JPH01304295A - Method of constructing tunnel - Google Patents
Method of constructing tunnelInfo
- Publication number
- JPH01304295A JPH01304295A JP63134333A JP13433388A JPH01304295A JP H01304295 A JPH01304295 A JP H01304295A JP 63134333 A JP63134333 A JP 63134333A JP 13433388 A JP13433388 A JP 13433388A JP H01304295 A JPH01304295 A JP H01304295A
- Authority
- JP
- Japan
- Prior art keywords
- lining
- tunnel
- excavation
- cutter
- muck
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/10—Making by using boring or cutting machines
- E21D9/1053—Making by using boring or cutting machines for making a slit along the perimeter of the tunnel profile, the remaining core being removed subsequently, e.g. by blasting
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
【発明の詳細な説明】
〈産業上の利用分野〉
この発明は、地山のゆるみを防止しながら大断面のトン
ネルの掘削および覆工を行うトンネル構築方法に関する
。DETAILED DESCRIPTION OF THE INVENTION <Industrial Application Field> The present invention relates to a tunnel construction method for excavating and lining a tunnel with a large cross section while preventing the loosening of the ground.
〈従来の技術〉
従来の1〜ンネル構築方法として、シールド工法やパイ
プルーフ工法などがあり、また、トンネル構築の補助工
法として高圧ジエン1−グラウ1〜工法、フォアパイリ
ング工法などが知られている。このうち、シールド工法
は、トンネルの全断面を一度に掘削しながら、後方をセ
グメントまたは場所打ちコンクリートで覆工していくも
のである。また、高圧ジェノトグラウl−工法は比較的
小径の複数の穴をポーリング作業や600−1000k
g/cdノ高圧ジェット水の射出により形成し、この孔
(例えば径が40〜60nwn)中にグラウトを注入し
てトンネル周辺例えば600〜800rrtIlの径の
地盤強度を増強し、防護を行うものである。<Conventional technology> Conventional tunnel construction methods include the shield method and pipe roof construction method, and auxiliary tunnel construction methods include the high-pressure diene construction method and the forepiling construction method. . Among these methods, the shield method involves excavating the entire section of the tunnel at once and lining the rear with segments or cast-in-place concrete. In addition, the high-pressure Genoto Grau l- method requires poling work with multiple relatively small diameter holes, and
It is formed by injecting high-pressure jet water at g/cd, and injects grout into this hole (for example, diameter of 40 to 60 nwn) to strengthen and protect the ground around the tunnel, for example, the diameter of 600 to 800 rrtIl. be.
ところで、超電導電力貯蔵や空気貯蔵を行なうためには
、地下地盤に直径10〜20mにも及ぶトンネルが必要
となり、このトンネル内には電力貯蔵用の超電導コイル
が設置される。このため、上記トンネル形成のため、地
盤の掘削が必要となるが、上記従来のトンネル掘削にて
行われたシールド工法では、そのトンネルが大断面であ
る場合に、補助工法なくしては、切羽を安定させること
が難しく、トンネル周辺の地山を緩めやすく、また、掘
削残土が大量に出るため残土排出上が作業に占める比重
が大きくなって、掘削土、覆工の各作業の支障となり、
施工能率が落ちるという問題点があった。また、地圧に
よってシール1〜機が拘束されるために、大きな推進力
を要し、場合によってはトンネルが大きく変形するなど
の問題点もあった。By the way, in order to perform superconducting power storage and air storage, a tunnel with a diameter of 10 to 20 m is required in underground ground, and a superconducting coil for power storage is installed in this tunnel. For this reason, excavation of the ground is required to form the tunnel, but with the shield method used in conventional tunnel excavation, if the tunnel has a large cross section, it is impossible to cut the face without an auxiliary method. It is difficult to stabilize the ground, which tends to loosen the ground around the tunnel, and because a large amount of excavated soil is produced, the removal of the excavated soil becomes a large part of the work, which becomes a hindrance to the excavated soil and lining work.
There was a problem that construction efficiency decreased. In addition, since the seals 1 to 1 are restrained by ground pressure, a large propulsion force is required, and in some cases, the tunnel may be significantly deformed.
