JPH01190824A - Earth work method for reinforcing slope by reinforcing member of belt form - Google Patents

Earth work method for reinforcing slope by reinforcing member of belt form

Info

Publication number
JPH01190824A
JPH01190824A JP1547188A JP1547188A JPH01190824A JP H01190824 A JPH01190824 A JP H01190824A JP 1547188 A JP1547188 A JP 1547188A JP 1547188 A JP1547188 A JP 1547188A JP H01190824 A JPH01190824 A JP H01190824A
Authority
JP
Japan
Prior art keywords
casing
reinforcing
reinforcing material
slope
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1547188A
Other languages
Japanese (ja)
Other versions
JPH0460165B2 (en
Inventor
Shohei Senda
昌平 千田
Kazuo Suzuki
和夫 鈴木
Yuichi Minegishi
峯岸 雄一
Masakatsu Kawamura
川村 正勝
Masatsugu Yamaguchi
政嗣 山口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DOBOKU KENKYU CENTER
Raito Kogyo Co Ltd
Original Assignee
DOBOKU KENKYU CENTER
Raito Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DOBOKU KENKYU CENTER, Raito Kogyo Co Ltd filed Critical DOBOKU KENKYU CENTER
Priority to JP1547188A priority Critical patent/JPH01190824A/en
Publication of JPH01190824A publication Critical patent/JPH01190824A/en
Publication of JPH0460165B2 publication Critical patent/JPH0460165B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

PURPOSE:To improve reinforcing effect by inserting a casing which contains a reinforcing member of a belt form with highly pressurized fluid discharged into a bed rock, pulling up the casing, and thereby anchoring the base end of the reinforcing member onto the slope of the bed rock. CONSTITUTION:The base end of a casing 12 is driven by a hammer 11, and concurrently the hammer 11 is advanced along a guide cell 10 with highly pressurized water W injected out of the nozzles at the tip end of the casing 12 so as to be inserted into the specified depth while cutting a bed rock. Then, a detachable pin 15 is pulled out, the hammer 11 is retreated along the guide cell 10 so that a reinforcing member 1 in a belt form and a tip end shoe 13 are left in the bed rock. And then, the base end of the reinforcing member 1 is anchored onto the slope of the bed rock.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、自然地山斜面または切土斜面あるいは盛土斜
面から帯状補強材を挿入設置して安定化を図る斜面補強
土工法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a slope-reinforcing earthwork method in which a band-shaped reinforcing material is inserted and installed from a natural mountain slope, a cut slope, or an embankment slope to stabilize the slope.

〔従来の技術〕[Conventional technology]

斜面の安定や支持力の増大を目的としたものに補強土工
法がある。この場合、盛土体の補強の場合と自然地山(
切土斜面のこともあり、以下断りない限り自然地山とい
う)の補強の場合とに大別できる。
Reinforced earthwork methods are aimed at stabilizing slopes and increasing their bearing capacity. In this case, in the case of reinforcement of the embankment body and in the case of natural ground (
It can also be divided into cases of reinforcing cut slopes (hereinafter referred to as natural ground unless otherwise specified).

前者の盛土体の補強の例として代表的なのは、テールア
ルメ工法で、各段の盛土の度に、鋼棒や鋼板を水平に設
置するものである。また、盛土の補強に当り、ネット材
などを用いる補強材のみの場合と、テールアルメ工法の
ように、擁壁を設ける場合とがある。
A typical example of the former method of reinforcing embankments is the Terre Armé method, in which steel bars or steel plates are installed horizontally at each level of embankment. In addition, when reinforcing the embankment, there are cases where only reinforcement materials such as net materials are used, and cases where a retaining wall is provided as in the Terre Alme construction method.

