JPH01322013A - Temporary protection method for slope embankment rubble - Google Patents
Temporary protection method for slope embankment rubbleInfo
- Publication number
- JPH01322013A JPH01322013A JP63155716A JP15571688A JPH01322013A JP H01322013 A JPH01322013 A JP H01322013A JP 63155716 A JP63155716 A JP 63155716A JP 15571688 A JP15571688 A JP 15571688A JP H01322013 A JPH01322013 A JP H01322013A
- Authority
- JP
- Japan
- Prior art keywords
- rubble
- slope
- water surface
- metal wire
- chains
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/11—Hard structures, e.g. dams, dykes or breakwaters
Landscapes
- Revetment (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は海中に構築された捨石による傾斜堤か、波浪に
よって崩壊するのを防止するための傾斜堤捨石の散乱防
止方法に関する。DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a slope embankment made of rubble built underwater, and a method for preventing scattering of rubble on a slope bank to prevent it from collapsing due to waves.
(従来の技術)
一般に防波堤や埋立地の外縁の護岸として捨石を積み上
げ、その両面を傾斜させた傾斜堤か構築されている。こ
の傾斜堤は最終的には捨石間隙に水中コンクリートを打
設したり、あるいはその外側にコンクリートブロックを
積み上げて外面を覆い、全体が波浪によっても崩壊しな
い水中構築物に仕上げている。(Prior Art) Generally, as a breakwater or a revetment at the outer edge of a reclaimed land, a sloping embankment is constructed by piling up rubble stones and sloping both sides. In the end, this sloping embankment is constructed by pouring underwater concrete into the gaps between the rubble stones, or by stacking concrete blocks on the outside to cover the exterior, creating an underwater structure that will not collapse even in the face of waves.
(発明が解決しようとする課題)
上述の如き傾斜堤の構築に際しては捨石の積み上げが先
行してなされ、次いで崩壊防止のコンクリート打設等の
施工がなされるものであり、捨石か所定の傾斜堤形状に
積み上げられた後、崩壊防止の最終施工かなされるまで
に時間的に間隔があき、この間に波浪によって水面付近
の捨石が傾斜に沿って転落し、水深の深いところに堆積
し、傾斜坑が変形してしまうという問題がある。(Problem to be Solved by the Invention) When constructing a slope embankment as described above, rubble is first piled up, and then concrete is poured to prevent collapse. After being piled up into a shape, there is a time interval before the final construction to prevent collapse is carried out, and during this time, the waves cause the rubble near the water surface to fall down along the slope, accumulate in the deep water, and cause the slope shaft to collapse. There is a problem in that it is deformed.
このような問題を解決するための手段としてテトラポッ
ト等のコンクリートブロックを一次的に傾斜板表面に並
べて設置する方法か考えられるが、このような方法では
施工に多大の時間を要するとともに仮被覆のため、その
後の原画面への復旧に時間を要する等の問題がある。One possible solution to this problem is to temporarily install concrete blocks such as tetrapods on the surface of the inclined plate, but such a method requires a lot of time for construction and requires temporary covering. Therefore, there is a problem that it takes time to restore the original screen after that.
本発明は上述の如き従来の問題にかんがみ、短時間にて
傾斜板の仮被覆及びその除去が可能であり、しかも充分
に捨石の崩壊が防止できる傾斜板捨石の散乱防止方法の
提供を目的としたものである。In view of the above-mentioned conventional problems, the present invention aims to provide a method for preventing scattering of sloped board rubble, which enables temporary covering of sloped boards and its removal in a short time, and which can sufficiently prevent the rubble from collapsing. This is what I did.
(問題点を解決するための手段)
上述の如き従来の問題を解決し、所期の目的を達成する
ための本発明の特徴は、海中に構築され少くとも表面に
捨石が積まれた傾斜板の表面に該傾斜板の入射側傾斜面
の静水面下より反対側傾斜面にかけて該捨石が通過不能
な大きさの網目の金属線材網をもって覆い、該金属線材
網の外面に、その重量によって前記金属線材網の剥離を
防止させるチェーンを付設すること及び海中に構築され
少くとも表面に捨石が積まれた傾斜板の表面の、少なく
とも静水面より上の部分を透水性の繊維布で覆うととも
に、その上に該傾斜板の入射側傾斜面の静水面下より反
対側傾斜面にかけて該捨石が通過不能な大きさの網目の
金属線材網をもって覆い、該金属線材網の外面に、その
重量によって前記金属線材網の剥離を防止させるチェー
ンを付設することに存する。(Means for Solving the Problems) A feature of the present invention for solving the above-mentioned conventional problems and achieving the intended purpose is to use an inclined plate constructed underwater and having at least the surface piled with rubble. The surface of the inclined plate is covered with a metal wire net having a mesh size so that the rubble cannot pass from below the static water surface of the incident side inclined surface to the opposite side inclined surface, and the outer surface of the metal wire net is Attaching a chain to prevent the metal wire net from peeling off, and covering at least the part above the still water surface of the surface of the inclined plate built underwater and at least on the surface with rubble with a water-permeable fiber cloth, On top of that, a metal wire net with a mesh size that cannot allow the rubble to pass is covered from below the static water surface of the incident side slope of the slope plate to the opposite side slope, and the outer surface of the metal wire net is The purpose is to attach a chain to prevent the metal wire mesh from peeling off.
(作用)
この傾斜板捨石の散乱防止方法は、金属線材網によって
外面か覆われ、しかもチェーンによって押さえられるこ
とにより、波が打ち寄せた際の揚力に対向して捨石の浮
き上りを防止されるとともに、外面にある捨石か引く波
とともに転落するのが阻止される。更にこれとともに洗
掘された捨石の堆積による傾斜面下側位置の盛り上りを
も阻止し、傾斜板あ変形か修復を要しない程度におさえ
られる。(Function) This method for preventing the scattering of sloping rubble is that the outer surface is covered with a metal wire net and is held down by a chain, which prevents the rubble from floating up against the lifting force when the waves hit. , the debris on the outside or the receding waves will prevent you from falling. Furthermore, this also prevents the build-up of the lower part of the slope due to the accumulation of scoured rubble, and the deformation of the slope plate can be suppressed to the extent that it does not require repair.
また繊維布の使用によって水面上の傾斜板天端両縁の角
部の捨石崩落が防止される。Furthermore, the use of fiber cloth prevents rubble from collapsing at the corners of both edges of the top of the inclined plate above the water surface.
(実施例) 次に本発明の実施例を図面について説明する。(Example) Next, embodiments of the present invention will be described with reference to the drawings.
第1図、第2図は埋立護岸用の傾斜板に実施した場合を
示しており、図中1は1個当り10〜200kgの捨石
を積み上げて形成した傾斜板本体である。この傾斜板本
体1の天端部外面を波の入射側傾斜面a及び埋立IJ!
l#J斜面すとも静水面付近に到るまで透水性の繊維シ
ート3にて被覆する。この繊維シート3には入射側傾斜
面a側の端縁にめくれ上りを防止するための重りとして
チェーン4を取り付けておく。次いでこの繊維シート3
の上に金属線材R5を被覆する。この金属線材網5はワ
イヤーローブを捨石2が透過できない程度の大きさの網
目に編み込んだものを使用し、入射側傾斜面aの最下部
稍上より埋立側傾斜面すの静水面より稍下にかけて連続
して被覆する。然る後、波浪によって金属線材lI45
の浮き上りを防止するための重りとしてチェーン6(N
o、I〜■)を金属線材網5の上に設置し、固定する。Figures 1 and 2 show the case where the present invention is applied to a slope plate for a reclaimed seawall, and 1 in the figure is a slope plate main body formed by piling up rubble weighing 10 to 200 kg each. The outer surface of the top end of the inclined plate main body 1 is the wave incident side inclined surface a and the reclaimed surface IJ!
The slope of l#J is covered with a water-permeable fiber sheet 3 up to the vicinity of the still water surface. A chain 4 is attached to the edge of the fiber sheet 3 on the side of the incident side inclined surface a as a weight to prevent it from curling up. Next, this fiber sheet 3
A metal wire R5 is coated on top of the metal wire R5. This metal wire net 5 is made by weaving wire lobes into a mesh of such a size that the rubble 2 cannot pass through, and is placed from slightly above the lowest part of the incident side slope a to slightly below the still water surface of the reclaimed side slope. Cover continuously. After that, the metal wire lI45 was destroyed by the waves.