一方、上記高圧ジェットプラウ1−工法などのトンネル
構築の際の補助工法は、小断面のトンネル掘削には適す
るが、大断面のトンネル掘削には施工技術および安全性
、経済性の点で不向きであるという問題点があった。On the other hand, auxiliary methods for tunnel construction, such as the high-pressure jet plow 1 method described above, are suitable for excavating small-section tunnels, but are not suitable for large-section tunnel excavation in terms of construction technology, safety, and economy. There was a problem.
これに対して、ある程度大断面のトンネルが形成可能な
パイプルーフ工法も提案されている。これは第9図およ
び第10図に示すように、掘削1〜ンネル1内の切羽付
近に走行可能なパイプ打込機2を入れるとともに、この
パイプ打込機2によって、地山4内にパイプ3を掘進方
向に向って末広かりどなるように削孔・圧入し、この後
、各パイプ3内のアースオーガ5を駆動させながらパイ
プ3から掘進方向に伸長させて、このアースオーガ5に
より順次掘削を行うものである。また、このような掘削
によって作られたトンネル1の内面には上記各パイプ3
を覆うようにしてコンクリ−1−覆工6が施される。つ
まり、かかるパイプルーフ工法ではI〜ンネル1−の大
断面形状に合わせて所定数のパイプ3を所定形状に配設
することにより、大断面のトンネルを形成することがで
きる。なお、第10図において、7は掘削径覆工を行う
部分である。In contrast, a pipe roof construction method has been proposed that allows the formation of tunnels with a relatively large cross section. As shown in FIGS. 9 and 10, a movable pipe driving machine 2 is inserted near the face in the excavation 1 to tunnel 1, and the pipe driving machine 2 is used to insert the pipe into the ground 4. 3 is drilled and press-fitted so that it widens in the direction of excavation, and then, while driving the earth auger 5 in each pipe 3, it extends from the pipe 3 in the direction of excavation, and the earth auger 5 excavates one by one. This is what we do. In addition, the above-mentioned pipes 3 are installed on the inner surface of the tunnel 1 created by such excavation.
Concrete 1-lining 6 is applied so as to cover it. That is, in this pipe roof construction method, a tunnel with a large cross section can be formed by arranging a predetermined number of pipes 3 in a predetermined shape according to the large cross-sectional shape of the tunnel 1-. In addition, in FIG. 10, 7 is a part where excavation diameter lining is performed.
〈発明が解決しようとする課題〉
しかしながら、かかるパイプループ工法にあっては、パ
イプ3の長さが作業上制約を受けるので、数10mの間
隔て本杭トンネルの掘削と防護工を交互に繰り返さなけ
ればならず、手間がかかり過ぎるほか、パイプ3を水平
方向に精度よく設置できないので、余掘りが多くなるこ
と、また、トンネル周囲全体を一応に施工することが困
難であることがら地山が緩み易くなるとともに、防護工
は仮設のため別途覆工を要して、工費、工程が増大する
という問題点があった。<Problem to be solved by the invention> However, in this pipe loop construction method, the length of the pipe 3 is subject to operational constraints, so excavation of the main pile tunnel and protection work are repeated alternately at intervals of several tens of meters. In addition to being too time-consuming and difficult to install, the pipe 3 cannot be installed horizontally with high accuracy, resulting in a lot of extra digging.Also, it is difficult to construct the entire area around the tunnel, so the ground is In addition to being susceptible to loosening, the protection works were temporary and required separate lining, which increased construction costs and processes.
この発明はかかる従・来の問題点に着[1してなされた
ものであり、地山を緩めずに、安全にしかも簡単な作業
にてトンネルを効率的に構築することができるトンネル
構築方法を得ることを目的とする。This invention has been made to address these conventional problems, and provides a tunnel construction method that allows tunnels to be constructed efficiently, safely and easily, without loosening the ground. The purpose is to obtain.
〈課題を解決するための手段〉
この発明にかかるトンネル構築方法は、地山をカッタに
より掘削して形成した環状の覆工部空間に、場所打ちの
覆工材を打設していき、この覆工材の打設に遅れて切羽
の掘削を実施するようにするものである。この場合、補
助カッタにより環状覆工空間の内側に作業坑を形成する
こともできる。<Means for Solving the Problems> In the tunnel construction method according to the present invention, a cast-in-place lining material is cast in a ring-shaped lining space formed by excavating the ground with a cutter. This will allow the excavation of the face to be carried out after the lining material is placed. In this case, a working hole can also be formed inside the annular lining space using the auxiliary cutter.
また、地山の掘削によるすりを利用し、これとセメント
等の固化材を添加して覆工部空間に打設することもでき
る。Alternatively, it is also possible to use a pickpocket created by excavating the ground and add a hardening material such as cement to the pickpocket and then pour it into the lining space.
〈作用〉
この発明における地山の掘削は、環状のカッタにより中
間を残して1ヘンネルが掘進され、これによって作った
環状の覆工部空間に場所打ちの覆工材を打設し、その後
、かかる覆工を行った環状部空間の内部にある残土を掘
削、搬出して、大断面のトンネルを構築していく。<Function> In the excavation of the ground according to the present invention, one hemnel is excavated with a ring-shaped cutter leaving the middle part, and a cast-in-place lining material is placed in the ring-shaped lining space created by this, and then, The remaining soil inside the annular space that has been lined will be excavated and carried out to construct a tunnel with a large cross section.
〈発明の実施例〉
以下に、この発明の実施例を図について説明する。第1
図はこの発明で使用するシールドタイプの掘削機を示す
概略縦断面図、第2図は同じく掘削機による環状と補助
のカッタを示す正面図である。同図において、11はト
ンネルの掘削が行われる地山、12はこの地山11に対
し、水平方向の環状の覆工部空間13を、地山を掘進し
ながら形成する環状のカッタで、第2図に示すように、
このカッタ]2はリング状に配置した複数のカッタ部材
12aからなる。さらに、このカッタ部材12aはカッ
タピッ1へと土砂取込口とを備えたものからなり、各カ
ッタピッ1〜の1つ1つがリング状部の切羽を掻き出す
ように動作して、上記掘削を行う。14−.15は環状
のカッタコ2の内外周に連設されたシール1〜における
環状のスキンプレー1〜で、このうち15は後述の場所
打ちコンクリ−)−(覆工材)の型枠としても用いられ
る。なお、スキンブレート14−.15はフリクション
をカッ1〜するために全体としてテーパ状をなしている
。<Embodiments of the Invention> Examples of the invention will be described below with reference to the drawings. 1st
The figure is a schematic vertical cross-sectional view showing a shield type excavator used in the present invention, and FIG. 2 is a front view showing the annular and auxiliary cutter of the same excavator. In the figure, reference numeral 11 denotes the ground where the tunnel will be excavated, and reference numeral 12 denotes an annular cutter that forms a horizontal annular lining space 13 in the ground 11 while excavating the ground. As shown in Figure 2,
This cutter] 2 consists of a plurality of cutter members 12a arranged in a ring shape. Further, the cutter member 12a is provided with a dirt intake port into the cutter pit 1, and each of the cutter pits 1 operates to scrape out the face of the ring-shaped portion to perform the above-mentioned excavation. 14-. 15 is an annular skin play 1~ in the seal 1~ provided in succession on the inner and outer peripheries of the annular cutter 2, of which 15 is also used as a formwork for cast-in-place concrete (lining material) to be described later. . In addition, skin plate 14-. 15 has a tapered shape as a whole to reduce friction.
16はカッタ12に隣接して設けられた作業坑掘削に用
いるブームカッタなどの補助カッタであり、これがカッ
タ12の内側上部に図示のように設けられるほか、内側
下部またはこれら2つの部分に設けられる場合がある。Reference numeral 16 denotes an auxiliary cutter such as a boom cutter used for excavating a working hole, which is provided adjacent to the cutter 12. In addition to being provided at the upper inner side of the cutter 12 as shown in the figure, this is also provided at the lower inner side or these two parts. There are cases.
17はズリ収容部で、これが覆工部空間13を作るカッ
タ12の近傍に設けられ、これにスクリューコンベアを
含む排土装置18か連設されている。この排土装置18
は、ズリ収容部17内から排出されるズリとともにポン
プにより送出される硬化材を混練して、プレスリング1
9に設けた覆工材押出し口20を通して、掘削機後部の
覆工部空間13内に圧入するように作用する。ここで、
21は上記のポンプ、22はこのポンプ21によって送
出する硬化材を収容した硬化材タンク、23は硬化相を
送出するのに用いるパイプである。このパイプ23は補
助カッタ16によって掘削した作業坑24内にガイドさ
れて、上記排土装置18に連結されている。25は補助
カッタ16の後方に連設された作業坑用シールドである
。26は覆工材を圧縮する上記プレスリング19に支持
させて、掘削機を前進させるジヤツキである。なお、こ
のジヤツキ26と排土装置]8とは、これら複数のプレ
スリング19に対して交互に円形状に並設されている。Reference numeral 17 denotes a waste storage section, which is provided near the cutter 12 that creates the lining space 13, and an earth removal device 18 including a screw conveyor is connected thereto. This soil removal device 18
The press ring 1 is made by kneading the hardening material delivered by the pump with the waste discharged from the waste storage part 17.
The lining material is press-fitted into the lining space 13 at the rear of the excavator through the lining material extrusion port 20 provided at 9. here,
21 is the above pump, 22 is a hardening material tank containing the hardening material to be delivered by this pump 21, and 23 is a pipe used to deliver the hardening phase. This pipe 23 is guided into a working hole 24 excavated by an auxiliary cutter 16 and connected to the earth removal device 18 . Reference numeral 25 denotes a working shaft shield connected to the rear of the auxiliary cutter 16. Reference numeral 26 is a jack that is supported by the press ring 19 that compresses the lining material and moves the excavator forward. Note that the jacks 26 and the earth removal device] 8 are arranged in parallel in a circular shape alternately with respect to the plurality of press rings 19.
27は覆工部空間13内に圧入充てんされた覆工材であ
る。A lining material 27 is press-fitted into the lining space 13.
次に、上記掘削機によるトンネル構築方法について、第
3図を参照しながら説明する。まず、掘削機のカッタ1
2および補助カッタ16を切羽に当てて、環状に掘削し
ていき、掘削によって生じたズリを作業坑24を通して
外部へ排出するとともに、そのズリの一部をズリ収容部
17に取り込んで、排土装置18に送り込む。一方、こ
の排土装置18しこは、硬化材タンク22からポンプ2
1によって硬化材が送り込まれ、この硬化材と上記ズリ
とがスクリューコンベアにより混練され、ここで覆工材
を作る。そして、この覆工材はスクリューコンベアの押
出し圧力しこより覆工材押出し口20からプレスリング
19の外側、すなわち環状の覆工部空間13内に押出さ
れる。このプレスリンク19は、上記のようにジヤツキ
26を支持して覆工部空間13内の覆工材を加圧するた
め、この覆工材は圧密されて硬化が促進される。こうし
て、再び、上記掘削機による掘削を行い、ジヤツキによ
る推進を実施した後再び覆工材の覆工を行う。すなわち
、第3図(a)は、掘削機による掘削および推進を行っ
て覆工材のプレスリング]−9の外側に覆工材を充てん
した後の状態を示し、このとき、次の推進に備えてジヤ
ツキ26が最も収縮した状態に維持される。そして、こ
の状態において、硬化した覆工により囲まれた部分の地
山を、後方から順次掘削していく。つまり芯抜きを行う
。Next, a method for constructing a tunnel using the excavator will be explained with reference to FIG. 3. First, cutter 1 of the excavator
2 and the auxiliary cutter 16 are applied to the face to excavate in an annular shape, and the waste generated by the excavation is discharged to the outside through the working hole 24, and a part of the waste is taken into the waste storage part 17, and the soil is removed. into the device 18. On the other hand, this earth removal device 18 is moved from the hardening material tank 22 to the pump 2.
A hardening material is sent in by No. 1, and this hardening material and the above-mentioned shear are kneaded by a screw conveyor to form a lining material. Then, this lining material is extruded from the lining material extrusion port 20 to the outside of the press ring 19, that is, into the annular lining space 13 by the extrusion pressure lever of the screw conveyor. Since the press link 19 supports the jack 26 and pressurizes the lining material in the lining space 13 as described above, the lining material is consolidated and hardening is promoted. In this way, the excavation is carried out again by the excavator, propulsion is carried out by the jack, and then the lining is again covered with the lining material. That is, FIG. 3(a) shows the state after the lining material has been filled on the outside of the lining material press ring]-9 by excavation and propulsion with an excavator, and at this time, the lining material is filled in the outside of the lining material press ring]-9. In preparation for this, the jack 26 is maintained in its most contracted state. In this state, the area surrounded by the hardened lining is excavated sequentially from the rear. In other words, core removal is performed.