他方、自然地山に対するものとしては、鉄筋を平行的に
挿入する工法と、網状鉄筋を互に平行にならないように
挿入する工法のみである。両者は、共に地山を穿孔した
後鉄筋を挿入しその周りにモルタル類を充填して約10
0鶴前後の小口経机を形成するものである。なお、前者
は、モルタル類の充填を行わない場合もある。
On the other hand, as for natural ground, there are only two methods: one in which reinforcing bars are inserted in parallel, and one in which reticulated reinforcing bars are inserted in a non-parallel manner. For both, after drilling into the ground, reinforcing bars were inserted and mortar was filled around them.
It forms the small mouth of around 0 cranes. Note that in the former case, filling with mortar may not be performed.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

ところが、従来の自然地山に対する補強土工法は、鉄筋
またはこれを含む小口経机を、曲げモーメントおよび剪
断に対する抵抗体として作用させ、これにより補強を図
るものである。したがって、その目的からすれば、補強
材を多数自然地山に設置する必要があり、このためその
補強材の挿入およびグラウト注入・定着などの後処理に
全体として多大な手間を要する。
However, in the conventional earthwork reinforcement method for natural ground, reinforcement is achieved by using reinforcing bars or edge bars containing reinforcing bars to act as resistors against bending moments and shearing. Therefore, for this purpose, it is necessary to install a large number of reinforcing materials in the natural ground, and therefore, a great deal of effort is required as a whole for post-processing such as inserting the reinforcing materials and injecting and fixing the grout.

また、自然地山の崩落の防止には、多くの場合、補強材
を引張抵抗体として働かすことが有効であることを本発
明者らは知見したが、前記従来の工法では、専ら補強材
を曲げおよび剪断の抵抗体として働かせており、したが
って補強効果が十分に発揮しないものであった。
In addition, the present inventors have discovered that in many cases it is effective to use reinforcing materials as tensile resistors to prevent the collapse of natural lands; however, in the conventional construction methods described above, reinforcing materials are It functions as a bending and shearing resistor, and therefore does not have a sufficient reinforcing effect.

そこで、本発明の主たる目的は、自然地山に対する補強
効果が大きく、しかも施工能率が高い補強土工法を提供
することにある。
Therefore, the main object of the present invention is to provide a reinforced earth construction method that has a large reinforcing effect on natural ground and has high construction efficiency.

〔問題点を解決するだめの手段〕[Failure to solve the problem]

前記問題点を解決するための本発明は、中空扁平状のケ
ーシング内に厚みが0.6〜2Qmmの帯状補強材を挿
入し、ケーシング内またはケーシング先端前方位置から
高圧液を吐出させながら、高圧液の吐出による穿孔作用
によって穿孔しながら帯状補強材を収容するケーシング
を地山中に所定深度まで挿入し、その後ケーシングを引
き抜き、帯状補強材は地山中に残し、帯状補強材の基端
部を斜面に定着することを特徴とするものである。
The present invention aims to solve the above-mentioned problems by inserting a band-shaped reinforcing material with a thickness of 0.6 to 2 Qmm into a hollow flat casing, and discharging high-pressure liquid from inside the casing or from a position in front of the casing tip. The casing that accommodates the reinforcing strip is inserted into the ground to a predetermined depth while perforating by the perforating action of liquid discharge, and then the casing is pulled out, the reinforcing strip remains in the ground, and the base end of the reinforcing strip is placed on the slope. It is characterized by being established in

〔作 用〕[For production]

本発明では、帯状補強材を地山中に挿入設置するため、
一つの材料当りの表面積が大きいので、地山が崩落しよ
うとするときの引張抵抗がきわめて大きく、地山の補強
効果が大きい。逆に、補強効果が大きいため、少い帯状
補強材の挿入設置で足り、その施工工数が全体として削
減される。
In the present invention, in order to insert and install the belt-shaped reinforcing material into the ground,
Since the surface area per material is large, the tensile resistance when the ground tries to collapse is extremely large, and the reinforcing effect of the ground is large. On the other hand, since the reinforcing effect is large, it is sufficient to insert and install a small number of reinforcing strips, and the number of construction steps is reduced overall.

他方、本発明に係わる厚みが0.6〜201mの厚い帯
状補強材を圧入や打撃により設置することは強度的に到
底無理であるが、これをケーシングにて包み、そのケー
シングを高圧液の吐出による穿孔作用により挿入し、そ
の後ケーシングのみを引き抜き帯状補強材を地山中に残
せば、容易に地山中に挿入設置できる。
On the other hand, it is absolutely impossible to install the thick strip-shaped reinforcing material of the present invention with a thickness of 0.6 to 201 m by press-fitting or hammering, but it is impossible to install it by press-fitting or hammering. The reinforcing material can be easily inserted into the ground by inserting it by the drilling action of the casing, and then pulling out only the casing and leaving the strip reinforcing material in the ground.

すなわち、高圧液の吐出による穿孔作用のみでは、穿孔
力として不十分であったり、地盤が崩落しがちな場合に
は、帯状補強材に強制的に前進力を与える必要がある。
That is, in cases where the perforating action by discharging high-pressure liquid alone is insufficient as a perforating force or when the ground tends to collapse, it is necessary to forcibly apply forward force to the belt-shaped reinforcing material.

この際には、帯状補強材に押圧や打撃力を与えることが
必要となるけれども、先に述べたように、薄い帯状補強
材は強度および耐変形性の点で十分でない。これに対し
て、本発明に従って、薄い帯状補強材をケーシングに包
み、ケーシングに押圧や打撃力を与えることにより、帯
状補強材の変形を防止しながら地山中に挿入設置できる
。しかも、この場合、押圧や打撃力と相俟って高圧液の
穿孔力が付加されるから、地盤に左右されずにケーシン
グおよび帯状補強材の挿入が可能となる。
In this case, it is necessary to apply pressure or impact force to the reinforcing strip, but as described above, thin reinforcing strips do not have sufficient strength and deformation resistance. On the other hand, according to the present invention, by wrapping the thin reinforcing material in a casing and applying pressure or impact force to the casing, the reinforcing material can be inserted into the ground while preventing deformation of the reinforcing material. Moreover, in this case, the piercing force of the high-pressure liquid is added in conjunction with the pressing and impacting forces, so that the casing and the reinforcing strip can be inserted without being affected by the ground.

〔実施例〕〔Example〕

以下本発明を図面を参照しながらさらに詳説する。 The present invention will be explained in more detail below with reference to the drawings.

本発明では、第2図に示すように、鋼板等からなる帯状
補強材を用いる。この場合の厚みtとしては、O16〜
20鶴、特に好ましくは1〜1011のものが用いられ
、幅Wは501■以上、特には100mm以上のものが
用いられ、上限は300 **、場合により1100(
bまでとされる。長さLとしては、種々のものが用いら
れるが、施工を斜面上で行うことによる施工性や設置機
の制約から、最長は10m程度とされる。
In the present invention, as shown in FIG. 2, a strip-shaped reinforcing material made of a steel plate or the like is used. In this case, the thickness t is O16~
20 cranes, particularly preferably 1 to 1011, are used, and the width W is 501 square or more, especially 100 mm or more, and the upper limit is 300**, and in some cases 1100 (
Up to b. Various lengths can be used as the length L, but the longest length is about 10 m due to the ease of construction and restrictions on installation equipment due to the construction being carried out on a slope.

さて、かかる帯状補強材1は、後述する挿入設置例に従
って、第1図のように切取自然地山2斜面から予想すべ
り線!より深くまで挿入設置する。
Now, according to the insertion installation example described later, the strip-shaped reinforcing material 1 is cut out from the slope of the natural ground 2 as shown in Fig. 1 to find the expected slip line! Insert and install deeper.

疑似擁壁的な施工を行う場合、βに達しなくともよい。When constructing a pseudo-retaining wall, it is not necessary to reach β.

この挿入設置が終了したならば、斜面上にモルタル類の
吹付工等により保護壁3を構成するとともに、帯状補強
材1の基端を斜面に対して定着する。
After this insertion and installation is completed, the protective wall 3 is formed on the slope by spraying mortar or the like, and the base end of the band-shaped reinforcing material 1 is fixed to the slope.

この定着手段としては、種々のものを採用できるが、た
とえば第4図のように、補強材10基端を折曲したり、
第5図のように折り返したりして、保護壁3と一体化を
図る方法や、第6図のように、保護壁3上に定着板4を
設け、クサビ5を打ち込むことにより定着することがで
きる。
Various fixing means can be used as this fixing means, but for example, as shown in FIG. 4, the base end of the reinforcing material 10 is bent,
As shown in FIG. 5, it can be folded back to integrate with the protection wall 3, or as shown in FIG. can.

一方、補強材1は、斜め挿入でもよいが、通常は水平に
挿入するのが好ましい。配置例は、第3図のように千鳥
配置のほか、高さ方向に層状の配列であってもよい。ま
た、必要ならば、従来例の断面円形鉄筋6挿入工法を併
用してもよい。補強材の配列ピッチ水平間隔Pは0.5
 m〜2mが好ましく、また高さ間隔りは0.5〜3m
が好ましい。
On the other hand, the reinforcing material 1 may be inserted diagonally, but it is usually preferable to insert it horizontally. Examples of the arrangement include a staggered arrangement as shown in FIG. 3, as well as a layered arrangement in the height direction. Furthermore, if necessary, the conventional method of inserting reinforcing bars 6 with a circular cross section may be used in combination. The horizontal spacing P of the reinforcing material is 0.5
m to 2 m is preferable, and the height interval is 0.5 to 3 m.
is preferred.

一方、補強材の挿入設置に当っては、高圧液の吐出によ
る穿孔作用を利用したものを採用し、しかも圧入および
または打撃力を併用したものが望ましい。この場合、補
強材1の厚みが薄<、挿入時における耐力がないので、
第7図〜第15図のように、ケーシングを用いて圧入す
るのがよい。
On the other hand, when inserting and installing the reinforcing material, it is preferable to use a method that utilizes the perforation effect produced by the discharge of high-pressure liquid, and to also use press-fitting and/or impact force. In this case, since the thickness of the reinforcing material 1 is thin and there is no yield strength at the time of insertion,
It is preferable to press fit using a casing as shown in FIGS. 7 to 15.

これを説明すると、地山の斜面外にガイドセル10を足
場(図示せず)などに固定し、これにその長平方向に進
退するビューラー型やクルツブ型等のエアー式または油
圧式ハンマー11を設けておく。また、収納孔12aを
有する扁平角形のケーシング12内に帯状補強材1を挿
入しておくとともに、ケーシング12の先端に、幅広の
山形先端シュー13を配置する。さらに、ケーシング1
2の基端とハンマー110ンドとは、着脱自在に連結ブ
ラケット14を介して連結する。
To explain this, a guide cell 10 is fixed to a scaffold (not shown) or the like outside the slope of the ground, and an air or hydraulic hammer 11 such as a Buehler type or Krutsub type that moves forward and backward in the long plane direction is installed on the guide cell 10. I'll keep it. Further, the reinforcing strip 1 is inserted into a flat rectangular casing 12 having a storage hole 12a, and a wide chevron-shaped tip shoe 13 is placed at the tip of the casing 12. Furthermore, casing 1
The proximal end of the hammer 110 is detachably connected to the base end of the hammer 110 via a connecting bracket 14.

他方、ケーシング12に、たとえば収納孔12’aの両
側部に圧送管18,18を溶接や保持座19により固定
し、その基部の連結部18a、18aをケーシング12
外に導出しておき、高圧液たとえば高圧水Wの圧送源に
接続しておく。また、連結管18.18の先端には、カ
ップル20.2.0を介して噴出ノズル2121を取付
けておく。
On the other hand, the pressure feed pipes 18, 18 are fixed to the casing 12, for example, on both sides of the storage hole 12'a, by welding or by a holding seat 19, and the connecting parts 18a, 18a at the base are fixed to the casing 12.
It is led out and connected to a pressure supply source for high pressure liquid, such as high pressure water W. Furthermore, a jet nozzle 2121 is attached to the tip of the connecting pipe 18.18 via a couple 20.2.0.

これら噴出ノズル21..21は、ケーシング12の先
端より前方に突出させ、先端シュー13の貫通孔13c
、1’3cに挿入しておく。
These jet nozzles 21. .. 21 is made to protrude forward from the tip of the casing 12, and is inserted into the through hole 13c of the tip shoe 13.
, insert it at 1'3c.

かかる圧入および打撃を伴う高圧水による穿孔挿入機を
用いて、予め補強材1をケーシング12内に挿入すると
ともに、補強材1の基部において着脱ピン15によりケ
ーシング12と連結し、ケーシング12は先端シュー1
3、後部の凹部13aに嵌合させ、さらに補強材1の先
端を先端シュー13の連結突部13bにおいて連結ピン
16により連結した状態で、ハンマー11によりケーシ
ング12の基端へハンマー力を与えるとともに、ハンマ
ー11をガイドセル10に沿って前進させ、さらに高圧
水Wを噴出ノズル21.21から噴出させ地盤を切削し
ながら所定深度まで挿入する。
The reinforcing material 1 is inserted into the casing 12 in advance using a punching and inserting machine using high-pressure water that involves press-fitting and impact, and the reinforcing material 1 is connected to the casing 12 by a detachable pin 15 at the base of the reinforcing material 1, and the casing 12 is connected to the tip shoe. 1
3. Apply hammer force to the base end of the casing 12 with the hammer 11 while fitting the reinforcing member 1 into the rear recess 13a and connecting the tip of the reinforcing member 1 with the connecting pin 16 at the connecting protrusion 13b of the tip shoe 13. , the hammer 11 is advanced along the guide cell 10, and high-pressure water W is ejected from the ejection nozzles 21 and 21 to cut the ground and insert it to a predetermined depth.

その後、着脱ピン15を抜き、ハンマー11をガイドセ
ル10に沿って後退させ、ケーシング12、噴出ノズル
21.21および連結管18.18を引き抜き、補強材
1および先端シュー13を地山中に残す。
Thereafter, the detachable pin 15 is pulled out, the hammer 11 is moved back along the guide cell 10, and the casing 12, the jet nozzle 21.21, and the connecting pipe 18.18 are pulled out, leaving the reinforcing material 1 and the tip shoe 13 in the ground.

補強材1の挿入孔内には、グラウトを注入充填した方が
、地山との付着力が高まるので、実施例では、ケーシン
グ12の内部に注入管17を接続しておく。
Injecting grout into the insertion hole of the reinforcing material 1 increases adhesion to the ground, so in the embodiment, the injection pipe 17 is connected to the inside of the casing 12.

この実施例に従うと、ケーシング12、補強材1および
先端シュー13の挿入設置が終了した後、斜面外からグ
ラウトGを注入管17に供給して収納孔12a内に導き
その先端開口から注入する。
According to this embodiment, after the insertion and installation of the casing 12, reinforcing material 1, and tip shoe 13 are completed, grout G is supplied from outside the slope to the injection tube 17, guided into the storage hole 12a, and injected from the tip opening thereof.

この注入作業は、ケーシング12の引抜過程で行うのが
好ましいが、引抜完了間近のケーシング12がその引抜
きに伴う空孔に臨んでいる状態で行ってもよい。また、
ケーシング12に注入管を付設せず、ケーシングを引抜
いた空孔に、別途注入ホースを挿入しグラウトGの注入
を行ってもよい。
This injection work is preferably carried out during the process of drawing out the casing 12, but it may also be carried out in a state where the casing 12, which is about to be drawn out, is facing the hole caused by the drawing. Also,
The grout G may be injected by inserting a separate injection hose into the hole from which the casing is pulled out, without attaching an injection pipe to the casing 12.

上記例において先端シュー13を用いず、ケーシング先
端を盲または先細加工状態で盲にしておいても挿入は可
能であるが、実施例のように、補強材lの厚みより基端
の巾が厚い先端シュー13を用いると、第16図のよう
に、地山が崩落しようとするときにおける、帯状補強材
1の抵抗体として作用し、グラウトGの注入効果と相俟
って、強固な引張抵抗体を構成できる。
In the above example, insertion is possible even if the tip shoe 13 is not used and the tip of the casing is left blind or tapered, but as in the example, the width of the proximal end is thicker than the thickness of the reinforcing material l. When the tip shoe 13 is used, as shown in Fig. 16, it acts as a resistor for the strip reinforcement material 1 when the ground is about to collapse, and together with the injection effect of the grout G, it provides strong tensile resistance. You can compose your body.

なお、本発明における帯状補強材としては、鋼板のほか
、他の金属板、付着力を高めるために縞金属板など表面
に凹凸を形成したもの、合成樹脂板、網体、パンチング
メタル、あるいはそれらの複合板、耐腐食性向上のため
にメツキ等の表面処理したもの等を用いることができる
。
In addition to steel plates, the belt-shaped reinforcing material in the present invention may include other metal plates, striped metal plates with irregularities formed on the surface to increase adhesion, synthetic resin plates, nets, punched metal, or other metal plates. Composite plates with surface treatments such as plating to improve corrosion resistance can be used.

本発明における高圧液としては、水のほか種々の液を用
いることができ、またその液中に穿孔力を高めるための
砥粒等の粒子を混入してもよい。
As the high-pressure liquid in the present invention, various liquids other than water can be used, and particles such as abrasive grains may be mixed into the liquid to increase the drilling power.

噴出圧力は、50 kg/cm2以上、特に200 k
g/cm2以上が好ましい。噴出ノズル21の形態は第
15図のものでもよい。
The ejection pressure is 50 kg/cm2 or more, especially 200 k
g/cm2 or more is preferable. The form of the ejection nozzle 21 may be that shown in FIG. 15.

上記例では、先端シュー13を用いるため、噴出ノズル
21をケーシング12先端より前方に位置させたが、先
端シュー13を用いない場合などにおいては、突出させ
る必要はない。
In the above example, since the tip shoe 13 is used, the ejection nozzle 21 is positioned forward of the tip of the casing 12, but if the tip shoe 13 is not used, it is not necessary to project it.

〔発明の効果〕〔Effect of the invention〕

以上通り、本発明によれば、自然地山に対する補強効果
が高く、しかも施工能率に優れるなどの利点がもたらさ
れる。
As described above, according to the present invention, advantages such as a high reinforcing effect on natural ground and excellent construction efficiency are brought about.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明工法の実施状態の全体図、第2図は帯状
補強材の斜視図、第3図はその配置側図、第4図〜第6
図は補強材頭部の定着側図、第7図は補強材の挿入装置
例の斜視図、第8図はケーシングのみの引抜状態斜視図
、第9図は先端シューと帯状補強材の連結態様図、第1
0図は先端シューの正面図、第11図は先端シューおよ
びケージングの先端部の水平断面図、第12図はその側
面図、第13図はケーシングの正面図、第14図は、そ
の水平断面図、第15図は他の先端シュー例の水平断面
図、第16図は地盤中に帯状補強材を挿入しグラウトを
注入した状態の概要図である。 ■・・・帯状補強材、2・・・地山、3・・・保護壁、
6・・・鉄筋、10・・・ガイドセル、11・・・ハン
マー、12・・・ケーシング、13・・・先端シュー、
17・・・注入管、1日・・・噴出ノズル、G・・・グ
ラウト、W・・・高圧水。
Figure 1 is an overall view of the implementation state of the construction method of the present invention, Figure 2 is a perspective view of the band-shaped reinforcement, Figure 3 is a side view of its arrangement, and Figures 4 to 6.
The figure is a fixation side view of the reinforcing material head, FIG. 7 is a perspective view of an example of the reinforcing material insertion device, FIG. 8 is a perspective view of only the casing in a pulled out state, and FIG. 9 is a state of connection between the tip shoe and the strip-shaped reinforcing material. Figure, 1st
Figure 0 is a front view of the tip shoe, Figure 11 is a horizontal cross-sectional view of the tip shoe and the tip of the casing, Figure 12 is a side view thereof, Figure 13 is a front view of the casing, and Figure 14 is a horizontal cross-section thereof. 15 is a horizontal sectional view of another example of the tip shoe, and FIG. 16 is a schematic diagram of a state in which a reinforcing strip is inserted into the ground and grout is injected. ■... Band reinforcement material, 2... Earth, 3... Protection wall,
6... Reinforcing bar, 10... Guide cell, 11... Hammer, 12... Casing, 13... Tip shoe,
17... Injection pipe, 1st... Spray nozzle, G... Grout, W... High pressure water.

Claims (1)

【特許請求の範囲】[Claims] (1)中空扁平状のケーシング内に厚みが0.6〜20
mmの帯状補強材を挿入し、ケーシング内またはケーシ
ング先端前方位置から高圧液を吐出させながら、高圧液
の吐出による穿孔作用によって穿孔しながら帯状補強材
を収容するケーシングを地山中に所定深度まで挿入し、
その後ケーシングを引き抜き、帯状補強材は地山中に残
し、帯状補強材の基端部を斜面に定着することを特徴と
する帯状補強材による斜面補強土工法。
(1) Thickness of 0.6 to 20 mm inside the hollow flat casing
Insert the strip-shaped reinforcing material of mm in diameter, and while discharging high-pressure liquid from inside the casing or from the front position of the tip of the casing, insert the casing containing the strip-shaped reinforcing material into the ground to a predetermined depth while perforating the hole by the perforating action of the discharge of the high-pressure liquid. death,
A slope reinforcement earthwork method using a band-shaped reinforcing material, which is characterized in that the casing is then pulled out, the band-shaped reinforcing material is left in the ground, and the base end of the band-shaped reinforcing material is fixed on the slope.
JP1547188A 1988-01-26 1988-01-26 Earth work method for reinforcing slope by reinforcing member of belt form Granted JPH01190824A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1547188A JPH01190824A (en) 1988-01-26 1988-01-26 Earth work method for reinforcing slope by reinforcing member of belt form

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1547188A JPH01190824A (en) 1988-01-26 1988-01-26 Earth work method for reinforcing slope by reinforcing member of belt form

Publications (2)

Publication Number Publication Date
JPH01190824A true JPH01190824A (en) 1989-07-31
JPH0460165B2 JPH0460165B2 (en) 1992-09-25

Family

ID=11889712

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1547188A Granted JPH01190824A (en) 1988-01-26 1988-01-26 Earth work method for reinforcing slope by reinforcing member of belt form

Country Status (1)

Country Link
JP (1) JPH01190824A (en)

Also Published As

Publication number Publication date
JPH0460165B2 (en) 1992-09-25

Similar Documents

Publication Publication Date Title
US7866922B2 (en) Equipment and method for constructing micropiles in soil, in particular for the anchorage of active anchors
JPH072799Y2 (en) Rock anchor
AT392517B (en) METHOD AND DEVICE FOR SECURING NON OR. Moderately stable, non-cohesive to slightly cohesive geological formations
CN210918889U (en) Reinforced cement anchor rod
JP3878104B2 (en) Construction method of double pipe digging rock bolt using drilling rod
JP5631371B2 (en) Equipment for extracting buried piles
KR102430248B1 (en) grouting device for pressing multi-level areas by one-step with backflow shutoff valve of double wedge type
JP3940735B2 (en) Earth retaining method
JPH0460165B2 (en)
KR100627642B1 (en) Steel pipe indentation device and steel pipe indentation method using the same
EP0189158B1 (en) Process and apparatus for sealing off refuse tips and contaminated areas
JP4884276B2 (en) Rotating press pile construction method and slope construction equipment
JPH02120410A (en) concrete sheet pile
JPS5842496Y2 (en) spray cleaning device
KR20120097242A (en) Directional grouting method and device
JP2004332529A (en) Drilling method for collapse ground, lock bolt working method, and ground anchor working method
JP2011252319A (en) Reinforcement material for natural ground reinforcement earth method and natural ground reinforcement earth method
WO1995021989A1 (en) A method for providing a substantially leakproof shielding layer in the ground and a device for performing the method
JP2007070980A (en) Seismic reinforcement method for masonry wall and masonry wall reinforcement used therefor
JPH03202508A (en) Slope surface reinforcing earth construction using band-shaped stiffener
RU2138643C1 (en) Method and device for construction of tunnel in loose ground
JPS6120107Y2 (en)
JPH01190826A (en) Earth work method for reinforcing slope by reinforcing member of belt form
JPH0578602B2 (en)
CA1040096A (en) Wellpoint jetting head

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees