JP2819528B2 - How to install rebar - Google Patents
How to install rebarInfo
- Publication number
- JP2819528B2 JP2819528B2 JP15217895A JP15217895A JP2819528B2 JP 2819528 B2 JP2819528 B2 JP 2819528B2 JP 15217895 A JP15217895 A JP 15217895A JP 15217895 A JP15217895 A JP 15217895A JP 2819528 B2 JP2819528 B2 JP 2819528B2
- Authority
- JP
- Japan
- Prior art keywords
- main
- reinforcing bar
- beam member
- column
- bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000003014 reinforcing effect Effects 0.000 claims description 124
- 238000009434 installation Methods 0.000 claims description 78
- 230000002787 reinforcement Effects 0.000 claims description 67
- 238000010276 construction Methods 0.000 claims description 53
- 238000000034 method Methods 0.000 claims description 20
- 238000009415 formwork Methods 0.000 description 9
- 230000002265 prevention Effects 0.000 description 9
- 238000012966 insertion method Methods 0.000 description 5
- 239000004567 concrete Substances 0.000 description 4
- 230000000694 effects Effects 0.000 description 4
- 230000005540 biological transmission Effects 0.000 description 3
- 239000011178 precast concrete Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 1
- 230000009191 jumping Effects 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 230000032258 transport Effects 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、構築中の柱等に設置さ
れたプレキャスト梁部材等に対して、梁用主筋を設置す
る鉄筋の設置方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of installing a reinforcing bar for installing a main reinforcing bar for a precast beam member or the like installed on a column or the like under construction.
【0002】[0002]
【従来の技術】図13は、プレキャスト梁部材を示した
斜視図、図14は、図13に示すプレキャスト梁部材と
は別のプレキャスト梁部材を示した斜視図、図15乃至
図17は、図13及び図14に示すプレキャスト梁部材
を用いて柱梁構造物を構築する際の一工程を示した斜視
図、図18は、完成した柱梁構造物を示した斜視図であ
る。FIG. 13 is a perspective view showing a precast beam member, FIG. 14 is a perspective view showing another precast beam member different from the precast beam member shown in FIG. 13, and FIGS. FIG. 18 is a perspective view showing one step of constructing a column-beam structure using the precast beam members shown in FIGS. 13 and 14, and FIG. 18 is a perspective view showing a completed column-beam structure.
【0003】従来、図18に示すように、直交する大梁
1A、1B及びこれら大梁1A、1Bを支持する柱2か
らなる柱梁構造物3を構築する方法として鉄筋後挿入工
法が実施されている。即ち従来の鉄筋後挿入工法では、
まず図示しないPCプラント等によりプレキャスト梁部
材5A、5Bを製造する。プレキャスト梁部材5Aは、
図13に示すように、前記大梁1Aを基本的に構成する
形、即ち図13の矢印A、B方向に伸延した形で、プレ
キャストコンクリートにより形成された梁本体7を有し
ており、梁本体7は複数(図13では2つのみ図示して
いるが3つ以上でもよい)の本体片7aにより分割構成
されている。従って、隣接する本体片7a、7a間には
隙間としての梁仕口部9が形成されている。梁本体7内
部の底部側には、図13の矢印A、B方向に伸延した複
数の下部主筋10が基本的に埋設されており、従ってこ
れら下部主筋10は梁仕口部9を矢印A、B方向に通過
する形で複数の本体片7aに亙って埋設されている。梁
本体7には、各本体片7a内に基本的に埋設された形
で、複数のスターラップ11が矢印A、B方向に並んで
設けられており、各本体片7aの上部側では、これらス
ターラップ11の上部、即ち逆U字型の部分が外部上方
に突出し露出している。Conventionally, as shown in FIG. 18, a post-rebar insertion method has been implemented as a method for constructing a beam-to-column structure 3 composed of orthogonal beams 1A and 1B and columns 2 supporting the beams 1A and 1B. . That is, in the conventional rebar insertion method,
First, precast beam members 5A and 5B are manufactured by a PC plant or the like (not shown). The precast beam member 5A is
As shown in FIG. 13, a beam main body 7 made of precast concrete is provided in a form basically constituting the girder 1A, that is, in a form extending in the directions of arrows A and B in FIG. Reference numeral 7 is divided into a plurality of (three or more in FIG. 13 but three or more) main body pieces 7a. Therefore, a beam connection 9 as a gap is formed between the adjacent main body pieces 7a, 7a. A plurality of lower main reinforcements 10 extending in the directions of arrows A and B in FIG. 13 are basically buried on the bottom side inside the beam main body 7. It is buried across a plurality of body pieces 7a so as to pass in the direction B. The beam main body 7 is provided with a plurality of stirrups 11 arranged in the directions of arrows A and B in a form basically buried in each main body piece 7a. An upper portion of the stirrup 11, that is, an inverted U-shaped portion is protruded upward from the outside and is exposed.
【0004】また、プレキャスト梁部材5Bは、図14
に示すように、プレキャスト梁部材5Aと同様に、複数
(図14では2つのみ図示しているが3つ以上でもよ
い)の本体片7aにより分割構成され、図14の矢印
A、B方向に伸延した梁本体7を有しており、隣接する
本体片7a、7a間には隙間としての梁仕口部9が形成
されている。また、梁本体7内部の底部側には、図14
の矢印A、B方向に伸延した複数の下部主筋10が、梁
仕口部9を矢印A、B方向に通過する形で基本的に埋設
されており、各本体片7a内には複数のスターラップ1
1が、これらスターラップ11の上部を外部上方に突出
露出させた形で埋設されている。しかし、プレキャスト
梁部材5Bは、更に梁仕口部9において、該梁仕口部9
と対応する柱2に対するフープ筋となり得る形で、複数
のフープ筋12を上下方向に並べた形で有しており、プ
レキャスト梁部材5Bの梁本体7の上部には、矢印A、
B方向に伸延した複数の上部主筋13が設置されてい
る。なお、これら上部主筋13は、梁本体7の上端側に
突出した複数のスターラップ11内に挿入された形で、
かつ梁仕口部9を矢印A、B方向に通過する形で設置さ
れている。Further, the precast beam member 5B is shown in FIG.
As shown in FIG. 14, similarly to the precast beam member 5A, it is divided into a plurality of (only three in FIG. 14, but three or more in FIG. 14) body pieces 7a, and can be divided in the directions of arrows A and B in FIG. It has an elongated beam body 7, and a beam connection 9 as a gap is formed between adjacent body pieces 7a, 7a. Also, at the bottom side inside the beam main body 7, FIG.
A plurality of lower main reinforcements 10 extending in the directions of arrows A and B are basically buried so as to pass through the beam connection portion 9 in the directions of arrows A and B. Wrap 1
1 are buried in such a manner that the upper portions of these stirrups 11 are projected and exposed to the outside. However, the precast beam member 5B further includes a beam joint 9 at the beam joint 9.
A plurality of hoops 12 are arranged in the up and down direction so as to be a hoop for the column 2 corresponding to the column 2. Arrows A,
A plurality of upper main bars 13 extending in the B direction are provided. The upper main reinforcing bars 13 are inserted into a plurality of stirrups 11 protruding toward the upper end of the beam main body 7.
In addition, it is installed so as to pass through the beam connection 9 in the directions of arrows A and B.
【0005】以上のように構成されたプレキャスト梁部
材5A、5Bを製造すると共に、前記柱梁構造物3の柱
2のうち大梁1A、1Bよりも下側の部位に対する配筋
(図示せず)をなし、図15に示すように型枠15を設
置する。なお、型枠15の設置により、該型枠15によ
って囲まれた柱形成空間16が形成され、該柱形成空間
16の隣接上側には柱仕口部17が形成される。なお、
柱仕口部17には上下方向の複数の柱主筋19が柱形成
空間16側から連続した形で建込まれているが、これら
柱主筋19のうち該柱仕口部17の部位にはフープ筋が
設置されていない。次いで、図示しない支保工等を介し
て、前記柱形成空間16の上端側に、図15に示すよう
に、前記プレキャスト梁部材5Aを、該プレキャスト梁
部材5Aの梁仕口部9が前記柱形成空間16の上側の柱
仕口部17に整合し重なって配置されるように、また図
13で示したプレキャスト梁部材5Aの伸延方向(矢印
A、B方向)が図15に示す水平な矢印C、D方向に一
致するように設置する。つまり、構築中の柱2にプレキ
ャスト梁部材5Aを設置する。その後、図示しない支保
工等を介して、前記柱形成空間16の上端側に、図16
に示すように、前記プレキャスト梁部材5Bを、該プレ
キャスト梁部材5Bの梁仕口部9が前記柱形成空間16
の上側の柱仕口部17に整合し重なって配置されるよう
に、また図14で示したプレキャスト梁部材5Bの伸延
方向(矢印A、B方向)が図16に示す水平な矢印E、
F方向(即ち、矢印C、D方向に直角な方向)に一致す
るように設置する。設置により、プレキャスト梁部材5
Bの梁仕口部9に設けられていた複数のフープ筋12
は、柱仕口部17の複数の柱主筋19に対して設置され
た。[0005] The precast beam members 5A and 5B constructed as described above are manufactured, and reinforcing bars (not shown) are arranged on portions of the columns 2 of the column structure 3 below the large beams 1A and 1B. And formwork 15 is installed as shown in FIG. The installation of the formwork 15 forms a column forming space 16 surrounded by the formwork 15, and a column opening 17 is formed on the upper side adjacent to the column forming space 16. In addition,
A plurality of main pillars 19 in the vertical direction are erected in the pillar joint 17 from the pillar forming space 16 side. No streaks are installed. Next, as shown in FIG. 15, the precast beam member 5A is connected to the upper end side of the column forming space 16 via a support (not shown). The extending direction (directions of arrows A and B) of the precast beam member 5A shown in FIG. 13 is aligned with the horizontal arrow C shown in FIG. 15 so as to be aligned with and overlap with the column connection 17 on the upper side of the space 16. , D direction. That is, the precast beam member 5A is installed on the column 2 under construction. Then, via a support (not shown) or the like, the upper end side of the column forming space 16 is placed as shown in FIG.
As shown in FIG. 3, the precast beam member 5B is connected to the beam forming portion 9 of the precast beam member 5B by the column forming space 16.
14 and the extension direction (arrow A, B direction) of the precast beam member 5B shown in FIG. 14 is aligned with the horizontal arrow E shown in FIG.
It is installed so as to match the direction F (that is, the direction perpendicular to the directions of the arrows C and D). By installation, precast beam members 5
The plurality of hoop bars 12 provided in the beam connection portion 9 of B
Are installed with respect to the plurality of pillar main bars 19 of the pillar connection portion 17.
【0006】次いで、プレキャスト梁部材5Aの梁本体
7の上部側に、図17に示すように、プレキャスト梁部
材5Bの上部主筋13と同様の複数の上部主筋13を設
置する。即ち、上部主筋13を、例えば1本づつ、該上
部主筋13の先端部13bとプレキャスト梁部材5Aの
端部7bが矢印C、D方向に対向する形で(例えばクレ
ーン等の揚重手段で揚重した状態で)順次位置決め配置
し、位置決め配置された上部主筋13をプレキャスト梁
部材5Aに向けて順次移動させる。この上部主筋13の
移動は、該上部主筋13をプレキャスト梁部材5Aの梁
本体7の図17の矢印D側(或いは矢印C側)の端部7
b側から、該梁本体7の上部側に突出した複数のスター
ラップ11内に挿入させる形で、かつ該上部主筋13を
梁本体7の上側を矢印C方向に(或いは矢印D方向に)
ひっぱる形で行う。以上のように複数の上部主筋13を
順次移動させて、プレキャスト梁部材5A上の所定の位
置に順次配置する。配置により複数の上部主筋13の設
置が完了する。プレキャスト梁部材5Aに対する上部主
筋13の設置の後、プレキャスト梁部材5A、5Bの梁
仕口部9、9と重なった柱仕口部17に適宜な型枠(図
示せず)を設置し(更に、これらプレキャスト梁部材5
A、5Bに支持させる形でプレキャスト部材からなるス
ラブ6を設置し)、前記型枠15で囲まれた柱形成空間
16及び柱仕口部17等にコンクリートを打設充填し
て、図18に示すように、大梁1A、1B及びこれら大
梁1A、1Bを支持する柱2からなる柱梁構造物3を構
築完成する。Next, as shown in FIG. 17, a plurality of upper main reinforcements 13 similar to the upper main reinforcement 13 of the precast beam member 5B are installed on the upper side of the beam main body 7 of the precast beam member 5A. That is, the upper main bars 13 are lifted one by one, for example, in such a manner that the tip 13b of the upper main bar 13 and the end 7b of the precast beam member 5A face in the directions of arrows C and D (for example, by a lifting means such as a crane). (In a state of being overlapped with each other), the upper main reinforcing bars 13 are sequentially moved toward the precast beam member 5A. The upper main bar 13 is moved by moving the upper main bar 13 to the end 7 of the beam main body 7 of the precast beam member 5A on the arrow D side (or arrow C side) in FIG.
From the side b, the upper main reinforcement 13 is inserted into a plurality of stirrups 11 projecting upward from the beam main body 7 in the direction of arrow C (or in the direction of arrow D).
Perform in the form of a pull. As described above, the plurality of upper main reinforcing bars 13 are sequentially moved and are sequentially arranged at predetermined positions on the precast beam member 5A. By the arrangement, the installation of the plurality of upper main bars 13 is completed. After the installation of the upper main reinforcing bar 13 on the precast beam member 5A, an appropriate formwork (not shown) is installed on the column connection 17 overlapping the beam connections 9, 9 of the precast beam members 5A, 5B (further, FIG. , These precast beam members 5
A, a slab 6 made of a precast member is installed so as to be supported by A and 5B), and concrete is poured into and filled in the column forming space 16 and the column connection portion 17 surrounded by the formwork 15, and FIG. As shown in the drawing, the construction of the beam-to-column structure 3 including the girders 1A and 1B and the columns 2 supporting the girders 1A and 1B is completed.
【0007】[0007]
【発明が解決しようとする課題】しかし、上述した従来
の鉄筋後挿入工法では、上部主筋13のプレキャスト梁
部材5Aに対する位置決め配置する作業は、上部主筋1
3を1本づつプレキャスト梁部材に対して位置決めする
形で行うので煩雑な作業であった。また、上部主筋13
のプレキャスト梁部材5Aに対する位置決め配置する
際、上部主筋13は空中にクレーン等の揚重手段で吊下
されているだけであり、該上部主筋13の位置は作業員
の手などを介して固定されるしかなかった。従って、上
部主筋13の位置決め配置作業は困難であった。また手
などを介さずに、より確実に位置決め配置作業を行うこ
とが望まれていた。However, in the above-described conventional rebar insertion method, the work of positioning the upper main reinforcing bar 13 with respect to the precast beam member 5A is performed by the upper main reinforcing bar 1A.
3 is performed in a form of positioning one by one with respect to the precast beam member, which is a complicated operation. In addition, upper main bar 13
When the positioning is performed with respect to the precast beam member 5A, the upper main reinforcing bar 13 is merely suspended in the air by a lifting means such as a crane, and the position of the upper main reinforcing bar 13 is fixed via a worker's hand or the like. I had no choice. Therefore, the positioning and arranging work of the upper main bar 13 has been difficult. In addition, it has been desired to perform the positioning and placement operation more reliably without intervention of a hand or the like.
【0008】そこで本発明は上記事情に鑑み、プレキャ
スト梁部材等の梁部材に対する梁用主筋の位置決め配置
作業を簡単かつ容易に、しかも確実に行うことにより、
構築中の柱等に設置された梁部材に対する梁用主筋の設
置を簡単かつ容易に、しかも確実に行うことができる鉄
筋の設置方法を提供することを目的とする。In view of the above circumstances, the present invention provides a simple and easy and reliable operation for positioning and positioning a beam main reinforcing bar with respect to a beam member such as a precast beam member.
It is an object of the present invention to provide a method of installing a reinforcing bar that can easily, easily, and surely install a beam main reinforcing bar on a beam member installed on a column or the like under construction.
【0009】[0009]
【課題を解決するための手段】即ち本発明のうち第一の
発明は、構築中の柱(2)に設置された梁部材(5A)
に梁用主筋(13)を設置する際、前記梁部材(5A)
上に設置すべき前記梁用主筋(13)の設置方向(矢印
C、D方向)延長上に位置する、別の構築中の柱(2)
に対し、前記梁用主筋(13)を水平に載置した鉄筋載
置手段(20)を係合させて、該鉄筋載置手段(20)
の前記梁用主筋(13)の載置方向(矢印C、D方向)
と、前記梁部材(5A)の前記梁用主筋(13)の設置
方向(矢印C、D方向)とを一致させる形で位置決め
し、前記梁用主筋(13)を、前記鉄筋載置手段(2
0)側から前記梁部材(5A)に向かって水平に移動さ
せ、前記梁用主筋(13)の移動により、前記梁用主筋
(13)を前記梁部材(5A)の上側の所定の位置に配
置するようにして構成される。That is, a first aspect of the present invention is a beam member (5A) installed on a column (2) under construction.
When installing the beam main reinforcement (13) in the beam, the beam member (5A)
Another column under construction (2) which is located on the extension of the installation direction (arrows C and D directions) of the main beam reinforcement (13) to be installed on top
The rebar placing means (20) on which the beam main reinforcement (13) is placed horizontally is engaged with the rebar placing means (20).
Mounting direction of the main bar (13) for the beam (arrow C and D directions)
And the installation direction (arrow C, D directions) of the beam main reinforcing bar (13) of the beam member (5A) is positioned so as to be coincident with each other, and the beam main reinforcing bar (13) is positioned by the reinforcing bar mounting means ( 2
0), the beam is horizontally moved toward the beam member (5A), and the beam main bar (13) is moved to a predetermined position above the beam member (5A) by the movement of the beam main bar (13). It is configured to be arranged.
【0010】また本発明のうち第二の発明は、第一の発
明による鉄筋の設置方法において、前記梁用主筋(1
3)を、前記鉄筋載置手段(20)側から前記梁部材
(5A)に向かって水平に移動させる際に、前記梁用主
筋(13)の先端部(13b)にガイドキャップ部材
(42)を装着して移動させる。[0010] In a second aspect of the present invention, there is provided the method for installing a reinforcing bar according to the first aspect, wherein:
When moving 3) horizontally from the rebar placement means (20) toward the beam member (5A), a guide cap member (42) is attached to the tip (13b) of the beam main reinforcement (13). Attach and move.
【0011】また本発明のうち第三の発明は、第一の発
明による鉄筋の設置方法において、前記梁用主筋(1
3)を、前記鉄筋載置手段(20)側から前記梁部材
(5A)に向かって水平に移動させる際に、前記梁部材
(5A)の上側にコロ手段(43)を設置し、前記梁用
主筋(13)の移動は、該梁用主筋(13)を前記コロ
手段(43)に乗せる形で行う。[0011] In a third aspect of the present invention, there is provided the method for installing a reinforcing bar according to the first aspect, wherein the main reinforcing bar for a beam (1) is provided.
When moving 3) horizontally from the rebar placement means (20) toward the beam member (5A), a roller means (43) is installed above the beam member (5A), The main bar (13) is moved by placing the main bar (13) on the roller means (43).
【0012】また本発明のうち第四の発明は、第一の発
明による鉄筋の設置方法において、前記鉄筋載置手段
(20)の係合は、前記梁部材(5A)上に設置すべき
前記梁用主筋(13)の設置方向(矢印C、D方向)延
長上に位置する、別の構築中の、互いに隣接した複数の
柱(2、2)に対して行う。According to a fourth aspect of the present invention, in the reinforcing bar installation method according to the first aspect, the engagement of the reinforcing bar mounting means (20) is to be installed on the beam member (5A). This is performed on a plurality of columns (2, 2) adjacent to each other, which are located on the extension of the installation direction (the directions of arrows C and D) of the main beam reinforcement (13) and are under construction.
【0013】また本発明のうち第五の発明は、第一の発
明による鉄筋の設置方法において、前記鉄筋載置手段
(20)には、複数の梁用主筋(13)を、前記梁部材
(5A)において配筋されるべき複数の梁用主筋(1
3)の配筋状態に対応した状態で載置した。According to a fifth aspect of the present invention, in the method for installing a reinforcing bar according to the first aspect, the reinforcing bar mounting means (20) includes a plurality of main bars (13) for the beam and the beam member (20). 5A) A plurality of beam main reinforcements (1
It was placed in a state corresponding to the bar arrangement state of 3).
【0014】なお、括弧内の番号等は、図面における対
応する要素を示す便宜的なものであり、従って、本記述
は図面上の記載に限定拘束されるものではない。以下の
「作用」の欄についても同様である。It should be noted that the numbers in parentheses and the like are for convenience of indicating corresponding elements in the drawings, and therefore, the present description is not limited to the description on the drawings. The same applies to the following “action” column.
【0015】[0015]
【作用】上記した構成により本発明のうち第一の発明で
は、鉄筋載置手段(20)を、該鉄筋載置手段(20)
の載置方向(矢印C、D方向)と梁部材(5A)の設置
方向(矢印C、D方向)とを一致させる形で位置決めす
ることにより、鉄筋載置手段(20)に載置された梁用
主筋(13)が、該梁用主筋(13)を設置すべき梁部
材(5A)に対して位置決め配置される。また、鉄筋載
置手段(20)を位置決めする作業は、鉄筋載置手段
(20)を構築中の柱(2)に係合させることにより行
なわれる。According to the first aspect of the present invention, the rebar placing means (20) is replaced by the rebar placing means (20).
Is positioned on the rebar mounting means (20) by positioning the mounting direction (arrows C and D directions) of the beam and the installation direction (arrows C and D directions) of the beam member (5A) so as to match. The beam main reinforcement (13) is positioned and arranged with respect to the beam member (5A) where the beam main reinforcement (13) is to be installed. The work of positioning the reinforcing bar mounting means (20) is performed by engaging the reinforcing bar mounting means (20) with the column (2) under construction.
【0016】また本発明のうち第二の発明では、梁用主
筋(13)の移動は、該梁用主筋(13)の先端部(1
3b)に装着されたガイドキャップ部材(42)によ
り、前記梁部材(5A)の上側の障害物(11)による
該梁用主筋(13)に対する抵抗を低減させる形で行わ
れる。In the second aspect of the present invention, the movement of the beam main reinforcing bar (13) is performed by moving the tip (1) of the beam main reinforcing bar (13).
The guide cap member (42) attached to 3b) is used to reduce the resistance of the obstacle (11) above the beam member (5A) to the main beam reinforcement (13).
【0017】また本発明のうち第三の発明では、梁用主
筋(13)の移動はコロ手段(43)を介して行われ
る。In the third aspect of the present invention, the movement of the main beam reinforcement (13) is performed via roller means (43).
【0018】また本発明のうち第四の発明では、鉄筋載
置手段(20)を構築中の複数の柱(2、2)に係合さ
せることにより、鉄筋載置手段(20)の位置は2箇所
以上で固定される。In the fourth aspect of the present invention, the position of the reinforcing bar mounting means (20) can be adjusted by engaging the reinforcing bar mounting means (20) with the plurality of columns (2, 2) being constructed. It is fixed at two or more places.
【0019】また本発明のうち第五の発明では、鉄筋載
置手段(20)を梁部材(5A)に対して位置決めした
後、複数の梁用主筋(13)を該梁部材(5A)に向か
って水平に移動させて、該梁部材(5A)の上側の所定
の位置で移動停止させるだけで、これら複数の梁用主筋
(13)は、該梁部材(5A)において配筋されるべき
配筋状態で配置される。According to a fifth aspect of the present invention, after positioning the reinforcing bar mounting means (20) with respect to the beam member (5A), a plurality of beam main reinforcing bars (13) are attached to the beam member (5A). By simply moving the beam horizontally and stopping at a predetermined position above the beam member (5A), the plurality of beam main reinforcing bars (13) should be arranged in the beam member (5A). It is arranged in a bar arrangement state.
【0020】[0020]
【実施例】以下、本発明の実施例を図面に基づき説明す
る。図1は、鉄筋設置装置の一例を示した側面図、図2
は、図1のI矢視図、図3は、図1のII矢視図、図4
は、図2のX1−Y1線断面図、図5は、図2のX2−
Y2線断面図、図6は、図1に示す鉄筋設置装置により
鉄筋設置作業を行なっている図、図7は、図6のX3−
Y3線断面図、図8は、図1に示す鉄筋設置装置の鉄筋
押付手段付近の拡大図、図9は、図8のIII矢視断面
図、図10は、図2のX4−Y4線断面図、図11は、
図1に示す鉄筋設置装置の落下防止手段付近の拡大図、
図12は、構造物全体を示した水平断面図、図13は、
プレキャスト梁部材を示した斜視図、図14は、図13
に示すプレキャスト梁部材とは別のプレキャスト梁部材
を示した斜視図、図15乃至図17は、図13及び図1
4に示すプレキャスト梁部材を用いて柱梁構造物を構築
する際の一工程を示した斜視図、図18は、完成した柱
梁構造物を示した斜視図である。なお、本発明の鉄筋の
設置方法を用いて梁用主筋が設置され構築される柱梁構
造物は、従来の鉄筋後挿入工法により構築されていた柱
梁構造物と同様なものであるので、「従来の技術」の項
で引用した図13乃至図18を、本実施例においても引
用する。Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a side view showing an example of a reinforcing-bar installation device, and FIG.
Is a view as seen from the direction of the arrow I in FIG. 1, FIG. 3 is a view as seen from the direction of the arrow II in FIG.
Is a sectional view taken along line X1-Y1 of FIG. 2, and FIG. 5 is a sectional view taken along line X2-Y1 of FIG.
FIG. 6 is a cross-sectional view taken along the line Y2, FIG. 6 is a diagram showing a reinforcing bar installation operation performed by the reinforcing bar installation device shown in FIG. 1, and FIG.
8 is an enlarged view of the vicinity of the rebar pressing means of the rebar installation device shown in FIG. 1, FIG. 9 is a cross-sectional view taken along the arrow III of FIG. 8, and FIG. 10 is a cross-section taken along line X4-Y4 of FIG. FIG. 11, FIG.
An enlarged view of the vicinity of the fall prevention means of the reinforcing bar installation device shown in FIG. 1,
FIG. 12 is a horizontal sectional view showing the entire structure, and FIG.
FIG. 14 is a perspective view showing a precast beam member, and FIG.
15 and 17 are perspective views showing another precast beam member different from the precast beam member shown in FIGS.
FIG. 18 is a perspective view showing one step in constructing a column-beam structure using the precast beam member shown in FIG. 4, and FIG. 18 is a perspective view showing a completed column-beam structure. In addition, the beam-column structure in which the beam main reinforcement is installed using the reinforcing-bar installation method of the present invention is the same as the beam-column structure constructed by the conventional rebar insertion method, FIGS. 13 to 18 cited in the section of “Prior Art” are also cited in this embodiment.
【0021】構造物50は、図12及び図18に示すよ
うに、地盤(図示せず)上に立設構築された基本的に鉄
筋コンクリートからなる構築途中の構造物であり、構築
完了後にはマンション等として使用される構造物であ
る。構造物50は、複数の柱2及び、水平な矢印C、D
方向に伸延した複数の大梁1A及び、矢印C、D方向と
は垂直で、かつ水平な矢印E、F方向に伸延した複数の
大梁1Bを有している。これら柱2及び大梁1A、1B
は、ラーメン構造等の所定の柱梁構造をなす形で互いに
接合されている。これら柱2及び大梁1A、1Bには、
該柱2及び大梁1A、1Bに支持された形で、水平なス
ラブ6が複数(図18では二点鎖線により1つのみ図
示)支持されており、これらスラブ6は多層状に配置さ
れている。即ち、構造物50は多層状に配置されたスラ
ブ6により多層階を有した構造物となっている。各スラ
ブ6を支持している各階の複数の大梁1A、1Bは、図
12に示すように互いに直交して接合して、格子状の梁
構造物51を形成している。梁構造物51は、大梁1
A、1Bの接合箇所となる格子の交点位置51aにおい
て、それぞれ柱2に支持され接合された状態になってい
る。構造物50は上述したように構築途中であるため途
中階の床側のスラブ6(図示せず)までが構築完了して
おり、該スラブ6上には、該スラブ6を下方から支持し
ている複数の柱2(図示せず)の位置に対応した位置
に、図1に示すように、これら柱2を上方に略1階高分
だけ延長構築し得る形で配筋(図示せず)がそれぞれな
され、該配筋がなされた部位に型枠15がそれぞれ設置
されている。これら型枠15の設置により、各型枠15
内部には柱形成空間16が形成されており、各柱形成空
間16の隣接上側には柱仕口部17が形成されている。
各柱仕口部17には上下方向の複数の柱主筋19が柱形
成空間16側から連続した形で建込まれているが、これ
ら柱主筋19のうち柱仕口部17の部位にはフープ筋が
設置されていない。なお、柱形成空間16内の図示しな
い配筋及び該柱形成空間16の上側の柱仕口部17は、
将来、柱2として構築されることから、これらは構築中
の柱2を構成している。As shown in FIG. 12 and FIG. 18, the structure 50 is a structure which is being built upright on the ground (not shown) and is basically made of reinforced concrete and is being constructed. It is a structure used as an equivalent. The structure 50 includes a plurality of pillars 2 and horizontal arrows C and D.
It has a plurality of girders 1A extending in the directions and a plurality of girders 1B extending in the directions of the arrows E and F, which are perpendicular to the directions of the arrows C and D. These pillars 2 and girders 1A, 1B
Are joined to each other in a predetermined column-beam structure such as a ramen structure. These pillars 2 and girders 1A and 1B
A plurality of horizontal slabs 6 (only one is shown by a two-dot chain line in FIG. 18) are supported by the columns 2 and the girders 1A and 1B, and these slabs 6 are arranged in a multilayer shape. . That is, the structure 50 is a structure having a multi-story structure by the slabs 6 arranged in a multi-layer shape. The plurality of girders 1A and 1B of each floor supporting each slab 6 are orthogonally joined to each other as shown in FIG. 12 to form a lattice-shaped beam structure 51. The beam structure 51 is a girder 1
At the intersections 51a of the grids, which are the joining points of A and 1B, they are supported by the columns 2 and joined. Since the structure 50 is under construction as described above, the construction up to the slab 6 (not shown) on the floor on the middle floor is completed, and the slab 6 is supported on the slab 6 from below. As shown in FIG. 1, reinforcing bars (not shown) are provided at positions corresponding to the positions of the plurality of pillars 2 (not shown) in such a manner that these pillars 2 can be extended upward by approximately one floor height as shown in FIG. 1. And the formwork 15 is installed in each of the locations where the arrangement is made. By installing these molds 15, each mold 15
A column forming space 16 is formed inside, and a column connection portion 17 is formed above and adjacent to each column forming space 16.
A plurality of vertical column main reinforcements 19 are erected in each column connection 17 from the column forming space 16 side. No streaks are installed. In addition, a reinforcement (not shown) in the column forming space 16 and a column connection portion 17 above the column forming space 16 are
Since these will be constructed as pillars 2 in the future, these constitute pillars 2 under construction.
【0022】前記複数の構築中の柱2(即ち、柱形成空
間16内の図示しない配筋及び該柱形成空間16の上側
の柱仕口部17からなるもの)のうち少なくとも1つの
柱2には、図16に示すようにプレキャスト梁部材5
A、5Bが設置されている。プレキャスト梁部材5A、
5Bは従来の鉄筋後挿入工法で使用されているものと同
様に構成されている。即ち、プレキャスト梁部材5A
は、図13に示すように、複数(図13では紙面の都合
上2つのみ示しているが本実施例では3つあるものとす
る)のプレキャストコンクリート製の本体片7aにより
分割構成され、図13の矢印A、B方向に伸延した梁本
体7を有しており、隣接する本体片7a、7a間には隙
間としての梁仕口部9が形成されている。また、梁本体
7内部の底部側には、図13の矢印A、B方向に伸延し
た複数の下部主筋10が、梁仕口部9を矢印A、B方向
に通過する形で基本的に埋設されており、各本体片7a
内には複数のスターラップ11が、これらスターラップ
11の上部を外部上方に突出させた形で埋設されてい
る。また、プレキャスト梁部材5Bは、図14に示すよ
うに、プレキャスト梁部材5Aと同様に、複数(図14
では紙面の都合上2つのみ示しているが本実施例では3
つあるものとする)の本体片7aにより分割構成され、
図14の矢印A、B方向に伸延した梁本体7を有してお
り、隣接する本体片7a、7a間には隙間としての梁仕
口部9が形成されている。また、梁本体7内部の底部側
には、図14の矢印A、B方向に伸延した複数の下部主
筋10が、梁仕口部9を矢印A、B方向に通過する形で
基本的に埋設されており、各本体片7a内には複数のス
ターラップ11が、これらスターラップ11の上部を外
部上方に突出させた形で埋設されている。しかし、プレ
キャスト梁部材5Bは、更に梁仕口部9において、該梁
仕口部9と対応する柱2のフープ筋となり得る形で、複
数のフープ筋12を上下方向に並べた形で有しており、
プレキャスト梁部材5Bの梁本体7の上側には、矢印
A、B方向に伸延した複数の上部主筋13が設置されて
いる。なお、これら上部主筋13は、梁本体7の上端側
に突出した複数のスターラップ11内に挿入された形
で、しかも梁仕口部9を矢印A、B方向に通過する形で
設置されている。At least one pillar 2 of the plurality of pillars 2 being constructed (that is, the pillars 2 are composed of reinforcing bars (not shown) in the pillar forming space 16 and the pillar connection portion 17 above the pillar forming space 16). Is the precast beam member 5 as shown in FIG.
A and 5B are installed. Precast beam member 5A,
5B is configured similarly to that used in the conventional rebar insertion method. That is, the precast beam member 5A
As shown in FIG. 13, is divided into a plurality of main cast pieces 7a made of precast concrete (in FIG. 13, only two are shown for the sake of space, but there are three in this embodiment). It has a beam main body 7 extending in the directions of arrows A and B of 13, and a beam connection portion 9 as a gap is formed between adjacent main body pieces 7a. In addition, a plurality of lower main reinforcements 10 extending in the directions of arrows A and B in FIG. 13 are basically buried at the bottom side inside the beam main body 7 so as to pass through the beam connection 9 in the directions of arrows A and B. Each body piece 7a
A plurality of stirrups 11 are embedded inside the stirrups 11 in such a manner that upper portions of the stirrups 11 project upward and outward. Further, as shown in FIG. 14, the precast beam member 5B has a plurality of precast beam members 5A as shown in FIG.
In FIG. 2, only two are shown due to space limitations.
The main body piece 7a).
It has a beam main body 7 extending in the directions of arrows A and B in FIG. 14, and a beam connection 9 as a gap is formed between adjacent main body pieces 7a. Further, a plurality of lower main reinforcements 10 extending in the directions of arrows A and B in FIG. 14 are basically buried on the bottom side inside the beam main body 7 so as to pass through the beam connection 9 in the directions of arrows A and B. A plurality of stirrups 11 are embedded in each main body piece 7a in such a manner that the upper portions of the stirrups 11 project upward and outward. However, the precast beam member 5B further has a plurality of hoop streaks 12 arranged vertically in the beam joint portion 9 so as to be able to serve as a hoop streak of the column 2 corresponding to the beam joint portion 9. And
Above the beam main body 7 of the precast beam member 5B, a plurality of upper main bars 13 extending in the directions of arrows A and B are provided. The upper main reinforcing bars 13 are inserted in a plurality of stirrups 11 protruding toward the upper end of the beam main body 7 and are installed so as to pass through the beam connection 9 in the directions of arrows A and B. I have.
【0023】従って、上述したプレキャスト梁部材5A
は、図16に示すように、該プレキャスト梁部材5Aの
各梁仕口部9が前記構築中の柱2における柱仕口部17
に整合し重なって配置されるように、また図13で示し
たプレキャスト梁部材5Aの伸延方向(矢印A、B方
向)が図16に示す水平な矢印C、D方向に一致するよ
うに、図示しない支保工等により支持された形で設置さ
れている。従って、将来、該プレキャスト梁部材5Aに
設置されるべき上部主筋13は矢印C、D方向に沿って
設置されるべきであり、つまり該プレキャスト梁部材5
Aの上部主筋13の設置方向は矢印C、D方向となって
いる。また、上述したプレキャスト梁部材5Bは、該プ
レキャスト梁部材5Bの各梁仕口部9が前記構築中の柱
2における柱仕口部17に整合し重なって配置されるよ
うに、また図14で示したプレキャスト梁部材5Bの伸
延方向(矢印A、B方向)が図16に示す水平な矢印
E、F方向に一致するように、図示しない支保工等によ
り支持された形で設置されている。なお、プレキャスト
梁部材5Bの梁仕口部9のうち1つの梁仕口部9は、図
16に示すように、プレキャスト梁部材5Aの梁仕口部
9のうちの1つの梁仕口部9と重なって配置されてお
り、従ってプレキャスト梁部材5A、5Bはこれら梁仕
口部9、9において直交している。なお、前記構築中の
柱2に設置されたプレキャスト梁部材5Aの矢印D側に
は、図1に示すように、互いに隣接した構築中の柱2、
2が存在しており、これら構築中の柱2、2にはプレキ
ャスト梁部材5A、5Bが未だ設置されていない。Therefore, the above-mentioned precast beam member 5A
As shown in FIG. 16, each beam port 9 of the precast beam member 5A is connected to a column port 17 of the column 2 under construction.
13 so that the direction of extension (directions of arrows A and B) of the precast beam member 5A shown in FIG. 13 matches the horizontal directions of arrows C and D shown in FIG. It is installed in a form that is supported by non-supporters. Therefore, in the future, the upper main reinforcement 13 to be installed on the precast beam member 5A should be installed along the directions of arrows C and D, that is, the precast beam member 5A.
The installation direction of the upper main bar 13 of A is in the direction of arrows C and D. Further, the precast beam member 5B described above is arranged such that each beam connection portion 9 of the precast beam member 5B is aligned with and overlaps with the column connection portion 17 of the column 2 under construction. The precast beam member 5B is supported by a not-shown support or the like so that the extending direction (the direction of arrows A and B) of the precast beam member 5B matches the horizontal directions of arrows E and F shown in FIG. As shown in FIG. 16, one of the beam connections 9 of the precast beam member 5B is one of the beam connections 9 of the precast beam member 5A. Therefore, the precast beam members 5A, 5B are orthogonal to each other at these beam connections 9, 9. In addition, as shown in FIG. 1, on the arrow D side of the precast beam member 5A installed on the column 2 under construction,
2, the precast beam members 5A, 5B are not yet installed on the columns 2, 2 under construction.
【0024】一方、前記構築中の柱2に設置されたプレ
キャスト梁部材5Aには鉄筋設置装置20が設置されて
いる。鉄筋設置装置20は、図1に示すように、複数の
ワイヤ26を介して、クレーン等の揚重手段40により
吊下揚重されたフレーム21を有しており、フレーム2
1は水平な矢印C、D方向に伸延して形成されている。
フレーム21の矢印C、D方向の長さL1は、矢印C、
D方向に隣接した構築中の柱2、2間の距離P1の2倍
分の長さに略等しくなっており、フレーム21の矢印C
側の先端部である鉄筋送出先端部24には、図8に示す
ように、下方に面した天面28aと図8の紙面左方向
(即ち矢印C方向)に面した当接壁面28bとによって
形成されたアングル状の位置決め部28が設けられてい
る。即ち、鉄筋設置装置20は、フレーム21の位置決
め部28をプレキャスト梁部材5Aの矢印D側の端部7
bに係合させた形で設置されている(なお、プレキャス
ト梁部材5Aの最も矢印D側の本体片7aの長さは前記
距離P1の略2分の1に等しくなっている。)。フレー
ム21には矢印C、D方向に並んだ2箇所に柱設置部2
2がそれぞれ設けられており、柱設置部22、22間の
矢印C、D方向の間隔は前記距離P1と略等しくなって
いる。なお、矢印C側の柱設置部22とフレーム21の
矢印C側の端部21bまでの間隔及び、矢印D側の柱設
置部22とフレーム21の矢印D側の端部21cまでの
間隔は共に前記距離P1の略2分の1の大きさになって
いる。On the other hand, a reinforcing bar installation device 20 is installed on the precast beam member 5A installed on the column 2 under construction. As shown in FIG. 1, the reinforcing bar installation device 20 has a frame 21 suspended and lifted by a lifting means 40 such as a crane via a plurality of wires 26.
1 is formed to extend in the directions of horizontal arrows C and D.
The length L1 of the frame 21 in the directions of the arrows C and D is represented by an arrow C,
The length is approximately equal to twice the distance P1 between the pillars 2 and 2 being constructed adjacent to each other in the direction D.
As shown in FIG. 8, the rebar sending tip 24, which is the tip on the side, has a top surface 28a facing downward and a contact wall surface 28b facing leftward in FIG. 8 (that is, the direction of arrow C). The formed angle-shaped positioning portion 28 is provided. That is, the reinforcing-bar installation device 20 moves the positioning portion 28 of the frame 21 to the end 7 on the arrow D side of the precast beam member 5A.
(The length of the main body piece 7a closest to the arrow D of the precast beam member 5A is equal to approximately one half of the distance P1.) In the frame 21, two pillar installation portions 2 are arranged in the directions of arrows C and D.
2 are provided, and the interval between the column installation portions 22 in the directions of arrows C and D is substantially equal to the distance P1. The distance between the column installation part 22 on the arrow C side and the end 21b on the arrow C side of the frame 21 and the distance between the column installation part 22 on the arrow D side and the end 21c on the arrow D side of the frame 21 are both set. The distance P1 is approximately half the size of the distance P1.
【0025】各柱設置部22には、図2及び図3に示す
ように、上下方向に貫通した位置合わせ穴22a、22
aがそれぞれ設けられており、各位置合わせ穴22a
は、矢印C、D方向及び矢印E、F方向に伸延した辺を
もつ長方形状に形成されている。各位置合わせ穴22a
の矢印C、D方向の長さは前記柱形成空間16の矢印
C、D方向の長さ(従って柱2の矢印C、D方向の長
さ)よりも長い長さL2となっており、各位置合わせ穴
22aの矢印E、F方向の幅は前記柱形成空間16の矢
印E、F方向の幅(従って柱2の矢印E、F方向の幅)
と略等しい幅L3となっている。各位置合わせ穴22a
には矢印C、D方向に伸延した複数の棒部材23が設け
られており、従って該位置合わせ穴22aにはこれら棒
部材23により上下方向に貫通した複数のスリット穴2
5が矢印C、D方向に伸延した形で形成されている。な
お、各柱設置部22において位置合わせ穴22aの下方
には、図4及び図5に示すように、内部が下方に向かっ
て拡大するテーパ状のガイド面22bが形成されてい
る。即ち、鉄筋設置装置20は、上述した各柱設置部2
2が、図1に示すように、前記プレキャスト梁部材5A
の矢印D側に存在している、互いに隣接した構築中の柱
2、2に対応した形で配置されており、各柱設置部22
の位置合わせ穴22a(即ち複数のスリット穴25)に
は、これら構築中の柱2、2の柱仕口部17、17にお
ける複数の柱主筋19が貫通している。つまり、鉄筋設
置装置20は柱設置部22、22を介して構築中の柱
2、2に係合している。As shown in FIGS. 2 and 3, each pillar installation portion 22 has positioning holes 22a, 22a vertically penetrated therethrough.
a is provided, and each alignment hole 22a is provided.
Is formed in a rectangular shape having sides extending in directions of arrows C and D and directions of arrows E and F. Each alignment hole 22a
Is longer than the length of the column forming space 16 in the directions of arrows C and D (therefore, the length of the column 2 in the directions of arrows C and D) is L2. The width of the alignment hole 22a in the directions of arrows E and F is the width of the column forming space 16 in the directions of arrows E and F (therefore, the width of the column 2 in the directions of arrows E and F).
The width L3 is substantially equal to the width L3. Each alignment hole 22a
Are provided with a plurality of rod members 23 extending in the directions of arrows C and D. Therefore, in the positioning hole 22a, a plurality of slit holes 2 penetrated in the vertical direction by the rod members 23 are provided.
5 is formed to extend in the directions of arrows C and D. In addition, as shown in FIGS. 4 and 5, a tapered guide surface 22b whose inside expands downward is formed below the alignment hole 22a in each pillar installation portion 22. That is, the reinforcing-bar installation device 20 includes the above-described column installation sections 2
2, the precast beam member 5A as shown in FIG.
Are arranged corresponding to the columns 2 and 2 adjacent to each other and being constructed, which are present on the arrow D side of
The plurality of column main reinforcements 19 in the column connection portions 17 of the columns 2, 2 under construction penetrate through the positioning holes 22a (i.e., the plurality of slit holes 25). That is, the reinforcing-bar installation device 20 is engaged with the columns 2, 2 under construction via the column installation portions 22, 22.
【0026】フレーム21上には、図1乃至図3或いは
図10(なお図10はフレーム21を省略した形で示し
ている)に示すように、前記柱設置部22、22以外の
部位に、複数(図では4個)の下側ローラ27が設けら
れており、各下側ローラ27は矢印E、F方向に伸延し
た略円柱状に形成されており、図の矢印G、H方向に回
転自在に軸支されている。なお下側ローラ27には外径
が軸方向に小さくなったくびれ部27aが複数箇所(図
では5箇所)設けられている。これら複数の下側ローラ
27上には、梁用主筋である複数の上部主筋13(図で
は5本)が水平な矢印C、D方向に並列に載置されてい
る。即ち、鉄筋設置装置20の上部主筋13の載置方向
は矢印C、D方向となっている。なお、各上部主筋13
は、くびれ部27aにおいて各下側ローラ27に載置さ
れている。更にフレーム21上には、図1乃至図3或い
は図10に示すように、前記矢印C側の柱設置部22よ
りも矢印C側の位置及び、前記矢印D側の柱設置部22
よりも矢印D側の位置に、それぞれ1個づつの上側ロー
ラ29が設けられており(なお上側ローラ29の個数は
2個以上であってもよい)、各上側ローラ29は、下側
ローラ27と略同様に矢印E、F方向に伸延した略円柱
状に形成されており、図の矢印G、H方向に回転自在に
軸支されている。なお上側ローラ29にも外径が軸方向
に小さくなったくびれ部29aが、前記下側ローラ27
のくびれ部27aと矢印C、D方向に対応した位置に複
数箇所(即ち図では5箇所)設けられている。各上側ロ
ーラ29は、前記複数の下側ローラ27に載置された複
数の上部主筋13に上側から当接しており、各上側ロー
ラ29と各上部主筋13との当接は前記くびれ部27a
においてなされている。As shown in FIG. 1 to FIG. 3 or FIG. 10 (note that FIG. 10 is shown with the frame 21 omitted) on the frame 21, A plurality (four in the figure) of lower rollers 27 are provided, and each lower roller 27 is formed in a substantially cylindrical shape extending in the directions of arrows E and F, and rotates in the directions of arrows G and H in the figure. It is freely supported. The lower roller 27 is provided with a plurality of constrictions 27a (five in the figure) whose outer diameters are reduced in the axial direction. On these lower rollers 27, a plurality of upper main bars 13 (five in the figure), which are beam main bars, are placed in parallel in horizontal arrows C and D directions. That is, the mounting direction of the upper main reinforcing bar 13 of the reinforcing bar installation device 20 is the direction of the arrows C and D. In addition, each upper main bar 13
Is mounted on each lower roller 27 at the constricted portion 27a. Further, on the frame 21, as shown in FIG. 1 to FIG. 3 or FIG. 10, a position on the arrow C side with respect to the column installation portion 22 on the arrow C side, and the column installation portion 22 on the arrow D side.
Each of the upper rollers 29 is provided at a position on the arrow D side (the number of the upper rollers 29 may be two or more). It is formed in a substantially columnar shape extending in the directions of arrows E and F in substantially the same manner as described above, and is rotatably supported in the directions of arrows G and H in the figure. The upper roller 29 also has a constricted portion 29a whose outer diameter is reduced in the axial direction.
A plurality of locations (that is, five locations in the figure) are provided at positions corresponding to the constricted portion 27a and the directions of the arrows C and D. Each upper roller 29 abuts from above on a plurality of upper main reinforcements 13 placed on the plurality of lower rollers 27, and the contact between each upper roller 29 and each upper main reinforcement 13 is determined by the constricted portion 27a.
It has been done in.
【0027】更にフレーム21上には、図1及び図3、
或いは図8及び図9に示すように、前記矢印C側の柱設
置部22より矢印C側の位置で、しかも矢印C側の前記
上側ローラ29よりも矢印C側の位置(即ち鉄筋送出先
端部24)及び該上側ローラ29よりも矢印D側の位置
に、それぞれ1個づつの駆動ローラ31、31が設けら
れており、各駆動ローラ31は、矢印E、F方向に伸延
した略円柱状に形成されており、矢印E、F方向に伸延
した回転軸CT1、CT1を中心に図の矢印G、H方向
に回転自在に軸支されている。なお、各駆動ローラ31
は前記下側ローラ27の設置レベルと等しくなってお
り、従って各駆動ローラ31の上端レベルと前記下側ロ
ーラ27のくびれ部27aにおける上端レベルとは等し
くなっている。従って、各駆動ローラ31は、複数の下
側ローラ27に載置されている複数の上部主筋13の下
側に当接している。またフレーム21には、図1及び図
3に示すように、所定の駆動モータ30が設けられてお
り、該駆動モータ30と各駆動ローラ31との間は、該
駆動モータ30からの動力を伝達自在なチェーン等の動
力伝達部材30aを介して接続されている。従って駆動
モータ30の駆動により、各駆動ローラ31は矢印G、
H方向に回転駆動し得るようになっている。また各駆動
ローラ31の矢印G、H方向への回転駆動により、前記
複数の下側ローラ27に載置されている複数の上部主筋
13は、矢印C、D方向に搬送され得るようになってい
る。なお、複数の上部主筋13に対して前記複数の上側
ローラ29が上側から当接しているので、複数の上部主
筋13と各駆動ローラ31との間の当接は所定の押圧力
を維持する形で効果的に行われる。つまり、各駆動ロー
ラ31による複数の上部主筋13の搬送は効果的に行わ
れる。1 and 3 on the frame 21.
Alternatively, as shown in FIGS. 8 and 9, a position on the arrow C side from the column installation portion 22 on the arrow C side, and a position on the arrow C side from the upper roller 29 on the arrow C side (that is, the reinforcing bar sending tip portion). 24) and one drive roller 31 is provided at a position on the arrow D side with respect to the upper roller 29, and each drive roller 31 has a substantially cylindrical shape extending in the directions of arrows E and F. It is formed, and is rotatably supported in the directions of arrows G and H in the figure around the rotation axes CT1 and CT1 extending in the directions of arrows E and F. Each drive roller 31
Is equal to the installation level of the lower roller 27, so that the upper end level of each drive roller 31 is equal to the upper end level of the constricted portion 27a of the lower roller 27. Therefore, each drive roller 31 is in contact with the lower side of the plurality of upper main bars 13 placed on the plurality of lower rollers 27. As shown in FIGS. 1 and 3, the frame 21 is provided with a predetermined drive motor 30, and between the drive motor 30 and each drive roller 31, the power from the drive motor 30 is transmitted. They are connected via a power transmission member 30a such as a flexible chain. Accordingly, the driving of the driving motor 30 causes each driving roller 31 to move in the direction of the arrow G,
It can be driven to rotate in the H direction. Further, the plurality of upper main bars 13 placed on the plurality of lower rollers 27 can be transported in the directions of arrows C and D by the rotational driving of the driving rollers 31 in the directions of arrows G and H. I have. Since the plurality of upper rollers 29 are in contact with the plurality of upper main bars 13 from above, the contact between the plurality of upper main bars 13 and each of the drive rollers 31 maintains a predetermined pressing force. Effectively done in. That is, the conveyance of the plurality of upper main bars 13 by each drive roller 31 is effectively performed.
【0028】更にフレーム21には、図1、図3、図
8、図9に示すように、鉄筋押付手段32が設けられて
いる。鉄筋押付手段32は、フレーム21側に固定接合
された基部34を有しており、基部34にはピン34a
を介して操作本体33が枢着されている。操作本体33
には矢印E、F方向に伸延した軸部材33bが設けられ
ており、軸部材33bには、略円柱状に形成された押付
ローラ35が、該軸部材33bと同軸状に挿嵌設置され
ている。なお、押付ローラ35は軸部材33bを中心
に、即ち図の回転軸CT2を中心に矢印G、H方向に回
転自在になっており、更に押付ローラ35は軸部材33
bに沿って矢印E、F方向に摺動移動自在になってい
る。操作本体33と基部34には、前記ピン34aを中
心にして操作本体33を基部34に対して回動移動させ
得る所定の移動機構が備えられており、操作本体33側
は前記ピン34aを中心にしてフレーム21に対して図
1或いは図8の矢印J、K方向に回動自在になってい
る。なお、操作本体33のうち基部34と反対側は、作
業員が手で持って操作し得る操作部33aとなってい
る。また、押付ローラ35を軸部材33bに沿って矢印
E、F方向に移動させて、該押付ローラ35を前記複数
の下側ローラ27に載置された複数の上部主筋13のう
ちの任意の上部主筋13に選択的に対応させ、操作部3
3aを図8の矢印J方向に操作して操作本体33を矢印
J方向に移動させることにより、該押付ローラ35を、
選択された上部主筋13に押し付けることができるよう
になっている。なお、押付ローラ35の中央部には外径
が軸方向に小さくなったくびれ部35aが形成されてお
り、押付ローラ35による上部主筋13の押し付けは該
くびれ部35aにおいてなされるようになっている。更
に、押付ローラ35は鉄筋送出先端部24に配置されて
おり、操作本体33を矢印J方向に移動させることによ
り、該押付ローラ35を上部主筋13に押し付けた際に
は、該押付ローラ35は上述した鉄筋送出先端部24側
の駆動ローラ31の上方に近接して位置するようになっ
ている。Further, as shown in FIGS. 1, 3, 8, and 9, the frame 21 is provided with rebar pressing means 32. The rebar pressing means 32 has a base 34 fixedly joined to the frame 21 side.
The operation main body 33 is pivotally connected via the. Operation body 33
Is provided with a shaft member 33b extending in the directions of arrows E and F. A pressing roller 35 formed in a substantially columnar shape is fitted and installed on the shaft member 33b coaxially with the shaft member 33b. I have. The pressing roller 35 is rotatable in the directions of arrows G and H about the shaft member 33b, that is, about the rotation axis CT2 in the figure.
It is slidable in the directions of arrows E and F along b. The operation main body 33 and the base 34 are provided with a predetermined moving mechanism capable of rotating the operation main body 33 with respect to the base 34 around the pin 34a. 1 or 8 in the directions of arrows J and K in FIG. The side of the operation main body 33 opposite to the base 34 is an operation section 33a that can be operated by the operator while holding it by hand. Further, the pressing roller 35 is moved in the directions of arrows E and F along the shaft member 33b, and the pressing roller 35 is moved to an arbitrary upper portion of the plurality of upper main reinforcing bars 13 placed on the plurality of lower rollers 27. The operation unit 3 is selectively associated with the main muscle 13.
The pressing roller 35 is moved by moving the operation body 33 in the direction of the arrow J by operating 3a in the direction of the arrow J in FIG.
It can be pressed against the selected upper main bar 13. A constricted portion 35a having an outer diameter reduced in the axial direction is formed at the center of the pressing roller 35, and the pressing of the upper main bar 13 by the pressing roller 35 is performed in the constricted portion 35a. . Further, the pressing roller 35 is disposed at the rebar sending tip 24, and when the operating body 33 is moved in the direction of arrow J to press the pressing roller 35 against the upper main bar 13, the pressing roller 35 It is located above and close to the drive roller 31 on the side of the rebar delivery tip 24 described above.
【0029】更にフレーム21の矢印D側の端部付近に
は、図1、図2、図11に示すように、落下防止手段3
6が設けられている。落下防止手段36は、一端がピン
37bを介してフレーム21側に枢着され、従ってフレ
ーム21に対して図の矢印P、Q方向に回動自在な本体
37を有しており、本体37には、作業員が手で持って
操作し得る操作部37aが設けられている。また、本体
37には、該本体37を最も矢印P側に移動配置した
際、即ち本体37をフレーム21上に載置する形で落下
防止手段36を設置した状態において、フレーム21上
に載置されている前記上部主筋13が矢印D方向に移動
することを防止し得る形の移動防止壁部39が、該上部
主筋13の後端よりもやや矢印D側に配置された形で形
成されており、前記上部主筋13の後端付近が上方向に
跳上り移動することを防止し得る形の移動防止天井部3
9aが、該上部主筋13の後端付近のやや上方に配置さ
れた形で形成されている。なお、本体37を最も矢印Q
側に移動配置した際、即ち落下防止手段36の取外し状
態においては、特に移動防止天井部39aが、前記上部
主筋13の上方から取り除かれた状態になるようになっ
ている。Further, near the end on the arrow D side of the frame 21, as shown in FIGS.
6 are provided. One end of the fall prevention means 36 is pivotally attached to the frame 21 side via a pin 37b, and thus has a main body 37 that is rotatable with respect to the frame 21 in the directions of arrows P and Q in the figure. Is provided with an operation section 37a which can be operated by a worker. Also, when the main body 37 is moved to the position indicated by the arrow P, ie, the main body 37 is mounted on the frame 21 while the fall prevention means 36 is mounted thereon. A movement preventing wall portion 39 having a shape capable of preventing the upper main bar 13 from moving in the direction of arrow D is formed so as to be slightly disposed on the arrow D side of the rear end of the upper main bar 13. And a movement prevention ceiling 3 having a shape capable of preventing the vicinity of the rear end of the upper main bar 13 from jumping upward.
9a is formed so as to be arranged slightly above near the rear end of the upper main bar 13. In addition, the main body 37 is indicated by the arrow Q
When it is moved to the side, that is, when the fall prevention means 36 is removed, the movement prevention ceiling 39 a is particularly removed from above the upper main bar 13.
【0030】構築途中の構造物50及び鉄筋設置装置2
0及びプレキャスト梁部材5A、5Bは以上のように構
成されているので、鉄筋設置装置20を用いて、構築途
中の構造物50の構築作業を進めると次のようになる。
即ち、構築途中の構造物50のうち構築完了した最も上
側のスラブ6上に、複数の柱2に対する配筋(図示せ
ず)を行い、これら配筋に対して型枠15をそれぞれ設
置する。これら構築中の柱2のうち少なくとも1つの柱
2(例えば図12に示す、矢印C、D方向に隣接する柱
2A、2Bに対応する柱2、2)にプレキャスト梁部材
5A(例えば図12に示す範囲H1に対応する長さのプ
レキャスト梁部材5A、即ち、3つの本体片7aからな
り、中央の本体片7aの長さが前記距離P1に略等し
く、両端の本体片7a、7aの長さが前記距離P1の2
分の1に略等しいもの、つまり全長が前記距離P1の2
倍に略等しいもの)を矢印C、D方向に設置する。プレ
キャスト梁部材5Aの設置の後、プレキャスト梁部材5
Aを設置した構築中の柱2(或いはプレキャスト梁部材
5Aを設置した構築中の柱2とその他の構築中の柱2)
にプレキャスト梁部材5B(例えば図12に示す範囲H
2に対応する長さの2つのプレキャスト梁部材5B、即
ち、3つの本体片7aからなり、中央の本体片7aの長
さが前記距離P1に略等しく、両端の本体片7a、7a
の長さが前記距離P1の2分の1に略等しいもの、つま
り全長が前記距離P1の2倍に略等しいもの)を矢印
E、F方向に、従ってこれらプレキャスト梁部材5A、
5Bが直交する形で設置する。なお、プレキャスト梁部
材5Aが設置された構築中の柱2のうち最も矢印D側の
柱2に対して矢印D側に隣接した2つの構築中の柱2、
2(例えば図12に示す柱2C、2Dに対応する柱2、
2)にはプレキャスト梁部材5Aが設置されていない。The structure 50 under construction and the reinforcing bar installation device 2
0 and the precast beam members 5A and 5B are configured as described above, so that the construction work of the structure 50 under construction using the reinforcing bar installation device 20 proceeds as follows.
That is, on the uppermost slab 6 where the construction is completed among the structures 50 under construction, reinforcing bars (not shown) for the plurality of columns 2 are provided, and the formwork 15 is installed for each of these reinforcing bars. At least one of the pillars 2 under construction (for example, pillars 2 and 2 corresponding to pillars 2A and 2B adjacent to each other in the directions of arrows C and D shown in FIG. 12) has a precast beam member 5A (for example, FIG. 12). A precast beam member 5A having a length corresponding to the range H1 shown, that is, three main body pieces 7a, the length of the central body piece 7a is substantially equal to the distance P1, and the length of the main body pieces 7a, 7a at both ends Is 2 of the distance P1
One that is approximately equal to one-half, that is, the total length is 2 of the distance P1
Are installed in the directions of arrows C and D. After installing the precast beam member 5A, the precast beam member 5
Pillar 2 under construction with A installed (or pillar 2 under construction with precast beam member 5A installed and other pillar 2 under construction)
The precast beam member 5B (for example, a range H shown in FIG. 12)
2, two precast beam members 5B having a length corresponding to 2, that is, three main body pieces 7a, the length of the central main body piece 7a is substantially equal to the distance P1, and the main body pieces 7a, 7a at both ends are provided.
Is substantially equal to one half of the distance P1, that is, the total length is substantially equal to twice the distance P1) in the directions of the arrows E and F, and thus these precast beam members 5A,
5B is installed so as to be orthogonal. In addition, two columns 2 under construction adjacent to the column 2 on the most arrow D side among the columns 2 under construction on which the precast beam members 5A are installed,
2 (for example, columns 2 corresponding to columns 2C and 2D shown in FIG. 12,
In 2), the precast beam member 5A is not installed.
【0031】次いで、鉄筋設置装置20を揚重手段40
を介して地上(図示せず)に降ろし、該鉄筋設置装置2
0の複数の下側ローラ27上に、長さが前記距離P1の
2倍に略等しい複数の(5本の)上部主筋13を載置す
る。なお、鉄筋設置装置20の上側ローラ29及び鉄筋
押付手段32は、フレーム21に対してボルト等を介し
て着脱自在になっている。従って、上部主筋13の載置
は、これら上側ローラ29及び鉄筋押付手段32をフレ
ーム21から取外した後、容易に行われる。また、上部
主筋13の載置時には、落下防止手段36の本体37を
矢印Q側に移動させておき、上部主筋13の載置動作の
邪魔にならないようにしておく。また、上部主筋13の
載置は、これら上側ローラ29及び鉄筋押付手段32を
フレーム21から取外さず、図8に示すように、駆動モ
ータ30及び動力伝達部材30aにより駆動ローラ3
1、31を図の矢印H方向に回転駆動させておき、載置
すべき上部主筋13の矢印D側(即ち、後端側)をこの
駆動ローラ31(特に鉄筋送出先端部24側の駆動ロー
ラ31)に当接させて、該駆動ローラ31により該上部
主筋13を矢印D方向に搬送させる形で、該上部主筋1
3を複数の下側ローラ27の上に所定位置に配置するよ
うにしてもよい。Next, the reinforcing bar installation device 20 is
To the ground (not shown) via the
A plurality of (five) upper main reinforcements 13 whose lengths are approximately equal to twice the distance P1 are placed on the lower rollers 27 of zero. The upper roller 29 and the reinforcing bar pressing means 32 of the reinforcing bar installation device 20 are detachable from the frame 21 via bolts or the like. Therefore, the upper main bar 13 is easily placed after the upper roller 29 and the reinforcing bar pressing means 32 are removed from the frame 21. When the upper main reinforcement 13 is placed, the main body 37 of the fall prevention means 36 is moved to the arrow Q side so as not to disturb the placing operation of the upper main reinforcement 13. The upper main bar 13 is placed without removing the upper roller 29 and the rebar pressing means 32 from the frame 21, as shown in FIG. 8, by the drive motor 30 and the power transmission member 30 a.
1 and 31 are driven to rotate in the direction of arrow H in the drawing, and the arrow D side (that is, the rear end side) of the upper main bar 13 to be placed is positioned on the drive roller 31 (particularly the drive roller on the side of the rebar feed tip 24). 31), and the upper main bar 13 is conveyed by the drive roller 31 in the direction of arrow D.
3 may be arranged at a predetermined position on the plurality of lower rollers 27.
【0032】複数の下側ローラ27上に複数の上部主筋
13を載置した後、揚重手段40を介して鉄筋設置装置
20を揚重運搬し、該鉄筋設置装置20を前記プレキャ
スト梁部材5Aに対して位置決め設置する。なお、鉄筋
設置装置20の揚重運搬時には、落下防止手段36の本
体37を矢印P側に移動させた状態にしておくことによ
り、前記載置されている上部主筋13が、運搬中の振動
等により矢印D方向に移動しフレーム21から落下する
ことを防止しておく。また、前記載置されている上部主
筋13の後端付近が、運搬中の振動等により不用意に上
方向に跳上ることを防止しておく。また、鉄筋設置装置
20のプレキャスト梁部材5Aに対する位置決め設置
は、図1に示すように、鉄筋設置装置20の2つの位置
合わせ穴22a、22aに、プレキャスト梁部材5Aが
設置された構築中の柱2のうち最も矢印D側の柱2に対
して矢印D側に隣接した2つの構築中の柱2、2、従っ
てプレキャスト梁部材5Aの上部主筋13の設置方向で
ある矢印C、D方向の延長上に位置する、プレキャスト
梁部材5Aが設置されているものとは別の構築中の柱
2、2(例えば図12に示す柱2C、2Dに対応する柱
2、2)の柱仕口部17、17の複数の柱主筋19を貫
通させる形、即ち鉄筋設置装置20を柱設置部22、2
2を介して前記2つの構築中の柱2、2に係合させて、
鉄筋設置装置20の上部主筋13の前記載置方向と、前
記プレキャスト梁部材5Aの上部主筋13の設置方向、
即ち矢印C、D方向を一致させる形で行う。また、鉄筋
設置装置20のプレキャスト梁部材5Aに対する位置決
め設置においては、上述した載置方向と設置方向を一致
させると共に、鉄筋設置装置20の位置決め部28をプ
レキャスト梁部材5Aの矢印D側の端部7bに係合させ
る。なお、鉄筋設置装置20の設置完了後も、揚重手段
40による鉄筋設置装置20の揚重支持は続けておく。
ところで、鉄筋設置装置20の2つの位置合わせ穴22
a、22aの下方には、上述したように内部が下方に向
かって拡大するテーパ状のガイド面22b、22bが形
成されているので、構築中の柱2、2をフレーム21の
位置合わせ穴22a、22aの下側から上方に向けて貫
通させる際には、内部が下方に向かって拡大するテーパ
状のガイド面22b、22bによって、前記構築中の柱
2、2の上端側(即ち、複数の柱主筋19)が位置合わ
せ穴22a、22aに容易に挿入される。After the plurality of upper main reinforcing bars 13 are placed on the plurality of lower rollers 27, the reinforcing bar setting device 20 is lifted and transported via the lifting means 40, and the reinforcing bar setting device 20 is connected to the precast beam member 5A. It is positioned and installed with respect to. In addition, at the time of lifting and transporting of the reinforcing bar installation device 20, by keeping the main body 37 of the fall prevention means 36 moved to the arrow P side, the upper main reinforcing bar 13 placed beforehand can be subjected to vibration during transportation. To prevent it from moving in the direction of arrow D and dropping from the frame 21. In addition, it is prevented that the vicinity of the rear end of the upper main bar 13 which is placed as described above is inadvertently jumped upward due to vibration during transportation. In addition, as shown in FIG. 1, the positioning and installation of the reinforcing-bar installation device 20 with respect to the precast beam member 5A is performed by installing the precast beam member 5A in the two alignment holes 22a and 22a of the reinforcing-bar installation device 20. 2, two columns 2 and 2 under construction, which are adjacent to the column 2 closest to the arrow D side on the arrow D side, and thus extend in the directions indicated by the arrows C and D, which are the installation directions of the upper main reinforcement 13 of the precast beam member 5A. The pillar connection portion 17 of the pillars 2 and 2 (for example, the pillars 2 and 2 corresponding to the pillars 2C and 2D shown in FIG. 12) under construction different from the one on which the precast beam member 5A is installed. , 17 through the plurality of pillar main bars 19, that is, the reinforcing bar installation device 20 is
2 to engage the two columns 2, 2 under construction,
The installation direction of the upper main reinforcement 13 of the reinforcing bar installation device 20 and the installation direction of the upper main reinforcement 13 of the precast beam member 5A,
That is, the adjustment is performed in a manner that the directions of the arrows C and D are made to coincide. In the positioning and installation of the reinforcing bar installation device 20 with respect to the precast beam member 5A, the mounting direction and the installation direction are matched with each other, and the positioning portion 28 of the reinforcing bar installation device 20 is positioned at the end of the precast beam member 5A on the arrow D side. 7b. In addition, even after the installation of the reinforcing bar installation device 20 is completed, the lifting support of the reinforcing bar installation device 20 by the lifting means 40 is continued.
By the way, the two alignment holes 22 of the reinforcing bar installation device 20 are provided.
As described above, the tapered guide surfaces 22b, 22b whose insides expand downward as described above are formed below the a, 22a, so that the pillars 2, 2 under construction are aligned with the alignment holes 22a of the frame 21. , 22a, when penetrating upward from the lower side, the upper ends of the columns 2, 2 under construction (that is, a plurality of columns) are formed by the tapered guide surfaces 22b, 22b whose inside expands downward. The column main bar 19) is easily inserted into the alignment holes 22a, 22a.
【0033】鉄筋設置装置20をプレキャスト梁部材5
Aに設置した後、鉄筋設置作業を行う。即ち、駆動モー
タ30及び動力伝達部材30aにより駆動ローラ31、
31を、図6に示すように、矢印G方向に回転駆動さ
せ、前記複数の下側ローラ27に載置された上部主筋1
3を矢印C方向、即ち前記プレキャスト梁部材5A側に
搬送させる。上部主筋13を搬送させて、上部主筋13
をフレーム21から前記プレキャスト梁部材5A側に送
出することにより、該上部主筋13を、該プレキャスト
梁部材5Aの上側に沿って矢印C方向に移動させて、図
17に示すように、該プレキャスト梁部材5Aの上側の
所定の位置に配置し設置する。なお、搬送すべき各上部
主筋13の先端部13bに、図6及び図7に示すように
ガイドキャップ部材の一例である、矢印C方向にとがっ
たキャップ42を予めそれぞれ装着しておく。キャップ
42の設置により、該上部主筋13をプレキャスト梁部
材5Aの上側を移動させる際、特に、該上部主筋13を
移動させて、プレキャスト梁部材5Aの上側のスターラ
ップ11内に挿入させる際、先端部13bに装着された
キャップ42により、スターラップ11にぶつかるなど
して該スターラップ11から受ける上部主筋13に対す
る抵抗を低減させることができる。つまり、上部主筋1
3の先端部13bが、スターラップ11等にひっかかり
にくくなり、鉄筋設置作業がより円滑に行える。ガイド
キャップ部材は本実施例のキャップ42ような先端がと
がったもの以外に、先端が丸くなったものなど、スター
ラップ11等の障害物から受ける上部主筋13に対する
抵抗を低減させることができる形状のものならどのよう
なものでもよい。The rebar installation device 20 is connected to the precast beam member 5.
After installation at A, the rebar installation work is performed. That is, the drive roller 31, the drive motor 30, and the power transmission member 30a
6 is rotated in the direction of arrow G, as shown in FIG.
3 is transported in the direction of arrow C, that is, in the precast beam member 5A side. The upper main bar 13 is transported, and the upper main bar 13 is moved.
From the frame 21 to the precast beam member 5A side, thereby moving the upper main reinforcing bar 13 in the direction of arrow C along the upper side of the precast beam member 5A, and as shown in FIG. It is arranged and installed at a predetermined position above the member 5A. As shown in FIGS. 6 and 7, caps 42, which are an example of a guide cap member and are pointed in the direction of arrow C, are attached to the distal end portion 13b of each upper main bar 13 to be transported. When the upper main bar 13 is moved above the precast beam member 5A by the installation of the cap 42, especially when the upper main bar 13 is moved and inserted into the stirrup 11 above the precast beam member 5A, With the cap 42 attached to the portion 13b, the resistance to the upper main bar 13 received from the stirrup 11 by hitting the stirrup 11 can be reduced. That is, upper main bar 1
The tip portion 13b of the third hardly gets stuck on the stirrup 11 or the like, and the reinforcing bar installation work can be performed more smoothly. The guide cap member has a shape capable of reducing the resistance to the upper main bar 13 received from an obstacle such as the stirrup 11, such as a tip having a rounded tip, in addition to a pointed tip such as the cap 42 of the present embodiment. Anything can be used.
【0034】また、鉄筋設置作業の際、予めプレキャス
ト梁部材5Aの上側に、図6及び図7に示すように、コ
ロ手段として複数の略円柱状のコロ部材43を設置して
おく。コロ部材43の設置により、上部主筋13をプレ
キャスト梁部材5Aの上側に沿って矢印C方向に移動さ
せる際には、該上部主筋13は複数のコロ部材43の上
に乗り、これらコロ部材43を介して円滑にすべり移動
する。なお、コロ部材43は、両端部(即ち、矢印E、
F側の各端部)のうち少なくとも一端を、該コロ部材4
3の全長を伸縮させる形で突出後退自在な鞘管状に構成
する(しかも、適宜なバネ等によりコロ部材43の全長
を伸ばした状態に維持するように構成する)ことが好ま
しい。つまり、コロ部材43をプレキャスト梁部材5A
の上側に設置する際、或いはプレキャスト梁部材5Aの
上側から撤去する際には、該コロ部材43の全長を縮め
た状態で設置・撤去が容易に行える。上述したキャップ
42及びコロ部材43は、上部主筋13の設置完了後に
撤去される。Further, at the time of the rebar installation work, a plurality of substantially cylindrical roller members 43 are previously set as roller means on the upper side of the precast beam member 5A as shown in FIG. 6 and FIG. When the upper main reinforcement 13 is moved in the direction of arrow C along the upper side of the precast beam member 5A by installing the roller members 43, the upper main reinforcement 13 rides on the plurality of roller members 43 and Slides smoothly through. The roller member 43 has both ends (that is, arrows E,
At least one end of each of the F-side ends)
It is preferable that the entire length of the roller member 43 is configured to extend and retract to form a sheath tube that can freely protrude and retract (and that the entire length of the roller member 43 is maintained in an extended state by an appropriate spring or the like). That is, the roller member 43 is connected to the precast beam member 5A.
When the roller member 43 is installed on the upper side or removed from the upper side of the precast beam member 5A, the roller member 43 can be easily installed and removed with the overall length thereof reduced. The above-described cap 42 and roller member 43 are removed after the installation of the upper main reinforcement 13 is completed.
【0035】前記プレキャスト梁部材5Aに対する上部
主筋13の設置の後、構築中の構造物50のうちその他
の構築中の柱2に対してもプレキャスト梁部材5A、5
B等を設置し、設置されたプレキャスト梁部材5Aに対
しては、鉄筋設置装置20を介して上述した方法と同様
にして上部主筋13を設置する(或いは、従来の方法に
より上部主筋13を設置する。)。次いで、プレキャス
ト梁部材5A、5Bの梁仕口部9、9と重なった各柱仕
口部17等に対して適宜な型枠(図示せず)を設置し、
プレキャストコンクリート製のスラブ6等を、前記設置
されたプレキャスト梁部材5A、5Bに支持させる形で
設置し、前記各型枠15で囲まれた柱形成空間16及び
各柱仕口部17等にコンクリートを打設充填して、図1
8に示すように、大梁1A、1B及びこれら大梁1A、
1Bを支持する柱2からなる柱梁構造物3を、スラブ6
と一体となる形で構築完成させる。その後、完成された
スラブ6上に続けて、上述した方法により次の階の柱梁
構造物3及びスラブ6を構築するようにして構造物50
を完成させる。After the installation of the upper main reinforcement 13 on the precast beam member 5A, the precast beam members 5A, 5A and 5B are also applied to the other columns 2 under construction among the structures 50 under construction.
B, etc., and the upper main reinforcing bar 13 is installed on the installed precast beam member 5A via the reinforcing bar installing device 20 in the same manner as described above (or the upper main reinforcing bar 13 is installed by a conventional method). I do.) Next, an appropriate formwork (not shown) is installed for each of the column joints 17 overlapping the beam joints 9, 9 of the precast beam members 5A, 5B,
Precast concrete slabs 6 and the like are installed in such a manner as to be supported by the installed precast beam members 5A and 5B, and concrete is formed in the column forming spaces 16 and the column joints 17 surrounded by the formwork 15 and the like. Fig. 1
8, the girders 1A, 1B and these girders 1A,
The beam-to-column structure 3 composed of the columns 2 supporting the slab 6
Complete the construction in an integrated manner. After that, on the completed slab 6, the column 50 and the slab 6 of the next floor are constructed by the above-described method to construct the structure 50.
To complete.
【0036】なお上述した実施例において、鉄筋載置手
段である鉄筋設置装置20には、図2及び図3に示すよ
うに、複数の上部主筋13を、前記プレキャスト梁部材
5Aにおいて配筋されるべき複数の上部主筋13の配筋
状態(図17に図示)に対応した状態で載置しているの
で、鉄筋設置装置20をプレキャスト梁部材5Aに対し
て位置決めした後、図6に示すように、複数の上部主筋
13を該プレキャスト梁部材5Aに向かって水平に移動
させて、該プレキャスト梁部材5Aの上側の所定の位置
で移動停止させるだけで、これら複数の上部主筋13
は、該プレキャスト梁部材5Aにおいて配筋されるべき
配筋状態で配置される。In the above-described embodiment, as shown in FIGS. 2 and 3, a plurality of upper main reinforcing bars 13 are arranged in the reinforcing bar installation device 20 as the reinforcing bar mounting means in the precast beam member 5A. Since it is placed in a state corresponding to the arrangement state of the plurality of upper main reinforcements 13 (shown in FIG. 17), after the reinforcing-bar installation device 20 is positioned with respect to the precast beam member 5A, as shown in FIG. By simply moving the plurality of upper main reinforcing bars 13 horizontally toward the precast beam member 5A and stopping the movement at a predetermined position above the precast beam member 5A, the plurality of upper main reinforcing bars 13 are moved.
Are arranged in a reinforcing arrangement to be arranged in the precast beam member 5A.
【0037】また上述した実施例において、下側ローラ
27に載置された複数の上部主筋13のうち、搬送途中
の上部主筋13の先端側がプレキャスト梁部材5A側に
おいて不用意な抵抗を受け、駆動ローラ31、31によ
り上部主筋13を搬送する力が該抵抗に打ち勝てない場
合には、図8及び図9に示すように、鉄筋押付手段32
において押付ローラ35を矢印E、F方向に移動させる
ことにより、該押付ローラ35を前記抵抗を受けている
上部主筋13に対向させると共に、操作本体33を矢印
J方向に移動させて押付ローラ35を、前記対向させた
上部主筋13に対して押付けることにより、前記抵抗を
受けている上部主筋13と前記駆動ローラ31、31と
の間の押圧力を増加させる。押圧力を増加させることに
より、前記駆動ローラ31、31により上部主筋13を
搬送する力を増加させて、前記抵抗を受けている上部主
筋13を該抵抗に打ち勝たせる形で続けて搬送すること
ができる。In the above-described embodiment, of the plurality of upper main reinforcements 13 placed on the lower roller 27, the leading end of the upper main reinforcement 13 in the middle of conveyance receives an inadvertent resistance on the precast beam member 5A side and is driven. If the force for conveying the upper main bar 13 by the rollers 31 cannot overcome the resistance, as shown in FIGS.
By moving the pressing roller 35 in the directions of arrows E and F, the pressing roller 35 is opposed to the upper main bar 13 receiving the resistance, and the operating body 33 is moved in the direction of arrow J to move the pressing roller 35. The pressing force between the upper main bar 13 receiving the resistance and the drive rollers 31, 31 is increased by pressing the upper main bar 13 opposed to the upper main bar 13. Increasing the pressing force increases the force for transporting the upper main reinforcement 13 by the drive rollers 31, 31, and continuously transports the upper main reinforcement 13 receiving the resistance in a form that overcomes the resistance. Can be.
【0038】また上述した実施例では、構築中の柱2に
設置されたプレキャスト梁部材5Aに上部主筋13を設
置する場合について説明したが、本発明による鉄筋設置
方法は、例えば構築中の柱に打設設置された現場打ちコ
ンクリートによる梁部材に上部主筋等の梁用主筋を設置
する際にも適用できる。即ち、この場合にも上述した実
施例と同様の手順により、鉄筋設置装置20等の鉄筋載
置手段を用いて、梁部材に上部主筋等の梁用主筋を設置
すればよい。In the above-described embodiment, the case where the upper main reinforcing bar 13 is installed on the precast beam member 5A installed on the column 2 under construction has been described. The present invention can also be applied to a case where a beam main reinforcement such as an upper main reinforcement is installed on a cast-in-place cast-in-place concrete beam member. That is, also in this case, the beam main reinforcement such as the upper main reinforcement may be installed on the beam member by using the reinforcing bar mounting means such as the reinforcing bar installation device 20 in the same procedure as in the above-described embodiment.
【0039】[0039]
【発明の効果】以上説明したように本発明のうち第一の
発明は、構築中の柱2等の柱に設置されたプレキャスト
梁部材5A、現場打ちコンクリートによる梁部材等の梁
部材に上部主筋13等の梁用主筋を設置する際、前記梁
部材上に設置すべき前記梁用主筋の矢印C、D方向等の
設置方向延長上に位置する、別の構築中の柱に対し、前
記梁用主筋を水平に載置した鉄筋設置装置20等の鉄筋
載置手段を係合させて、該鉄筋載置手段の前記梁用主筋
の矢印C、D方向等の載置方向と、前記梁部材の前記梁
用主筋の設置方向とを一致させる形で位置決めし、前記
梁用主筋を、前記鉄筋載置手段側から前記梁部材に向か
って水平に移動させ、前記梁用主筋の移動により、前記
梁用主筋を前記梁部材の上側の所定の位置に配置するよ
うにして構成される。即ち、鉄筋載置手段を、該鉄筋載
置手段の載置方向と梁部材の設置方向とを一致させる形
で位置決めすることにより、鉄筋載置手段に載置された
梁用主筋は、該梁用主筋を設置すべき梁部材に対して位
置決め配置される。よって、梁用主筋の梁部材に対する
位置決め配置は、該梁用主筋を1本づつ梁部材に対して
位置決めする形で行う必要がなく、鉄筋載置手段を位置
決めすることにより一度に簡単に行うことができる。ま
た、梁部材及び該梁部材が設置されている構築中の柱及
び該構築中の柱以外の別の構築中の柱は、これら相互の
位置が互いに固定的であるため、該別の構築中の柱に対
して鉄筋載置手段を係合させることにより、該鉄筋載置
手段は前記梁部材に対して位置決めされる。従って、鉄
筋載置手段を、該鉄筋載置手段の載置方向と梁部材の設
置方向とを一致させる形で位置決めする作業は、鉄筋載
置手段を前記構築中の柱に係合させることにより、言い
替えれば前記構築中の柱をガイドとしてを利用すること
により簡単にしかも確実に行なわれる。即ち、梁用主筋
の梁部材に対する位置決め配置は、前記構築中の柱をガ
イドとしてを利用することにより容易にしかも確実に行
なわれる。以上のように、梁部材に対する梁用主筋の位
置決め配置作業を簡単かつ容易に、しかも確実に行うこ
とにより、構築中の柱等に設置された梁部材に対する梁
用主筋の設置を簡単かつ容易に、しかも確実に行うこと
ができるAs described above, according to the first aspect of the present invention, the upper main reinforcement is applied to a beam member such as a precast beam member 5A installed on a pillar such as a pillar 2 under construction or a beam member made of cast-in-place concrete. At the time of installing the beam main reinforcement such as 13, the beam main reinforcement to be installed on the beam member is positioned on an extension of the installation direction, such as the arrow C or D direction, of the beam main reinforcement. A reinforcing bar mounting means such as a reinforcing bar setting device 20 on which a main reinforcing bar is horizontally mounted is engaged, and the mounting direction of the main reinforcing bar for the beam of the reinforcing bar mounting device, such as the arrow C and D directions, and the beam member The beam main reinforcement is positioned so as to match the installation direction of the beam main reinforcement, and the beam main reinforcement is horizontally moved from the rebar mounting means side toward the beam member, and the movement of the beam main reinforcement causes the The main beam reinforcement is arranged at a predetermined position above the beam member. . That is, by positioning the reinforcing bar mounting means so that the mounting direction of the reinforcing bar mounting means and the installation direction of the beam member coincide with each other, the beam main reinforcing bar mounted on the reinforcing bar mounting means can It is positioned and arranged with respect to the beam member on which the main reinforcement is to be installed. Therefore, it is not necessary to position the main bars for beams relative to the beam members in such a manner that the main bars for beams are positioned one by one with respect to the beam members. Can be. In addition, the beam member and the column under construction on which the beam member is installed and the column under construction other than the column under construction are mutually fixed in position, so that the column under construction is different from the column under construction. By engaging the reinforcing bar mounting means with the column, the reinforcing bar mounting means is positioned with respect to the beam member. Therefore, the work of positioning the reinforcing bar mounting means in such a manner that the mounting direction of the reinforcing bar mounting means and the installation direction of the beam member coincide with each other is performed by engaging the reinforcing bar mounting means with the column under construction. In other words, by using the column under construction as a guide, it can be performed simply and reliably. In other words, the positioning of the main beams for the beam relative to the beam member can be easily and reliably performed by using the column under construction as a guide. As described above, the positioning and positioning of the beam main reinforcing bar with respect to the beam member is performed simply and easily and reliably, so that the beam main reinforcing bar can be easily and easily installed on the beam member installed on the column or the like under construction. And it can be done reliably
【0040】また本発明のうち第二の発明は、第一の発
明による鉄筋の設置方法において、前記梁用主筋を、前
記鉄筋載置手段側から前記梁部材に向かって水平に移動
させる際に、前記梁用主筋の先端部13b等の先端部に
キャップ42等のガイドキャップ部材を装着して移動さ
せるので、前記梁用主筋の移動は、該梁用主筋の先端部
に装着されたガイドキャップ部材により、前記梁部材の
上側の障害物(例えばスターラップ11等)による該梁
用主筋に対する抵抗を低減させる形で行われる。よっ
て、第一の発明による効果に加えて、梁用主筋を梁部材
に向かって水平に移動させる動作は円滑に行えるので、
梁部材に梁用主筋を設置する作業は円滑に行うことがで
きる。A second aspect of the present invention is the method of installing a reinforcing bar according to the first aspect, wherein the main beam reinforcing bar is horizontally moved from the side of the reinforcing bar mounting means toward the beam member. Since a guide cap member such as a cap 42 is attached to the tip of the beam main bar tip 13b or the like and moved, the beam main bar is moved by the guide cap attached to the tip of the beam bar. The member is used to reduce the resistance of the obstacle above the beam member (for example, the stirrup 11) to the main bar for the beam. Therefore, in addition to the effect of the first invention, the operation of moving the beam main reinforcement horizontally toward the beam member can be performed smoothly,
The work of installing the beam main reinforcement on the beam member can be performed smoothly.
【0041】また本発明のうち第三の発明は、第一の発
明による鉄筋の設置方法において、前記梁用主筋を、前
記鉄筋載置手段側から前記梁部材に向かって水平に移動
させる際に、前記梁部材の上側にコロ部材43等のコロ
手段を設置し、前記梁用主筋の移動は、該梁用主筋を前
記コロ手段に乗せる形で行うので、梁用主筋の移動はコ
ロ手段を介して円滑に行われる。よって、第一の発明に
よる効果に加えて、梁部材に梁用主筋を設置する作業は
円滑に行うことができる。According to a third aspect of the present invention, there is provided the reinforcing bar installation method according to the first aspect, wherein the main beam reinforcing bar is horizontally moved from the side of the reinforcing bar mounting means toward the beam member. A roller means such as a roller member 43 is installed above the beam member, and the movement of the beam main reinforcement is performed in such a manner that the beam main reinforcement is mounted on the roller means. Done smoothly. Therefore, in addition to the effect of the first invention, the work of installing the beam main reinforcement on the beam member can be performed smoothly.
【0042】また本発明のうち第四の発明は、第一の発
明による鉄筋の設置方法において、前記鉄筋載置手段の
係合は、前記梁部材上に設置すべき前記梁用主筋の設置
方向延長上に位置する、別の構築中の、互いに隣接した
複数の柱に対して行うので、鉄筋載置手段を、該鉄筋載
置手段の載置方向と梁部材の設置方向とを一致させる形
で位置決めする作業は、鉄筋載置手段を前記構築中の複
数の柱に係合させることにより行なわれる。つまり、第
一の発明による効果に加えて、鉄筋載置手段の位置は複
数の構築中の柱において、即ち2箇所以上で固定される
ため、該鉄筋載置手段の位置決めは正確に行なわれる。According to a fourth aspect of the present invention, in the method for installing a reinforcing bar according to the first aspect, the engagement of the reinforcing bar mounting means is performed in a direction in which the main reinforcing bar for a beam to be installed on the beam member. Since this is performed on a plurality of columns that are adjacent to each other and are under construction, which are located on the extension, the reinforcing bar mounting unit is configured to match the mounting direction of the reinforcing bar mounting unit with the installation direction of the beam member. The work of positioning is performed by engaging the reinforcing bar mounting means with the plurality of columns under construction. In other words, in addition to the effect of the first invention, since the position of the reinforcing bar mounting means is fixed at a plurality of columns under construction, that is, at two or more positions, the positioning of the reinforcing bar mounting means is performed accurately.
【0043】また本発明のうち第五の発明は、第一の発
明による鉄筋の設置方法において、前記鉄筋載置手段に
は、複数の梁用主筋を、前記梁部材において配筋される
べき複数の梁用主筋の配筋状態に対応した状態で載置し
たので、鉄筋載置手段を梁部材に対して位置決めした
後、複数の梁用主筋を該梁部材に向かって水平に移動さ
せて、該梁部材の上側の所定の位置で移動停止させるだ
けで、これら複数の梁用主筋は、該梁部材において配筋
されるべき配筋状態で配置される。よって、第一の発明
による効果に加えて、梁部材の上側まで移動されて来た
複数の梁用主筋を、該梁部材上において、配筋されるべ
き配筋状態に並べて配置する手間が省けて都合がよい。According to a fifth aspect of the present invention, in the method of installing a reinforcing bar according to the first aspect, the reinforcing bar mounting means includes a plurality of main bars for beams, and a plurality of reinforcing bars to be arranged in the beam member. Since it was placed in a state corresponding to the reinforcing state of the beam main reinforcement, after positioning the reinforcing bar mounting means with respect to the beam member, a plurality of beam main reinforcements were moved horizontally toward the beam member, By simply stopping the movement at a predetermined position above the beam member, the plurality of beam main reinforcements are arranged in a reinforcement arrangement to be arranged in the beam member. Therefore, in addition to the effect of the first invention, it is possible to save the trouble of arranging a plurality of beam main reinforcing bars that have been moved to the upper side of the beam member on the beam member in a reinforcing bar arrangement state to be laid. It is convenient.
【図1】図1は、鉄筋設置装置の一例を示した側面図で
ある。FIG. 1 is a side view showing an example of a reinforcing-bar installation device.
【図2】図2は、図1のI矢視図である。FIG. 2 is a view on arrow I of FIG. 1;
【図3】図3は、図1のII矢視図である。FIG. 3 is a view taken in the direction of arrow II in FIG. 1;
【図4】図4は、図2のX1−Y1線断面図である。FIG. 4 is a sectional view taken along line X1-Y1 of FIG. 2;
【図5】図5は、図2のX2−Y2線断面図である。FIG. 5 is a sectional view taken along line X2-Y2 in FIG. 2;
【図6】図6は、図1に示す鉄筋設置装置により鉄筋設
置作業を行なっている図である。FIG. 6 is a diagram showing that a reinforcing-bar setting operation is being performed by the reinforcing-bar setting device shown in FIG. 1;
【図7】図7は、図6のX3−Y3線断面図である。FIG. 7 is a sectional view taken along line X3-Y3 of FIG. 6;
【図8】図8は、図1に示す鉄筋設置装置の鉄筋押付手
段付近の拡大図である。FIG. 8 is an enlarged view of the vicinity of a rebar pressing means of the rebar installation device shown in FIG. 1;
【図9】図9は、図8のIII矢視断面図である。FIG. 9 is a sectional view taken along the arrow III in FIG. 8;
【図10】図10は、図2のX4−Y4線断面図であ
る。FIG. 10 is a sectional view taken along line X4-Y4 of FIG. 2;
【図11】図11は、図1に示す鉄筋設置装置の落下防
止手段付近の拡大図である。FIG. 11 is an enlarged view of the vicinity of a fall prevention means of the reinforcing-bar installation device shown in FIG. 1;
【図12】図12は、構造物全体を示した水平断面図で
ある。FIG. 12 is a horizontal sectional view showing the entire structure.
【図13】図13は、プレキャスト梁部材を示した斜視
図である。FIG. 13 is a perspective view showing a precast beam member.
【図14】図14は、図13に示すプレキャスト梁部材
とは別のプレキャスト梁部材を示した斜視図である。FIG. 14 is a perspective view showing a precast beam member different from the precast beam member shown in FIG.
【図15】図15は、図13及び図14に示すプレキャ
スト梁部材を用いて柱梁構造物を構築する際の一工程を
示した斜視図である。FIG. 15 is a perspective view showing one step in constructing a column-beam structure using the precast beam members shown in FIGS. 13 and 14.
【図16】図16は、図13及び図14に示すプレキャ
スト梁部材を用いて柱梁構造物を構築する際の一工程を
示した斜視図である。FIG. 16 is a perspective view showing one step in constructing a column-beam structure using the precast beam members shown in FIGS. 13 and 14.
【図17】図17は、図13及び図14に示すプレキャ
スト梁部材を用いて柱梁構造物を構築する際の一工程を
示した斜視図である。FIG. 17 is a perspective view showing one step in constructing a column-beam structure using the precast beam members shown in FIGS. 13 and 14.
【図18】図18は、完成した柱梁構造物を示した斜視
図である。FIG. 18 is a perspective view showing a completed column-beam structure.
2……柱 5A……プレキャスト梁部材(梁部材) 13……梁用主筋(上部主筋) 13b……先端部 20……鉄筋載置手段(鉄筋設置装置) 42……ガイドキャップ部材(キャップ) 43……コロ手段(コロ部材) 2 Column 5A Precast beam member (beam member) 13 Beam main bar (upper main bar) 13b Tip 20 Rebar mounting means (rebar installation device) 42 Guide cap member (cap) 43 Roller means (roller member)
Claims (5)
を設置する際、 前記梁部材上に設置すべき前記梁用主筋の設置方向延長
上に位置する、別の構築中の柱に対し、前記梁用主筋を
水平に載置した鉄筋載置手段を係合させて、該鉄筋載置
手段の前記梁用主筋の載置方向と、前記梁部材の前記梁
用主筋の設置方向とを一致させる形で位置決めし、 前記梁用主筋を、前記鉄筋載置手段側から前記梁部材に
向かって水平に移動させ、 前記梁用主筋の移動により、前記梁用主筋を前記梁部材
の上側の所定の位置に配置するようにして構成した鉄筋
の設置方法。When a main beam for a beam is installed on a beam member installed on a column under construction, when another main beam for a beam which is to be installed on the beam member is located on an extension of the installation direction of the main bar for a beam, The rebar placement means, on which the beam reinforcement is horizontally mounted, is engaged with the column, and the mounting direction of the beam reinforcement of the reinforcement placement means and the installation of the beam reinforcement of the beam member. The main bars for beams are moved horizontally from the rebar placing means side toward the beam members, and the main bars for beams are moved by the movement of the main bars for beams. A method of installing a reinforcing bar configured to be arranged at a predetermined position on the upper side.
前記梁部材に向かって水平に移動させる際に、 前記梁用主筋の先端部にガイドキャップ部材を装着して
移動させることを特徴とする請求項1記載の鉄筋の設置
方法。2. The method according to claim 2, wherein the main bar for beam is horizontally moved from the reinforcing bar mounting means side toward the beam member, wherein a guide cap member is attached to a distal end portion of the main bar for beam. The method of claim 1, wherein the reinforcing bar is installed.
前記梁部材に向かって水平に移動させる際に、 前記梁部材の上側にコロ手段を設置し、 前記梁用主筋の移動は、該梁用主筋を前記コロ手段に乗
せる形で行うことを特徴とする請求項1記載の鉄筋の設
置方法。3. When the main bar for beams is moved horizontally from the side of the rebar placing means toward the beam member, a roller means is provided above the beam member, and the main bars for beam are moved. 2. The method according to claim 1, wherein the main reinforcement for the beam is mounted on the roller means.
に設置すべき前記梁用主筋の設置方向延長上に位置す
る、別の構築中の、互いに隣接した複数の柱に対して行
うことを特徴とする請求項1記載の鉄筋の設置方法。4. Engagement of the reinforcing bar mounting means is performed with respect to a plurality of columns adjacent to each other which are located on an extension of the main beam reinforcing bar to be installed on the beam member and are under construction. The method for installing a reinforcing bar according to claim 1, wherein
を、前記梁部材において配筋されるべき複数の梁用主筋
の配筋状態に対応した状態で載置したことを特徴とする
請求項1記載の鉄筋の設置方法。5. A reinforcing bar mounting means, wherein a plurality of main bars for beams are mounted in a state corresponding to the arrangement of the plurality of main bars for beams to be laid in the beam members. The method for installing a reinforcing bar according to claim 1.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP15217895A JP2819528B2 (en) | 1995-05-26 | 1995-05-26 | How to install rebar |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP15217895A JP2819528B2 (en) | 1995-05-26 | 1995-05-26 | How to install rebar |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH08326318A JPH08326318A (en) | 1996-12-10 |
| JP2819528B2 true JP2819528B2 (en) | 1998-10-30 |
Family
ID=15534762
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP15217895A Expired - Fee Related JP2819528B2 (en) | 1995-05-26 | 1995-05-26 | How to install rebar |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2819528B2 (en) |
-
1995
- 1995-05-26 JP JP15217895A patent/JP2819528B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH08326318A (en) | 1996-12-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US20190226210A1 (en) | Beam-column connection structure and method for forming the same | |
| JP2819528B2 (en) | How to install rebar | |
| JP2819527B2 (en) | Rebar installation equipment | |
| JP2819529B2 (en) | Rebar installation equipment | |
| JP7186655B2 (en) | Construction method of beam-column connection structure | |
| KR200368859Y1 (en) | a steel processing machinery for a Circle Rod Structure | |
| KR101666981B1 (en) | Connecting structure of prefabricated steel frame | |
| JP3586121B2 (en) | Mixed structure of reinforced concrete column and steel beam and its construction method | |
| JPH07217080A (en) | Two-layer type reinforcing steel net | |
| JP3862427B2 (en) | Construction method for receiving girders for jumping scaffolds and jumping scaffolds | |
| JP6826887B2 (en) | Prefabricated structure erection method, prefabricated structure | |
| JP2004052389A (en) | Panel zone construction method and precast beam | |
| JP3187618B2 (en) | How to assemble beam reinforcement | |
| JP2007217869A (en) | Structure for joining precast concrete walls together | |
| JP4392684B2 (en) | Rebar rod jig, rebar rod assembly method | |
| JPH06173390A (en) | Connecting method for precast concrete column | |
| JP2002115402A (en) | Earthquake-resistant reinforcing wall and its construction method | |
| KR102099379B1 (en) | loading device for steel processing structure | |
| JP2025054529A (en) | Reinforcing bar placement device, reinforcing bar placement method, and reinforcing bar support stand | |
| JPH1046820A (en) | Column reinforcement installation stand and column reinforcement installation method using the same | |
| JP3622119B2 (en) | Basic bar arrangement method | |
| JP2984626B2 (en) | PC pillar construction method and its PC pillar | |
| JP2003278272A6 (en) | Precast concrete column and its construction method | |
| JP2000265546A (en) | Method of constructing columns, and method of constructing columns and beams | |
| JP2775712B2 (en) | How to build rebar |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |