the present invention, the intermittent operation of the slime removing device makes it easier for the slime settled at the bottom of the hole to be stored in the slime storage cylinder.

【0013】また請求項5の発明が、請求項2におい
て、前記スライム収容筒は、複数の収容筒ユニットが着
脱自在に接合されて構成されていることを特徴とする。
According to a fifth aspect of the present invention, in the second aspect, the slime accommodating cylinder is formed by detachably joining a plurality of accommodating cylinder units.

【0014】請求項5の発明によれば、スライム収容筒
の長さを小孔の深さに応じて簡単に変えることができ
る。
According to the fifth aspect of the present invention, the length of the slime container can be easily changed according to the depth of the small hole.

【0015】[0015]

【発明の実施の形態】以下、本発明の現場打ちコンクリ
ート杭の施工方法(以下施工方法という)の実施の形態
を図面に基づいて説明する。図1は第1の実施の形態の
施工方法の断面図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a method for constructing a cast-in-place concrete pile according to the present invention (hereinafter referred to as a construction method) will be described below with reference to the drawings. FIG. 1 is a sectional view of the construction method according to the first embodiment.

【0016】まず、図1の(1)に示すように、地盤1
に掘削機で所定の孔径および深さの現場打ちコンクリー
ト杭用の孔(以下杭孔という)2を削孔し、該杭孔2内
に安定液を入れて孔壁を保護する。この杭孔2の孔底3
は中央部に向かって20度に傾斜し、該中央部に25c
m径で、長さが4mの小孔4を掘削し、底ざらいバケッ
トで一次スライム処理をする。このように小孔4を杭孔
2の中央部に設けたのでスライムが集めやすくなる。
First, as shown in FIG.
Then, a hole (hereinafter referred to as a pile hole) 2 for cast-in-place concrete pile having a predetermined hole diameter and depth is drilled by an excavator, and a stable liquid is poured into the pile hole 2 to protect the hole wall. Hole 3 of this pile hole 2
Is inclined 20 degrees toward the center, and 25c
A small hole 4 with a diameter of 4 m and a length of 4 m is excavated, and a primary slime treatment is performed with a bucket having a rough bottom. Since the small hole 4 is provided at the center of the pile hole 2 as described above, slime can be easily collected.

【0017】次に、孔径などを確認した後に、同図の
(2)に示すように、鉄筋籠5をクレーン10で吊り上
げて杭孔2内に建て込むが、安定液中に浮遊しているス
ライム6は順次沈下して小孔4に堆積する。また孔底3
に沈下したスライムも、そこから小孔4に滑り込んで集
められるようになる。また地盤の土質性状によっては鉄
筋籠を建て込む直前に、再度底ざらいバケットによるス
ライム処理を行うと効果が大きくなる。
Next, after confirming the hole diameter and the like, as shown in (2) of the figure, the reinforced cage 5 is lifted by the crane 10 and built into the pile hole 2, but is suspended in the stable liquid. The slime 6 gradually sinks and accumulates in the small holes 4. Hole bottom 3
The slime that has settled down is also slid into the small holes 4 and collected there. In addition, depending on the soil properties of the ground, the effect can be enhanced if slime treatment is again performed with a rough bottom bucket immediately before a reinforcing cage is built.

【0018】次に、同図の(3)に示すように、頭部に
サクションポンプ7を備えたトレーミー管8を杭孔2内
に挿入して、小孔4に沈積したスライム6を吸い上げ
る。この小孔4には沈下したほとんどのスライム6が堆
積しているため、簡単に除去することができるが、例え
少し残ったとしても杭の支持力や強度に及ぼす影響は小
さい。
Next, as shown in (3) of the figure, a trammy tube 8 provided with a suction pump 7 at the head is inserted into the pile hole 2, and the slime 6 deposited in the small hole 4 is sucked up. Most of the settled slime 6 is deposited in the small hole 4 and can be easily removed. However, even if a small amount remains, the influence on the supporting force and strength of the pile is small.

【0019】このように小孔4からスライム6を除去し
たら、トレミー管8からサクションポンプ7を取り外
し、コンクリート9を杭孔2内に打設すると、孔底3に
小杭11aが形成された現場打ちコンクリート杭11が
構築される。
After the slime 6 has been removed from the small hole 4 in this way, the suction pump 7 is removed from the tremie pipe 8 and concrete 9 is poured into the pile hole 2 to form a small pile 11a at the bottom 3 of the hole. The cast-in-place concrete pile 11 is constructed.