Chain 6 (N
o, I to ■) are placed on the metal wire net 5 and fixed.
このチェーン6は傾斜板法線に平行に一定間隔毎に設置
する。また水面付近の洗掘を受けて転落した捨石が堆積
する静水面より稍下側位置には、傾斜面の盛り上りか強
く押えられるようチェーン6を二重に設置している。The chains 6 are installed at regular intervals parallel to the normal line of the inclined plate. In addition, a double chain 6 is installed at a position slightly below the still water surface where rubble that has fallen due to scouring near the water surface is deposited, so as to strongly press down on the bulge of the slope.
(実験例1)
1、実験条件
第3図に示すように、m維布及び金属線材網の被覆位置
をNo、 1〜No、 3のように違えて本発明を実施
した各試験例及び第4図に示す無対策の対象例A、6ト
ンテトラポツト7を使用した対象例Bに対し、周期T百
=5.8秒、波高H了−2,77mの波浪を想定し、ま
た各実施例及び各対象例とも捨石重量が10〜200
kg、また各実施例における金属線材網は直径19”+
nmのワイヤーロープを36■メツシユで編み込んだも
の、チェーンは70 kg/ mのものをそれぞれ想定
して試験を行なった。(Experimental Example 1) 1. Experimental Conditions As shown in Fig. 3, the present invention was carried out by changing the covering positions of the m-fiber cloth and the metal wire mesh as shown in No. 1 to No. 3. For example A with no countermeasure shown in Figure 4 and example B using 6-ton tetrapot 7, waves with a period T = 5.8 seconds and a wave height H - 2.77 m were assumed, and each implementation The weight of rubble is 10 to 200 in both the example and each target example.
kg, and the metal wire mesh in each example has a diameter of 19”+
The test was conducted assuming that the wire rope was woven with a 36 mm mesh and the chain was 70 kg/m.
また各試験例No、 1〜N0.3及び対象例A、−B
の傾斜堤本体天端高さ、並びに試験時の水位は第1表の
如くである。In addition, each test example No. 1 to No. 3 and target examples A and -B
Table 1 shows the height of the top of the sloping embankment and the water level at the time of the test.
第1表
表中 LWLはローウォーターレベルを、HWLはハイ
ウォーターレベルを示し、また天端高さは、その地域に
おける基準高さく例えば東京ポイント)を基準にした高
さを示している。(第2表も同じ)
なお、第3図において試験例No、 1〜No、 3と
も(イ)は縦断面図、(ロ)は平面図を表している。In Table 1, LWL indicates the low water level, HWL indicates the high water level, and the crown height indicates the height based on the standard height in the area (for example, Tokyo Point). (The same applies to Table 2) In addition, in FIG. 3, for Test Examples No. 1 to No. 3, (a) represents a longitudinal sectional view, and (b) represents a plan view.
2、実験結実
現地1時間波浪作用後の傾斜坑本体形状の変化は、第4
図に示す如くであった。即ち、イ)試験例No、 1
引き減時に静水面付近の捨石か斜面に沿って転落し、第
3図No、 1中のチェーンNo、 IIIの位置に堆
積した。2. Changes in the shape of the inclined shaft body after 1 hour of wave action at the experimental site are as follows:
It was as shown in the figure. That is, a) Test Example No. 1 During the withdrawal, the chain fell along the rubble or slope near the still water surface, and was deposited at the chain No. III in Figure 3.
傾斜基本体の変形は顕著でない。The deformation of the inclined base body is not significant.
口)試験例No、 2
引き減時に静水面付近の捨石か斜面に沿って転落し、第
3図No、 2中のチェーンM■の位置に堆積した。ま
た、越波により天端部及び天端後部の肩部か洗掘された
。(Example) Test Example No. 2 During the evacuation, it fell down along the slope or rubble near the still water surface, and was deposited at the position of chain M■ in Figure 3, No. 2. In addition, the crest and the shoulder at the rear of the crest were scoured by overtopping waves.
護岸の変形は顕著でない。Deformation of the seawall is not significant.
ハ)試験例No、 3
引き減時に静水面付近の捨石か斜面に沿って転落し、第
3図No、 3中のチェーンM■〜No、 I[[の位
置に堆積した。c) Test Example No. 3 When the water was being drained, it fell down along the slope or rubble near the still water surface, and was deposited at the positions of the chains M■ to No. I in Figure 3, No. 3.
護岸の変形は顕著でない。Deformation of the seawall is not significant.
二)対象例A
引き減時に表層の捨石か斜面下側に転落し、水深の深い
所に堆積した。2) Target example A During the evacuation, rubble on the surface layer fell down to the lower side of the slope and was deposited in deep water.
護岸の変形は大きい。The deformation of the seawall is significant.
ホ)対象例B 引き減時にてテトラポットが斜面に沿ってずり落ちな。e) Target example B Do not allow the tetrapod to slide down the slope when it is being drained.
引き減時に静水面付近の捨石が吸いだされて水深の深い
所に転落した。When the water receded, rubble near the still water surface was sucked out and fell into the deep water.
護岸の変形は顕著でない。Deformation of the seawall is not significant.
(実験例2)
■、実験条件
前述した実施例に示した配置に金属線材網を付設し、繊
維網を付設した場合と付設しない場合、更にそれらにつ
いて傾斜面の勾配を違えた第2表に示す試験例No、
4〜No、 7について実験例1と同じ条件にて試験を
行った。(Experimental Example 2) ■, Experimental Conditions Table 2 shows the cases in which a metal wire net was attached to the arrangement shown in the above-mentioned example, with and without a fiber net attached, and the slope of the slope was different for each case. Test example No.
Tests No. 4 to No. 7 were tested under the same conditions as Experimental Example 1.
第2表
2、試験結実
現地5時間波浪作用後の傾斜基本体の形状変化は、第5
図に示す如くであった。即ち、イ)試験例No、 4
入射波側の護岸天端肩部から水面下0.5m付近の捨石
が約0.6m洗掘され、水深2〜3mの第2図中のチェ
ーンNO■の位置に約0.6mの厚さで堆積した。入射
波側の天端部は、洗掘により約0.9m後退した。Table 2 2. Changes in the shape of the inclined basic body after 5 hours of wave action at the test site are shown in the fifth table.
It was as shown in the figure. That is, a) Test example No. 4 The rubble was scoured approximately 0.6 m from the shoulder of the top of the seawall on the incident wave side at around 0.5 m below the water surface, and the chain No. ■ in Figure 2 at a water depth of 2 to 3 m A thickness of approximately 0.6 m was deposited at the location. The top end on the incident wave side retreated by approximately 0.9 m due to scouring.
また、埋立側の護岸天端肩部の捨石が、越波により若干
洗掘され水面付近に転落した。Additionally, the rubble at the top shoulder of the revetment on the reclaimed side was slightly scoured by the overtopping waves and fell near the water surface.
口)試験例NO,5
入射波側及び埋立側の護岸天端肩部は、布の効果により
変形がみられない。入射波側の水面付近の捨石が約0.
7m洗掘され、第2図中の水深2〜3mのチェーンNO
,Hの位置に約0.7mの厚さで堆積した。(Example) Test Example No. 5 No deformation was observed at the top shoulders of the seawall on the incident wave side and the reclaimed side due to the effect of the cloth. The number of rubble near the water surface on the incident wave side is approximately 0.
Chain No. 7 m has been scoured, and the water depth is 2 to 3 m in Figure 2.
, H with a thickness of about 0.7 m.
また、埋立側の水面付近の捨石が、越波により若干洗掘
され水面下に転落した。In addition, the rubble near the water surface on the reclaimed side was slightly scoured by the overtopping waves and fell below the water surface.
ハ)試験例No、 6
入射波側の護岸天端肩部から水面付近の捨石が約0,5
m洗掘され、第2図中の水深2〜3mのチェーン恥■の
位置に約0.5mの厚さで堆積し施工時断面のラインに
略一致した。入射波側の天端部は洗掘により約0.3m
後退した。C) Test example No. 6 The rubble near the water surface from the shoulder of the top of the seawall on the incident wave side is approximately 0.5
It was scoured and deposited in a thickness of about 0.5 m at the chain point (2) at a water depth of 2 to 3 m in Figure 2, and approximately coincided with the line of the cross section at the time of construction. The top end on the incident wave side is approximately 0.3m due to scouring.
I retreated.
また、埋立側の水面付近の捨石が、越波により若干洗掘
され水面下に転落した。In addition, the rubble near the water surface on the reclaimed side was slightly scoured by the overtopping waves and fell below the water surface.
二)試験例NO,7
入射波側及び埋笠側の護岸天端肩部は、布の効果により
変形が見られない。入射波側の水面付近の捨石が約0.
5m洗掘され、第2図中の水深2〜3mのチェーンNO
■の位置に約0,5mの厚さで堆積し施工時断面のライ
ンに略一致した。2) Test Example No. 7 No deformation was observed at the top shoulders of the revetment on the incident wave side and the buried shade side due to the effect of the cloth. The number of rubble near the water surface on the incident wave side is approximately 0.
Chain No. 5 was scoured, and the water depth is 2 to 3 meters in Figure 2.
It was deposited to a thickness of about 0.5 m at the position (2) and approximately coincided with the line of the cross section at the time of construction.
また、埋立側の水面付近の捨石が、越波により若干洗掘
され水面下に転落した。In addition, the rubble near the water surface on the reclaimed side was slightly scoured by the overtopping waves and fell below the water surface.
(発明の効果)
本発明の傾斜坑捨石の散乱防止方法は上述の如く構成さ
れ、繊維布、金属金網及び重り用のチェーンを傾斜堤外
面を覆うように付設することによって波浪による捨石散
乱か有効に防止されることとなったものであり、その付
設及び除去作業はテトラポット等のコンクリートブロッ
クの設置に比べて遥かに容易であり、短時間にて作業が
なし得られる。(Effects of the Invention) The method for preventing scattering of rubble in a slope mine according to the present invention is configured as described above, and is effective in preventing scattering of rubble due to waves by attaching fiber cloth, metal wire mesh, and weight chains so as to cover the outer surface of the slope embankment. The installation and removal work is much easier than installing concrete blocks such as tetrapods, and the work can be completed in a short time.
更にまた、これら資材は設置後に除去したものを次の傾
斜坑構築部分に再使用でき、経済的である。Furthermore, these materials can be removed after installation and reused for the next inclined shaft construction, which is economical.
第1図は本発明の実施例を示す部分平面図、第2図は第
1図中のA−A線断面図、第3図は実施−12=
例1の付設状態を示す説明図、第4図は実験例1の実験
結果を示す説明図、第5図は実験例2の実験結果を示す
説明図である。
a・・・・・・入射側傾斜面、b・・・・・・埋立側傾
斜面、1・・・・・・傾斜基本体、2・・・・・・捨石
、3・・・・・・繊維布、4・・・・・・チェーン、5
・・・・・・金属線材網、6・・・・・・チェーン。FIG. 1 is a partial plan view showing an embodiment of the present invention, FIG. 2 is a sectional view taken along the line A-A in FIG. FIG. 4 is an explanatory diagram showing the experimental results of Experimental Example 1, and FIG. 5 is an explanatory diagram showing the experimental results of Experimental Example 2. a... Slanted surface on the incident side, b... Slanted surface on the reclaimed side, 1... Slanted basic body, 2... Rubble, 3...・Fiber cloth, 4...Chain, 5
...Metal wire mesh, 6...Chain.
Claims (2)
斜堤の表面に該傾斜堤の入射側傾斜面の静水面下より反
対側傾斜面にかけて該捨石が通過不能な大きさの網目の
金属線材網をもって覆い、該金属線材網の外面に、その
重量によって前記金属線材網の剥離を防止させるチェー
ンを付設することを特徴としてなる傾斜堤捨石の散乱防
止方法。(1) On the surface of a sloped embankment constructed in the sea, at least on the surface of which rubble is piled up, there is a mesh of a size that prevents the rubble from passing from below the still water surface of the slope on the entrance side of the slope to the slope on the opposite side. 1. A method for preventing scattering of slope embankment rubble, comprising covering the slope with a metal wire net and attaching a chain to the outer surface of the metal wire net to prevent the metal wire net from peeling off due to its weight.
斜堤の表面の、少なくとも静水面より上の部分を透水性
の繊維布で覆うとともに、その上に該傾斜堤の入射側傾
斜面の静水面下より反対側傾斜面にかけて該捨石が通過
不能な大きさの網目の金属線材網をもって覆い、該金属
線材網の外面に、その重量によって前記金属線材網の剥
離を防止させるチェーンを付設することを特徴としてな
る傾斜堤捨石の散乱防止方法。(2) Cover at least the part above the still water surface of the surface of the sloping embankment built underwater and at least on the surface with rubble piled up, with water-permeable fiber cloth, and on top of that, cover the entrance side slope of the slanted levee. A metal wire net with a mesh size that the rubble cannot pass from below the still water surface to the opposite slope is covered, and a chain is attached to the outer surface of the metal wire net to prevent the metal wire net from peeling off due to its weight. A method for preventing scattering of rubble on a slope embankment.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63155716A JPH0692646B2 (en) | 1988-06-23 | 1988-06-23 | Temporary protection method for sloped rubble |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63155716A JPH0692646B2 (en) | 1988-06-23 | 1988-06-23 | Temporary protection method for sloped rubble |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH01322013A true JPH01322013A (en) | 1989-12-27 |
| JPH0692646B2 JPH0692646B2 (en) | 1994-11-16 |
Family
ID=15611929
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP63155716A Expired - Lifetime JPH0692646B2 (en) | 1988-06-23 | 1988-06-23 | Temporary protection method for sloped rubble |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0692646B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2014177777A (en) * | 2013-03-14 | 2014-09-25 | Railway Technical Research Institute | Tree planting method of earthquake resistant tide embankment banking slope face |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS491035A (en) * | 1972-04-18 | 1974-01-08 | ||
| JPS4995445A (en) * | 1973-01-16 | 1974-09-10 | ||
| JPS6318537U (en) * | 1986-07-17 | 1988-02-06 |
-
1988
- 1988-06-23 JP JP63155716A patent/JPH0692646B2/en not_active Expired - Lifetime
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS491035A (en) * | 1972-04-18 | 1974-01-08 | ||
| JPS4995445A (en) * | 1973-01-16 | 1974-09-10 | ||
| JPS6318537U (en) * | 1986-07-17 | 1988-02-06 |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2014177777A (en) * | 2013-03-14 | 2014-09-25 | Railway Technical Research Institute | Tree planting method of earthquake resistant tide embankment banking slope face |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0692646B2 (en) | 1994-11-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US3344609A (en) | Prevention of beach erosion and encouragement of land restoration | |
| US3842606A (en) | Beach-protectors | |
| KR100335334B1 (en) | Optimized middle armor concrete block | |
| EP3736382B1 (en) | Erosion prevention unit and erosion prevention method | |
| KR100993335B1 (en) | Revetment protection works using gabion and construction method thereof | |
| SU1559036A1 (en) | Method and apparatus for protecting bank against washout of water flow | |
| JPH01322013A (en) | Temporary protection method for slope embankment rubble | |
| RU195367U1 (en) | Prefabricated waterworks module | |
| JP3425477B2 (en) | Sand mound foundation construction method by mat covering | |
| JP4482859B2 (en) | Stabilization method behind the revetment | |
| JP2022019818A (en) | Scourage prevention structure and crushed stone unit | |
| JP3693613B2 (en) | Protective mat | |
| Jachowski | Interlocking precast concrete block seawall | |
| RU2200793C2 (en) | Reinforced rubble concrete fixing | |
| JPH067047Y2 (en) | Cover sheet for reclaimed seawall | |
| CN210507308U (en) | Bottom protection structure for local scouring protection of coastal and offshore engineering structures | |
| JP4067705B2 (en) | Transmission type breakwater made of steel plate cell type structure | |
| JP3077022B2 (en) | Wave-dissipating structure | |
| JPH0715863Y2 (en) | Caisson revetment joint water barrier | |
| KR100411530B1 (en) | Water Stream Tunnel Prevent Hole of Construction On The Water and Execution Methode Thereof | |
| KR100519112B1 (en) | Scour protection | |
| KR200341959Y1 (en) | Structure of Preventing Water Stream Tunnel of Underwater Fabric | |
| JP2971807B2 (en) | Underwater foundation mound protection net structure | |
| KR100494355B1 (en) | Structure of Preventing Water Stream Tunnel of Underwater Fabric | |
| CN200992694Y (en) | Artificial island winter downtime protection net device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20071116 Year of fee payment: 13 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081116 Year of fee payment: 14 |
|
| EXPY | Cancellation because of completion of term | ||
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081116 Year of fee payment: 14 |