JPH01105807A - Connection structure of precast concrete floor panel - Google Patents

Connection structure of precast concrete floor panel

Info

Publication number
JPH01105807A
JPH01105807A JP26315087A JP26315087A JPH01105807A JP H01105807 A JPH01105807 A JP H01105807A JP 26315087 A JP26315087 A JP 26315087A JP 26315087 A JP26315087 A JP 26315087A JP H01105807 A JPH01105807 A JP H01105807A
Authority
JP
Japan
Prior art keywords
slabs
precast concrete
reinforcing bars
connection structure
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP26315087A
Other languages
Japanese (ja)
Inventor
Yoichi Takiguchi
瀧口 洋一
Hiromichi Yasunami
博道 安波
Hisao Yamashita
久男 山下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP26315087A priority Critical patent/JPH01105807A/en
Publication of JPH01105807A publication Critical patent/JPH01105807A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: To reduce the connection gap by projecting a threaded reinforcing bar from a connection end face of a precast concrete slab, and fixing each threaded reinforcing bar to an anchor plate provided between the slabs to be connected using a nut in a non-overlapped manner. CONSTITUTION: A large number of threaded reinforcing bars 5 are projected on a connection end surface of a precast concrete slab (PC slab). In connecting the PC slabs 2 to each other, the threaded reinforcing bar 5 is arranged on the PC slab 2 so that the threaded reinforcing bars 5 on the connection end face are not intersected with each other. The threaded reinforcing bar 5 of the slab 2 to be connected is inserted in an anchor plate 6 piercing the threaded reinforcing bar 5, and then, tightened by a nut 7. A concrete is placed in a connection part of both slabs 2 to complete the connection of the PC slab 2. Connection of the PC slabs 2 with small intervals between the slabs can be realized.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、商架橋等の路面を形成するために多(用いら
れているプレキャストコンクリート床版同士の接続構造
に関するものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a connection structure between precast concrete slabs, which is used for forming road surfaces such as commercial bridges.

(従来の技術) 従来、プレキャストコンクリート床版同士の接続構造と
しては第10.11.12図に示すように、主桁1の上
72ンジ上に設置されたプレキャストコンクリート床版
2.2の鉄筋3.3の端部3a、3a同士を互いにラッ
プさせて重ね継手を形成し、さらにその床版2.2の間
にコンクリート4を打設して床版2.2同士を一体的に
連結した構造のものが知られている。
(Prior art) Conventionally, as shown in Fig. 10.11.12, the connection structure between precast concrete slabs is the reinforcing bars of the precast concrete slabs 2.2 installed on the top 72 inches of the main girder 1. The ends 3a and 3a of 3.3 were lapped together to form a lap joint, and concrete 4 was poured between the floor slabs 2.2 to integrally connect the floor slabs 2.2. structure is known.

この重ね継手で床版2.2同士を接続する場合、打設コ
ンクリート4と鉄筋継手端1り’53a、3aとの一体
化による強化およびその重ね接続部の強度などの理由か
ら床版2.2同士の重ね長さ1を鉄筋3の径dの約30
倍程度設定することが要求されている。
When connecting the floor slabs 2.2 to each other with this lap joint, the deck slabs 2. The overlapping length 1 of the two is approximately 30 of the diameter d of the reinforcing bar 3.
It is required that the setting be approximately twice that.

(発明が解決しようとする問題1代) ところが、最近は交通適所期間を極力短くするよう求め
られていること等により、この重ね長さ邪に打設するコ
ンクリート4の強度が短時間で発揮するいわゆる超速硬
コンクリートが用いられるようになってきている。この
超速硬コンクリートは従来のコンクリートに比較して約
20倍の価格であり、この大きな玉ね長さ1に用いると
工期は短縮できるが大変コストが高い床版となる欠点が
ある。
(Problem to be solved by the invention) Recently, however, due to the demand to shorten the period of time required for transportation as much as possible, the strength of the concrete 4, which is poured at an irregularly stacked length, is exerted in a short period of time. So-called super-rapid hardening concrete has come into use. This ultra-quick hardening concrete is about 20 times more expensive than conventional concrete, and when used for this large ball length 1, the construction period can be shortened, but it has the disadvantage of resulting in a very expensive floor slab.

この重ね長さを短くする接続構造としては、実公昭60
−22083号公報開示のものがある。
As a connection structure to shorten this overlap length,
There is one disclosed in No.-22083.

これは第13図に示すようにプレキャストコンクリート
床版2.2を鉄筋3の継手端が千鳥状になるように載置
し、この千鳥状に配列された鉄筋3の上面に7ラツトパ
ー9を置き、その後上側に抜は止めの突状11を溶接し
た座金12を挿入し、それをナツト10でねじ込み固定
し、両床版間にコンクリート4を打設した接続構造であ
る。
As shown in Fig. 13, the precast concrete slab 2.2 is placed so that the joint ends of the reinforcing bars 3 are arranged in a staggered manner, and 7 rattupers 9 are placed on the top surface of the reinforcing bars 3 arranged in a staggered manner. After that, a washer 12 with a protrusion 11 welded to the upper side to prevent removal is inserted, and this is screwed and fixed with a nut 10, and concrete 4 is poured between both deck slabs.

この接続構造では、フラットバー9をプレキャストコン
クリート床版2載置後設置するので現場施工は簡単であ
るが、鉄筋の力を伝達する際の力の軸線がずれ、この継
手部の変形が太き(なり、コンクリートのひび割れが大
きくなる欠点がある。
In this connection structure, the flat bar 9 is installed after the precast concrete slab 2 is placed, so on-site construction is easy. (This has the disadvantage of increasing the cracks in the concrete.

これに対し、鉄筋3の上下部に7ラツトバーを設置して
対応することも開示されているが、設置時の7ラツトバ
ーの保持、フラットバーの寸法製作精度が必要となる等
、現場作業が非常に煩雑となる欠点がある。
To deal with this, it is disclosed that 7 rat bars are installed above and below the reinforcing bars 3, but this requires a lot of on-site work, such as the need to hold the 7 rat bars during installation and the precision of the dimensions of the flat bar. The disadvantage is that it is complicated.

また、実開昭60−70616号公報には、フラットバ
ーに代わる部材として第14図に示すような中継部材1
3を用いることが開示されている。
In addition, Japanese Utility Model Application No. 60-70616 discloses a relay member 1 as shown in FIG. 14 as a member to replace the flat bar.
It is disclosed to use 3.

この中継部材13は、一対の(IIII@部14とこの
両側板部を連結する連結板15とから構成され、側板部
14には鉄筋の継手端がそれぞれ嵌合する切欠孔16が
設けられている。
This relay member 13 is composed of a pair of (III@ portions 14 and a connecting plate 15 that connects the side plate portions, and the side plate portions 14 are provided with notch holes 16 into which the joint ends of the reinforcing bars fit respectively. There is.

この構造だと切欠孔16が鉄筋の引張力で最大曲げモー
メントが発生する場所であり、側板部14のこの部分に
切欠孔16を設けると側板部14の板厚を厚くすること
が必要となり、構造上の欠点となる。*た、側板部14
と連結板15との溶接量が多(なり、製作費が高くなる
。
In this structure, the notch hole 16 is the place where the maximum bending moment occurs due to the tensile force of the reinforcing bars, and if the notch hole 16 is provided in this part of the side plate part 14, it is necessary to increase the thickness of the side plate part 14, This is a structural defect. *Side plate part 14
A large amount of welding is required between the connecting plate 15 and the connecting plate 15, which increases the manufacturing cost.