【0020】なお、孔底3の傾斜、小孔4の径や長さ
は、上記のものに限定されるものではなく、杭孔2の大
きさおよび地盤1に性状に応じて変えることもでき、例
えば、小孔4が25cmで、長さが8m程度であれば、
ほとんどのスライム処理は可能である。
The inclination of the hole bottom 3 and the diameter and length of the small hole 4 are not limited to those described above, but can be changed according to the size of the pile hole 2 and the properties of the ground 1. For example, if the small hole 4 is 25 cm and the length is about 8 m,
Most slime treatments are possible.

【0021】次に、図2に基づいて第2の実施の形態の
施工方法について説明する。この実施の形態において
は、図3に示すような、スライム除去装置を使用する。
このスライム除去装置12は、スライム収容筒13と、
この上部に設けた水中ポンプ14と、該水中ポンプ14
の周囲に設けた集積板15とから構成されている。
Next, a construction method according to a second embodiment will be described with reference to FIG. In this embodiment, a slime removing device as shown in FIG. 3 is used.
The slime removing device 12 includes a slime container 13 and
A submersible pump 14 provided above the submersible pump 14
And an accumulating plate 15 provided around the periphery.

【0022】スライム収容筒13は複数の収容筒ユニッ
ト16が接続されて構成され、該収容筒ユニット16を
継ぎ足したり、取り外したりして長さの調整ができるよ
うになっている。この収容筒ユニット16は、水は通す
がスライムは通さないメッシュシート17で外面が覆わ
れ、上面と底面とには他の収容筒ユニット16と連通す
る孔18が開いているが、スライム収容筒13の最下端
における収容筒ユニット16は上面にだけ孔18が開い
ている。
The slime container 13 is formed by connecting a plurality of container units 16, and the length of the slime container 13 can be adjusted by adding or removing the unit. The outer surface of the housing cylinder unit 16 is covered with a mesh sheet 17 that allows water to pass but does not allow slime to pass, and a hole 18 that communicates with another housing cylinder unit 16 is opened on the upper surface and the bottom surface. The housing cylinder unit 16 at the lowermost end of 13 has a hole 18 formed only on the upper surface.

【0023】また、スライム収容筒13における最上端
の収容筒ユニット16には水中ポンプ14の吐出口14
aが接続されて、ここからスライム収容筒13内にスラ
イム6が吐き出されるようになっている。したがって、
スライム6はスライム収容筒13における最下端の収容
筒ユニット16から堆積し、順次上方の収容筒ユニット
16に堆積するようになっている。
In addition, a discharge port 14 of a submersible pump 14 is
a is connected, and the slime 6 is discharged into the slime container 13 from here. Therefore,
The slime 6 is deposited from the lowermost storage cylinder unit 16 in the slime storage cylinder 13 and is sequentially deposited in the upper storage cylinder unit 16.

【0024】このようなスライム収容筒13はスライム
6が満杯になったら、水中ポンプ14を取り外して、そ
のまま廃棄することもできるが、収容筒ユニット16同
士を分解して、その中からスライム6を除去した後に、
洗浄して再使用することもできる。
When the slime 6 becomes full, the submersible pump 14 can be removed from the slime container 13 and discarded as it is. However, the container units 16 are disassembled and the slime 6 is removed from the container. After removal,
It can be washed and reused.

【0025】このようなスライム除去装置12を用いた
施工方法は、まず図2の(1)に示すように、地盤1に
掘削機で所定の孔径および深さの杭孔2を削孔し、該杭
孔2内に安定液を入れて孔壁を保護する。この杭孔2の
孔底3は中央部に向かって20度に傾斜し、前記中央部
に25cm径で、長さが4mの小孔4を掘削し、底ざら
いバケットで一次スライム処理をする。このように小孔
4を杭孔2の中央部に設けたのでスライムが集めやすく
なる。
In the construction method using such a slime removing device 12, first, as shown in FIG. 2A, a pile hole 2 having a predetermined hole diameter and a predetermined depth is drilled in a ground 1 by an excavator. Stabilizing liquid is put into the pile hole 2 to protect the hole wall. The hole bottom 3 of the pile hole 2 is inclined at 20 degrees toward the center, a small hole 4 having a diameter of 25 cm and a length of 4 m is excavated in the center, and primary slime treatment is performed with a bucket having a rough bottom. Since the small hole 4 is provided at the center of the pile hole 2 as described above, slime can be easily collected.

【0026】次に、同図の(2)に示すように、スライ
ム除去装置12をケーブル19で杭孔2内に吊り降ろ
し、小孔4内に落とし込んで集積板15で上部開口部を
覆う。また孔径調査をする場合は、(3)に示すよう
に、調査装置12aにスライム除去装置12を吊り下げ
て小孔4に設置することにより、吊り下げ工程は特に必
要としない。
Next, as shown in FIG. 2B, the slime removing device 12 is hung down in the pile hole 2 by the cable 19, dropped into the small hole 4, and the upper opening is covered with the collecting plate 15. In the case of investigating the hole diameter, as shown in (3), by suspending the slime removing device 12 on the investigating device 12a and installing the slime removing device 12 in the small hole 4, the suspending step is not particularly required.

【0027】次に、同図の(4)に示すように、鉄筋籠
5をクレーン10で吊り上げて杭孔2内に建て込むが、
安定液中に浮遊しているスライム6は順次沈下して集積
板15に堆積する。また孔底3に沈下したスライム6
も、そこから集積板15に滑り込んで集められる。
Next, as shown in (4) of the same figure, the reinforced basket 5 is lifted by the crane 10 and built into the pile hole 2.
The slime 6 floating in the stabilizing liquid sinks sequentially and accumulates on the collecting plate 15. In addition, slime 6 which settled at the bottom 3 of the hole
Are also slid from there onto the collecting plate 15 and collected.

【0028】次に、同図の(5)に示すように、スライ
ム除去装置12の水中ポンプ14が間欠運転して集積板
15のスライム6をスライム収容筒13内に収容し、し
ばらくの間水中ポンプ14が間欠運転を続けると集積板
15上のスライム6が全てスライム収容筒13内に収容
される。この間欠運転は地盤の土質性状、杭径の大きさ
や杭の長さによって変更することができ、一般的には5
分間隔で1分間運転するようになる。
Next, as shown in (5) of the same figure, the submersible pump 14 of the slime removing device 12 intermittently operates to store the slime 6 of the stacking plate 15 in the slime storage cylinder 13, When the pump 14 continues the intermittent operation, all the slime 6 on the stacking plate 15 is stored in the slime storage cylinder 13. This intermittent operation can be changed depending on the soil properties of the ground, the diameter of the pile, and the length of the pile.
It will run for 1 minute at minute intervals.

【0029】この集積板15には沈下したほとんどのス
ライム6が集積しているため、スライム収容筒13に収
容することが簡単にできる。そしてスライム6で満杯に
なったスライム除去装置12を、ケーブル19で引き上
げるとともに、鉄筋籠5を杭孔2内に建て込む。この鉄
筋籠5の建て込みと、スライム除去装置12の回収はス
ライムの残存状況によって決めることができる。また鉄
筋籠5の建て込みは後工程にした方が作業はしやすくな
るが、スライム除去が不十分の場合は、ケーブル9処理
をしながら鉄筋籠5を建て込むことにより、トレミー管
8の設置直前までスライム処理ができる。また引き上げ
られたスライム6はスライム収容筒13内に入れたまま
で廃棄するため廃棄処理が簡単にできる。
Since most of the slime 6 that has settled is accumulated on the accumulation plate 15, it can be easily stored in the slime storage cylinder 13. Then, the slime removing device 12 filled with the slime 6 is pulled up by the cable 19, and the reinforced basket 5 is built in the pile hole 2. The installation of the rebar basket 5 and the recovery of the slime removing device 12 can be determined depending on the remaining slime. In addition, it is easier to install the reinforced basket 5 in the post-process, but if the slime removal is insufficient, the reinforced basket 5 is installed while treating the cable 9 so that the tremy pipe 8 is installed. Slime processing can be performed until just before. Further, since the raised slime 6 is discarded while being kept in the slime container 13, the disposal process can be simplified.

