JPH0214596B2 - - Google Patents
Info
- Publication number
- JPH0214596B2 JPH0214596B2 JP19027082A JP19027082A JPH0214596B2 JP H0214596 B2 JPH0214596 B2 JP H0214596B2 JP 19027082 A JP19027082 A JP 19027082A JP 19027082 A JP19027082 A JP 19027082A JP H0214596 B2 JPH0214596 B2 JP H0214596B2
- Authority
- JP
- Japan
- Prior art keywords
- gas
- pipe
- communication
- opening
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L55/00—Devices or appurtenances for use in, or in connection with, pipes or pipe systems
- F16L55/18—Appliances for use in repairing pipes
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Pipe Accessories (AREA)
- Paper (AREA)
- Pipeline Systems (AREA)
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明発明は、ガス導管等の工事の際に用いる
工事用連絡部材に関するものである。DETAILED DESCRIPTION OF THE INVENTION (Industrial Field of Application) The present invention relates to a construction communication member used for construction of gas pipes and the like.
(従来の技術)
ガスを需要家に流通している状態で、ガス管を
切断して、ガス管の一部を交換したり、分岐管を
設けたり、或は補修を行なう方法として、ノーブ
ロ工法といわれる方法によつて行われていた。こ
の方法は、例えば特定個所のガス管を補修するよ
うな場合、その補修個所をまたいで、バイパス管
を設け、このバイパス管に補修完了までガスを流
通させるのであるが、工事の最初から完了まで、
需要家に対して、ガスの流通状態を完全に維持し
ながら行なう工法である。かかる方法に於いて
は、バイパス管を敷設した後、ガス管へのガスの
流通の一時的停止を、ゴム風船をガス管内でふく
らませることによつて行なわれていた。(Prior art) The no-blow construction method is a method for cutting a gas pipe and replacing a part of the gas pipe, installing a branch pipe, or performing repairs while gas is being distributed to consumers. It was done by a method called. In this method, for example, when repairing a gas pipe at a specific location, a bypass pipe is installed across the repaired location, and gas is passed through this bypass pipe until the repair is completed. ,
This is a construction method that maintains the complete flow of gas to customers. In this method, after the bypass pipe is installed, the flow of gas to the gas pipe is temporarily stopped by inflating a rubber balloon within the gas pipe.
(発明が解決しようとする課題)
かかるゴム風船によるガスの一時的停止は、ゴ
ム風船の破損による事故発生の可能性があること
に加えて、ゴム風船を準備することと、それを膨
張させるための機器、それの取扱い作業等が必要
となり、信頼性と作業性に問題があつた。そこ
で、燃料ガスを需要家に供給している状態に於い
て、ガス管の工事を行なうため、事故の発生は完
全に防止しなければならなく、また、バイパス管
の敷設に際しては作業性がよくなければならない
課題がある。(Problem to be Solved by the Invention) Temporary stoppage of gas from such a rubber balloon may cause an accident due to breakage of the rubber balloon, as well as the need to prepare the rubber balloon and inflate it. equipment and handling work, etc., and there were problems with reliability and workability. Therefore, since gas pipe construction is carried out while fuel gas is being supplied to consumers, it is necessary to completely prevent accidents from occurring, and it is also important to ensure that work efficiency is high when installing bypass pipes. There are issues that must be addressed.
(課題を解決するための手段)
前記目的を達成するための手段として、以下の
構成から成る連絡部材を必要とする。即ち、連通
部材の長さ方向の中央部にガス連通孔を設け、該
ガス連通孔の半径方向に開口部を設け、該開口部
の背部には、その長さ方向にガスパージ溝を設け
る構成とし、かかる構成の連通部材を、上部に係
合部を設けた内管の先端に取着けると共に、ガス
パージ孔と螺合部、そして下部にフランジ部を設
けた固定用外管内に、前記内管を装入し、該内管
の上部には前記係合部と係合する締付部材を装置
した連絡部材を構成する。(Means for Solving the Problem) As a means for achieving the above object, a communication member having the following configuration is required. That is, a gas communication hole is provided in the center of the communication member in the longitudinal direction, an opening is provided in the radial direction of the gas communication hole, and a gas purge groove is provided in the longitudinal direction at the back of the opening. The communicating member having such a structure is attached to the tip of an inner tube that has an engaging portion on the upper part, and the inner tube is placed inside an outer fixing tube that has a gas purge hole, a threaded portion, and a flange portion on the lower part. A connecting member is provided at the upper part of the inner tube and includes a tightening member that engages with the engaging portion.
(作用)
連通部材がガス管内で変形してガスを遮断する
と同時に開口部からガスが流入してバイパス通路
に導入される。ガス管内のガスは前記開口部3の
背部にあるガスパージ溝から流入してガスパージ
孔から排出させる。(Function) At the same time as the communication member deforms within the gas pipe and blocks the gas, gas flows in from the opening and is introduced into the bypass passage. Gas in the gas pipe flows into the gas purge groove at the back of the opening 3 and is discharged through the gas purge hole.
(実施例)
本発明の実施例を図について説明すると次の通
りである。(Example) An example of the present invention will be described below with reference to the drawings.
符号1はゴム等の弾性部材から成る連通部材で
あり、この連通部材1は、その長さ方向の中央部
にガス連通孔2を設け、該ガス連通孔2の半径方
向に開口部3を設け、該開口部3の背部には、そ
の長さ方向にガスパージ溝4を設ける構成とし、
かかる構成の連通部材1を、上部に係合部5を設
けた内管6の先端に取着けると共に、ガスパージ
孔8と螺合部9、そして下部にフランジ部13を
設けた固定用外管10内に、前記内管6を装入
し、該内管6の上部には前記係合部5と係合する
締付部材7を装置したものである。 Reference numeral 1 denotes a communication member made of an elastic member such as rubber, and this communication member 1 has a gas communication hole 2 in its longitudinal center, and an opening 3 in the radial direction of the gas communication hole 2. , a gas purge groove 4 is provided at the back of the opening 3 in the length direction thereof,
The communication member 1 having such a structure is attached to the tip of an inner tube 6 which has an engaging portion 5 at its upper portion, and an outer fixing tube 10 which has a gas purge hole 8, a threaded portion 9, and a flange portion 13 at its lower portion. The inner tube 6 is inserted into the inner tube, and a tightening member 7 that engages with the engaging portion 5 is provided on the upper part of the inner tube 6.
しかして、前記構成の連絡部材の使用方法を、
実施例図に基き説明すると次の通りである。い
ま、ガス管Bの特定個所Dを切断して工事を行な
う場合、その特定個所Dを切断しても、ガスの供
給に支障がないようにバイパス通路Eをつくらね
ばならない。このため、特定個所をまたいだガス
管B上に前記構成の連絡部材A,A′を設置する。 Therefore, the method of using the connecting member having the above configuration is as follows.
The explanation will be as follows based on the drawings of the embodiment. If construction is to be carried out by cutting a specific point D of the gas pipe B, a bypass passage E must be created so that even if the specific point D is cut, there will be no problem with gas supply. For this reason, the connecting members A and A' having the above configuration are installed on the gas pipe B that straddles the specific location.
先ず、第2図に於いて、ガス管B上に台座11
を固定し、その台座11上に固定用レバー12を
備えたシヤツター弁Cを装置する。そして、シヤ
ツター弁Cに穿孔機(図示せず)を取着けてガス
管Bを穿孔した後、その穿孔機を取り外す。シヤ
ツター弁Cを閉じた状態で今度は、前記外管10
のフランジ部12を固定用レバー12により押圧
して、前記内管6をシヤツター弁C上に取着け、
連結部材A,A′間にバイパス通路Eを取着ける。
次に第3図に於いて、ガス連絡用部材Aのうち図
中左側の連絡用部材AのシヤツターCを開けて内
管6を押し下げると、その先端に取着けられた弾
性体から成る連通部材1は、ガス管B内に装入す
る。この状態に於いて、ガス連通孔2から入つた
ガスは、図中矢印の通り、バイパス通路Eを流れ
てガス連絡部材A′側の弾性体から成る連通部材
1に至り、そこのガス連通孔2から外管10内に
出て、ガスパージ孔8から流出する。この流出に
よつてバイパス通路E中の空気はガスと共に完全
にパージされる。他方、連絡部材A側にガスパー
ジ溝4から外管10内に入つたガスは図中矢印の
通り、ガスパージ孔8から流通して外管10内の
空気をガスと共に完全に流出する。この状態が第
3図に示す状態である。第3図の状態ではガス管
Bにガスが流れており、ガスの供給は差支えな
い。次に、第4図に於いて、連絡部材A′側のシ
ヤツター弁Cを開として、連絡部材A側と同様の
状態とする。この状態ではガス管Bのみならず、
バイパス通路Eにもガスが流れており全通状態と
なる。かかる状態に於いて、両方の連結部材A,
A′の締付部材7を回わすと、締付部材7と螺合
部9が螺合することにより、締付部材7と係合部
5が係合して内管6を押動する。そして、その押
動は、先端の連通部材1が変形してガスを遮断す
るまで押圧する。かかる如く、締付部材7を回動
させ、内管6は回動しないので、開口部3も回動
せず、即ちその開口位置は変らない。しかして、
ガスはガス連通孔2から連絡部材A′側のガス連
通孔2へと流れて、特定個所Dには流れない。即
ちバイパス通路Eのみ流れてガス管Bには流れな
い。かかる状態が第5図の状態である。この状態
で、特定個所Dの切断等を行ない工事を実行す
る。工事完了後は、締付部材7、シヤツター弁C
及びガスパージ孔8等の操作を行ない、即ち前記
したと反対の操作を行ない、最後に連絡部材A,
A′を取り外し、プラグをシヤツター弁Cに取着
け、穿孔個所を閉止した後、バイパス通路Eと共
にシヤツター弁C及び台座11を取り除き工事を
完了する。 First, in Fig. 2, the pedestal 11 is placed on the gas pipe B.
is fixed, and a shutter valve C equipped with a fixing lever 12 is installed on the pedestal 11. Then, a perforator (not shown) is attached to the shutter valve C to perforate the gas pipe B, and then the perforator is removed. With the shutter valve C closed, the outer tube 10
Press the flange portion 12 of the lever 12 with the fixing lever 12 to attach the inner pipe 6 onto the shutter valve C,
A bypass passage E is installed between connecting members A and A'.
Next, in FIG. 3, when the shutter C of the gas communication member A on the left side in the figure is opened and the inner tube 6 is pushed down, the communication member made of an elastic body attached to the tip of the gas communication member A is opened. 1 is inserted into the gas pipe B. In this state, gas entering from the gas communication hole 2 flows through the bypass passage E as indicated by the arrow in the figure, reaches the communication member 1 made of an elastic body on the gas communication member A' side, and passes through the gas communication hole there. 2 into the outer tube 10 and flows out from the gas purge hole 8. Due to this outflow, the air in the bypass passage E is completely purged together with the gas. On the other hand, the gas that has entered the outer tube 10 from the gas purge groove 4 on the communication member A side flows through the gas purge hole 8 as indicated by the arrow in the figure, and the air in the outer tube 10 is completely discharged together with the gas. This state is the state shown in FIG. In the state shown in FIG. 3, gas is flowing through the gas pipe B, and there is no problem with the gas supply. Next, in FIG. 4, the shutter valve C on the communication member A' side is opened to create the same state as on the communication member A side. In this state, not only gas pipe B but also
Gas also flows through the bypass passage E, so that it is in a full flow state. In this state, both connecting members A,
When the tightening member 7 of A' is rotated, the tightening member 7 and the threaded portion 9 are screwed together, so that the tightening member 7 and the engaging portion 5 are engaged and the inner tube 6 is pushed. The pushing motion is continued until the communicating member 1 at the tip deforms and blocks the gas. In this way, since the tightening member 7 is rotated but the inner tube 6 is not rotated, the opening 3 is also not rotated, that is, its opening position does not change. However,
Gas flows from the gas communication hole 2 to the gas communication hole 2 on the communication member A' side, and does not flow to the specific location D. That is, the gas flows only through the bypass passage E and does not flow into the gas pipe B. Such a state is the state shown in FIG. In this state, the construction work is carried out by cutting at specific locations D, etc. After the construction is completed, tighten the tightening member 7 and shutter valve C.
and gas purge hole 8, etc., that is, perform the operations opposite to those described above, and finally connect the connecting members A,
A' is removed, a plug is attached to the shutter valve C, and the perforation is closed. After that, the bypass passage E, the shutter valve C and the pedestal 11 are removed to complete the work.
かかる際、特に重要なことは、特定個所Dに取
着けた新らしい管中の空気をパージすることであ
る。これは第6図に示すように、連絡部材A′側
のガスパージ孔8を開けた後、連絡部材A側の締
付部材7をゆるめることによつて、弾性体1の押
圧がやわらかくなり、ガスは特定個所Dにも流
れ、その後連絡部材A′側の弾性体から成る連通
部材1のガスパージ溝4を通過してガスパージ孔
8から流出し管内空気をパージする。従つて特定
個所には空気は存在しなくなる。 In this case, what is particularly important is to purge the air in the new pipe attached to the specific location D. As shown in Fig. 6, by opening the gas purge hole 8 on the side of the connecting member A' and loosening the tightening member 7 on the side of the connecting member A, the pressure of the elastic body 1 is softened, and the gas The gas also flows to a specific point D, and then passes through the gas purge groove 4 of the communication member 1 made of an elastic body on the side of the communication member A', flows out from the gas purge hole 8, and purges the air in the pipe. Therefore, air no longer exists in the specific location.
(発明の効果)
本発明は以上の通り、独特構成の連絡部材によ
つて、バイパス通路の設置及び除去を容易に行な
うことができると同時に、最も重要とされる各部
所の空気をガスと共に容易にパージすることがで
きる最大のメリツトがある。かかることによつて
従来実行されてきた台座及びシヤツター弁を左右
に二個所ずつ合計四個所設置して、安全を計りつ
つゴム風船を膨張収縮させながら行なつてきた作
業を一挙に簡略化できると同時にゴム風船を使用
しないので安全性が最大に確保される大きな利点
がある。(Effects of the Invention) As described above, the present invention makes it possible to easily install and remove a bypass passage by using a uniquely configured communication member, and at the same time, it is possible to easily remove air from each of the most important parts together with gas. The biggest advantage is that it can be purged. By doing so, we believe that the conventional work of installing pedestals and shutter valves in four locations, two on the left and right, and inflating and deflating rubber balloons while ensuring safety, can be simplified at once. At the same time, since no rubber balloons are used, there is a great advantage of ensuring maximum safety.
第1図は連絡部材の説明図、第2図ないし第6
図は、作業状態を示す説明図である。
符号1……弾性体から成る連通部材、2……ガ
ス連通孔、3……開口部、4……ガスパージ溝、
5……係合部、6……内管、7……締付部材、8
……ガスパージ孔、9……螺合部、10……外
管、11……台座、12……固定用レバー、13
……フランジ部、A……ガス連絡部材、B……ガ
ス管、C……シヤツター弁、D……工事等の特定
個所、E……バイパス通路。
Figure 1 is an explanatory diagram of the connecting member, Figures 2 to 6
The figure is an explanatory diagram showing the working state. Reference numeral 1... Communication member made of an elastic body, 2... Gas communication hole, 3... Opening, 4... Gas purge groove,
5... Engaging portion, 6... Inner pipe, 7... Tightening member, 8
... Gas purge hole, 9 ... Threaded part, 10 ... Outer tube, 11 ... Pedestal, 12 ... Fixing lever, 13
...Flange portion, A...Gas communication member, B...Gas pipe, C...Shutter valve, D...Specific location such as construction, E...Bypass passage.
Claims (1)
にガス連通孔を設け、該ガス連通孔の半径方向に
開口部を設け、該開口部の背部には、その長さ方
向にガスパージ溝を設け、かかる構成の連通部材
を上部に係合部を設けた内管の先端に取着けると
共に、ガスパージ孔と螺合部、そして下部にフラ
ンジ部を設けた固定用外管内に、前記内管を装入
し、該内管の上部には、前記係合部と係合する締
付部材を装置したガス導管等の工事用連絡部材。1. A gas communication hole is provided in the longitudinal center of the communication member made of an elastic material, an opening is provided in the radial direction of the gas communication hole, and a gas purge groove is provided in the longitudinal direction at the back of the opening. A communicating member having such a structure is attached to the tip of an inner tube having an engaging portion at the upper portion, and the inner tube is placed inside an outer fixing tube having a gas purge hole, a threaded portion, and a flange portion at the lower portion. A connecting member for construction work such as a gas conduit pipe, which is inserted into the inner pipe and is provided with a tightening member that engages with the engaging portion at the upper part of the inner pipe.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19027082A JPS5980599A (en) | 1982-10-29 | 1982-10-29 | Non-ejection communicating member of gas conduit, etc. |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19027082A JPS5980599A (en) | 1982-10-29 | 1982-10-29 | Non-ejection communicating member of gas conduit, etc. |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5980599A JPS5980599A (en) | 1984-05-10 |
| JPH0214596B2 true JPH0214596B2 (en) | 1990-04-09 |
Family
ID=16255353
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP19027082A Granted JPS5980599A (en) | 1982-10-29 | 1982-10-29 | Non-ejection communicating member of gas conduit, etc. |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5980599A (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0646079B2 (en) * | 1985-05-23 | 1994-06-15 | 東京瓦斯株式会社 | Gas meter replacement construction method |
| JPS62150121A (en) * | 1985-12-25 | 1987-07-04 | Tokyo Gas Co Ltd | No-blow tool used in gas meter replacing work |
-
1982
- 1982-10-29 JP JP19027082A patent/JPS5980599A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5980599A (en) | 1984-05-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4351349A (en) | Pipe repair kit apparatus and method | |
| US4756338A (en) | Pipe repair assemblies to repair pipe when fluids therein are under high pressure | |
| JPH02501155A (en) | Method and apparatus for attaching objects within fluid containing conduits | |
| US4466273A (en) | Leak detection system | |
| US3773067A (en) | Apparatus for effecting operations on a fitting on a high pressure gas main | |
| US4342338A (en) | Boot for sealing ruptured gas or water mains and tool for application | |
| US5285806A (en) | Method and apparatus for temporarily sealing off pipelines | |
| US4144908A (en) | Pipe plugging device and method | |
| US3626576A (en) | Method for repairing pressure lines such as gas mains and the like | |
| US5967191A (en) | Method for servicing a live pipeline | |
| CN108626514A (en) | PE pipe leakage restorative procedures | |
| US3774646A (en) | Line stopping assembly using an inflatable element | |
| US3774647A (en) | Line stopping assembly using an inflatable element | |
| EP1564474B1 (en) | No interrupt service tee and method | |
| JPH0214596B2 (en) | ||
| JPH0875077A (en) | Piping repair method | |
| USRE27895E (en) | Method for repairing pressure lines such as gas mains and the like | |
| EP1198683B1 (en) | A method of closing a pipe | |
| JP4915915B2 (en) | Channel blockage tool | |
| JPH10132181A (en) | Bypass forming method | |
| JP3073049B2 (en) | Method and apparatus for reconnecting gas supply pipe | |
| JPH04116091U (en) | Bag for shutting off fluid conduits | |
| KR102572095B1 (en) | A pipe inner space block device for preventing foreign object inflow | |
| JPH0374696A (en) | Method for repairing feed pipe for gas conduit | |
| JPH048995A (en) | Fluid cutoff device |