本発明は、これらの欠点なく両床版間間隔を短縮できる
プレキャストコンクリート床版の接続構造を提供する。
The present invention provides a connection structure for precast concrete slabs that can shorten the distance between both slabs without these drawbacks.

(問題点を解決するための手段) 本発明は、互いに接続すべきプレキャストコンクリート
床版の端面同士を間隔をおいて向かい合わせ、それら両
床版の鉄筋の各継手端同士を連結し、両床服間にコンク
リートを打設して接続するプレキャストコンクリート床
版の接続構造においで、床版に継手層にねじを有する鉄
筋を用い、両床版の鉄筋継手端が貫通する開孔部を設け
たアンカー板に両床版の鉄筋継手端をお互いに交錯しな
いよう貫通させ、両床版の鉄筋継手端にナツトをはめ込
みアンカー板を介して締結した後置床版間にコンクリー
トを打設したことを特徴とするプレキャストコンクリー
ト床版の接続構造である。
(Means for Solving the Problems) The present invention has the end surfaces of precast concrete slabs to be connected to each other facing each other at intervals, and the respective joint ends of the reinforcing bars of both slabs are connected to each other. In the connection structure of precast concrete slabs that are connected by pouring concrete between the slabs, reinforcing bars with threads are used in the joint layer of the slab, and an opening is provided through which the joint ends of the reinforcing bars of both slabs pass through. The feature is that the reinforcing bar joint ends of both deck slabs are passed through the anchor plate so that they do not cross each other, nuts are fitted into the reinforcing bar joint ends of both deck slabs, and concrete is poured between the subsequent slabs that are connected via the anchor plate. This is a precast concrete slab connection structure.

(作用) 両床版の鉄筋継手端が貫通する開化部を設けたアンカー
板を介して締結するのは、鉄筋の軸力線方向をずらすこ
となく強度的に向上させて両床版を短い間隔で接続する
ためである。また、施工に際しては、アンカー板を一方
の床版の鉄筋継手端にあらかじめ貫通させておく等、ア
ンカー板の取り扱いを容易とし、接続を簡単、確実にす
ることができる。
(Function) The method of fastening both slabs through anchor plates with openings through which the joint ends of the reinforcing bars penetrate improves strength without shifting the direction of the axial force line of the reinforcing bars, and allows both slabs to be connected at a short distance. This is to connect with. In addition, during construction, the anchor plate can be easily handled by penetrating the reinforcing bar joint end of one floor slab in advance, and the connection can be made simple and reliable.

(実施例) 第1図、第2図は本発明の接続構造の例を示す。(Example) 1 and 2 show examples of the connection structure of the present invention.

両プレキャストコンクリート床版2の鉄筋5が各継手端
がお互いに交錯しないよう配置してあり、アンカー板6
の各開化部に両床履の鉄筋継手端を貫通させ、ナツト7
で締結し、コンクリート4を打設しである。接続部分の
開隔mはMSio〜12図に示した接続構造における重
ね長さ1に比べて小さくてよい。
The reinforcing bars 5 of both precast concrete slabs 2 are arranged so that their respective joint ends do not cross each other, and the anchor plates 6
Pass the reinforcing bar joint ends of both sandals through each opening of the nut 7.
and then concrete 4 was poured. The opening distance m of the connection portion may be smaller than the overlapping length 1 in the connection structure shown in FIGS.

第3図には本発明の接続構造で使用するアンカー板6の
形状例を示す。アンカー板6は鋼板からなり、その中央
部に鉄筋5を貫通させる開化部8が、プレキャストコン
クリート床版同士で千鳥に配置する鉄筋ピッチに合わせ
て設けである。そして、第4図に示すように鉄筋5を開
化部8に貫通させ、ナツト7で締結するのである。
FIG. 3 shows an example of the shape of the anchor plate 6 used in the connection structure of the present invention. The anchor plate 6 is made of a steel plate, and the opening part 8 through which the reinforcing bars 5 pass through the center part thereof is provided in accordance with the pitch of the reinforcing bars arranged in a staggered manner between the precast concrete floor slabs. Then, as shown in FIG. 4, the reinforcing bar 5 is passed through the opening 8 and fastened with a nut 7.

このように切欠部でなく開化部とすることによ9力の紬
縄を合わせ、強度的に向上させ、アンカー板厚を薄くで
きる。
In this way, by making the opening part instead of the notch part, the nine-strength pongee rope can be combined, the strength can be improved, and the thickness of the anchor plate can be reduced.

第5図は本発明の接続!Ft造の施工手順の例を示す。Figure 5 shows the connection of the present invention! An example of the construction procedure for Ft construction is shown below.

まず、同図(a)のようにねじを有する鉄筋5を持つプ
レキャストコンクリート床版2をたとえば桁の上部7ラ
ンシ上に設置する。次に、同図(b)に示すように予め
アンカー板6を相対する鉄筋に当たらない位置まで鉄筋
に挿入した他のプレキャストコンクリート床版2を設置
する。この際、他のプレキャストコンクリート床版のね
じ鉄筋端部にはナツト7をセットしておくのが便利であ
る。
First, as shown in FIG. 3A, a precast concrete floor slab 2 having reinforcing bars 5 with screws is installed, for example, on the upper 7 rungs of the girder. Next, as shown in FIG. 6(b), another precast concrete floor slab 2 is installed in which the anchor plate 6 is inserted into the reinforcing bars to a position where it does not hit the opposing reinforcing bars. At this time, it is convenient to set nuts 7 at the ends of the threaded reinforcing bars of other precast concrete slabs.

相対する両床版の鉄筋は千鳥状になるよう製作しておく
。
The reinforcing bars for both opposing slabs should be fabricated in a staggered manner.

鉄筋5は圧延によってねじを形成したねじ鉄筋が最適で
あるが、丸棒にねじ切りしたものでもよい。
The reinforcing bar 5 is optimally a threaded reinforcing bar with a thread formed by rolling, but it may also be a threaded round bar.

両プレキャストコンクリート床版を設置したならば、同
図(c)に示すようにアンカー板6を損へ移動させ、同
図(d)に示すようにナツトを両方からトルクレンチ等
を用いて所定のトルクにより締め付け、その後両床版間
にコンクリートを打設することにより接続を完了する。
Once both precast concrete slabs have been installed, move the anchor plate 6 to the bottom as shown in Figure (c), and tighten the nuts from both sides using a torque wrench etc. as shown in Figure (d). Tighten with torque and then complete the connection by pouring concrete between both slabs.

また、第6図(a)に示すように先に設置したプレキャ
ストコンクリート床版2の鉄筋5に、同図(b)に示す
ようにアンカー板6を挿入した後、同図(c)−(e)
に示すように他のプレキャストコンクリート床版を設置
して締結することも可能である。
Further, as shown in FIG. 6(a), after inserting the anchor plate 6 into the reinforcing bars 5 of the precast concrete slab 2 previously installed, as shown in FIG. 6(b), e)
It is also possible to install and fasten other precast concrete slabs as shown in .

この場合も、アンカー板6を挿入した鉄筋端部にはナツ
ト7をセットしておくのが便利である。
In this case as well, it is convenient to set the nut 7 at the end of the reinforcing bar into which the anchor plate 6 is inserted.

継手部に引張力のみが働く場合は以上に示した片ナツト
方式で良いが、引張力と圧縮力の両者が働く場合は、第
7図に示すようにダブルナツト方式とし、アンカーFi
6を各鉄筋において両側からナツト7で締め付けること
とするのが好ましい。
If only tensile force acts on the joint, the single nut method shown above is sufficient, but if both tensile force and compressive force act, the double nut method as shown in Figure 7 is used, and the anchor Fi
6 is preferably tightened with nuts 7 from both sides of each reinforcing bar.

このように、アンカー板の取り扱いは簡単であり、現場
での作業も簡単に行える。
In this way, the anchor plate is easy to handle and can be easily worked on site.

第8図、第9図は本発明の接続構造によりプレキャスト
コンクリート床版を連続して接続した例を示す。
FIGS. 8 and 9 show an example in which precast concrete slabs are connected in succession using the connection structure of the present invention.

(発明の効果) 本発明の接続構造によれば、鉄筋の輸力線方向をずらさ
ずに短い間隔でプレキャストコンクリート床版同士を接
続することができる。また、アンカー板の取り扱い容易
で、プレキャストコンクリート床版の接続が簡単、確実
に行える。
(Effects of the Invention) According to the connection structure of the present invention, precast concrete slabs can be connected at short intervals without shifting the load line direction of the reinforcing bars. In addition, the anchor plates are easy to handle, and precast concrete slabs can be connected easily and reliably.

【図面の簡単な説明】 第1図、flfJ2図は本発明の接続構造の例を示す図
、 第3図、第4図は本発明の接続構造で使用するアンカー
板の形状例を示す図、 PPJs図、第6図、第7図は本発明の接続a″iの施
工手順例を示す図、 第8図、第9図は本発明の4t−続構造によりプレキャ
ストコンクリート床版を連続して接続した例を示す図、 第10−14図は従来のプレキャストコンクリート床版
の接続構造を示す図である。 1・・・主桁、2・・・プレキャストコンタリート床版
、3・・・鉄筋、4・・・コンクリ−上、5・・・鉄筋
、6・・・アンカー板、7・・・ナツト、8・・・開孔
部、9・・・7.ラットパー、10・・・ナツト、11
・・・突状、12・・・座金、13・・・中継部材、1
4・・・側板部、15・・・連結板、16・・・切欠孔
。
[Brief Description of the Drawings] Figures 1 and 2 are diagrams showing examples of the connection structure of the present invention, Figures 3 and 4 are diagrams showing examples of the shape of the anchor plate used in the connection structure of the present invention, PPJs diagrams, Figures 6 and 7 are diagrams showing examples of construction procedures for connection a″i of the present invention, and Figures 8 and 9 are diagrams showing examples of construction procedures for connection a″i of the present invention. Figures 10-14 are diagrams showing the connection structure of conventional precast concrete slabs. 1... Main girder, 2... Precast concrete slab, 3... Reinforcing bars. , 4... Concrete top, 5... Rebar, 6... Anchor plate, 7... Nut, 8... Opening part, 9... 7. Rat par, 10... Nut, 11
... protrusion, 12 ... washer, 13 ... relay member, 1
4... Side plate portion, 15... Connecting plate, 16... Notch hole.

Claims (1)

【特許請求の範囲】[Claims] (1)互いに接続すべきプレキャストコンクリート床版
の端面同士を間隔をおいて向かい合わせ、それら両床版
の鉄筋の各継手端同士を連結し、両床版間にコンクリー
トを打設して接続するプレキャストコンクリート床版の
接続構造において、床版に継手端にねじを有する鉄筋を
用い、両床版の鉄筋継手端が貫通する開孔部を設けたア
ンカー板に両床版の鉄筋継手端をお互いに交錯しないよ
う貫通させ、両床版の鉄筋継手端にナットをはめ込みア
ンカー板を介して締結した後両床版間にコンクリートを
打設したことを特徴とするプレキャストコンクリート床
版の接続構造。
(1) Face the end faces of the precast concrete slabs that are to be connected to each other at intervals, connect the joint ends of the reinforcing bars of both slabs, and connect by pouring concrete between both slabs. In the connection structure of precast concrete slabs, reinforcing bars with screws at the joint ends are used in the slab, and the joint ends of the reinforcing bars of both slabs are connected to an anchor plate with an opening through which the joint ends of the reinforcing bars pass through. This connection structure of precast concrete slabs is characterized in that the reinforcing bars are passed through so as not to intersect with each other, nuts are fitted into the reinforcing joint ends of both slabs, the joints are fastened via anchor plates, and then concrete is poured between both slabs.
JP26315087A 1987-10-19 1987-10-19 Connection structure of precast concrete floor panel Pending JPH01105807A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26315087A JPH01105807A (en) 1987-10-19 1987-10-19 Connection structure of precast concrete floor panel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26315087A JPH01105807A (en) 1987-10-19 1987-10-19 Connection structure of precast concrete floor panel

Publications (1)

Publication Number Publication Date
JPH01105807A true JPH01105807A (en) 1989-04-24

Family

ID=17385499

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26315087A Pending JPH01105807A (en) 1987-10-19 1987-10-19 Connection structure of precast concrete floor panel

Country Status (1)

Country Link
JP (1) JPH01105807A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100544304B1 (en) * 2002-06-18 2006-01-23 (주) 선암기술연구소 Building blocks for bridge deck
JP2011021362A (en) * 2009-07-15 2011-02-03 Kawada Industries Inc Joint structure of precast composite floor slab
JP2016008410A (en) * 2014-06-24 2016-01-18 株式会社Ihiインフラ建設 Reinforcement joint structure for precast concrete floor slab
JP2017036554A (en) * 2015-08-07 2017-02-16 株式会社ピーエス三菱 Cast-in-place joint structure of precast floor slab
JP2018115554A (en) * 2018-05-07 2018-07-26 本清鋼材株式会社 Floor slab installation method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100544304B1 (en) * 2002-06-18 2006-01-23 (주) 선암기술연구소 Building blocks for bridge deck
JP2011021362A (en) * 2009-07-15 2011-02-03 Kawada Industries Inc Joint structure of precast composite floor slab
JP2016008410A (en) * 2014-06-24 2016-01-18 株式会社Ihiインフラ建設 Reinforcement joint structure for precast concrete floor slab
JP2017036554A (en) * 2015-08-07 2017-02-16 株式会社ピーエス三菱 Cast-in-place joint structure of precast floor slab
JP2018115554A (en) * 2018-05-07 2018-07-26 本清鋼材株式会社 Floor slab installation method

Similar Documents

Publication Publication Date Title
US3369334A (en) Building system
US2786349A (en) Prestressed concrete building
JP2024503042A (en) panelized serrated beam assembly
JP2000045227A (en) Joining method and joining structure between cast-in-place concrete slab and steel girder
JP3101163B2 (en) How to join columns and beams
US3374592A (en) Precast column with shear-head sections
JPH08270071A (en) Column-beam joint structure of concrete structures
JP2002004220A (en) Joint device for panel members in composite floor slab
JPH08184121A (en) Precast flooring joint structure
CN111980435B (en) Prestressed underpinning and reinforcement device and method for double-T slab structures
JPH01223247A (en) Joint structure between steel-concrete composed board and steel girder
JPS6349776B2 (en)
JP2000120021A (en) Floor-slab installing-section structure of bridge
CN118390741A (en) Reinforcing steel bar separation connection prefabricated part based on perforated connection plate and connection method
CN110725439A (en) A prefabricated steel-concrete shear wall and its construction method
JPH0426483Y2 (en)
CN116411663A (en) A new steel-concrete building composite structure
CN211114417U (en) Novel steel-concrete composite beam structure of tensile shear
JP7240102B2 (en) Precast synthetic slab, method of joining precast synthetic slab and beam material, and joining structure
KR100555246B1 (en) Honeycomb girder type prestressed concrete composite beam and bridge construction method using the same
JP2972958B2 (en) Beam-to-column connection method
KR920007243B1 (en) Assembly channel beam bridge
CN105986631A (en) Combined beam connecting structure with orifice plates and application thereof
JPH0128162B2 (en)
JPH0421852Y2 (en)