第3図(b)は再び掘削を行うとともしこ、ジヤツキ2
6を伸長して掘削機の掘進を行う状態を示す。Figure 3 (b) shows that when excavating again, Tomoko and Jack 2
6 is extended to show the excavator digging.
この推進によってスキンプレート14.15も同時に前
進する。第3図(c)は上記推進後、シャツキ26を再
び収縮させるとともにプレスリング19も前進させ、覆
工材押出し口20から覆工材を圧入して、新しい覆工3
0を直前に施工した覆工31の地なりに連設していく状
態を示す。なお、第3図(b)、第3図(c)に示す掘
削終了および覆工材圧入の再施工中にも、上記芯部の残
土40を掘削して排出する。Due to this propulsion, the skin plates 14.15 are also moved forward at the same time. FIG. 3(c) shows that after the above-mentioned propulsion, the shatsuki 26 is contracted again, the press ring 19 is also moved forward, the lining material is press-fitted from the lining material extrusion port 20, and a new lining 3
0 is shown being installed continuously along the ground of the lining 31 that was constructed immediately before. Incidentally, even when the excavation is completed and the lining material is being re-injected as shown in FIGS. 3(b) and 3(c), the remaining soil 40 in the core portion is excavated and discharged.
第4図乃至第8図はこの発明のトンネル構築方法を実施
するための他のシールド掘削機を示す。4 to 8 show other shield excavators for carrying out the tunnel construction method of the present invention.
このシールド掘削機は、泥水掘削を行うものであり、同
図において、30は一端が図示しないポンプにつながれ
た送泥管であり、この送泥管30の他端は、第5図に示
すカッタ]2のカッタピッ1へ12aのうち最上のもの
の後方で泥水を吐出するようになっている(第4図)。This shield excavator performs mud excavation, and in the same figure, 30 is a mud feeding pipe whose one end is connected to a pump (not shown), and the other end of this mud feeding pipe 30 is connected to a cutter shown in FIG. ] Mud water is discharged to the cutter pit 1 of No. 2 at the rear of the uppermost one of the cutter pits 12a (Fig. 4).
なお、12bはカッタ]2の土砂取込口である。31は
−・端が図示しないポンプやタンクにつながれた排泥管
であり、この排泥管31の他端は、リンク状のカッタ1
2の下部後方で二箇所に臨むように設けられている(第
6図)。32はコンクリート打設管で、これの一端が、
スキンプレート15の他端付近に設けたコンクリート打
設口に連設するように設けら九でいる。これらの各送泥
管30、排泥管3]およびコンクリート打設管32は、
作業坑用シールド25にて囲まれた作業坑24内を通し
て設置されている。なお、33はスキンプレー1〜14
..15間を前後2室に隔成して前室に泥水を溜めるよ
うにするバルクヘッド、34は型枠である。この他、第
1図に示したものと同一の構成部分には同一符号を付し
て、その重複する説明を省略する。Note that 12b is the earth and sand inlet of the cutter 2. 31 is a sludge draining pipe whose end is connected to a pump or tank (not shown), and the other end of this sludge draining pipe 31 is connected to a link-shaped cutter 1.
It is located at the rear of the lower part of No. 2 so as to face two places (Fig. 6). 32 is a concrete pouring pipe, one end of which is
It is provided so as to be continuous with a concrete pouring hole provided near the other end of the skin plate 15. These mud feeding pipes 30, mud draining pipes 3] and concrete casting pipes 32 are as follows:
It is installed through the working shaft 24 surrounded by a working shaft shield 25. In addition, 33 is skin play 1-14
.. .. A bulkhead 34 is a formwork that separates the room 15 into two chambers, front and rear, and stores muddy water in the front chamber. In addition, the same components as shown in FIG. 1 are designated by the same reference numerals, and redundant explanation thereof will be omitted.
この実施例におけるシールド掘削機においても、カッタ
12はリング状をなし、トンネル断面の覆工部にあたる
部分とサービス用の作業坑24部分とを、カッタ12と
ブームカッタなどの補助カッタ16によりそれぞれ掘削
し、内側の土砂は掘削しない、そして、この掘削は切羽
付近に送泥管30を通じて泥水を満たし泥水掘削を行う
。また、掘削された土砂は泥水とともに排泥管31を通
じてポンプなどによりシールド掘削機の外側に流体輸送
して、排出するが、一部は先の実施例のようにしてコン
クリートの骨材として利用することもできる。In the shield excavator of this embodiment as well, the cutter 12 has a ring shape, and the cutter 12 and the auxiliary cutter 16 such as a boom cutter excavate the lining part of the tunnel cross section and the service work shaft 24 part. However, the inner earth and sand are not excavated, and muddy water excavation is performed by filling the vicinity of the face with muddy water through the mud feeding pipe 30. Further, the excavated earth and sand are transported to the outside of the shield excavator by a pump or the like through the mud drainage pipe 31 and discharged, but some of it is used as aggregate for concrete as in the previous embodiment. You can also do that.
一方、コンクリートはコンクリート打設管32を通して
スキンプレート15のコンクリート打設口からスキンプ
レート15の外側(外周側)へ送り込まれ、プレスリン
グ19の後方のスキンプレート14.15間に打設され
る。この場合においても、1スパン(型枠長)の掘削が
完了したら、第7図にも示すような推進用のジヤツキ2
6を縮め、プレスリング19を切羽側に引き寄せながら
、覆工コンクリートを打設する。ここでは、地山が外枠
となり、作業坑の型枠34は第8図に示すように掘削機
のテール部で組み立てられる。On the other hand, concrete is sent to the outside (outer circumferential side) of the skin plate 15 from the concrete pouring port of the skin plate 15 through the concrete pouring pipe 32, and is poured between the skin plates 14 and 15 behind the press ring 19. In this case, once the excavation of one span (formwork length) is completed, the propulsion jack 2 as shown in Fig.
6 and place the lining concrete while drawing the press ring 19 toward the face side. Here, the earth serves as the outer frame, and the formwork 34 of the working shaft is assembled at the tail of the excavator, as shown in FIG.
このように、この発明では覆工部空間13をまず掘削に
よって形成し、この覆工部空間13への覆工材の充てん
固化後に芯抜きを行い、かかる作業を繰り返し実行する
ことによって大断面のトンネルを形成することができる
のである。As described above, in the present invention, the lining space 13 is first formed by excavation, and after the lining material is filled and solidified into the lining space 13, the core is removed, and by repeating this operation, a large cross-section can be formed. It is possible to form a tunnel.
なお、上記実施例では、ズリの搬出、排出および覆工材
搬入などを行う作業坑24は、第2図に示すように、上
部に設けるほか、上下部2個所に設けてもよく、これら
作業坑は、掘削したズリの排出を安全かつ円滑に実施で
きる。また、かかる作業坑24は覆工部空間13の内側
または外側の1個所または複数個所に設けることもでき
、必要に応じてその形や大きさを異ならしめてもよい。In the above embodiment, the work shaft 24 for transporting and discharging waste, and carrying in lining material, etc. may be provided at the upper part or at two locations, upper and lower, as shown in FIG. The excavated waste can be safely and smoothly discharged from the pit. Further, the working shaft 24 may be provided at one or more locations inside or outside the lining space 13, and may have a different shape and size as necessary.
そしてかかる作業坑24はトンネルの掘削作業を効率化
し、作業の安全性に寄与するものとなる。The working shaft 24 makes the tunnel excavation work more efficient and contributes to the safety of the work.
また、上記の1〜ンネル構築方法では、馬蹄形、卵形、
長円形などあらゆる形状の大断面トンネルも構築可能で
ある。In addition, in the above-mentioned method 1 to channel construction, horseshoe-shaped, egg-shaped,
It is also possible to construct large-section tunnels of all shapes, including oval shapes.
さらに、上記実施例では掘進に推進形のジヤツキ26を
用いたが、このジヤツキをプレスジヤツキとして、推力
(つまり反力)を周辺の覆工内面に固定したクリッパか
ら得るようにしてもよい。Further, in the above embodiment, a propelling type jack 26 is used for digging, but this jack may be a press jack, and the thrust (that is, reaction force) may be obtained from a clipper fixed to the inner surface of the surrounding lining.
〈発明の効果〉
以上説明してきたように、この発明によれば、大断面の
トンネル掘削の際における地山応力の解放を極力小さく
するために、掘削断面を環状掘削と芯抜き掘削の2工程
に分割して掘削するようにしたので、芯部の掘削よりも
覆工を数m以上も先行させることができ、覆工内側の掘
削を安全かつ効率的に実施でき、地山のゆるみを極力少
なくすることが可能となる従来のパイプルーフ工法にお
けるごとき仮設のための防護工が不要となり、工費を安
く、しかも工程を簡略化、短縮化できるという効果が得
られる。また、掘削したズリを覆工材として利用するこ
とにより、作業坑における残土、ズリの排出処理を20
%〜30%も低減できるなどの効果が得られる。<Effects of the Invention> As described above, according to the present invention, in order to minimize the release of rock stress during tunnel excavation of a large cross section, the excavation cross section is divided into two steps: annular excavation and core excavation. Since the excavation is divided into two parts, the lining can be excavated several meters or more before the core excavation, making it possible to excavate the inside of the lining safely and efficiently, and to minimize the loosening of the ground. This eliminates the need for protective work for temporary construction as in the conventional pipe roof construction method, resulting in lower construction costs and the effect of simplifying and shortening the process. In addition, by using the excavated waste as lining material, it is possible to dispose of the remaining soil and waste in the working tunnel by 20 minutes.
% to 30% can be achieved.
第1図はこの発明にがかるI・ンネル構築方法を実施す
るための掘削機を示す縦断面図、第2図は掘削機のカッ
タを示す正面図、第3図はこの発明のトンネル構築方法
の施工順序を示す施工要領図、第4図は掘削機の他の実
施例を示す断面図、第5図は同じく正面図、第6図は第
4図のA−A線断面図、第7図は同じ<B−B線断面図
、第8図はC−C線断面図、第9図は従来のパイプルー
フ工法を示す説明図、第10図はパイプルーフ工法によ
るトンネルの施工断面図である。
11・・地盤、12・・カッタ、13・・覆コー部空間
、16・・補助カッタ、18・・排土装置a、22・・
硬化材タンク、24・・作業坑、26・・ジヤツキ、2
7・・覆工。FIG. 1 is a longitudinal sectional view showing an excavator for carrying out the tunnel construction method according to the present invention, FIG. 2 is a front view showing a cutter of the excavator, and FIG. 4 is a sectional view showing another embodiment of the excavator, FIG. 5 is a front view, FIG. 6 is a sectional view taken along line A-A in FIG. 4, and FIG. 7 is a construction procedure diagram showing the construction order. are the same < A sectional view taken along the line B-B, Fig. 8 is a sectional view taken along the line C-C, Fig. 9 is an explanatory diagram showing the conventional pipe roof construction method, and Fig. 10 is a sectional view showing the construction of a tunnel using the pipe roof construction method. . 11...Ground, 12...Cutter, 13...Covering section space, 16...Auxiliary cutter, 18...Earth removal device a, 22...
Hardening material tank, 24... Working pit, 26... Jacket, 2
7. Lining.
Claims (1)
部空間を形成し、この覆工部空間に場所打ちの覆工材を
打設していき、この覆工材の打設に遅れて切羽の掘削を
実施するトンネル構築方法。 2)環状をなすカッタの内側に補助カッタにより環状の
覆工部空間の内側に作業坑を形成する請求項1記載のト
ンネル構築方法。 3)地山の掘削によるずりに固化材を添加して覆工部空
間に打設する請求項1又は2記載のトンネル構築方法。[Claims] 1) An annular cutter excavates the ground to form an annular lining space, and a cast-in-place lining material is placed in this lining space. A tunnel construction method in which the face is excavated after the construction materials are placed. 2) The tunnel construction method according to claim 1, wherein a working hole is formed inside the annular lining space by an auxiliary cutter inside the annular cutter. 3) The tunnel construction method according to claim 1 or 2, wherein a solidifying material is added to the shear caused by excavating the ground and the tunnel is cast into the lining space.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63134333A JP2604622B2 (en) | 1988-06-02 | 1988-06-02 | Tunnel construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63134333A JP2604622B2 (en) | 1988-06-02 | 1988-06-02 | Tunnel construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH01304295A true JPH01304295A (en) | 1989-12-07 |
| JP2604622B2 JP2604622B2 (en) | 1997-04-30 |
Family
ID=15125888
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP63134333A Expired - Lifetime JP2604622B2 (en) | 1988-06-02 | 1988-06-02 | Tunnel construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2604622B2 (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2011148871A1 (en) * | 2010-05-26 | 2011-12-01 | 株木建設株式会社 | Tunnel excavation apparatus, and tunnel excavation method |
| CN107152042A (en) * | 2017-05-23 | 2017-09-12 | 中交第二航务工程局有限公司 | Churning clump of piles occlusion reinforcing engineering method is tilted for wearing the micro-disturbance in house under shield |
| CN110645017A (en) * | 2019-09-05 | 2020-01-03 | 湖南帝星智能科技有限公司 | Pouring device, lining trolley and pouring process |
-
1988
- 1988-06-02 JP JP63134333A patent/JP2604622B2/en not_active Expired - Lifetime
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2011148871A1 (en) * | 2010-05-26 | 2011-12-01 | 株木建設株式会社 | Tunnel excavation apparatus, and tunnel excavation method |
| JP4934234B2 (en) * | 2010-05-26 | 2012-05-16 | 株木建設株式会社 | Tunnel excavation apparatus and tunnel excavation method |
| JP2012132307A (en) * | 2010-05-26 | 2012-07-12 | Kabuki Construction Co Ltd | Tunnel excavation device and tunnel excavation method |
| US8814472B2 (en) | 2010-05-26 | 2014-08-26 | Kabuki Construction Co., Ltd. | Tunnel excavation apparatus and tunnel excavation method |
| CN107152042A (en) * | 2017-05-23 | 2017-09-12 | 中交第二航务工程局有限公司 | Churning clump of piles occlusion reinforcing engineering method is tilted for wearing the micro-disturbance in house under shield |
| CN110645017A (en) * | 2019-09-05 | 2020-01-03 | 湖南帝星智能科技有限公司 | Pouring device, lining trolley and pouring process |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2604622B2 (en) | 1997-04-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2005171549A (en) | Tunnel construction method | |
| JPS5873693A (en) | Partial widening of tunnel due to shield construction method | |
| JPH01304295A (en) | Method of constructing tunnel | |
| JP2979044B2 (en) | Large-scale underground structures and their construction methods | |
| JPH07331998A (en) | Constructing method of rock cavern | |
| JP3171459B2 (en) | Shield method | |
| JP2648051B2 (en) | Construction method of arch shell in tunnel precedent | |
| JPH0525989A (en) | Vertical type shield method | |
| JP3454442B2 (en) | Excavation method and device for large section underground space | |
| JPH0768858B2 (en) | Construction method of large-section shield tunnel | |
| JP2819224B2 (en) | Reaction force support structure for shaft excavator | |
| JPH04309692A (en) | Underground space construction method | |
| JPH0548840B2 (en) | ||
| JPH0643796B2 (en) | Shield machine | |
| JPH04309694A (en) | Underground space construction method | |
| JPH0696949B2 (en) | Construction method of rectangular section tunnel and shield machine used for it | |
| JP2693028B2 (en) | Construction method of human hole in middle of pipeline | |
| JPH05287983A (en) | How to construct a long, large-diameter underground space | |
| JPH0462299A (en) | Larger section tunnel and construction method thereof | |
| JPH0517354B2 (en) | ||
| JPH0666079A (en) | Vertical shaft excavator and excavation method using the same | |
| JP2544829B2 (en) | How to build an underground cavity | |
| JPH10159074A (en) | Construction method of underground structure in excavation method | |
| JPH0637836B2 (en) | Tunnel lining method | |
| JP2966173B2 (en) | Tunnel excavation ground reinforcement method |