【0030】このように孔2からスライム除去装置12
を撤去したら、同図の(6)に示すように、トレミー管
8を杭孔2内に挿入してコンクリート9を打設すると、
小杭11aが形成された現場打ちコンクリート杭11が
構築される。
As described above, the slime removing device 12
Is removed, and as shown in (6) of the same figure, the tremee pipe 8 is inserted into the pile hole 2 and the concrete 9 is cast.
The cast-in-place concrete pile 11 on which the small pile 11a is formed is constructed.

【0031】なお、孔底3の傾斜および小孔4の径や長
さは、上記のものに限定されるものではなく、杭孔2の
大きさおよび地盤1に性状に応じて変えることもでき
る。
The inclination of the hole bottom 3 and the diameter and length of the small hole 4 are not limited to those described above, but can be changed according to the size of the pile hole 2 and the properties of the ground 1. .

【0032】[0032]

【発明の効果】小孔に集めたスライムをトレミー管で吸
い上げるので、スライムを施工順序に沿って少しも残す
ことなく簡単に除去することができる。
As the slime collected in the small holes is sucked up by the tremy tube, the slime can be easily removed without leaving any slime along the construction order.

【0033】小孔にスライムを集めることができるの
で、二次処理で杭孔の中心部のみのスライム処理が可能
となる。特に、拡底部がある場合は、先端部のスライム
が小孔に集まってくるので効果は大きい。
Since the slime can be collected in the small holes, the slime treatment only at the center of the pile hole can be performed in the secondary treatment. In particular, when there is an enlarged bottom portion, the effect is great because the slime at the tip gathers in the small holes.

【0034】スライムをスライム収容筒で簡単に除去す
ることができるとともに、スライムを孔底から除去した
後もスライム収容筒に入れたままで廃棄処理することが
できる。
The slime can be easily removed by the slime container, and the slime can be disposed of in the slime container even after the slime is removed from the bottom of the hole.

【0035】底部が中央部側に10〜30の角度で傾斜
したことにより、底部に沈下したスライムが小孔に集積
しやすくなる。
Since the bottom is inclined at an angle of 10 to 30 toward the center, the slime settled at the bottom easily accumulates in the small holes.

【0036】スライム除去装置の間欠運転によって、孔
底に沈下したスライムがスライム収容筒に収容しやすく
なる。
The intermittent operation of the slime removing device makes it easier for the slime settled at the bottom of the hole to be stored in the slime storage cylinder.

【0037】スライム収容筒の長さを小孔の深さに応じ
て簡単に変えることができる。
The length of the slime container can be easily changed according to the depth of the small hole.

【図面の簡単な説明】[Brief description of the drawings]

【図1】第1の実施の形態の施工方法の断面図である。FIG. 1 is a sectional view of a construction method according to a first embodiment.

【図2】第2の実施の形態の施工方法の断面図である。FIG. 2 is a sectional view of a construction method according to a second embodiment.

【図3】(1)はスライム除去装置の正面図、(2)は
同斜視図である。
FIG. 3A is a front view of the slime removing device, and FIG. 3B is a perspective view of the same.

【図4】(1)および(2)は従来の施工方法の断面図
である。
FIGS. 4A and 4B are cross-sectional views of a conventional construction method.

【符号の説明】[Explanation of symbols]

1 地盤 2 杭孔 3、21 孔底 4 小孔 5 鉄筋籠 6、22 スライム 7 サクションパイプ 8 トレミー管 9 コンクリート 10 クレーン 11 コンクリート杭 12 スライム除去装置 13 スライム収容筒 14 水中ポンプ 15 集積板 16 収容筒ユニット 17 メッシュシート 18 孔 19 ケーブル DESCRIPTION OF SYMBOLS 1 Ground 2 Pile hole 3, 21 Hole bottom 4 Small hole 5 Reinforced cage 6, 22 Slime 7 Suction pipe 8 Ptolemy pipe 9 Concrete 10 Crane 11 Concrete pile 12 Slime removal device 13 Slime storage cylinder 14 Submersible pump 15 Stacking plate 16 Storage cylinder Unit 17 Mesh sheet 18 holes 19 Cable

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 現場打ちコンクリート杭用の孔の底部に
小孔を削孔し、該小孔内にスライムを沈積させつつ、前
記孔内に鉄筋籠を建て込み、前記小孔からトレミー管で
スライムを吸い上げてコンクリートを孔内に打設するこ
とを特徴とする現場打ちコンクリート杭の施工方法。
1. A small hole is drilled at the bottom of a hole for a cast-in-place concrete pile, and a reinforced basket is built in the hole while slime is deposited in the small hole. A method for constructing a cast-in-place concrete pile, comprising sucking slime and placing concrete in a hole.
【請求項2】 現場打ちコンクリート杭用の孔の底部に
小孔を削孔し、該小孔内に、スライム収容筒の上部に水
中ポンプを設け、該水中ポンプでスライムをスライム収
容筒に集積するスライム除去装置を挿入し、該スライム
除去装置によりスライムをスライム収容筒内に集積しつ
つ、前記孔内に鉄筋籠を建て込んだ後、前記スライム除
去装置を引き上げてコンクリートを打設することを特徴
とする現場打ちコンクリート杭の施工方法。
2. A small hole is drilled at the bottom of the hole for the cast-in-place concrete pile, and a submersible pump is provided in the small hole above the slime container, and the slime is accumulated in the slime container by the submerged pump. Inserting a slime removing device, and stacking a reinforcing bar cage in the hole while accumulating slime in the slime container by the slime removing device, and then pulling up the slime removing device and placing concrete. Characteristic construction method of cast-in-place concrete pile.
【請求項3】 現場打ちコンクリート杭用の孔の底部
は、中央部側に10〜30の角度で傾斜していることを
特徴とする請求項1または2に記載の現場打ちコンクリ
ート杭の施工方法。
3. The method for constructing a cast-in-place concrete pile according to claim 1, wherein the bottom of the hole for the cast-in-place concrete pile is inclined at an angle of 10 to 30 toward the center. .
【請求項4】 前記スライム除去装置は間欠運転するこ
とを特徴とする請求項2に記載の現場打ちコンクリート
杭の施工方法。
4. The method according to claim 2, wherein the slime removing device is operated intermittently.
【請求項5】 前記スライム収容筒は、複数の収容筒ユ
ニットが着脱自在に接合されて構成されていることを特
徴とする請求項2に記載の現場打ちコンクリート杭の施
工方法。
5. The method for constructing a cast-in-place concrete pile according to claim 2, wherein the slime storage cylinder is configured by detachably joining a plurality of storage cylinder units.
JP10777799A 1999-04-15 1999-04-15 On-site concrete pile construction method Expired - Fee Related JP3615082B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10777799A JP3615082B2 (en) 1999-04-15 1999-04-15 On-site concrete pile construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10777799A JP3615082B2 (en) 1999-04-15 1999-04-15 On-site concrete pile construction method

Publications (2)

Publication Number Publication Date
JP2000297429A true JP2000297429A (en) 2000-10-24
JP3615082B2 JP3615082B2 (en) 2005-01-26

Family

ID=14467762

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10777799A Expired - Fee Related JP3615082B2 (en) 1999-04-15 1999-04-15 On-site concrete pile construction method

Country Status (1)

Country Link
JP (1) JP3615082B2 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100412272C (en) * 2004-01-19 2008-08-20 北京市机械施工公司 Concrete transplanting steel bar cage pile forming technical method of long screw hole drilling and center pump pressure
CN103114576A (en) * 2013-02-05 2013-05-22 山西太行建设开发有限公司 Post grouting construction method for cast-in-place concrete pile
CN105714769A (en) * 2016-03-17 2016-06-29 中国水利水电第十一工程局有限公司 Construction method for anti-sliding cast-in-place pile
CN109915043A (en) * 2019-03-19 2019-06-21 安徽联开建设工程有限责任公司 A kind of construction method of spiral Squeezing Soil Pile hole drill tool and bored concrete pile
CN113216840A (en) * 2021-05-18 2021-08-06 浙江交工集团股份有限公司 Impact pore-forming ultra-long bored pile and construction method
CN113513009A (en) * 2021-07-29 2021-10-19 江苏瑞沃建设集团有限公司 A kind of foundation treatment structure of deep silt and treatment method thereof
CN114482024A (en) * 2022-03-20 2022-05-13 陈政杰 Binding method of reinforcement cage in hollow hole in the middle of defective cast-in-place pile
CN114687341A (en) * 2022-04-25 2022-07-01 中铁四局集团第一工程有限公司 Construction method for river-crossing bridge pile foundation
CN114922163A (en) * 2022-04-11 2022-08-19 中交隧道工程局有限公司 Anti-floating construction process for steel reinforcement cage of drilled secant pile
CN118241976A (en) * 2024-05-29 2024-06-25 中国矿业大学(北京) Rotary drilling rig and reinforcement cage distribution integrated equipment and foundation construction method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046542B (en) * 2012-12-04 2015-09-30 中建三局建设工程股份有限公司 Deep foundation pit inner support steel tube column and cast-in-place concrete pile construction technology simultaneously

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100412272C (en) * 2004-01-19 2008-08-20 北京市机械施工公司 Concrete transplanting steel bar cage pile forming technical method of long screw hole drilling and center pump pressure
CN103114576A (en) * 2013-02-05 2013-05-22 山西太行建设开发有限公司 Post grouting construction method for cast-in-place concrete pile
CN105714769A (en) * 2016-03-17 2016-06-29 中国水利水电第十一工程局有限公司 Construction method for anti-sliding cast-in-place pile
CN109915043A (en) * 2019-03-19 2019-06-21 安徽联开建设工程有限责任公司 A kind of construction method of spiral Squeezing Soil Pile hole drill tool and bored concrete pile
CN113216840A (en) * 2021-05-18 2021-08-06 浙江交工集团股份有限公司 Impact pore-forming ultra-long bored pile and construction method
CN113216840B (en) * 2021-05-18 2023-12-29 浙江交工集团股份有限公司 Impact-drilled ultra-long bored piles and construction methods
CN113513009A (en) * 2021-07-29 2021-10-19 江苏瑞沃建设集团有限公司 A kind of foundation treatment structure of deep silt and treatment method thereof
CN114482024A (en) * 2022-03-20 2022-05-13 陈政杰 Binding method of reinforcement cage in hollow hole in the middle of defective cast-in-place pile
CN114922163A (en) * 2022-04-11 2022-08-19 中交隧道工程局有限公司 Anti-floating construction process for steel reinforcement cage of drilled secant pile
CN114687341A (en) * 2022-04-25 2022-07-01 中铁四局集团第一工程有限公司 Construction method for river-crossing bridge pile foundation
CN118241976A (en) * 2024-05-29 2024-06-25 中国矿业大学(北京) Rotary drilling rig and reinforcement cage distribution integrated equipment and foundation construction method

Also Published As

Publication number Publication date
JP3615082B2 (en) 2005-01-26

Similar Documents

Publication Publication Date Title
JP2000297429A (en) Construction method of cast-in-place concrete pile
JP2018091038A (en) Pipe drawing-out method of existing wellhole
JP3878772B2 (en) Construction method of cast-in-place concrete pile to put long steel frame
JP2640841B2 (en) Slime treatment method in cast-in-place pile method
JP7164232B1 (en) submersible sand pump
CN215329975U (en) A kind of water collection well reinforcement anti-loss structure
JP7126401B2 (en) slime processing system
JP3119233U (en) bucket
CN211498904U (en) Precipitation well spare that strong filteration permeates water by force
CN114960714B (en) Near-water foundation pit drainage seepage-proofing structure and construction method
JP2004257065A (en) Pile head treatment method of cast-in-place concrete pile and partition frame used for it
JP6116619B2 (en) Pile head processing equipment
JPS62101715A (en) Slime processor
JP2715789B2 (en) Construction method of underground diaphragm wall
JPH0536573B2 (en)
JP3004799U (en) Submersible pump device
JP7112813B2 (en) Surplus soil removal device and surplus soil removal system
JPS5918488B2 (en) Slime processing method in stable liquid drilling method
JPH01263314A (en) Disposing method for extra-banking concrete by screw pump
JPH042134B2 (en)
JP4743784B2 (en) Tube submerging method and temporary tube closure temporary cover used for the method
JP2775144B2 (en) Sandy soil for packed drain and packed drain method
JP2814822B2 (en) Construction method of underground diaphragm wall
CN111021385A (en) A kind of precipitation method for dealing with quicksand when digging hole of artificial digging pile encounters quicksand layer
JPH09302663A (en) Construction method for cast-in-place pile

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040524

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040716

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20041012

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20041028

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees